JLC CONSTRUCTION

1521 BAMBANG ST. STA. CRUZ, MANILA

PROJECT EXECUTION PLAN


BULK EXCAVATION & SLOPE
PROTECTION
Doña Elena Tower, Sta. Mesa, Manila

1
Document Review
Name Title Signature Date
Prepared by: Mr. Norwind C. Tabelina Safety Officer/Project
Coordinator
Reviewed by: Engr. Fortunato Mondala Jr. Project Manager

Noted by: Mr. Dan V. Jimenez General Manager

Checked by: Mr. Juanito Cuerquez Safety Practitioner

Checked by: Owner FLYACE

Approved by: Owner FLYACE


CONTENTS: 1. PROJECT INFORMATION / OVERVIEW
 General Project Information
 Scope Definition
2. PROGRAMME & PLANNING
 Work Schedule
3. SITE LOGISTICS & TEMPORARY WORKS
 Site Access Plan
 Sump Pit, Pump Location & Drainage
Systems
 Traffic Flows
 Equipment Schedule
 Manpower Schedule
4. CONSTRUCTION METHODOLOGY
 Excavation Works
 Excavation Phasing Schedule
 Hauling Flow
 Slope Protections Works
 Equipment
 Phasing Schedule
 Soil Nailing Procedure & Diagram
5. EVACAUTION PLAN & SIGNAGES
6. TABLE OF ORGANIZATION
Project Information / Overview

 Proposed Doña Elena Tower


Bulk Excavation & Slope
Protection Project

 Location: P. Sanchez St. Cor. 3rd


St. Sta.Mesa, Manila

 Owner: FLYACE

 Project Duration: 100 days


Scope Definition

Design and Build


 Bulk Excavation Works and Design & Build of Slope Protection

General Project Scope Inclusion;

 Bonds and Insurances


 Bulk Excavation and Disposal
 Trimming Works (Horizontal and Vertical)
 Slope Protection Works (Design and Build)
Work Schedule
EXCAVATION WORKS SCHEDULE

In reference with the Existing 3 Times a Week Hauling Schedule


SITE LOGISTICS and TEMPORARY WORKS

WASHBAY

TEMP.SITE OFFICE

GATE
EQUIPMENT

BACKHOE 2 units
MOBILE CRANE 1 unit
DUMPTRUCK 40 units
ATLAST COMPRESSOR MACHINE 1
TURBOSOL SHOTCRETE MACHINE 1
DRY SHOTCRETE MACHINE 1
UMATIC DRILLING MACHINE 1
MIXER 1
MANPOWER

PROJECT MANAGER 1
PROJECT SUPERVISOR 2
EQUIPMENT CONTROLLER 1
BACKHOE OPERATOR/HELPER 4
DRILLING HELPER 4
SHOTCRETING OPERATOR 2
GROUTING OPERATOR 2
TRIMMER 4
DUMPTRUCK DRIVER 40
HELPER 10
METHODS - EXCAVATION
 Prepare excavation and conduct decommissioning activities according
to standards and specifications of authorities concerned.
 Removal (clearing) and stockpiling of top soil loading by backhoe
excavators to dump trucks for proper disposal.

 Cut works and excavation works will commence, Works shall include side
cutting, shoveling and stockpiling works at designated area accessible to
dump trucks. All side cuts and works will be done on a sloping manner
to avoid any erosion and/or cave-ins.
 All excavation works will be done on a daytime schedule while hauling
works will be scheduled during night time, maintaining a minimum target
of Seventy to Eighty (40-60) truckload per night.

 Paint markings of elevation points and references.


 Report uncovered soil to the Owner/General Contractor, if such soil
deviates from what is shown on the Boring Logs Report.

 Provision of sump pits in cases of any presence of seepages, spring


waters and/or caused by heavy rainfall for its diversion and
dewatering works.
 Manual trimming works will commence upon accomplishment of
elevation of 1.0 meter to 2.0 meters.
 Construction of ramp for accessibility.

 In cases of probable damages to adjacent properties and/or structures in


lieu of the excavation works to be performed, proper notification will be
made to the Owner/General Contractor for their resolution prior to
execution of such work.

 The remaining ramp will be excavated and haul


out using a metal bucket and a lifting crane.
 JLC Construction will also provide safe pedestrian walkways to
avoid accident and construct wash bays for vehicles to avert
scattering of soil along the adjacent area.

 Street sweeping will commence around 4:00 am to clear the roads of


debris and dirt.
 Breaking works shall start at 8:00 am daily and end at 6:00 pm or defend
on the approved working time by the management that is favorable to
the adjacent community.
 Hauling and disposal of excavated soil will start at 10:00 pm until 4:00
am or defend on the agreed hauling time with the owner.
METHODS – EXCAVATION – WASHBAY

3.0
Concrete pavement
6.0

TEMP.SITE OFFICE

GATE
METHODS – EXCAVATION – PHASING SCHEDULE

PHASE 2 PHASE 1
9,360cu.m. 23,040cu.m.
METHODS – EXCAVATION – SUMPPIT/PUMP LOCATION

Sump pit 1 Sump pit 2

Sump pit 2 Sump pit 3


METHODS – EXCAVATION – HAULING FLOW

backfilling into this


existing area and will be
dispose in the dumpsite
METHODS – SLOPE PROTECTION

Description:

This procedure considers that the excavation is done in


correlation with the excavated wall stabilization through soil
nailing and shotcreting, should the excavation proceeded
ahead of the soil stabilization then scaffolding works will be
needed to facilitate the soil nailing and shotcreting.
The works sequence are as follows:

1. Mobilized into the work location and position the


equipment so as not to hamper the excavated activities.
There are four basic equipment used in this soil
stabilization works, the compressor, the drill, the mixer
and the grout pump/shotcreting machine.
2. Excavation shall be 1m deep
for the top most nails then
followed by 1.5 meter (there
after) until the desired depth
of excavation is reached.
3. The soil nailing and
shotcreting shall follow the
excavation (as it
progresses) on a layer by
layer as described
4. Nail holes shall be drilled to the desired depth per
location (in accordance to the details indicated in the
drawings) followed by the insertion of the nail rod
followed by the injection of the cement based grout (the
sequence and timing of the insertion of nail rod and
injection of the grout depends on the stability of the soil
as less stable soil could collapse if the grout injection is
delayed.
5. When the nails are in-place and grouted, the weep holes
shall be installed simultaneous with the installation of the
reinforcing bars, wire mesh and anchor plates.
6. Shotcreting will follow once the weep holes and anchor
plates are in place.
7. When the top layer is completed, the succeeding layers
shall follow (on a layer by layer basis) as described in
item 2-6 until the project is completed.
8. When the last layer is completed, clearing and clean-
up shall proceed.
9. Completed projects shall be turned over.
10. Demobilization shall follow once the project is fully
accepted by the owner.
METHODS – SLOPE PROTECTION – PHASING
METHODS – SLOPE PROTECTION – ELEVATION A
METHODS – SLOPE PROTECTION – ELEVATION B
METHODS – SLOPE PROTECTION – ELEVATION C
METHODS – SLOPE PROTECTION – ELEVATION D
METHODS – SLOPE PROTECTION – ROCK ANCHORING
DETAILS
METHODS – SLOPE PROTECTION – ROCK ANCHORING
DETAILS
METHODS – SLOPE PROTECTION – EQUIPMENT

EQUIPMENT FOR SLOPE PROTECTION

ATLAST COPCO COMPRESSOR TURBOSOL SHOTCRETE DRY SHOTCRETE MACHINE


MACHINE MACHINE

SOIL NAILING 25mm dia.x 9.0m


UMATIC DRILLING MACHINE MIXER
SIGNAGES
ORGANIZATIONAL CHART