Professional Documents
Culture Documents
Tender Brief (Complex) Version April 11 Web120221
Tender Brief (Complex) Version April 11 Web120221
Consultancy Services
Consultant Type: ….
Tender No. …
CONTENTS
Introduction.......................................................................................................1
442500923.doc
2
442500923.doc
1
Introduction
The role of the Department of Health is “to enhance and protect the health and well-being of all
Victorians”. The Department delivers health care services through the public hospital system, community
based services and ambulance services, aged care and mental health services, directly and via funded
agencies. The Department seeks the provision of facilities which meet service requirements and which
provide value for money, while conforming to Government policies and probity requirements.
Capital Projects & Service Planning Branch (CPSP) manages or assists in the development of capital
projects to support the delivery of health services.
These Health projects require construction related consulting services. Requirements for the provision of
these services for this project are set out in this document as follows:
Section A: Project Specific Details
Section B: Standard Consultant Brief and Services (covering all consultant types)
2
1 The Client
1.1 Client
The Client will be the Department of Health and for all phases of the project, the Client will be represented
by a Project Control Group.
1.2 Principal
The Principal to the contract is the Secretary to the Department of Health.
2 The Project
2.1 Background
The CPSP Project Manager will include here a brief background to assist consultants in the preparation of
their tender. Background information may include details of the following:
Location of proposed project; history of current site, former site(s);
Relevant health region;
Existing health services;
Existing buildings;
History of additions to buildings or on the site;
Identification of new or updated service needs;
Completed preliminary studies, conclusions, outcomes;
Current state of development (example – Master Plan already prepared/not prepared)
442500923.doc
3
442500923.doc
4
Structural Engineers;
Hydraulic Engineers (cold water and sewerage);
Civil Engineers;
Fire Risk Assessment (safety audit);
Fire Safety Engineer;
Traffic Engineer; and
Building Certification Services Consultant
Quantity Surveyor (refer to Responsibilities of Consultants – 12.7)
Engineering and Services Consultants / Sub-Consultants (refer to Roles and
Responsibilities of Consultants – clause 12, sub-section 12.8: Engineering & other
Consultants, and other following sub-clauses):
Mechanical Engineers;
Electrical Engineers;
Hydraulic Engineers;
Communications and Security Engineers;
Fire Protection Services Consultants;
Lift Services Engineers
Sustainability (Environmental / Energy) Consultants#
442500923.doc
5
4.3 Warranty
The consultants will be required to warrant that the project design and documentation is fit-for-(the stated)
purpose, conforms to the objectives detailed in clause 2.2 above and meets the requirements of service
delivery set out by the service plan and this project specific brief.
4.5 Insurances
The consultants are to obtain and keep current for the duration of the project, Professional Indemnity
Insurance and Public Liability for amounts specified in Schedule 1 of the Agreement. Standard details of
insurances required are as follows:
442500923.doc
6
5 Program
The specific “Project Brief” will advise likely dates that the particular Consultancy will commence and be
completed. The project brief will also advise the anticipated date by which the handover of buildings
should be achieved.
The consultants are to provide a preliminary program to reflect these targets as part of their submission.
7 Proposal
7.1 Submission Inclusions
The consultant’s submission shall provide all information requested in this Project Brief.
7.1.1 General:
The submission shall include a response to each of the Selection Criteria in the order listed in clause 10
below.
The submission should include the following items to assist in consultant selection:
Methodology – provide a description of the manner in which the consultant would provide
the services as set out, including a proposed development program and reporting schedule
for the whole project.
Resources – nominate personnel to be assigned to the project; refer to sub-clause 7.4
below.
Resource availability – provide a clear affirmation confirming that the personnel nominated
in the submission would be available to be assigned to the project and would remain
available for the duration of the services. Where applicable, Table D in sub-clause 7.8
below is to be completed as part of the submission.
Referees - list of minimum 3 clients for whom the consultant(s) has recently carried out
similar consultancies, together with a contact for reference in each instance.
7.1.2 Fees.
Complying submissions shall have fee schedules set out in accordance with the format included in this
Project Brief. Where appropriate, the schedules shall be prepared for all consultant(s) including sub-
consultants (shown separately).
7.1.3 VIPP
The consultant’s attention is drawn to the Government’s Victorian Industry Participation Policy (VIPP).
The Policy applies to Government procurement activities for projects above the threshold values of $3
million or more in Metropolitan Melbourne and $1 million or more in Regional Victoria. The policy requires
a VIPP Plan certified by the Industry Capability Network Victoria Ltd (ICN) to be submitted as part of the
tendering and evaluation process. For consultancy engagements, where the tender amount (including
GST) is above the threshold values, tenderers must submit a Certified VIPP Plan to the Principal as part of
the Tender. Where the tender amount (including GST) is below the threshold values, this requirement
does not apply.
Tenderers are advised that the services of the Industry Capability Network Victoria (ICN) will be available
to assist them in implementing the policy in obtaining a certified VIPP plan to include with their tender
submission.
442500923.doc
7
Further information on the policy and templates are available on the Department of Innovation, Industry
and Regional Development (DIIRD) website www.diird.vic.gov.au/vipp
442500923.doc
8
7.4 Resources
The consultant’s submission for services shall nominate personnel to be assigned to the project. The
submission should also include a list of proposed sub-consultants, which contains such consultants’
professional experience. The submission should include the following for relevant consultant personnel,
and for each consultant and sub-consultant:
The names of the personnel who would be assigned to the project, their roles and
responsibilities, qualifications and other professional experience relevant to the conduct of
this study.
The person nominated to lead the team and the team’s clearly defined management
structure. The assigned staff together with allocation of time should be presented in the
consultant’s submission in a form as set out below: see Tables A, B and D.
442500923.doc
9
Table A:
Resource Rate Hours $ Allowance
(ex GST)
Director *
Team Leader *
Manager *
Consultant *
Admin *
Other
Other
Other
Total $
Table B
Resource Phase Phase Phase Phase Phase Phase Phase Phase Total Hours per
1 2 3 4 5 6 7 8 Resource
Hours Hours Hours Hours Hours Hours Hours Hours
Director *
Team Leader
*
Manager *
Consultant *
Other
Other
Other
Total Hours
per Phase
* Example titles only.
Note: Table B will not be used as any basis for the assessment of variations.
442500923.doc
10
A Phase 1
Phase 2
Phase 3 )%
Phase 4 )convert
Phase 5 )to $
Phase 6 )
Phase 7
Phase 8
B of Q )
Sub Total A (F + P)
[Fee based on building cost (estimated
TCC) of $ - see clause 6]
Aerial Photos
Asbestos Audit
Asset Management Plan
Attendance at VM/Design Review
BCA Modification
Building Permit Levy
Decanting
Environmental Survey
Fire Safety Audit
Risk Assessment
Geotechnical Assessment
Heritage Study
Business Case
Land Surveying
Presentation Model
Property Assessment
Prototype
Town Planning Permit
Design Review
Traffic Study
Video
Undertake Performance Based
Assessment
Other
Sub Total B
11
442500923.doc
12
Insert project status & timing Team Member 1 Team Member 2 Team Member 3 Team Member 4 Team Member 5 Team Member 6 Team Member 7 Team Member 8
(eg. In design documentation
Insert project name
due for completion Nov
2009.)
RESOURCE
COMMITMENTS (%)
CURRENT
TENDERS
Insert project name Insert phase(s) proposed Insert percentage of time proposed on current tender submissions
TOTAL TENDERED
8 Privacy Statement
The information provided in the consultant’s submission will, to the extent that it is not publicly available
information, be kept by the Department in accordance with the Information Privacy Principles under the
Information Privacy Act 2000. Please see the Privacy Policy Statement at www.health.vic.gov.au/privacy or
contact the Department’s Project Manager to request a hard copy by mail.
Each department must report summary details of all contracts in excess of $100,000 but less than $10
million on the Contracts Publishing System website.
Contracts over $10 million in value are to be disclosed in full on the Contracts Publishing System website,
subject to application of the exemption criteria in the Freedom of Information Act 1982.
For further information, refer to the Central Register of Major Government Contracts at
www.contracts.vic.gov.au.
9 Lodging of Submissions
Submissions should be clearly marked with the project identification details required by the Project Brief
and should clearly show the tender number. The tender submission should be delivered to the following
address:
Tender No. (include number)
Tender Box
The Department of Health
Mailroom, Basement Level 1 (B1)
50 Lonsdale Street
MELBOURNE VIC 3000
Submissions should be received no later than at the time and date indicated in the tender documents.
A4/A3 copies of the submission with their tender.
10 Selection Criteria
Assessment of detailed submissions will be against the Selection Criteria, to which weightings are shown
in the table below. The tender evaluation process will apply the weightings in a manner to ensure value
for money. The selection panel will short list consultants using the selection criteria then use the final
selection criteria, the fee proposal, to make a final selection:
Project Experience
The experience of the consulting organisation/group in working with or on a project of
this type, scale and environment.
Team / Management
The specific people to be engaged on the project; their experience (particularly in
relation to the projects mentioned for the above criterion), expertise and nominated
tasks; how they will be managed and coordinated. Consideration has to be given to the
consultant’s recognition of their responsibility to the project process.
Methodology / Approach
Having a sound understanding of the issues surrounding the particular project and
tailoring the sequence of activities to ensure that the desired project outcome is
achieved. Having identified critical activities and outputs. The ability to effectively
communicate key activities and steps to be performed. The ability to challenge and
promote lateral thought amongst all parties is an important consideration.
Program / Response
A demonstration that the consultants have an awareness of the time constraints placed
on the project, and having considered the particular timing issues relevant to the
project, have established the sequence of tasks and associated schedules necessary to
achieve any predetermined timelines.
Design Quality
Demonstrated ability to design and deliver facilities that support efficient service
delivery, are supportive of the needs of the various building occupants and visitors,
contribute to the creation of a high quality environment, are efficient to operate and
maintain and have the required flexibility to accommodate any planned or unplanned
future expansion or changes in use.
Environmental Performance
Demonstrate the consultant’s experience in the environmental performance of these
types of projects. Key performance elements are energy efficiency, water consumption,
waste management, material selection, biodiversity and indoor environment quality.
The consultant’s tender should address the following:
1. How are the sustainability goals and targets established?
2. What are appropriate performance indicators and monitoring methods?
3. How are Environmental benefits of options established?
442500923.doc
15
Client Focus
Competency in addressing client issues and concerns.
The ability of the client to elicit a cooperative and valuable contribution from the client.
Quality Assurance
A demonstration that the consultant has processes in place to ensure that the required
documents conform to the brief.
The tender submission should address if the consultant’s organisation has in place a
quality management system; the nature of the quality management system; details of
any other quality assurance procedures the consultant’s organisation would put in place
for the project.
Insurance Mandatory
Please provide the information as indicated below on your company’s public liability and
professional indemnity insurance arrangements.
Name of Insurer
Policy Number(s)
Expiry Date
Limit of Liability.
References Mandatory
Normally three referees should be provided to support the submission in relation to the
type of work/role envisaged.
Compliance Mandatory
Acknowledgement that the consultant is prepared to sign the Department’s Standard
Contract - refer to sub-clause 4.1 above.
442500923.doc
16
Fee Inclusions
Scope of services included in the fee proposal and the appropriateness of the quoted
amount to enable optimum service provision for the client.
442500923.doc
17
B: Bushfire provisions.
Consultants are to prepare designs and documentation in accordance with Ministerial Direction No. 3
– Bushfire provisions for buildings of a public nature issued under the Project Development and
Construction Management Act 1994.
Application of the Ministerial Direction will ensure that a bushfire attack level risk assessment, based
on the methods in AS 3959-2009 Construction of buildings in bushfire prone areas, is incorporated
into the design and documentation process.
The bushfire attack level risk assessment is to be conducted by a suitably qualified practitioner, which
can include a specifically trained registered building practitioner. The assessment applies to new
construction, rebuilding, alterations and additions, requiring one or more building permits.
Bushfire attack level risk assessments are, by their nature, a broad indicator only. Some design
attention may still be required in instances of low risk assessment, taking into consideration
surrounding conditions and potential threat, particularly from ember attack.
The risk level may be reduced / minimised by site maintenance and management arrangements, such
as appropriate landscaping and planting, and regular fuel reduction practices. Consultants should
therefore incorporate such non-building related measures into their design treatments.
18
Physical Assessment
Undertake a physical assessment of the assets including buildings and engineering services of the
existing facility. This will identify the general construction, finish and condition of the principal internal
and external elements together with a general analysis of the existing engineering services. The
strengths and deficiencies of the buildings and infrastructure should be highlighted. Alternatively,
confirm / modify the findings of any existing assessments.
Fire Safety and Risk Assessment - for buildings subject to Fire Risk Management (FRM)
Guidelines
A fire safety and risk assessment report is to be provided where proposed capital works may be
impacting on life safety to a client accommodation area of the facility. These works may be in the
building providing the client accommodation or in an ancillary building that may be a fire source
feature that can indirectly pose a fire risk to the occupants.
Fire safety and risk assessment is to be carried out by a qualified fire safety engineer. Building
practitioners registered in Victoria in the class of fire safety engineer and building surveyor may carry
out the fire safety and risk assessment to ascertain the adequacy and appropriateness of
management and fire precautions systems for the well being of clients and staff. In particular, fire
safety recommendations are to be part of a single integrated fire safety system throughout the site.
The department’s fire risk management strategy requires the consultant to determine priority works
necessary to meet the objectives of the Capital Development Guidelines for Fire Risk Management
(Series 7).
For existing buildings identification of fire hazards and immediate fire safety precautions is to be
undertaken in accordance with relevant codes and departmental guidelines (refer to Fire Risk
Management guidelines)..
The fire safety engineer will be expected to review options and provide advice at the master
plan/feasibility study stage and be involved in all stages of the design and documentation phases. The
fire safety engineer is to sign off that the documentation encapsulates the intent of the fire safety
report recommendations that were developed in accordance with the departmental Fire Risk
Management guidelines.
Functional Assessment
Undertake an assessment of the functional condition of each building and identify those areas which
affect the delivery of agreed services. This should be done in terms of both functional suitability and
functional adaptability. Alternatively, confirm / modify the findings of any existing assessments.
442500923.doc
19
Functional Brief
Schedule the requirements for pedestrian and vehicular access, car parking and any special
requirements as identified in the brief.
Associated Works
Describe any additional works which may be associated with the development of the project (eg. site
services, landscaping, demolition, temporary accommodation, etc.).
Engineering Services
Ascertain future service needs and assess existing services against their adequacy and
appropriateness to current and future needs, in particular fire safety requirements. Develop options for
meeting future service needs, with emphasis on solutions that are cost effective, readily maintained,
flexible and can be implemented with minimal disruption. Particular attention has to be given to energy
usage and performance. Alternative energy systems should be examined.
Project Confirmation
Develop and examine the proposal for the works to the point where the physical, operational and
financial parameters are identified and the proposal can be confirmed as the most appropriate scope
of work (to Cost Plan A level). It is then to be presented to the PCG for consideration and assessment.
Typical documentation required at the completion of this stage is as set out in the Department’s
Masterplan Report Checklist.
Approval is required before proceeding to the next phase.
442500923.doc
20
442500923.doc
21
442500923.doc
22
Typical documentation required at the completion of this stage is as set out in the Department’s
Design Development Report Checklist and should be based on the approved Schematic Design
developed in more detail. It will include but not necessarily be limited to the following:
Asset Management Plan (including items listed below)
Building Services including plant, reticulation, monitoring and control systems.
Construction sections (1:50) for facade, perimeter wall sections showing finishes at
junctions of walls and floors, ceilings, etc.
Coordinated reflected ceiling plans (1:100).
Developed Room Layouts (1:50).
Equipment Briefing Schedules.
Lift, stair and riser details (1:50).
Plans, Sections and Elevations (1:100).
Roof layout and drainage details.
Room Data Sheets.
Site Plan.
Siteworks and Landscaping layouts.
Review & confirm Cost Plan C (including life cycle & recurrent costs / square meter)
Description of the project operations in terms of :
- users’ performance requirements (eg low maintenance and low energy
consumption)
- design parameters (eg architectural / engineering capacity of structure and
systems).
Note: The Asset (or Facility) Management Plan is to be prepared to enable the facility to be managed
across its operational life. The Plan will include, but not be limited to
an asset register including age, condition, value and supplier data
operating plan(s) (including cleaning, energy and hotel services)
maintenance plan(s) (including replacement / refurbishment schedules)
compliance issues eg maintenance of essential services
projected costs for annual (recurrent/ongoing) requirements, eg. energy or cleaning,
and anticipated costs for the life cycle of the facility eg major plant or refurbishment of
systems.
Approval of the PCG is required before proceeding to Phase 5.
442500923.doc
23
Cost Plan D
Specification.
Tenderer’s Brief.
Working Drawings.
Program of key milestone dates.
442500923.doc
24
Overview
1. All consultants are to liaise with the PCG through the Department’s Project Manager.
2. Consultants are engaged to facilitate the planning and development of physical facilities to
provide health, aged care or mental health services for the Department of Health. All
consultants are to work as a consultant team to plan and deliver the stated facility.
3. The general responsibilities of consultants with respect to meeting attendance and reporting
requirements are set out in this sub-clause.
4. For a more detailed general description of the scope of the services required and the
responsibilities of the particular consultant, refer to the sub-clause relevant to the consultant’s
discipline.
Meeting Attendance
5. All consultants are required to attend regular (eg fortnightly) meetings throughout each phase of
the project. Meetings they are expected to attend include but are not necessarily limited to:
Consultant Team meetings
Design and Sustainability Principles Briefing
Design Team meetings
Design Review Workshops (including Peer Reviews for larger or more complex projects)
User Group meetings
Contractor’s meetings
Project Control Group meetings.
442500923.doc
25
Design Review
9. All consultants are required to prepare information for briefings and participate in Design
Reviews as required by the Project Manager or Principal Consultant. Design Reviews for larger
or more complex projects may include peer review.
Contractor’s Meeting
13. Consultant Team meetings and Design Team meetings are replaced by Contractor’s meetings
when construction commences. All consultants must attend as required by the Superintendent.
This is generally for the duration of the contract administration phase for their area of
responsibility. The Quantity Surveyor is to attend all Contractor’s meetings. The meetings are
chaired and minuted by the Contractor and held on site if feasible.
Reporting Requirements
15. All consultants must prepare monthly progress reports (generally no more than 3 pages in
length) for inclusion in the Project Manager’s Monthly Report to the Project Control Group. The
consultant’s progress report should include a brief summary of the status of the work and
outline any key issues or critical decisions to be made regarding their area of responsibility.
The Monthly Report must be in the format as set out by the Department’s guideline document.
442500923.doc
26
Management
3. Assume overall responsibility for the management and co-ordination of all development aspects
of the Project during the design, documentation, construction, equipping and commissioning
stages. During these stages, the Project Manager will be responsible for the overall
management of other consultants appointed by the Department or agency, with respect to
project matters. This will include an oversee and review role to ensure that relevant data is
provided to the PCG including:
Asset Management Plan reports
Business Planning
Functional Briefing
Business Case progress reports
Monthly reports
Design Reviews
The Project Manager will be responsible for co-ordination, consolidation and preparation of all
material required in the above reports, studies etc. in accordance with the Capital Development
Guidelines.
Liaison
9. Attend all meetings of the PCG, prepare agenda, record minutes and prepare monthly report
and circulate. Provide hard copies at meetings as appropriate. Recommend and advise on all
matters relating to the project and follow up as required.
10. The Project Manager is to:
Arrange and chair such progress meetings as are necessary for satisfactory co-ordination of
the work with user groups, consultants, contractor, sub-contractors and suppliers etc.
Report, recommend and advise on matters relating to the construction aspects of the project
for the Project Control Group.
Be involved in coordinating any opening ceremonies or media during the project in
association with the PCG and Project Co-ordinator.
442500923.doc
27
Work with the Centre and the contractor to ensure the commissioning and smooth occupancy
of the facility on a staged basis.
11. Ensure all statutory requirements are complied with and approvals are obtained as necessary
from Government, local Government and other authorities and bodies having jurisdiction over
the Project within the required time frame. Obtain modifications to the building regulations when
required.
12. Motivate and co-ordinate the work of the Principal Consultant and associated sub-consultants,
Quantity Surveyor and other specialist groups.
Reporting
13. Report to the PCG at monthly intervals or as required on:
Expenditure against budget and estimated cost to completion.
Actual progress compared with original program and work still to be completed.
Design and scope changes and change proposals.
Variations.
Issues.
14. Prepare detailed reports and regularly update program schedules, monitor future activities in
keeping with the requirements of the Master Project Program. Make recommendations on
activities to be expedited to meet predetermined completion dates.
15. Advise the PCG as necessary at all times on public and community relations and industrial
relations in relation to the project. The Project Manager will assist in arranging and providing
appropriate publicity and promotional material as required.
16. Prepare a detailed Asset Management Plan report including major plant update program
schedules, benchmark data for use in monitoring future asset performance and identification of
key activities to be undertaken to prepare facility budgets and strategic plans to meet service
delivery requirements and corporate / business plans. Inputs, for example costing, upgrade
&/or replacement and life cycles, an updated Asset Assessment workbook to reflect the “as-
built” configuration of the site, its buildings and the services, are to be provided by relevant
consultants, eg engineers and quantity surveyors.
Budget
17. Establish, through the Quantity Surveyor, costing systems to continuously monitor the
expenditure to provide feedback to the PCG and ensure that regular updated cash flow
requirements are prepared including:
Review and report on all payments.
Contingencies for design and construction.
Project variations and impact on approved budget.
18. Ensure that the budget is prepared for the Project by the Quantity Surveyor including accurate
cash flow projections. Arrange to re-examine and revise as necessary for cost control purposes.
19. Establish procedures regarding the issuing of variations and feedback to the Project Control
Group of the overall cost budget position; produce costs-to-completion information regularly
and keep the PCG fully informed. Prepare submissions for approval of variations by the PCG in
accordance with the relevant delegation.
20. Check that the design(s) produced complies with the overall cost budget and ensure that
consultants consider such items as cost efficiency in operation and maintenance. Ensure
adequate provisions are made for the most effective form of building services and future
requirements. Demonstrate the various options, and energy saving measures.
21. Ensure that all final accounts are dealt with according to the contract conditions and that all
claims are settled.
442500923.doc
28
Program
22. Develop the master program for the Project from the planning stage to final completion
identifying all critical target dates and milestones to meet the established completion dates.
This program will identify the priorities and any constraints that could interfere with the
achievement of the program. Ensure the program is sensitive to and incorporates appropriate
timelines for the service provision redevelopment tasks set out by the Agency/ Network.
23. Assess all planning, design and pre-tender construction programs as well as implementation
alternatives and regularly update the Master Program comparing it to current status for the
design, documentation, tender, construction and commissioning of all stages and communicate
to all parties.
24. Monitor design information flow and PCG approvals and ensure that program requirements are
being achieved.
25. Advise the Contractor of program procedures and requirements and ensure that program
requirements are being achieved including:
Monitor design information flow and PCG approvals.
Monitoring of all off-site activities, including necessary shop drawings.
Ensure that material is available, and orders are initiated on the Principal’s behalf for long
lead times items such as materials, plant and equipment.
Monitoring manufacturers’ progress in design, fabrication and delivery.
26. Identify problems and anticipate problems with contractor and sub-contractors, and take such
measures as are necessary to resolve these equitably. Fully report all potential delays to the
PCG.
Consultants
27. Advise on the scope and content of work to be undertaken by Consultants, also other Specialist
services which may be required, and assist in the selection, negotiations and agreement of
Consultant’s professional services engagements. Update and maintain in association with the
PCG the detailed briefs relevant to the particular consultant disciplines.
28. Direct and administer the work of the Consultant Team members, including the certification of
their accounts for payment by the PCG.
Tendering
29. Advise on alternative methods available for the construction of new and refurbished facilities
and the various contractual methods that could be utilised. Consider procedures for selection
and appointment of Contractors in conjunction with the PCG including the form of tendering,
form of contract, terms of payment and degree of sub-contracting required.
30. In association with the Architect and Quantity Surveyor, assist in the briefing, selection and
appointment process. This may involve a two stage process to call for expressions of interest
from which will be drawn a recommended list of Contractors who will be invited to tender on the
main contract subject to the PCG’s approval.
31. Assist in the calling and evaluation of tenders by participation on the selection panel. Make
sure all compliance requirements are addressed eg VIPP; prepare reports supporting
recommendations to the PCG regarding the appointment of the Contractor, subcontractors and
suppliers.
32. See that the contract documents are properly executed before work starts on site. Ensure that
the Contractor, any subcontractor and supplier have complied with statutory, insurance, and the
Code of Practice requirements and are fully aware of security requirements necessary during
the construction phase.
Contractual
33. Act as Superintendent under the construction contract and ensure the issuing of all certificates
required under the Conditions of Contract including certificates of Practical and Final
442500923.doc
29
Completion at the appropriate time and ratify any payments required and perform all duties
within prescribed times and limits set out in the contract.
34. Appoint Superintendent’s representatives where necessary or appropriate. Ensure
responsibilities are clearly defined.
35. Ensure that site possession will be available when required (advise on the site requirements
including the prior checking of any insurance, security, legal or planning restrictions affecting
the site).
36. Be registered as a ‘Building Practitioner’ or suitable equivalent under the Building Act and
ensure consultants and contractors be ‘Registered Building Practitioners’ or suitable equivalent
as required by the Building Act and carry appropriate professional indemnity and insurance.
37. Advise the PCG when:
Certificates of Practical Completion and Final Certificates are to be issued to allow the PCG to
first have the opportunity to inspect the works.
The Project or part of the Project is fit for use, occupation, client and/or training purposes.
38. Ensure provision of suitable prototypes of various components as required for assessment and
approval prior to full implementation in works.
39. Place orders on behalf of the Principal and negotiate and agree the scope of works relating to
public utilities, Statutory Authorities and other bodies having jurisdiction over the works to
ensure their works accord to program requirements, where these are not Contractors
responsibility.
40. Investigate and resolve any adjacent owner/occupier situations, preservation orders, rights of
way or easements. Ensure that the statutory authorities can provide the basic services
required.
41. Arrange site meetings as required to review progress of the Project construction and for the
purpose of discussing technical and financial matters arising from the Project. The Project
Manager will arrange issue of minutes (normally prepared by the contractor) of these meetings,
accurately recording all matters discussed and resolved and these shall be tabled for formal
acceptance at the subsequent meetings.
Quality Assurance
42. Undertake assessment of issues of ongoing asset management, minimising recurrent costs and
maximising energy efficiency principles. Co-ordinate and undertake design review processes as
required for the Project Control Group.
43. Ensure that all quality control and testing requirements are clearly established and
documented. Prepare an appropriate quality plan for the project in consultation with all other
consultants. Establish the Project requirements on such matters as professional accountability,
liquidated damages, insurance requirements, compliance with Government regulations in
relation to quality assurance and tendering.
44. Oversee the completion of design and contract documents for tendering are in accordance with
the agreed project quality plan and warrant that they are checked, coordinated and
comprehensive.
45. Review the works during the defects liability period and inspect with the Architect at the
expiration of this time. Recommend the release of retentions or other form of (bank) guarantee
at the expiration of defects liability period.
46. Ensure that adequate access is provided to service installations for maintenance and future
replacement.
Commissioning
47. Ensure that documentation of all specified or necessary construction and equipment, operating
manuals and as built drawings, including plans, elevations and details, are supplied in hard
copy and electronic format to the Principal. The Department also requires the provision of an
updated Asset Assessment workbook (initially completed during master planning) to reflect the
442500923.doc
30
“as-built” configuration of the site, its buildings, the facility’s services and the breakdown of its
Gross Floor Area according to the Health Planning Units Naming Conventions.
48. Ensure ‘plain English’ guides are prepared for all components and the commissioning program.
This is to include operational and maintenance contracts that form the basis of managing the
project.
49. Arrange for the preparation of equipment and furniture schedules including the tendering,
ordering, confirmation of receipt, final placement and performance testing of all reusable and
new items in preparation for handover to the Agency.
50. Ensure that all required pre-commissioning checks are carried out as necessary for the plant,
equipment and buildings. Arrange for training, additional commissioning, testing and
implementation phasing to suit the requirements of the users in order to ensure efficient
operation of the plant, equipment and buildings.
51. Ensure adequate provision of consultant services to cover commissioning issues and to allow
corrective measures to be undertaken in order that handover of buildings can be carried out in
an efficient manner.
Review
52. Evaluate the various planning and operational options available to the Network/Agency a
functional, cost and time oriented view. Recognise and report on capital and recurrent cost
ramifications with appropriate recommendation to the Network/Agency and the Department.
53. Co-ordinate and undertake Design review(s) as required by the PCG including provision of an
independent Design Review facilitator, planning consultant/technical adviser or other support as
required. Follow up on action plans resulting from the Design Review.
54. Ensure that appropriate equipment and plant operational policies are developed for
Network/Agency services with recurrent costs at sustainable levels of funding.
55. Review and develop procedures for monitoring defects liabilities.
56. Ensure the preparation and development of an Asset Management Plan for long term operation
of the facility. Ensure the maintenance and technical operating manuals are suitable for the
task and supplied in both hard and electronic copy.
57. Plan, co-ordinate and arrange a Post Occupancy Evaluation of the completed Centre at a time
suitable to the Project Control Group, normally at the end of defects liability period.
58. Advise the PCG on other matters associated with the capital redevelopment of the Centre as
detailed in the Master Plan but not limited to the use of the balance of the site.
Resourcing
59. Ensure that the Consultants and Contractors make adequate personnel available for the fully
professional execution of their obligations, both within the design and implementation areas.
442500923.doc
31
Scope of Services
2. Generally, in respect of the project: prepare proposals, plans and reports; supply copies of
plans and other relevant documents; evaluate information; attend meetings; recommend
payments; prepare and supply “as built” documentation; respond to management requests.
3. Initiate, evaluate and recommend design and construction variations to the project.
Attendance at Meetings
4. The Architect is required to:
Attend meetings of the Project Design and Construction Team, attend user group meetings
and attend meetings of the PCG to report and advise on the project on a regular basis;
For general meeting attendance requirements for the Architect, reference should be made to
the requirements for “All Consultants” in 12.2 above;
Reporting Requirements
5. Reporting responsibilities include:
Preparation of all reports including development reports, equipment lists, as built drawings,
asset management plans, post occupancy evaluation and other reports as required;
For the preparation of monthly reports: reference should be made to the requirements for “All
Consultants” in 12.2 above;
Phase Responsibilities
Master Planning
6. During the Master Planning stage, the responsibilities will be to:
Examine existing conditions; research and investigate for relevant information; determine
influences which may affect the proposed works;
Where existing assets are being upgraded or redeveloped, prepare an Asset Assessment
workbook to reflect the configuration of the site, its buildings, the facility’s services and the
breakdown of its Gross Floor Area according to the Health Planning Units Naming
Conventions.
Formulate strategies; consider energy efficiency in proposed design decisions; consider the
performance requirements set out in the Building Code of Australia, Part J, in anticipation of
the preparation of certificates;
Develop and prepare design proposals and options appropriate to the brief which conform to
current building regulations and planning requirements;
Present recommended design proposals in clear and co-ordinated format together with
appropriate reports
Feasibility Study
7. During the feasibility study:
Further develop design proposals;
Carry out a comprehensive assessment of possible alternative solutions;
442500923.doc
32
Design Review
8. During any review stage:
Participate in Design Reviews and any other reviews;
Prepare relevant documentation for presentation by the review team;
Schematic Design
9. During the Schematic Design stage:
Develop the recommended design to preliminary sketch plan stage;
Review and confirm scope and approved budget with consultant team
Ensure that the proposed designs from engineering and other disciplines conform to the brief;
Check that the design conforms to government regulations;
Prepare report to the PCG on progress, including advice on time, cost and quality
implications;
Business Case
10. During the Business Case development:
Prepare and develop suitable descriptive text describing the assessment and reporting on the
viability of options to assist the Quantity Surveyor in the preparation of relevant cost
information.
Prepare any required architectural information in a suitable form to be included in relevant
business case documentation, to enhance the business planning, evaluation and design
review assessment components of the business case, in a form that accords with
government and departmental guidelines.
Design Development
11. Design Development responsibilities of the Architect during this stage are:
Prepare Architectural plans, sections, elevations and 3D CAD drawings further developing the
design approved by the PCG;
Co-ordinate the development of associated mechanical, structural, electrical and other
engineering disciplines to conform to the brief and the approved design;
Commence the preparation of the specification and contract documentation;
Commence the preparation of Part J certificates for the building fabric (J1), glazing (J2),
building sealing (J3) and access for maintenance (Building fabric & Glazing); co-ordinate
the preparation of Part J certificates from the Services consultant for parts J4, J5, J6 and
J8;
Initiate preparation of equipment and furniture lists as appropriate;
Assist the Quantity Surveyor in monitoring of key decisions made in each discipline in terms
of their impact on capital costs of the project;
Ensure resolution of all outstanding design issues;
Identify optional items for inclusion in the project;
Present documentation to enable the PCG to approve completion of DD phase;
442500923.doc
33
Contract Documentation
12. The responsibilities of the Architect in the Contract Documentation Stage shall include the
following:
Complete the preparation of all architectural plans, sections, elevations, 3D CAD drawings
and details in clear and co-ordinated format, to enable the construction contractor to
efficiently implement the work;
Co-ordinate the completion of appropriate documentation from engineering disciplines and
other appropriate consultants;
Complete the preparation of the specification;
Complete the preparation and co-ordination of all Part J certificates to satisfy the “deemed to
satisfy” provisions; where the design of any component fails to achieve the “deemed to
satisfy” provisions, assist the ESD consultant to undertake performance based assessment;
Prepare contract documentation to enable tendering to proceed;
Supply to the nominated DH (CPSP) Project Manager, copies as requested in pdf format or
CAD format on disc, of A3/A4 floor plans, sections, elevations, 3D drawings, details,
specifications and other appropriate documents, at pre-tender phase. Hard copies shall
also be supplied as requested.
Construction
14. During project construction the Architect is to:
Provide advice, explanation and elaboration on the intent of the documented design;
Provide advice on acceptable alternatives to the design, layout, finishes and standard of
finish; and
Provide recommendations on payments to sub-consultants, contractors and suppliers where
requested.
442500923.doc
34
furniture, finishes and equipment schedules are to be provided in Microsoft excel format, set
out in a format suitable for the client to include on the asset register (eg description of the
item, date of purchase, model / make Nos., value, expected life, location);
the data on each disc is to include a complete list of all items, with the items on that particular
disc highlighted; and
all discs are to be clearly labelled with the project name, consultant or sub-consultant’s name,
practical completion date, CAD format information, disc name indicating flow plan, etc.
16. “As Built” drawings shall be based on information provided by contractors and verified wherever
possible by consultants, with particular attention to building services.
Asset Management
17. Should Building Information Modelling (BIM) be used in the documentation of the project, the
Architect shall hand over a copy of the “Contract Documentation” Model for use by the
Department of Health and its Agencies.
18. Ensure that an updated Asset Assessment workbook (initially completed during master
planning) is prepared to reflect the “as-built” configuration of the site, its buildings, the facility’s
services and the breakdown of its Gross Floor Area according to the Health Planning Units
Naming Conventions.
442500923.doc
35
442500923.doc
36
442500923.doc
37
Scope of Services
3 The Quantity Surveyor is required to:
Establish and maintain cost planning services for all stages of project development;
Maintain quality control systems that ensure all information and documentation provided is
complete, comprehensive, up to date, checked and coordinated;
Prepare financial analyses for the project in accordance with professional best practice and
with the Department’s requirements for benchmarking of projects;
Develop and update the project budget;
Provide the Project Control Group with regular updated estimates of project cost based on
the evolution of design and construction documentation;
Provide the Project Control Group with Cash Flows for the project;
Provide the Project Control Group with progressive statements of costs against the
anticipated final cost of the project and advise on methods to maintain agreed budgets as
required;
Prepare detailed financial analyses indicating capital and recurrent facility costs of
proposed building and services systems;
Prepare a detailed analysis of life cycle costs and recurrent facility operating costs of the
project for the following key stages:
- Business case;
- Schematic design (Cost Plan C);
- Tender Documentation Cost Plan D; and
- As built.
The detailed analyses shall be prepared in accordance with AS/NZ Standard 4536:1999
Life Cycle Costing—An Application Guide. The prepared material should be developed in
greater detail as the phases of the project progress. The resultant material should be
sufficient to enable the operating body to determine an operational budget, maintain an
asset register, depreciation of the assets and replacement costs for insurance purposes;
Prepare, process and make recommendations to the Project Control group concerning
payment of all accounts on the project;
Measure, value and negotiate the cost of claims to the contract, construction variations or
extensions of time and advise the Project Control Group;
Advise the Project Control Group on the status of contingency;
Advise the Project Control Group of costs associated with a change of scope or client
initiated requirements; and
Advise on the release of Bank Guarantees or other forms of security approved by the
Department.
Attendance at Meetings
4 The Quantity Surveyor is required to attend regular meetings throughout the course of the
project. For general meeting attendance requirements for the Quantity Surveyor, refer to the
requirements for “All Consultants” in 12.2 above.
442500923.doc
38
Reporting Requirements
5 The Quantity Surveyor is to provide the Project Control Group with formal reports throughout
the project. The minimum formal reports expected to be prepared by the Quantity Surveyor are:
Cost Plan A
Cost Plan B
Cost Plan C
Cost Plan D
Progress Cost reports
Final Costs
Cash Flows
Cost Analysis
Bills of Quantities
6 All Cost Plans prepared by the Quantity Surveyor must comply with the Australian Institute of
Quantity Surveyors’ “Australian Cost Management Manual” (based on the National Public
Work’s Council Cost Control Manual) and meet the Department’s requirements for
benchmarking purposes. The Cost Plans must separately identify allowances for:
Consultants’ fees
Design contingency
Prototypes
Site works (including landscaping and decontamination)
Building works and services
Furniture and equipment (on a groups 1, 2 and 3 basis).
Statutory and authority charges
Construction contingency
Cost escalation, prolongation and GST
Specialised equipment (eg security/bio-medical)
Design Review
7 The Quantity Surveyor participates in Design Reviews. During these reviews, the Quantity
Surveyor’s role is to:
Prepare briefing information on financial aspects of the project for participants;
Assist in the development of selected ideas generated in the Design Review into
working solutions;
Take follow up actions with the consultant team and key stakeholders.
Phase Responsibilities
Master Planning
9 During Master Planning, the Quantity Surveyor is to:
Prepare Cost Plan A based on Functional Areas, identifying the capital, recurrent (including
energy and maintenance) and operational costs of the project facility.
442500923.doc
39
Prepare benchmarks that allow Cost Plan A to be evaluated against comparable projects on
an area per unit, output (eg WEIS) and/or functional area basis or as otherwise required by
the Department.
Continuously monitor and assess key decisions and plans as they develop, to ensure they
conform to the scope of work and budget for the project.
Advise the Project Manager and the Consultant Team members of cost reduction options
as required to maintain the project within budget.
Prepare a Project Cash Flow outlining projected monthly requirements for the separate
project categories.
Feasibility Study
10 During the feasibility study the Quantity Surveyor is to:
Prepare a full cost analysis that examines capital, recurrent and life cycle costs for each
option developed for the project.
Prepare Cost Plan B for the preferred development option for inclusion in the Feasibility
Study Report to be produced by the project Architect. Cost Plan B is to reflect the general
project description, the service plan and features of the property. It is to be prepared on an
elemental basis and include all costs associated with the project.
Identify reasons for any major discrepancies from the project budget at the end of the
feasibility study and advise the Project Control Group on methods to maintain agreed
budgets.
Schematic Design
11 During the schematic design stage the Quantity Surveyor is to:
Monitor and assess all design decisions in terms of their impact on the capital and recurrent
costs of the project.
Monitor total costs and advise the Project Control Group on methods to maintain agreed
budgets.
Review and report to the Project Control Group and Project Manager on engineering
services specifications and engineering services cost estimates, as they are produced by
the engineering services consultants.
Develop detailed elemental breakdowns for all costs associated with the project into Cost
Plan C1 to set the Total End Cost (TEC) for the project. Cost Plan C1 is to be incorporated
into the Schematic Design report produced by the Project Architect.
Provide an initial report of recurrent operating costs of the project based on approximate
estimates once the building services systems are selected and the project budget set.
Business Case
12 During the Business Case process, the Quantity Surveyor is to assess and report on the
viability of options in accordance with Department of Treasury and Finance requirements (i.e. in
terms of net present value in cost per unit of output) or as otherwise directed by the Project
Control Group.
Design Development
13 During design development the Quantity Surveyor is to:
Monitor and assess key decisions made in each discipline in terms of their impact on
capital and recurrent costs of the project.
Identify responsibility for financial matters associated with special facilities and equipment.
14 At the completion of design development, the Quantity Surveyor is to:
Prepare Cost Plan C2 in consultation with all other consultants. Cost Plan C2 is to be
categorised both departmentally and elementally and incorporated into the Design
Development Report for the project.
442500923.doc
40
Highlight any departures from Cost Plan C1 and advise the Project Control Group on
methods to maintain agreed budgets.
Report to the Project Control Group and Project Manager on engineering services
specifications and engineering services cost estimates as they are produced by the
engineering services consultants.
Provide the Project Control Group with a report on the recurrent operating costs of the
project.
Contract Documentation
15 During contract documentation the Quantity Surveyor is to:
Incorporate the specifications and documentations produced by consultant team members
into pre-tender estimates and Bills of Quantities (if required) in accordance with AIQS
Standard Method of Measurement.
Establish a construction documentation programme with the superintendent to ensure
tender documentation is available for costing two weeks prior to the date of tender.
Ensure that all documents produced are checked and coordinated.
Monitor construction documentation and advise the Project Control Group of any changes
from tender documentation likely to have a significant impact on capital or recurrent costs of
the project.
Prepare Cost Plan D against the project budget and time frames. It must be based on
accurate assessments of marketplace cost conditions and predictions for time related costs
such as escalation (Cost Plan D is used to assess received tenders).
Review all pre tender estimates to ensure they do not exceed the approved budget.
Identify and sign off contingent liabilities at the completion of tender documentation.
Establish contract administration procedures with the Superintendent for proper handling of
issues such as variations that arise throughout the project.
Construction
17 During project construction the Quantity Surveyor is to:
Assess the status of work on the project.
Make monthly checks of claims for progress payments from the Contractor and make
recommendations to the Superintendent regarding payment.
Independently price all proposed variations prior to claim by the Contractor and make
recommendations to the Superintendent regarding payment.
Review any claims for extensions of time where costs are incurred and make
recommendations to the Superintendent regarding payment.
Prepare monthly Financial Reports for inclusion in the monthly Project Team Report to the
Project Control Group. The Financial Report must detail Budgets, Commitments (contracts
let), Contingencies and Expenditures across all project areas and contracts for the project,
442500923.doc
41
the status of all variations, both approved and pending, and monitor the project
contingencies. Financial information regarding fees and loose furniture and equipment to be
included in the Financial Report is provided to the Quantity Surveyor by the Superintendent.
Advise the Project Control Group of any unforeseen or potential cost impacts on the
project.
Provide end of financial year reconciliations against the project budget.
Prepare the Final Account with input from the Superintendent.
Reconcile final project costings.
Prepare a statement of the breakdown of final costs into Asset Components as defined in
the Victorian Department of Treasury and Finance directive FRD 103. (This document is
available by contacting the CP&SP Project Manager).
Prepare an interim financial statement of such component allocation, as at the date the
facility becomes operational.
Prepare the final statement when the project reaches financial closure.
442500923.doc
42
442500923.doc
43
442500923.doc
44
Advise on the selection, installation and type of services to any specialist equipment.
Contribute to the preparation of Business Case reports, tender documents, asset register,
operation and maintenance plan and energy management plan.
Prepare the design and documentation of the services systems to ensure that the systems
are low maintenance, have low energy requirements and comply with any energy efficiency
requirements of the Government of Victoria as well as any energy efficiency requirements
of the Building Code of Australia. (Any project seeking exemption is to be considered by the
Director, CPSP or Manager of Standards, CPSP.)
Prepare a BCA Part J certificate for the following components:
- Air movement (Deemed to Satisfy and Performance Based);
- Air conditioning (Deemed to Satisfy and Performance Based); and
- Access for maintenance (Building Services) (Deemed to Satisfy and Performance
Based).
Advise on acoustic treatment to various locations, including rooms, corridors plant rooms,
etc, to minimise noise, especially plant room noise or vibrations; advise on the engagement
of a specialist acoustic consultant as appropriate.
Administer the mechanical services components of the work during the construction stage
and issue the relevant completion certificates as required.
Monitor and check the work of each sub-consultant if relevant.
Maintain quality control systems that ensure all information and documentation provided is
complete, comprehensive, up to date, checked and coordinated.
Liaise with the Project Manager, Principal Consultant and other consultants throughout all
phases of the project.
3. The more specific responsibilities of mechanical engineers are to:
Analyse environmental and functional requirements as well as performance standards to be
met by systems.
Identify options and report on the recommended mechanical systems including:
- Design, location, area, size and approximate weight of equipment;
- Plant rooms sizes and locations (including access for maintenance, repairs and
replacement);
- All ductwork/pipe risers including ceiling, vertical and floor reticulation and prepare
single line duct layout;
- Specifications including testing and commissioning regimes for the major equipment,
system(s) and other interfaces; and
- Proposed standby and emergency arrangements.
Coordinate location of system components such as major plant and equipment, structural
penetrations, set downs and plinths with other services and architectural requirements.
Meet functional requirements to ensure system is fit for purpose, including essential
services.
Liaise with the electrical consultant regarding normal and critical power load of air
conditioning, heating, sterilisation, chilled water, ventilation and smoke spill.
Identify all work by others relating to service provision, including the builder and other
services consultants.
Define builder’s work in relation to services.
442500923.doc
45
Attendance at Meetings
4. For meeting attendance requirements for the mechanical engineer, refer to the requirements for
“All Consultants” in 12.2 above.
5. The mechanical engineers may be required to attend Project Control Group meetings at the
request of the Project Control Group or the Project Manager.
Reporting Requirements
6. The mechanical engineer must prepare monthly progress reports (generally no more than 3
pages in length) for inclusion in the Project Manager’s Monthly Report to the Project Control
Group. The engineers’ progress report should include a brief summary of the status of the work
and outline any key issues or critical decisions to be made regarding their area of responsibility.
Design Reviews
7. Mechanical engineers are required to:
Identify areas of high recurrent costs for consideration by the Project Control Group at the
Design Review.
Provide cost reduction options that may be needed to maintain the project cost within
Budget.
Phase Responsibilities
Feasibility Study
8. During the feasibility study, the mechanical engineer is responsible for the following tasks in
relation to their area of professional responsibility:
Following a comprehensive assessment of possible alternative solutions to the project’s
service requirements, prepare a Feasibility Study Report that includes a comparison of
capital development costs and ongoing operating and maintenance costs of each
alternative.
Provide the Project Manager and Project Control Group with advice and recommendations
on issues associated with their area of professional responsibility.
Continuously monitor architectural, structural and civil engineering and services decisions
for their functional, capital and/or recurrent cost impact.
Prepare benchmarks in accordance with Department of Health requirements for evaluation
of the Feasibility Study against comparable projects. (Typical benchmarks examine area
per unit/bed/client, measure output eg $ per WEIS/throughput/client and/or functional and
area basis. Benchmarks will include but not be limited to recurrent engineering services
costs).
Schematic Design
9. During schematic design the mechanical engineer is required to carry out the following tasks in
relation to their area of professional responsibility:
Analyse environmental and functional (area and room data sheets) requirements and
confirm performance standards to be met by mechanical systems.
Identify requirements for redundancy and for future expansion for sizing of major plant.
Prepare a schematic design Report following a comprehensive assessment of possible
alternative solutions to the project’s service requirements, including capital development
costs and ongoing operating and maintenance costs of each alternative. The Report is to
be provided to the Quantity Surveyor for inclusion in the Business Case report.
Identify the cost of capital required to achieve recurrent savings.
Provide the Project Manager and Project Control Group with advice and recommendations
on issues associated with their area of professional responsibility.
442500923.doc
46
Ensure the schematic design for their area of responsibility conforms to the scope of work
and budget for the project.
Continuously monitor architectural, structural and civil engineering and services decisions,
drawings and documentation for their functional, capital and/or recurrent cost impact.
Prepare benchmarks for evaluation of the Schematic Design against comparable projects in
accordance with Department of Health requirements.
Design Development
10. During design development the mechanical engineer is required to carry out the following tasks
in relation to their area of professional responsibility:
Resolve any outstanding design issues, including any changes to the Schematic Design
required as a result of the Design review.
Prepare a report that includes evaluation statements for all major decisions for inclusion in
the Design Development Report for the project.
Ensure design development for their area of responsibility meets the functional
requirements of the brief and is in accordance with the project budget.
Provide any information necessary to identify issues associated with special facilities and/or
major plant and equipment.
Ensure that all exposed furniture, fixtures and fittings are designed in accordance with
requirements for harm minimisation and are vandal proof with special attention to secure
facilities.
Provide the Quantity Surveyor with estimates of the cost of mechanical services for
inclusion in Cost Plan C2.
Provide the Architect with all the information required to finalise Room Data Sheets.
Prepare draft Specification if required.
Review all systems to ensure they coordinate with all others (eg architectural, structural,
electrical etc).
Contract Documentation
11. During contract documentation the mechanical engineer is required to undertake the following
tasks in relation to their area of professional responsibility:
Prepare contract documentation suitable for competitive tendering of the project including:
- Specifications
- Documentation
- Description of maintenance requirements for essential services, major plant and
equipment and any specialised facilities.
Ensure that documentation remains within the briefed areas and budgeted cost parameters
for the project.
Ensure that all documents are checked and coordinated in accordance with quality control
requirements.
Ensure tender documentation is available for checking, coordination and costing two weeks
prior to the date of tender.
Prepare a list of suitable sub-contractors where required.
Liaise with the Project Manager and Architect in the preparation of a construction schedule.
Establish agreed contract administration procedures with the Superintendent for the proper
handling of issues (eg variations) that arise throughout the project.
442500923.doc
47
Construction
13. During construction the mechanical engineer is required to:
Carry out all duties associated with their profession including those of Superintendent’s
Representative (SR) when required.
Obtain all required local authority approvals and liaise with authorities regarding inspections
and other requirements.
Identify hazardous areas or equipment to maintain safe work practices.
Incorporate services requirements for “Client Supplied Equipment”.
Monitor the installation of services to ensure they comply with the construction documents
and achieve the design intent.
Provide regular reports regarding the work’s progress, quality and compliance with
construction documents.
Examine and endorse all relevant shop drawings.
Check all off-site fabrication.
Provide any documentation required for the processing of variations.
Respond to Contractor’s requests for information and on site queries.
Amend contract drawings as required during construction and provide ’as built’ drawings
upon completion.
Ensure that the client is provided with:
- All approved operating and maintenance manuals.
- As-built drawings.
- Negatives/computer disks of installed services.
Ensure that a building services commissioning program is undertaken with maintenance
operators and that all guarantees and warranties are processed.
Witness the testing of all major equipment, systems and the interfaces with other services.
Make the final inspection and report to the Project Manager.
Issue a defects lists at Practical Completion.
Inspect the works at intervals during the Defects Liability Period.
442500923.doc
48
Asset Management
14. The mechanical engineer is to:
Prepare a register of all major plant and equipment included in the project that records:
- Type, model and name of manufacturer.
- Date of acquisition, purchase value and location of spares/back up.
- Design capacity, redundancy and life expectancy of elements.
Prepare an asset maintenance budget in conjunction with the Quantity Surveyor, indicating
the anticipated cash flow and annual budget for the life of the facility (say 15 to 20 years)
with a replacement or refurbishment schedule. It must include:
- Energy consumption costs (eg. electricity and gas for lighting, power, heating and
cooling).
- Operating and maintenance costs.
- Other sundry operating expenses.
- Contract management and supervision of out-sourced contracts
15. The Asset Management Plan must be provided in electronic and hard copy format. Documents
are to be recorded in a form suitable for monitoring and reporting (essential services,
accreditation and annual compliance checks).
442500923.doc
49
442500923.doc
50
Maintain quality control systems that ensure all information and documentation provided is
complete, comprehensive, up to date, checked and coordinated.
Liaise with the Project Manager, Principal Consultant and other consultants throughout all
phases of the project.
4. The more specific responsibilities of electrical engineers are to:
Analyse environmental and functional requirements as well as performance standards to be
met by systems.
Identify options and report on the recommended electrical services systems including:
- Design, location, area, size and approximate weight of equipment.
- High Voltage and Low Voltage supply and preferred route of cables into substation from
boundaries.
- Number and location of substations, meters and switch rooms including room sizes.
- Proposed standby and emergency arrangements including power supply backup and
essential engineering services loads.
- Mechanical, fire, communications and security distribution reticulation (cable trays used
and their location to be recorded).
- Lighting and power layout designed in accordance with the ring main and alternative
supply arrangements.
- Specifications including testing and commissioning regimes for the equipment, systems
and other interfaces.
Coordinate location of system components such as major plant and equipment, lighting and
power with other services and architectural requirements.
Meet functional requirements to ensure system is fit for purpose including load shedding,
alternative supply and maintenance of essential services. The consultant is to ensure the
facility can be supplied from portable equipment and the converters and system can
accommodate the contingency plan guideline.
Evaluate the performance and maintenance aspects of light fittings and high recurrent cost
elements and provide recommendations to the Principal Consultant.
Identify all work by others relating to service provision, including the builder and other
services consultants.
Define builder’s work in relation to services.
Prepare energy monitoring and management activities.
Feasibility Study
5. During the feasibility study, the electrical engineer is responsible for the following tasks in
relation to their area of professional responsibility:
Following a comprehensive assessment of possible alternative solutions to the project’s
service requirements, prepare a Feasibility Study Report that includes a comparison of
capital development costs and ongoing operating and maintenance costs of each
alternative.
Provide the Project Manager and Project Control Group with advice and recommendations
on issues associated with their area of professional responsibility.
Continuously monitor architectural, structural and civil engineering and services decisions
for their functional, capital and/or recurrent cost impact.
Prepare benchmarks in accordance with Department of Health requirements for evaluation
of the Feasibility Study against comparable projects. (Typical benchmarks examine area
per unit/bed/client, measure output eg $ per WEIS/throughput/client and/or functional and
area basis. Benchmarks will include but not be limited to recurrent engineering services
costs.)
442500923.doc
51
Schematic Design
6. During schematic design the electrical engineer is required to carry out the following tasks in
relation to their area of professional responsibility:
Analyse environmental and functional (area and room data sheets) requirements and
confirm performance standards to be met by electrical systems.
Identify requirements for redundancy and for future expansion for sizing of supply and
major equipment.
Prepare a Schematic Design Report following a comprehensive assessment of possible
alternative solutions to the project’s service requirements, including capital development
costs and ongoing operating and maintenance costs of each alternative. The Report is to
be provided to the Quantity Surveyor for inclusion in the Business Case report.
Identify the cost of capital required to achieve recurrent savings.
Provide the Project Manager and Project Control Group with advice and recommendations
on issues associated with their area of professional responsibility.
Ensure the schematic design for their area of responsibility conforms to the scope of work
and budget for the project.
Continuously monitor architectural, structural and civil engineering and services decisions,
drawings and documentation for their functional, capital and/or recurrent cost impact.
Prepare benchmarks for evaluation of the Schematic Design against comparable projects in
accordance with Department of Health requirements.
Design Review.
7. Electrical engineers are required to:
Identify areas of high recurrent costs for consideration by the Project Control Group at the
Design Review.
Provide cost reduction options that may be needed to maintain the project cost within
Budget.
Design Development
8. During design development the electrical engineer is required to carry out the following tasks in
relation to their area of professional responsibility:
Resolve any outstanding design issues, including any changes to the Schematic Design
required as a result of the Design Review.
Prepare a report that includes evaluation statements for all major decisions for inclusion in
the Design Development Report for the project.
Ensure design development for their area of responsibility meets the functional
requirements of the brief and is in accordance with the project budget.
Provide any information necessary to identify issues associated with special facilities and/or
major plant and equipment.
Ensure that all exposed furniture, fixtures and fittings are designed in accordance with
requirements for harm minimisation and are vandal proof with special attention to
requirements in secure facilities.
Provide the Quantity Surveyor with estimates of the cost of electrical services for inclusion
in Cost Plant C2.
Provide the Architect with all the information required to finalise Room Data Sheets.
Prepare draft Specification if required.
Review all systems to ensure they coordinate with all others (eg architectural, structural,
mechanical etc).
442500923.doc
52
Ensure design of safety and security systems for secure facilities are suitable for
maintenance by a single contractor.
Contract Documentation
9. During contract documentation the electrical engineer is required to undertake the following
tasks in relation to their area of professional responsibility:
Prepare contract documentation suitable for competitive tendering of the project including:
- Specifications
- Documentation
- Description of maintenance requirements for essential services, major plant and
equipment and any specialised facilities.
Ensure that documentation remains within the briefed areas and budgeted cost parameters
for the project.
Ensure documentation of safety and security systems for secure facilities is suitable for
maintenance by a single contractor.
Ensure that all documents are checked and coordinated in accordance with quality control
requirements.
Ensure tender documentation is available for checking, coordination and costing two weeks
prior to the date of tender.
Prepare a list of suitable sub-contractors where required.
Liaise with the Project Manager and Architect in the preparation of a construction schedule.
Establish agreed contract administration procedures with the Superintendent for the proper
handling of issues (eg variations) that arise throughout the project.
Construction
11. During construction, the electrical engineer is required to:
Carry out all duties associated with their profession including those of Superintendent’s
Representative (SR) when required.
Obtain all required local authority approvals and liaise with authorities regarding inspections
and other requirements.
Identify hazardous areas or equipment to maintain safe work practices.
Incorporate services requirements for Client Supplied Equipment.
Monitor the installation of services to ensure they comply with the construction documents
and achieve the design intent.
442500923.doc
53
Provide regular Reports regarding the work’s progress, quality and compliance with
construction documents.
Examine and endorse all relevant shop drawings.
Check all off-site fabrication.
Provide any documentation required for the processing of variations.
Respond to Contractor’s requests for information and on site queries.
Amend contract drawings as required during construction and provide ’as built’ drawings
upon completion.
Ensure that the client is provided with:
- All approved operating and maintenance manuals.
- As-built drawings.
- Negatives/computer disks of installed services
Ensure that a building services commissioning program is undertaken with maintenance
operators and that all guarantees and warranties are processed.
Witness the testing of all equipment and systems and the interfaces with other services.
Make the final inspection and report to the Project Manager.
Issue a defects lists at Practical Completion.
Inspect the works at intervals during the Defects Liability Period.
Asset Management
12. The electrical engineer is to:
Prepare a register of all major plant and equipment included in the project, recording:
- Type, model and name of manufacturer.
- Date of acquisition, purchase value and location of spares/back up.
- Design capacity, redundancy and life expectancy of elements.
Prepare an asset maintenance budget in conjunction with the Quantity Surveyor, indicating
the anticipated cash flow and annual budget for the life of the facility (say 15 to 20 years)
with a replacement or refurbishment schedule. It must include:
- Energy consumption costs (eg. electricity for lighting, power, heating and cooling).
- Operating and maintenance costs.
- Other sundry operating expenses.
- Contract management and supervision of out-sourced contracts
13. The Asset Management Plan must be provided in electronic and hard copy format. Documents
are to be recorded in a form suitable for monitoring and reporting (essential services,
accreditation and annual compliance checks).
442500923.doc
54
442500923.doc
55
Feasibility Study
5. During the feasibility study, the hydraulic services engineer is responsible for the following tasks
in relation to their area of professional responsibility:
Following a comprehensive assessment of possible alternative solutions to the project’s
service requirements, prepare a Feasibility Study Report that includes a comparison of
capital development costs and ongoing operating and maintenance costs of each
alternative.
Provide the Project Manager and Project Control Group with advice and recommendations
on issues associated with their area of professional responsibility.
Continuously monitor architectural, structural and civil engineering and services decisions
for their functional, capital and/or recurrent cost impact.
Prepare benchmarks in accordance with Department of Health requirements for evaluation
of the Feasibility Study against comparable projects. (Typical benchmarks examine area
per unit/bed/client, measure output eg $ per WEIS/throughput/client and/or functional and
area basis. Benchmarks will include but not be limited to recurrent engineering services
costs.)
Schematic Design
6. During schematic design the hydraulic services engineer is required to carry out the following
tasks in relation to their area of professional responsibility:
Analyse functional requirements and confirm performance standards to be met by hydraulic
services systems.
Identify requirements for redundancy and for future expansion for sizing of services.
442500923.doc
56
Design Review.
7. Hydraulic services engineers are required to:
Identify areas of high recurrent costs for consideration by the Project Control Group at the
Design Review.
Provide cost reduction options that may be needed to maintain the project cost within
Budget.
Design Development
8. During design development the hydraulic services engineer is required to carry out the following
tasks in relation to their area of professional responsibility:
Resolve any outstanding design issues, including any changes to the Schematic Design
required as a result of the Design Review.
Prepare a report that includes evaluation statements for all major decisions for inclusion in
the Design Development Report for the project.
Ensure design development for their area of responsibility meets the functional
requirements of the brief and is in accordance with the project budget.
Provide any information necessary to identify issues associated with special facilities and/or
major plant and equipment.
Ensure that all exposed furniture, fixtures and fittings are designed in accordance with
requirements for harm minimisation and are vandal proof.
Ensure design is undertaken to allow isolation of specific areas within secure facilities.
Provide the Quantity Surveyor with estimates of the cost of hydraulic services for inclusion
in Cost Plant C2.
Provide the Architect with all the information required to finalise Room Data Sheets.
Prepare draft Specification if required.
Review all systems to ensure they coordinate with all others (eg architectural, structural,
electrical etc).
Contract Documentation
9. During the contract documentation stage the hydraulic services engineer is required to
undertake the following tasks in relation to their area of professional responsibility:
Prepare contract documentation suitable for competitive tendering of the project including:
- Specifications
- Documentation
442500923.doc
57
Construction
11. During construction the hydraulic services engineer is required to:
Carry out all duties associated with their profession including those of Superintendent’s
Representative (SR) when required.
Obtain all required local authority approvals and liaise with authorities regarding inspections
and other requirements.
Identify hazardous areas or equipment to maintain safe work practices.
Incorporate services requirements for Client Supplied Equipment.
Monitor the installation of services to ensure they comply with the construction documents
and achieve the design intent.
Provide regular Reports regarding the work’s progress, quality and compliance with
construction documents.
Examine and endorse all relevant shop drawings.
Check all off-site fabrication.
Provide any documentation required for the processing of variations.
Respond to Contractor’s requests for information and on site queries.
Amend contract drawings as required during construction and provide ’as built’ drawings
upon completion.
Ensure that the client is provided with:
- All approved operating and maintenance manuals.
442500923.doc
58
- As-built drawings.
- Negatives/computer disks of installed services
Ensure that a building services commissioning program is undertaken with maintenance
operators and that all guarantees and warranties are processed.
Witness the testing of all equipment, systems and the interfaces with other services.
Make the final inspection and report to the Project Manager.
Issue a defects lists at Practical Completion.
Inspect the works at intervals during the Defects Liability Period.
Asset Management
12. The hydraulic services engineer is to:
Prepare a register of all major plant and equipment included in the project, recording:
- Type, model and name of manufacturer.
- Date of acquisition, purchase value and location of spares/back up.
- Design capacity, redundancy and life expectancy of elements.
Prepare an asset maintenance budget in conjunction with the Quantity Surveyor, indicating
the anticipated cash flow and annual budget for the life of the facility (say 15 to 20 years)
with a replacement or refurbishment schedule. It must include:
- Energy consumption costs (eg. electricity and gas for hot water, pumps).
- Operating and maintenance costs.
- Other sundry operating expenses.
- Contract management and supervision of out-sourced contracts
13. The Asset Management Plan must be provided in electronic and hard copy format. Documents
are to be recorded in a form suitable for monitoring and reporting (essential services,
accreditation and annual compliance checks).
Scope of Services
1. All such engineers must be qualified as specified in the Building Regulations.
2. Communication and Security engineers have a general responsibility for the following service
components of a project:
PABX, telephones, intercoms and site radio systems
Public Address System
CCTV surveillance
Pagers systems and nurse call systems
Security systems including duress alarms, electric strike door locks and restricted door
access
Emergency and Evacuation Warning System
442500923.doc
59
442500923.doc
60
- Specifications including testing and commissioning regimes for the equipment, systems
and other interfaces.
Integrate systems for radio, pager and mobile devices including duress alarm.
Prepare a single line plan of communications and security distribution systems.
Coordinate the location of all system components with other services and architectural
requirements.
Meet functional requirements to ensure system is fit for purpose including essential
services.
Identify all work by others relating to service provision, including the builder and other
services consultants.
Define builder’s work in relation to communications and security services.
Feasibility Study
5. During the feasibility study, the communications and security systems engineer is responsible
for the following tasks in relation to their area of professional responsibility:
Following a comprehensive assessment of possible alternative solutions to the project’s
service requirements, prepare a Feasibility Study Report that includes a comparison of
capital development costs and ongoing operating and maintenance costs of each
alternative.
Provide the Project Manager and Project Control Group with advice and recommendations
on issues associated with their area of professional responsibility.
Continuously monitor architectural, structural and civil engineering and services decisions
for their functional, capital and/or recurrent cost impact.
Prepare benchmarks in accordance with Department of Health requirements for evaluation
of the Feasibility Study against comparable projects. (Typical benchmarks examine area
per unit/bed/client, measure output eg $ per WEIS/throughput/client and/or functional and
area basis. Benchmarks will include but not be limited to recurrent engineering services
costs.)
Schematic Design
6. During schematic design communications and security engineers are required to carry out the
following tasks in relation to their area of professional responsibility:
Analyse functional requirements and confirm performance standards to be met by
communications and security systems.
Identify requirements for redundancy and for future expansion for sizing of major
equipment.
Prepare a schematic design Report following a comprehensive assessment of possible
alternative solutions to the project’s service requirements, including capital development
costs and ongoing operating and maintenance costs of each alternative. The Report is to
be provided to the Quantity Surveyor for inclusion in the Business Case report.
Identify the cost of capital required to achieve recurrent savings.
Provide the Project Manager and Project Control Group with advice and recommendations
on issues associated with their area of professional responsibility.
Ensure the schematic design for their area of responsibility conforms to the scope of work
and budget for the project.
Continuously monitor architectural, structural and civil engineering and services decisions,
drawings and documentation for their functional, capital and/or recurrent cost impact.
Prepare benchmarks for evaluation of the Schematic Design against comparable projects in
accordance with Department of Health requirements.
442500923.doc
61
Design Reviews.
7. Communications and security services engineers are required to:
Identify areas of high recurrent costs for consideration by the Project Control Group at the
Design Review.
Provide cost reduction options that may be needed to maintain the project cost within
Budget.
Design Development
8. During design development the communications and security services engineer is required to
carry out the following tasks in relation to their area of professional responsibility:
Resolve any outstanding design issues, including any changes to the Schematic Design
required as a result of the Design Review.
Prepare a report that includes evaluation statements for all major decisions for inclusion in
the Design Development Report for the project.
Ensure design development for their area of responsibility meets the functional
requirements of the brief and is in accordance with the project budget.
Provide any information necessary to identify issues associated with special facilities and/or
major plant and equipment.
Ensure fire safety and security systems for secure facilities are fully integrated, that all
exposed furniture, fixtures and fittings are designed in accordance with requirements for
harm minimisation and are vandal proof.
Provide the Quantity Surveyor with estimates of the cost of communications and security
services for inclusion in Cost Plant C2.
Provide the Architect with all the information required to finalise Room Data Sheets.
Prepare draft Specification if required.
Review all systems to ensure they coordinate with all others (eg architectural, structural,
electrical etc).
Contract Documentation
9. During the contract documentation stage the communications and security services engineer is
required to undertake the following tasks in relation to their area of professional responsibility:
Prepare contract documentation suitable for competitive tendering of the project including:
- Specifications
- Documentation
- Description of maintenance requirements for essential services, major plant and
equipment and any specialised facilities.
Ensure that documentation remains within the briefed areas and budgeted cost parameters
for the project.
Ensure that all documents are checked and coordinated in accordance with quality control
requirements.
Ensure tender documentation is available for checking, coordination and costing two weeks
prior to the date of tender.
Prepare a list of suitable sub-contractors where required.
Liaise with the Project Manager and Architect in the preparation of a construction schedule.
Establish agreed contract administration procedures with the Superintendent for the proper
handling of issues (eg variations) that arise throughout the project.
442500923.doc
62
Construction
11. During construction the communications and security services engineer is required to:
Carry out all duties associated with their profession including those of Superintendent’s
Representative (SR) when required.
Obtain all required local authority approvals and liaise with authorities regarding inspections
and other requirements.
Identify hazardous areas or equipment to maintain safe work practices.
Incorporate services requirements for Client Supplied Equipment.
Monitor the installation of services to ensure they comply with the construction documents
and achieve the design intent.
Provide regular Reports regarding the work’s progress, quality and compliance with
construction documents.
Examine and endorse all relevant shop drawings.
Check all off-site fabrication.
Provide any documentation required for the processing of variations.
Respond to Contractor’s requests for information and on site queries.
Amend contract drawings as required during construction and provide ’as built’ drawings
upon completion.
Ensure that the client is provided with:
- All approved operating and maintenance manuals.
- As-built drawings.
- Negatives/computer disks of installed services
Ensure that a building services commissioning program is undertaken with maintenance
operators and that all guarantees and warranties are processed.
Witness the testing of all equipment, systems and the interfaces with other services.
Make the final inspection and report to the Project Manager.
Issue a defects lists at Practical Completion.
Inspect the works at intervals during the Defects Liability Period.
Asset Management
12. The communications and security services engineer is to:
Prepare a register of all major plant and equipment included in the project, recording:
442500923.doc
63
442500923.doc
64
442500923.doc
65
Maintain quality control systems that ensure all information and documentation provided is
complete, comprehensive, up to date, checked and coordinated.
Liaise with the Project Manager, Principal Consultant and other consultants throughout all
phases of the project.
4. The more specific responsibilities of the civil engineer are to:
Analyse functional requirements and confirm performance standards to be met by civil
engineering systems.
Identify options and report on the recommended civil engineering systems including:
- Design, confirm areas, location and size including all interfaces with structural,
mechanical, electrical, hydraulic, communications and security systems.
- Proposed standby and emergency arrangements.
- Specifications including testing and commissioning regimes for materials and system(s)
and other interfaces.
Coordinate location of all system components with other structural, services and
architectural requirements.
Identify all work by others associated with the civil engineering services.
Define builder’s work in relation to civil engineering services.
Feasibility Study
5. During the feasibility study, the civil engineer is responsible for the following tasks in relation to
their area of professional responsibility:
Check the availability and capacity of storm water drainage services to the site and discuss
with local authority.
Assess implications for neighbouring properties and undertake survey and photo records of
conditions of adjacent properties.
Ensure geo-technical and land survey information is suitable for the preparation of design,
documentation and implementation of the project.
Following a comprehensive assessment of possible alternative solutions to the project’s
service requirements, prepare a Feasibility Study Report that includes a comparison of
capital development costs and ongoing operating and maintenance costs of each
alternative.
Provide the Project Manager and Project Control Group with advice and recommendations
on issues associated with their area of professional responsibility.
Continuously monitor architectural, structural and civil engineering and services decisions
for their functional, capital and/or recurrent cost impact.
Prepare benchmarks in accordance with Department of Health requirements for evaluation
of the Feasibility Study against comparable projects. (Typical benchmarks examine area
per unit/bed/client, measure output eg $ per WEIS/throughput/client and/or functional and
area basis. Benchmarks will include but not be limited to recurrent engineering services
costs.)
Schematic Design
6. During Schematic Design the civil engineer is required to carry out the following tasks in
relation to their area of professional responsibility:
Analyse environmental and functional requirements and confirm performance standards to
be met by civil engineering systems including provision for future development.
Identify requirements for redundancy and for future expansion for sizing of services.
Prepare a schematic design Report following a comprehensive assessment of possible
alternative solutions to the project’s service requirements, including capital development
442500923.doc
66
costs and ongoing operating and maintenance costs of each alternative. The Report is to
be provided to the Quantity Surveyor for inclusion in the Business Case report.
Confirm the location and dimensions of all major structural elements for all consultants on
detailed survey site plan.
Identify the cost of capital required to achieve recurrent savings.
Provide the Project Manager and Project Control Group with advice and recommendations
on issues associated with their area of professional responsibility.
Ensure the schematic design for their area of responsibility conforms to the scope of work
and budget for the project.
Continuously monitor architectural, structural and civil engineering and services decisions,
drawings and documentation for their functional, capital and/or recurrent cost impact.
Prepare benchmarks for evaluation of the Schematic Design against comparable projects in
accordance with Department of Health requirements.
Design Reviews.
7. Civil engineers are required to:
Identify areas of high recurrent costs for consideration by the Project Control Group at the
Design Review.
Provide cost reduction options that may be needed to maintain the project cost within
Budget.
Design Development
8. During design development the civil engineer is required to carry out the following tasks in
relation to their area of professional responsibility:
Resolve any outstanding design issues, including any changes to the Schematic Design
required as a result of the Design Review.
Prepare a report that includes evaluation statements for all major decisions for inclusion in
the Design Development Report for the project.
Ensure design development for their area of responsibility meets the functional
requirements of the brief and is in accordance with the project budget.
Provide any information necessary to identify issues associated with special facilities and/or
major plant and equipment.
Ensure that all exposed furniture, fixtures and fittings are designed in accordance with
requirements for harm minimisation and are vandal proof.
Ensure stormwater drains, culverts and similar are designed in a manner that maintains the
integrity of secure facilities.
Provide the Quantity Surveyor with estimates of the cost of civil engineering services for
inclusion in Cost Plant C2.
Prepare draft Specification if required.
Review all systems to ensure they coordinate with all others (eg architectural, structural,
electrical etc).
Confirm developed site levels, and storm water pipe and pit locations. Confirm no water
entrapment areas exist that are likely to result in water entry into or damage to any building
or pavement.
Contract Documentation
9. During contract documentation the civil engineer is required to undertake the following tasks in
relation to their area of professional responsibility:
442500923.doc
67
Prepare contract documentation suitable for competitive tendering of the project including:
- Specifications
- Documentation
- Description of maintenance requirements for essential services, major plant and
equipment and any specialised facilities.
Ensure that documentation remains within the briefed areas and budgeted cost parameters
for the project.
Ensure that all documents are checked and coordinated in accordance with quality control
requirements.
Ensure tender documentation is available for checking, coordination and costing two weeks
prior to the date of tender.
Prepare a list of suitable sub-contractors where required.
Liaise with the Project Manager and Architect in the preparation of a construction schedule.
Establish agreed contract administration procedures with the Superintendent for the proper
handling of issues (eg variations) that arise throughout the project.
Liaise with the Project Manager regarding the amount and detail of civil engineering tender
documents required for the procurement model to be used.
Construction
11. During construction, the civil engineer is required to:
Carry out all duties associated with their profession including those of Superintendent’s
Representative (SR) when required.
Obtain all required local authority approvals and liaise with authorities regarding inspections
and other requirements.
Identify hazardous areas or equipment to maintain safe work practices.
Incorporate services requirements for Client Supplied Equipment.
Monitor the installation of services to ensure they comply with the construction documents
and achieve the design intent.
Provide regular Reports regarding the work’s progress, quality and compliance with
construction documents.
Examine and endorse all relevant shop drawings.
Check all off-site fabrication.
Provide any documentation required for the processing of variations.
442500923.doc
68
Asset Management
12. The civil engineer is to:
Prepare a register of all major plant and equipment included in the project, recording:
- Type, model and name of manufacturer.
- Date of acquisition, purchase value and location of spares/back up.
- Design capacity, redundancy and life expectancy of elements.
Prepare an asset maintenance budget in conjunction with the Quantity Surveyor, indicating
the anticipated cash flow and annual budget for the life of the facility (say 15 to 20 years)
with a replacement or refurbishment schedule. It must include:
- Energy consumption costs (where applicable).
- Operating and maintenance costs.
- Other sundry operating expenses.
- Contract management and supervision of out-sourced contracts
13. The Asset Management Plan must be provided in electronic and hard copy format. Documents
are to be recorded in a form suitable for monitoring and reporting (essential services,
accreditation and annual compliance checks).
442500923.doc
69
442500923.doc
70
Feasibility Study
5. During the feasibility study, the structural engineer is responsible for the following tasks in
relation to their area of professional responsibility:
Consideration of the structural implications of the proposed development including future
expansion, reticulation of all services developed in conjunction with the Architect, Building
Services Engineer and other consultants.
Ensure geotechnical information is suitable for design, documentation and implementation
of the project.
Following a comprehensive assessment of possible alternative solutions prepare a
Feasibility Study Report.
Provide the Project Manager and Project Control Group with advice and recommendations
on issues associated with their area of professional responsibility.
Continuously monitor architectural, civil engineering and services decisions for their
functional, capital and/or recurrent cost impact.
Prepare benchmarks in accordance with Department of Health requirements for evaluation
of the Feasibility Study against comparable projects. (Typical benchmarks examine area
per unit/bed/client, measure output eg $ per WEIS/throughput/client and/or functional and
area basis.
Schematic Design
6. During Schematic Design the structural engineer is required to carry out the following tasks in
relation to their area of professional responsibility:
Analyse functional requirements and confirm performance standards to be met by structural
systems including provision for future development.
Prepare a schematic design Report following a comprehensive assessment of possible
alternative solutions including capital development costs of each alternative. The Report is
to be provided to the Quantity Surveyor for inclusion in the Business Case report.
Provide the Project Manager and Project Control Group with advice and recommendations
on issues associated with their area of professional responsibility.
Ensure the schematic design for their area of responsibility conforms to the scope of work
and budget for the project.
Ensure the structures are adequate for installation, removal and replacement of major
plant, equipment or similar loads.
Continuously monitor architectural, civil engineering and services decisions, drawings and
documentation for their functional, capital and/or recurrent cost impact.
Prepare benchmarks for evaluation of the Schematic Design against comparable projects in
accordance with Department of Health requirements.
Design Reviews.
7. Structural engineers are required to:
Identify areas of high cost for consideration by the Project Control Group at the Design
Review.
Provide cost reduction options that may be needed to maintain the project cost within
Budget.
442500923.doc
71
Design Development
8. During design development the structural engineer is required to carry out the following tasks in
relation to their area of professional responsibility:
Resolve any outstanding design issues, including any changes to the Schematic Design
required as a result of the Design Review.
Prepare a report that includes evaluation statements for all major decisions for inclusion in
the Design Development Report for the project.
Ensure design development for their area of responsibility meets the functional
requirements of the brief and is in accordance with the project budget.
Provide any information necessary to identify issues associated with special facilities and/or
major plant and equipment.
Ensure all elements and components are suitably fixed and reinforced where necessary
when designing secure facilities.
Confirm the location and dimensions of all major structural elements for all consultants.
Provide the Architect with all the information required to finalise Room Data Sheets.
Prepare draft Specification if required.
Review all systems to ensure their coordination with all other systems, eg architectural,
mechanical, electrical etc.
Contract Documentation
9. During contract documentation, the structural engineer is required to undertake the following
tasks in relation to their area of professional responsibility:
Prepare contract documentation suitable for competitive tendering of the project including:
- Specifications
- Documentation
Ensure that documentation remains within the briefed areas and budgeted cost parameters
for the project.
Ensure that all documents are checked and coordinated in accordance with quality control
requirements.
Ensure tender documentation is available for checking, coordination and costing two weeks
prior to the date of tender.
Liaise with the Project Manager and Architect in the preparation of a construction schedule.
Establish agreed contract administration procedures with the Superintendent for the proper
handling of issues (eg variations) that arise throughout the project.
Liaise with the Project Manager regarding the amount and detail of structural engineering
tender documents required for the procurement model to be used.
442500923.doc
72
Ensure that the successful contractor completes all schedules, programmes, and cash flow
before commencing work on the project.
Construction
11. During construction, the structural engineer is required to:
Carry out all duties associated with their profession including those of Superintendent’s
Representative (SR) when required.
Obtain all local authority approvals required and liaise with authorities regarding inspections
and other requirements.
Identify hazardous areas or equipment to maintain safe work practices.
Incorporate structural requirements for Client Supplied Equipment.
Monitor construction to ensure compliance with project documentation and design intent.
Provide regular Reports regarding the work’s progress, quality and compliance with
construction documents.
Provide any documentation required for the processing of variations.
Ensure that the client is provided with ‘as-built’ drawings.
Respond to Contractor’s requests for information and on site queries.
Amend contract drawings as required during construction and provide “as built” drawings
upon completion.
Examine and endorse all structural shop drawings.
Check off-site fabrications as required.
Periodically witness the testing of materials.
Ensure the preparation of as-built drawings by the Contractor and submission of
negatives/computer disk of installed services to the client.
Make the final inspection and report to the Project Manager.
Issue a defects lists at Practical Completion.
Inspect the works at intervals during the Defects Liability Period.
Asset Management
12. The structural engineer is to provide a record of all structural design computations required for
use in any refurbishment, redevelopment or demolition of the facility.
442500923.doc
73
442500923.doc
74
any energy efficiency requirements of the Building Code of Australia. (Any project seeking
exemption is to be considered by the Director, CMB or Manager of Standards, CMB.)
Administer their components of the work during the construction stage and issue the
relevant completion certificates as required.
Monitor and check the work of each sub-consultant (if relevant).
Maintain quality control systems that ensure all information and documentation provided is
complete, comprehensive, up to date, checked and coordinated.
Liaise with the Project Manager, Principal Consultant and other consultants throughout all
phases of the project.
4. The more specific responsibilities of the fire protection consultant are to:
Analyse environmental and functional requirements as well as performance standards to be
met by systems.
Identify options and report on the recommended fire protection services systems including:
- Design, confirm areas, locations and size including all interfaces with mechanical,
electrical, communications and security systems.
- Fire control room and valve room area requirements.
- Establish site water supply availability, pressure and flow rate.
- System layout and size, tappings including fire main, sprinkler hydrant/risers and
layout.
- Sprinkler head and smoke/heat detector layout.
- Hydrants, sprinklers riser and size of hydrant cupboards and sprinkler booster
connections.
- All water storage requirements including approximate weight of storage in relation to
architectural and structural design, including any structural penetrations etc.
- Proposed standby and emergency arrangements.
- Specifications including testing and commissioning regimes for the equipment,
system(s) and other interfaces.
Coordinate location of all system components with other services and architectural
requirements.
Ensure all passive, detection and suppression fire safety items required by the risk
assessment have been incorporated into the design.
Ensure all interfaces with mechanical, security and communication systems are integrated.
Identify all work by others associated with the fire services installation.
Define builder’s work in relation to fire protection services.
Feasibility Study
5. During the feasibility study, the fire protection consultant is responsible for the following tasks in
relation to their area of professional responsibility:
Following a comprehensive assessment of possible alternative solutions to the project’s
service requirements, prepare a Feasibility Study Report that includes a comparison of
capital development costs and ongoing operating and maintenance costs of each
alternative.
Provide the Project Manager and Project Control Group with advice and recommendations
on issues associated with their area of professional responsibility.
Continuously monitor architectural, structural and civil engineering and services decisions
for their functional, capital and/or recurrent cost impact.
Prepare benchmarks in accordance with Department of Health requirements for evaluation
of the Feasibility Study against comparable projects. (Typical benchmarks examine area
442500923.doc
75
Schematic Design
6. During Schematic Design the fire protection consultant is required to carry out the following
tasks in relation to their area of professional responsibility:
Analyse environmental and functional requirements and confirm performance standards to
be met by fire protection services systems.
Identify requirements for redundancy and for future expansion for sizing of water supply
and major equipment.
Prepare a Schematic Design Report following a comprehensive assessment of possible
alternative solutions to the project’s service requirements, including capital development
costs and ongoing operating and maintenance costs of each alternative. The Report is to
be provided to the Quantity Surveyor for inclusion in the Business Case report.
Identify the cost of capital required to achieve recurrent savings.
Provide the Project Manager and Project Control Group with advice and recommendations
on issues associated with their area of professional responsibility.
Ensure the schematic design for their area of responsibility conforms to the scope of work
and budget for the project.
Continuously monitor architectural, structural and civil engineering and services decisions,
drawings and documentation for their functional, capital and/or recurrent cost impact.
Prepare benchmarks for evaluation of the Schematic Design against comparable projects in
accordance with Department of Health requirements.
7. Where sufficient documentation exists at the schematic design stage, the Fire Safety Engineer
(refer to the role of the Fire Safety Engineer in sub-clause 12.16) is to undertake the following:
Desktop fire audit
Risk assessment
Assessment of compliance with the Building Code Australia—1996.
Design Review.
8. Fire protection consultants are required to:
Identify areas of high recurrent costs for consideration by the Project Control Group at the
Design Review.
Provide cost reduction options that may be needed to maintain the project cost within
Budget.
Design Development
9. During design development the fire protection consultant is required to carry out the following
tasks in relation to their area of professional responsibility:
Resolve any outstanding design issues, including any changes to the Schematic Design
required as a result of the Design Review.
Prepare a report that includes evaluation statements for all major decisions for inclusion in
the Design Development Report for the project.
Ensure design development for their area of responsibility meets the functional
requirements of the brief and is in accordance with the project budget.
Provide any information necessary to identify issues associated with special facilities and/or
major plant and equipment.
442500923.doc
76
Ensure fire safety and security systems for secure facilities are fully integrated, that all
exposed furniture, fixtures and fittings are designed in accordance with requirements for
harm minimisation and are vandal proof.
Provide the Quantity Surveyor with estimates of the cost of fire protection services for
inclusion in Cost Plant C2.
Provide the Architect with all the information required to finalise Room Data Sheets.
Prepare draft Specification if required.
Review all systems to ensure their coordination with all other systems, eg architectural,
structural, electrical etc).
Contract Documentation
10. During contract documentation, the fire protection consultant is required to undertake the
following tasks in relation to their area of professional responsibility:
Prepare contract documentation suitable for competitive tendering of the project including:
- Specifications
- Documentation
- Description of maintenance requirements for essential services, major equipment and
any specialised facilities.
Ensure that documentation remains within the briefed areas and budgeted cost parameters
for the project.
Ensure that all documents are checked and coordinated in accordance with quality control
requirements.
Ensure tender documentation is available for checking, coordination and costing two weeks
prior to the date of tender.
Prepare a list of suitable sub-contractors where required.
Liaise with the Project Manager and Architect in the preparation of a construction schedule.
Establish agreed contract administration procedures with the Superintendent for the proper
handling of issues (eg variations) that arise throughout the project.
11. Where insufficient documentation existed at the design development stage, the Fire Safety
Engineer (refer to sub-clause 12.16) is to undertake the following:
Desktop fire audit
Risk assessment
Assessment of compliance with the Building Code Australia—1996.
442500923.doc
77
Construction
13. During construction fire protection consultants are required to:
Carry out all duties associated with their profession including those of Superintendent’s
Representative (SR) when required.
Obtain all local authority approvals required and liaise with authorities regarding inspections
and other requirements.
Identify hazardous areas or equipment to maintain safe work practices.
Incorporate services requirements for Client Supplied Equipment.
Monitor the installation of services to ensure they comply with the construction documents
and achieve the design intent.
Provide regular reports regarding the project work’s:
- Progress
- Quality
- Schedule.
Examine and endorse all relevant shop drawings.
Check all off-site fabrication.
Provide any documentation required for the processing of variations.
Respond to Contractor’s requests for information and on site queries.
Amend contract drawings as required during construction and provide ’as built’ drawings
upon completion.
Ensure that the client is provided with:
- All approved operating and maintenance manuals.
- As-built drawings.
- Negatives/computer disks of installed services
Ensure that a building services commissioning program is undertaken with maintenance
operators.
Witness the testing of all equipment, systems and interfaces with other services.
Make the final inspection and report to the Project Manager.
Issue a defects lists at Practical Completion.
Inspect the works at intervals during the Defects Liability Period.
14. During construction the Fire Safety Engineer (refer to sub-clause 12.16) is required to:
Review proposals to alter the fire safety strategy
Prepare a supplementary report assessing the effects of the variations
Submit the report to the building Surveyor
Asset Management
15. During the Asset Management stage the fire protection consultant is to:
Prepare a register of all major plant and equipment included in the project, recording:
- Type, model and name of manufacturer.
- Date of acquisition, purchase value and location of spares/back up.
- Design capacity, redundancy and life expectancy of elements.
442500923.doc
78
Prepare an asset maintenance budget in conjunction with the Quantity Surveyor, indicating
the anticipated cash flow and annual budget for the life of the facility (say 15 to 20 years)
with a replacement or refurbishment schedule. It must include:
- Energy consumption costs (eg. electricity for detection, alarm and communication
systems).
- Operating and maintenance costs.
- Other sundry operating expenses.
- Contract management and supervision of out-sourced contracts
The Asset Management Plan must be provided in electronic and hard copy format.
Documents are to be recorded in a form suitable for monitoring and reporting (essential
services, accreditation and annual compliance checks).
442500923.doc
79
Scope of Services
2. It is intended that the Fire Safety Engineer will be appointed to undertake the following services
for all projects involving overnight client bed base accommodation with 24 hour support:
Input into the design process
Undertake risk assessment
Check contract documents
Inspect the fire safety works
Prepare site fire safety plan
Prepare emergency evacuation plan
Certify compliance with DHS Capital Development Guidelines.
3. The Fire Safety Engineer is responsible to ensure that all passive (eg. compartmentation,
egress, material selection and fire rating etc), detection and suppression fire safety systems
have been coordinated and that a total fire safety system is designed.
4. The Fire Safety Engineer will be expected to provide full professional services including the
following:
Liaise with the consultant team throughout the entire design process and attend team
meetings.
Input into the feasibility and schematic design stages and present appropriate fire safety
options.
Undertake a desktop audit and fire safety risk assessment (including quantitative analysis)
in accordance with the DHS Capital Development Guidelines—Series 7: Fire Risk
Management, at the completion of schematic design or when the floor plans have been
frozen and area functions are known.
Prepare a fire safety report for the development considering options, and clearly present
the recommendations.
Check the contract documents to confirm that the full scope of the fire safety
system/strategy has been incorporated in the documents.
Prepare a supplementary report for building surveyor assessment if the fire safety strategy
changes during contract documentation or during construction.
Prepare a fire safety plan for the site including maintenance and management issues, or
amend the existing plan to cover the new works.
Inspect the completed works to confirm that the full scope of the fire safety requirements
have been incorporated into the works.
Prepare suitable emergency evacuation plan for the building(s), or amend the existing plan
to cover the new works.
Participate in the POE review and consider the effectiveness of human factors such as
emergency procedures as well as the physical factors such as fire protection equipment.
Identify any non-compliances and make recommendations for corrective actions.
5. The Fire Safety Engineer is to ensure that a single integrated fire safety system applies to the
entire site. For projects involving existing buildings, the Fire Safety Engineer must source the
existing fire safety audit and risk assessment report(s) for the site. Where interfaces are
required with other disciplines, eg. security, mechanical or electrical, the Fire Safety Engineer
442500923.doc
80
must fully brief the relevant consulting team members of the interface requirements to ensure
integrity and integration of the systems.
6. The Fire Safety Engineer must certify via compliance statements that the proposes design
meets the requirements of the DH Capital Development Guidelines—Series 7: Fire Risk
Management, that the full scope of the fire safety works has been incorporated into the contract
documents, and that the full scope of the fire safety works have been completed.
442500923.doc
81
442500923.doc
82
- Identify options and report on the recommended lift services systems including:
- Design, confirm areas, location and size including all interfaces with mechanical,
electrical, communications and security systems.
- Lift overrun and shaft sizes.
- Lift motor room and approximate weights and location of equipment.
- Proposed standby and emergency arrangements.
- Specifications including testing and commissioning regimes for the equipment,
system(s) and other interfaces.
Coordinate location of all system components with other services and architectural
requirements.
Identify all work by others relating to service provision, including the builder and other
services consultants.
Define builder’s work in relation to transportation services.
Feasibility Study
5. During the feasibility study, the lift services engineer is responsible for the following tasks in
relation to their area of professional responsibility:
Following a comprehensive assessment of possible alternative solutions to the project’s
service requirements, prepare a Feasibility Study Report that includes a comparison of
capital development costs and ongoing operating and maintenance costs of each
alternative.
Provide the Project Manager and Project Control Group with advice and recommendations
on issues associated with their area of professional responsibility.
Continuously monitor architectural, structural and civil engineering and services decisions
for their functional, capital and/or recurrent cost impact.
Prepare benchmarks in accordance with Department of Health requirements for evaluation
of the Feasibility Study against comparable projects. (Typical benchmarks examine area
per unit/bed/client, measure output eg $ per WEIS/throughput/client and/or functional and
area basis. Benchmarks will include but not be limited to recurrent engineering services
costs.)
Schematic Design
6. During Schematic Design the lift services engineer is required to carry out the following tasks in
relation to their area of professional responsibility:
Analyse functional requirements and confirm performance standards to be met by lift
services systems.
Identify requirements for future vertical expansion for sizing of major lift plant.
Prepare a Schematic Design Report following a comprehensive assessment of possible
alternative solutions to the project’s service requirements, including capital development
costs and ongoing operating and maintenance costs of each alternative. The Report is to
be provided to the Quantity Surveyor for inclusion in the Business Case report.
Identify the cost of capital required to achieve recurrent savings.
Provide the Project Manager and Project Control Group with advice and recommendations
on issues associated with their area of professional responsibility.
Ensure the schematic design for their area of responsibility conforms to the scope of work
and budget for the project.
Continuously monitor architectural, structural and civil engineering and services decisions,
drawings and documentation for their functional, capital and/or recurrent cost impact.
442500923.doc
83
Prepare benchmarks for evaluation of the Schematic Design against comparable projects in
accordance with Department of Health requirements.
Design Reviews.
7. Lift services engineers are required to:
Identify areas of high recurrent costs for consideration by the Project Control Group at the
Design Review.
Provide cost reduction options that may be needed to maintain the project cost within
Budget.
Design Development
8. During design development the lift services engineers is required to carry out the following
tasks in relation to their area of professional responsibility:
Resolve any outstanding design issues, including any changes to the Schematic Design
required as a result of the Design Review.
Prepare a report that includes evaluation statements for all major decisions for inclusion in
the Design Development Report for the project.
Ensure design development for their area of responsibility meets the functional
requirements of the brief and is in accordance with the project budget.
Provide any information necessary to identify issues associated with special facilities and/or
major plant and equipment.
Ensure all exposed furniture, fixtures and fittings are designed in accordance with
requirements for harm minimisation and are vandal proof.
Provide the Quantity Surveyor with estimates of the cost of lift services for inclusion in Cost
Plant C2.
Provide the Architect with all the information required to finalise Room Data Sheets.
Prepare draft Specification if required.
Review all systems to ensure their coordination with all other systems, eg architectural,
structural, electrical etc.
Contract Documentation
9. During contract documentation the lift services engineer is required to undertake the following
tasks in relation to their area of professional responsibility:
Prepare contract documentation suitable for competitive tendering of the project including:
- Specifications
- Documentation
- Description of maintenance requirements for essential services, major plant and
equipment and any specialised facilities.
Ensure that documentation remains within the briefed areas and budgeted cost parameters
for the project.
Ensure that all documents are checked and coordinated in accordance with quality control
requirements.
Ensure tender documentation is available for checking, coordination and costing two weeks
prior to the date of tender.
Prepare a list of suitable sub-contractors where required.
Liaise with the Project Manager and Architect in the preparation of a construction schedule.
Establish agreed contract administration procedures with the Superintendent for the proper
handling of issues (eg variations) that arise throughout the project.
442500923.doc
84
Construction
11. During construction lift services engineers are required to:
Carry out all duties associated with their profession including those of Superintendent’s
Representative (SR) when required.
Obtain all local authority approvals required and liaise with authorities regarding inspections
and other requirements.
Identify hazardous areas or equipment to maintain safe work practices.
Incorporate services requirements for Client Supplied Equipment.
Monitor the installation of services to ensure they comply with the construction documents
and achieve the design intent.
Provide regular reports regarding the project work’s progress, quality and schedule.
Examine and endorse all relevant shop drawings.
Check all off-site fabrication.
Provide any documentation required for the processing of variations.
Respond to Contractor’s requests for information and on site queries.
Amend contract drawings as required during construction and provide ’as built’ drawings
upon completion.
Ensure that the client is provided with:
- All approved operating and maintenance manuals.
- As-built drawings.
- Negatives/computer disks of installed services
Ensure that a building services commissioning program is undertaken with maintenance
operators.
Witness the testing of all equipment, systems and interfaces with other services.
Make the final inspection and report to the Project Manager.
Issue a defects lists at Practical Completion.
Inspect the works at intervals during the Defects Liability Period.
Asset Management
12. The lift services engineer is to:
Prepare a register of all major plant and equipment included in the project, recording:
442500923.doc
85
442500923.doc
86
13 Other Consultants
13.1 Building Certification Services
1. The building surveyor is required to have appropriate qualifications and expertise to assess
designs against the performance requirements of the Building Code of Australia.
Scope of Services
2. The Building Certification Consultant is responsible to the client, through the Project Manager
during the project development process.
3. Fee proposals are to allow for the use of a traditional delivery process on the project, with
allowances being made for certification in stages (eg in relation to early works packages).
4. The Building Certification Consultant is responsible for the following services:
Building Certification
Structural Certification
Engineering Services Certification
Fire Safety Audit Report Certification.
442500923.doc
87
Undertake regulatory assessment of the fire safety provisions as part of the desk top fire
safety audit.
Certify that the fire safety audit report recommended strategy will satisfy the fire related
performance requirements of the Building Code of Australia and the DH Capital
Development Guidelines—Series 7: Fire Risk Management guideline.
Review tender documentation and if satisfied that the documentation generally complies
with the fire safety strategy, issue a Building Permit.
Review supplementary reports from the Fire Safety Engineer assessing the effects of
proposed variations to the fire safety strategy during construction and if satisfied that the
design satisfies the BCA 1996, relevant regulations and relevant DH Guidelines approve
the variation.
Retain detailed floor plans as required by regulations.
Where the facility is deemed as a secure facility, take steps to ensure that access to
detailed floor plans is restricted to only those persons approved by regulations or DH.
442500923.doc
88
Phase Responsibilities.
5. The services to be provided and key deliverables for each of the various phases of the project
are detailed in the guidelines.
6. Input will be required from the ES consultant during the following phases:
Masterplan/Fabric Survey;
Feasibility Study;
Preliminary Business Case;
Schematic Design;
Final Business Case;
Delivery Phase;
Implementation Phase; and
Post Occupancy Evaluation.
442500923.doc