Methodology Dona Elana Tower
Methodology Dona Elana Tower
Methodology Dona Elana Tower
1
Document Review
Name Title Signature Date
Prepared by: Mr. Norwind C. Tabelina Safety Officer/Project
Coordinator
Reviewed by: Engr. Fortunato Mondala Jr. Project Manager
Owner: FLYACE
WASHBAY
TEMP.SITE OFFICE
GATE
EQUIPMENT
BACKHOE 2 units
MOBILE CRANE 1 unit
DUMPTRUCK 40 units
ATLAST COMPRESSOR MACHINE 1
TURBOSOL SHOTCRETE MACHINE 1
DRY SHOTCRETE MACHINE 1
UMATIC DRILLING MACHINE 1
MIXER 1
MANPOWER
PROJECT MANAGER 1
PROJECT SUPERVISOR 2
EQUIPMENT CONTROLLER 1
BACKHOE OPERATOR/HELPER 4
DRILLING HELPER 4
SHOTCRETING OPERATOR 2
GROUTING OPERATOR 2
TRIMMER 4
DUMPTRUCK DRIVER 40
HELPER 10
METHODS - EXCAVATION
Prepare excavation and conduct decommissioning activities according
to standards and specifications of authorities concerned.
Removal (clearing) and stockpiling of top soil loading by backhoe
excavators to dump trucks for proper disposal.
Cut works and excavation works will commence, Works shall include side
cutting, shoveling and stockpiling works at designated area accessible to
dump trucks. All side cuts and works will be done on a sloping manner
to avoid any erosion and/or cave-ins.
All excavation works will be done on a daytime schedule while hauling
works will be scheduled during night time, maintaining a minimum target
of Seventy to Eighty (40-60) truckload per night.
3.0
Concrete pavement
6.0
TEMP.SITE OFFICE
GATE
METHODS – EXCAVATION – PHASING SCHEDULE
PHASE 2 PHASE 1
9,360cu.m. 23,040cu.m.
METHODS – EXCAVATION – SUMPPIT/PUMP LOCATION
Description: