Professional Documents
Culture Documents
Partially Prestressed Concrete Structures - A Design Challenge PDF
Partially Prestressed Concrete Structures - A Design Challenge PDF
Partially Prestressed Concrete Structures - A Design Challenge PDF
Concrete Structures
A Design Challenge
140
recent NATO-sponsored Workshop in
Paris (June 1984) reveal that there are
not only many differing approaches to
Synopsis
the design of partially prestressed con- The author presents a simplified
crete structures but also varying opin- approach for the design of partially
ions on the definition of partial pre- prestressed concrete structures.
stressing. In addition, experiences with It is shown that partial prestressing,
partially prestressed structures actually together with supplemental nonpre-
built were reported to be scarce. stressed reinforcement, offers a better
There are three major reasons why solution (as compared to fully pre-
partial prestressing is not fully accepted stressed sections) with regard to di-
today. mensioning and shaping of members,
I. Many existing design procedures simplification of reinforcement, de-
for analyzing cracked prestressed sec- flection and crack control, and redis-
tions are considered either too compli- tribution of stresses.
cated or the calculations are too long, The proposed design procedure is
2. Most codes of practice do not en- illustrated with examples of box girder
courage the use of partial prestressing. bridges; beams, double tees, and flat
3. Experience with actually built par- slabs for buildings; river tunnels; stor-
tially prestressed structures is lacking. age tanks; and other structures. Some
The purpose of this paper is to show of the examples pertain to precast
that the design of partially prestressed pretensioned members.
structures is relatively simple and to
present several design examples of ac-
tual structures. It should be mentioned
that much of this work has been done in
cooperation with Dr. Hugo Bachmanns. 7. of a concrete member:
in Switzerland. In this manner it has
been possible to unify the differing P"rt
K=
views on partial prestressing and to come Phil
up with a more general design procedure
The values of P arr and Pmt are final
for designing such structures. forces after subtraction of all losses.
Experiences gained so far show that It should be noted that this definition
partially prestressed concrete structures of x is only correct when both prestress-
can be designed and the structural di- ing forces have the same centroid.
mensions determined as easily as those When this is not the case, as for example
for reinforced or fully prestressed con-
when fewer tendons are used in partial
crete structures. In many cases, partial
prestressing, the degree of prestress
prestressing offers a better solution with
should be defined as the ratio:
regard to simplification of the rein-
forcement and shape of the members, ""Dec
control of deflection and crack width, K _
^Mmax
and favorable redistribution of bending
moment by stiffness reduction of where
cracked sections. ML, = moment which produces zero
The most obvious expression for the concrete stress at the extreme
degree of prestress, K, is the ratio of the fiber of a section (nearest to
applied partial prestressing force, Pp.,, the centroid of the prestress-
and the prestressing force, P,,tr, which ing force), when added to the
causes full prestress under maximum action of the effective pre-
load, i.e., zero stress at the extreme fiber stress alone
142
C-)
0
C
JJ
z F^ia^IA^i^1C\1
C
At
C,
200
CI1
200
11000
Fig. 1. Cross section of fully prestressed box girder in midspan with only nonprestressed reinforcement shown.
60
70
50
70
if x=0,68
zoo
60"' i20 70 60
50 4
Fig. 2. Location of tendons in box girder at midspan (2) and oversupport (1). The three
tendons per web, which are not necessary if partial prestressing (K = 0.68) is applied,
are shown hatched.
wall (taking into account losses of pre- over the support. This layout of the ten-
stress due to shrinkage and creep of the dons is fairly complex and, therefore,
concrete, relaxation of the prestressing not easy to carry out in the actual struc-
steel, and frictional losses during ten- ture. In addition, the solution is un-
sioning of the tendons). economical. If the prestressing tendons
Fig. 2 shows the location of the pre- were not spread over the bottom flange
stressing tendons at midspan and over and deck but rather kept only within the
the support, In both parts of the struc- web zone, a total of20 tendons would be
ture, three tendons from the web are required because of the smaller internal
spread apart in the bottom and top lever arm of the prestressing force.
flanges, respectively. This means that Bending moment in a box girder
along the length of the girder the ten- causes almost pure tension (or compres-
dons from the bottom flange first have to sion) in the top flange. As is generally
be curved sideways and then upward known, the required reinforcement per-
into the web. centage for pure tension is quite large
Three tendons from the web are (between 0.4 and 0.6 percent) since the
similarly curved into the bridge deck reinforcement should not be allowed to
144
Table 1. Amount of prestressed and nonprestressed
reinforcement in top and bottom flanges of box girder for two
values of degree of prestress.
K =1.02 K =0.68
A, A, Aa A,
mm2 mm' mmg mm2
Location (in') (in?) (in.2 ) (in.2)
2400
14o
U 135
^e0
_600
135
yea
_
146
Table 3. Initial concrete stresses at bo tt om fiber and safety factor for two
degrees of prestress.
method uses a prestressing bed with depth of the double tee or (2) decrease
straight strands, although draped strands the initial prestressing force by either
are also used. A cross section of a typical reducing the number of prestressing
double tee (manufactured in the strands and adding mild steel rein-
Netherlands) is given in Fig. 3. forcement in the middle part of the span,
The simply supported element has a or decreasing the initial stress in the
span of 18.30 m (60 ft) and a depth of strands in such a way that the initial
0.60 m (2 ft). The double tee has draped compressive stress in the bottom fiber at
tendons and the concrete quality is B midspan is 18 Nlmm2 (2610 psi) or less.
37.5 corresponding with a standard In both cases, partially prestressed con-
prism strength of 30 NImm 2 (4.35 ksi) at crete is used, permitting cracks in the
28 days. tensile zone at midspan.
The initial steel stress in the prestress- Fig. 4 shows the distribution of
ing steel at transfer is 1300 N/mm2 (189 strands and bars 'h k 12 over the sections
ksi). The dead load of the double tee is at midspan. The use of mild steel rein-
8.9 kN/m (0.62 kips/ft) and the live load
is 10.6 kN/m (0.74 kips/ft), or 55 percent
of the total load. In the case of full pre- ® bars 0kl2
stressing (K = 1) in each rib of the dou- bent up
near support 0 strands 7 0 kr:
ble tee, ten seven-wire strands with a
c ro ss section of 100 mm 2 (0.155 in. ․ )
each are needed. 12
After transfer of the prestress, the 30
compressive stress in the bo tt om fiber at i2
midspan is 23 N/mm 2 (3335 psi). The
30
compressive stresses in the anchorage
zones are also lower due to the use of 12
draped tendons. Note that the Dutch 30
Code allows only 18 N/mm 2 (2610 psi) 12
permissible initial compressive stress in 30
the bottom fiber for the given concrete 128
quality.
15
From this example, it is clear that with
the given span and depth, a fully pre- 135
stressed double tee cannot be used.
Therefore, one of the following so-
lutions must be chosen: (1) increase the Fig. 4. Solution with partial prestressing.
joist
150
4'k10- 350 L ^ 3 41 1 1-m l
75
f I ' I
mklo-3_ _
i40 3 of 14in)
925
I
I
I
I I
i
I
21O(2#31
0k 10-350
2I(t)E231
1 2mk1012*31
125 © I o
2 C
325
t a
L4k1214N4 1
I 1
400
Fig. 5. End section (left) and midspan section (right) of fully prestressed roof beam.
148
800
150
75
o longitudsnal reinforcement
1(2#3)
1375
DI
i ^^ I lh & 3 at 14 in)
DI I
o 1B12 (8-#4)
. 7\ I 3tendons
______
BBR -B20
220 45 45 5
220
0
0
co
7x2 s5k12
(7x2#4)
—4012
(4.#4)
31ooa12
150
Table 4. Mean concrete stresses and safety factor for two values of
degree of prestress.
K A: P. a Nfmm` (psi) Y
t o.L5
E
LA
Dk 25-200 k16-200
concreting after prestressing
(#t8at8"^ /{#5at8")
B.R.Y. –U R- 500
stirrups
(t16 (f^ 5),
ON 25-200 i,15-200
(;# 8 at 8 -) (#s at 8"?
152
tunnel roof. This will occur in the con- A further analysis of cracking shows
struction dock on both the upper face at that the crack widths calculated in this
midspan and on the lower (inner) face way are sensitive to the amount of cal-
near the center support, as well as under culated effective prestress. If this pre-
service conditions on the lower face at stress decreases to 90 percent of the
mispan and on the upper face near the value adopted, the crack width under
center support. The stress situation is dead plus live load will increase from
just the opposite for the bottom slab of 0.16 to 0.26 mm. This underlies the ex-
the tunnel. treme importance of taking into account
The reinforcement and prestress ar- realistic prestress losses.
rangements for the tunnel roof are The tunnel roof at the above men-
shown in Fig. 9. The area of the non- tioned center support can be charac-
prestressed reinforcement at the upper terized as follows:
as well as the lower face is approxi- • Degree of prestress – x = 0.73 (A,
mately 0.27 percent of the concrete = 0.82)
cross-sectional area. • Percentage of nonprestressed re-
The prestress is located about 0.11 m inforcement – p, = 0.27 percent
(3.6 ft) from both the upper face of the • Percentage of prestressed rein-
roof near the center support and at forcement – p,, = 0.27 percent
midspan from the lower face. The pre- • Mean concrete stress:
stressing tendons are entirely within the a,,^,a = –3.3 N/mm2 (-480 psi)
reinforcement installed at the upper and (prestress only)
lower faces. The prestressing system = –4.1 Nlmm 2 (-595 psi)
chosen for this tunnel is BBR-U3 with (stresses by horizontal water pres-
12 strands of 12.9 mm diameter and ini- sure included)
tial prestressing force of 1680 kN (386 It can be concluded that the tunnel
kips). roof and the bottom slab can be effi-
The calculations show that cracking ciently constructed with partially pre-
can be expected only in that part of the stressed concrete. This will result in a
tunnel roof which is adjacent to the simplified reinforcement arrangement
center support. The crack widths (given and a relatively simple prestress profile.
in mm) were calculated with the formula Moreover, crack widths can be very ef-
given in the Dutch Code of Practice for fectively controlled.
concrete construction:
5. Connection of Tank Wall to
w = (8) (10') r ( 2c + ^-) (1) Floor Slab
In many storage tank structures with
where horizontally prestressed concrete walls,
o•, = steel stress (N/mm2) the circular curved wall is designed to
c = concrete cover (mm) move freely in relation to the bottom or
(b k = bar diameter (mm) floor slab. The joint between wall and
p = As IAA floor is detailed in such a way that the
The calculated crack widths near the anticipated horizontal displacements
inner support are: can be properly accommodated and the
During stressing of the tendons joint remains liquid tight. A joint of this
.......... 0.11 mm on inner face type is shown in Fig. 10.
Under dead plus live load A special case is the joint between the
............. 0.16 mm on outer face base slab and the safety wall around a
Under abnormal load tank containing liquified natural gas
.......... 0.39 mm on outer face (LNG). This joint has to remain liquid
me
tight at very low temperatures to ensure much care and attention and which,
that, in the event of an inner tank failure, after being put into service, will con-
the cold liquid will not flow out over a tinue to need maintenance. If the
large area." Such a joint is complicated wall-to-floor slab connection is of
and expensive because the nonpre- monolithic construction, many problems
stressed reinforcement, the horizontal and difficulties are eliminated.
tendons, and the anchorages of the ver- Such a joint does not require extra
tical tendons are situated in the joint maintenance and the tank can be em-
area. In addition, the joint has to be in- bedded easily in backfill soil. However,
spected regularly and maintained. at the time of horizontally prestressing
Separate connection details are the wall, the deformation in the hori-
needed for transmitting to the base slab zontal direction is restrained by the
the horizontal forces that may act upon monolithic joint. This means that part of
the safety wall in the event of an exter- the prestress is transmitted to the floor
nal explosion or earthquake. Fur- slab, resulting in shear forces and
thermore, in the occurrence of differ- bending moments (with respect to the
ential settlement of the relatively flexi- horizontal plane) occurring in that part
ble slab, the joint will have to allow de- of the wall adjacent to the floor slab.
formation in the vertical direction. This can result in local curvature of the
Therefore, from a technical viewpoint, floor slab (see Fig. 11).
the construction of a wall-to-floor slab The bending stiffness and bending
connection is quite complex. moment at the wall-floor slab connec-
In the tanks of sewage treatment tion is reduced by cracking. Therefore,
plants and other such installations, a when partial prestressing is applied and
"free" joint between wall and base slab horizontal cracks in the wall occur, the
is a construction detail which requires bending stiffness and the vertical
154
Ld med
med wall
formed slab
hin
—pile (deformed)
rigid connection
Fig. 11. Deformation of wall and bottom slab due to horizontal prestressing of wall.
bending moment in the wall are re- The following data are relevant to the
duced (Fig. 12). Research has shown pattern of forces acting at the connec-
that the bending moment at the wall- tion:
floor connection can he nearly halved (1) Ring prestress (tangential stresses) of
and the shear forces reduced. tank wall:
The mild steel reinforcement and pre- (a) Free movement of wall in relation
stressing steel arrangements for a con- to the bottom: o- = –11.7 N/mm2
nection of this type are shown in Fig. 13. (-1695 psi).
This particular example concerns a (b) Monolithic connection, as in Fig.
safety tank for liquified petroleum gas 13, analyzed on nonlinear elastic
(LPG) according to the C-IS system. assumption: o = –2.6 Nlmm2
This is an isolated steel tank, sur- (-375 psi).
rounded by a prestressed concrete (2) Bending moment at connection (Fig.
safety tank. The circular space between 12a):
the walls is filled with nitrogen gas. The (a) Analyzed on linear elastic as-
tank wall has been designed to resist a sumption: M = –500 kNm/m
water pressure corresponding to a depth (-112 kip-ft/ft)
of 26 m (85.5 ft) in the water test. The (b) Analyzed on nonlinear elastic as-
wall-to-floor connection was found to sumption: M = –370 kNm/m (-85
meet expectations entirely. kip-ft/ft)
8m
7
6
5
r=25m 4 d w =O.6Orr
3
25akNm/m
(A
E
LE) 2 E
Q
1
oTI
I Mxx
2.QQrn J i 90mpJ
Fig. 12. Moment diagrams at wall-to4loor connection of tank. Left: after initial prestress. Right: water test and effective prestress.
LE = linear elastic, NLE = nonlinear elastic.
600
vertical prestressing
a (U-shaped)
sv - 0 PSV = 0.67
o i
) o o foundation slab
0 0
concrete piles
0.45 x 0.45 m
0 0
N N
EIIi 1111111 — o
1110
L 7,20
Fig. 14. Plan of middle panel, Unbonded tendons are concentrated in a zone of 31 in. (800 mm) around
centerlines of columns.
applied in the column strips and func- the reinforcing steel. As a result of this
tions as an artificially applied load time-dependent shortening of the con-
which counteracts part of the load in the crete, the longitudinal reinforcement
middle panel between the column strips also shortens and carries a larger pro-
(see Fig. 14). portion of the column's load, thus reliev-
As shown in Fig. 14, a load of 4.7 ing the concrete of part of the load.
kN/m2 (0.093 kips/ft) has been adopted, For an axially loaded column the con-
excluding the dead weight of the con- crete stress at time t = x can be calcu-
crete slab which is 0.22 m (9 in.) thick. lated by various methods. 1° Two of these
The column strips contain ten prestress- are:
ing tendons, each consisting of one 12.9 (1) Effective modulus method:
mm diameter strand. These tendons are
1
installed in the two mutually perpen- 7 pEt€n,,, )
(aco
dicular column strips which act as sup- r9 l + Tep(l+^m)
port strips. (2)
Fig. 15 shows the reinforcement and
prestressing arrangements at the slab- (2) Dischinger's method:
to-column connection. Studies indicate ac^ _ aco Ivey + Es^E^
that in flat slab floors the effect of the jl 4),,(i +n p^1(1–ems)
normal force due to prestress upon the (3)
crack width is often negligible.
The middle panel under considera- where
tion has been analyzed for two cases, np 4x
namely, prestress without bond and pre- = I +tip
stress with bond, both for p, = 0.27 per-
cent and a degree of prestress, K = 0.56. Although there are more advanced
The difference in p, of nonprestressed analytical methods than Dischinger's
reinforcement is small: p, = 0.44 percent equations to determine the concrete
for prestress without bond and pr = 0.41 stresses, it appears from the calculations
percent for prestress with bond. In both in Ref. 10 that this method gives the best
cases the safety factor y = 1.7 and the results when compared to test data.
mean concrete stress o-,,„ , ,, = —0.8 Although the preceding discussion
NImm2 ( - 116 psi). relates to a column, the theory also
At the center of the panel, the ap- applies to the tensile zone of a pre-
proximate crack width under full load is stressed concrete beam, except that the
0.26 mm without bond and 0.11 mm beam calculations are usually more
with bond. It is apparent from these val- complicated. The general behavior
ues that in the latter case the prestress- mode of a partially prestressed beam
ing steel acts also as reinforcement and subject to sustained load is that the
thus helps to reduce the crack width. compressive stress in the extreme fiber
of the concrete section decreases while
the compressive stress in the reinforcing
INFLUENCE OF steel increases, i.e., the tensile stress in
TIME-DEPENDENT EFFECTS the prestressing steel decreases.
Using Dischinger's method, the rela-
In a reinforced concrete column sub- tion between the concrete stress o-, in
ject to a large axial compressive load the bottom fiber, combinations of time-
over a long period of time, a redistribu- dependent effects p ; €, ), and the
tion of stresses occurs. This stress redis- reinforcement cross section (p„ ; p,) have
tribution is due to shrinkage and creep been plotted in Fig. 16.
of the concrete and elastic shortening of The example chosen is a partially pre-
220
180
_PS=6Pp
Fig. 16. Relation between concrete stress cr cz in bottom fiber and various
combinations of creep factor 4. and shrinkage value € , for three values of ps.
stressed concrete tee beam. Relaxation -250 x 10-", the magnitude of the
losses of the steel stresses were not time-dependent shortening in the ten-
taken into account. The calculation was sile zone is:
based on the assumption that the bend-
ingmomentM o due to the dead load does Ec+g 250 x 101
2(- 5.) --
not change with time and at t - 0 the
= -559x10
prestressing force is 573 kN (129 kips)
regardless of the cross-sectional area of Hence, the decrease in the steel stress
the nonprestressed steel. is 559 x 10- e x 205,000 = 114 N/mm2
Actually, the ultimate load carrying (16.5 ksi).
capacity of the member is increased For a bending moment:
when supplemental reinforcing steel is Md = 169kNmandPe = 521 (1100 -
placed in the tensile zone. Directly after 114) N, we now obtain rr, g = -4.5
tendon stressing, the compressive stress N/mm2 ( - 650 psi). For the case where p,
in the concrete is reduced from -6.1 = 0, Discbinger's method gives a value
N/mm2 (-885 psi) for p, = 0 to -5.3 of -4.7 N/mm2 (-680 psi),
N/mm2 (-770 psi) forp, = 2 p p or to -4.2 This calculation turns out to be very
N/mm2 (-610 psi) for p, = 6 p,. This is simple and as Fig. 16 shows, reasonably
due to the influence of the nonpre- accurate when p, = 0. However, if sup-
stressed steel. plemental reinforcing steel is present,
In the case where 0- = 2 and e cd,a = the concrete compressive stress o•,s
-250 x 10-8 , the following values of a which develops over time is consid-
are found: -4.7, -2.4, and -0.3 N/mm2 erably smaller. Therefore, the compres-
(-680, -350, and -45 psi), for p $ = 0, pg sive stress in the flexural tensile zone of
= 2 p n, and p a = 6 p p, respectively. a member can be significantly reduced
Fig. 16 shows that when increasing by time-dependent effects when non-
the ratio of nonprestressed reinforce- prestressed steel is added in the tensile
ment, p, (for an equal initial prestressing zone of an originally fully prestressed
force A„ a-,,), the compressive stress 0c2 section.
in the concrete on the flexural tensile However, in a partially prestressed
face of the beam decreases. This com- concrete member, part of the prestress-
pressive stress continues to decrease ing steel used to produce full prestress
with tine-dependent effects, 0. and is replaced by nonprestressed steel. In
E es. A this case, the time-dependent effects
Most codes of practice for fully pre- only moderately reduce (which can
stressed concrete members allow a often be neglected) the compressive
simplified method to calculate prestress stress. Therefore, a question arises as to
loss due to shrinkage and creep. This how the simplified analysis affects the
calculation neglects the nonprestressed magnitude of the decompression mo-
steel in the flexural tensile zone and ment, MB,,, and the crack width, w, as-
leads to the decrease of o- 2 , as indicated sociated with full load, Md+t .
by the dashed line in Fig. 16. The fol- To answer this question, a study was
lowing example illustrates the design conducted at the Delft University of
approach. Technology" using mathematical mod-
els in which the stress distributions in
the cross sections of partially pre-
Example
stressed structures were determined.
Suppose that immediately after Using the simplified design method,
stressing the tendons, the concrete several structures (double tees and box
stress at the level of the steel centroid is beam) were analyzed with different de-
-6.1 N/mm2 ( - 885 psi). With 0„ = 2 and grees of prestress.
162
E
z
cd
E
0
E
c
N
0
U)
C)
I-
0
E
0
u
C)
degree of prestress x
Fig. 17. Relation between decompression moment M. and degree of prestress K for
midspan section of double tee with span of 66 ft (20 m).
This simplified calculation procedure presented in Fig. 16, this is not the case.
resulted in an almost linear relationship To clearly show the effect of the steel
between the decompression moment cross section in the flexural tensile zone
Mme, and the degree of prestress K. The on the stress redistribution due to
mathematical models also showed what time-dependent effects (see Fig. 16),
the actual M,, versus K relationship is, reinforcement was added to the section
based on a particular variation of creep without the cross-sectional area of the
and shrinkage of the concrete)' The re- prestressing steel being reduced in
sult is presented in Fig. 17. proportion. However, in Fig. 17, such a
It appears from Fig. 17 that M cal- reduction was made in the calculations.
culated for various degrees of prestress The magnitude of the prestressing
by the simplified method differs only force is reduced when the steel cross-
slightly from M, computed by Dis- sectional area is increased so that the
chinger's method. Also, variations in ultimate moment Mu of the section re-
shrinkage and creep of the concrete mains constant. Therefore, reduction of
have little effect on the magnitude of the prestressing force means a decrease
M. The line terminating at 1175 kNm in the magnitude of the compressive
in the diagram was calculated by the stress o-, in addition to a decrease in
simplified method. The line terminating the influence of time-dependent effects.
at 1106 kNm relates to e,. , ,, = 200 x 10 As a result, the structure becomes
and 4 = 1.5. The next line relates to stiffer and the concrete stresses undergo
= 250 x 10- 1 and ¢. – 2.0, and the smaller increases per unit of bending
bottom line to e^g, m = 300 x 10 - 1 and ¢. _ moment than when there is little steel in
2.5. the flexural tensile zone. This applies
Although this study appears to con- more particularly to the stage where the
tradict the results of the calculations tensile zone is uncracked.
164
prestressed reinforcement crack width, at least a minimum amount
di p = diameter of prestressing steel, of nonprestressed reinforcement should
i.e., diameter of individual be used in the tensile zone of post-
wires or bars or the wires of tensioned beams or slabs in which
which a strand is composed cracking is not fully excluded. This also
To calculate the steel -stress at the is advocated by Bachmann"-' and
crack, it is necessary to take into account others.
the same proportion of the cross section In prestressed concrete with post-
of prestressing steel, namely, the cross tensioned tendons, the tendons are usu-
sectional area of the steel to be adopted ally located at somewhat greater dis-
as tensile reinforcement is equal to A, tances from the underside of the beam
plus cAp . For example, consider a pre- than the reinforcing bars are. For this
stressing cable comprising 20 strands (7 reason, too, the increase in stress in the
wires 0 p = 4 mm) in conjunction with prestressing steel due to cracking will
reinforcing bars 0, = 12 mm. Then: be less than that in the nonprestressed
c= i^ x 4 =0.25
reinforcement.
The research at Delft University
shows that the stress increase in the pre-
stressing steel after cracking may be-
Therefore, when cracking occurs in come quite significant when low de-
the tensile zone of a member with only gress of prestressing are employed. This
post-tensioned, grouted cables, there is, however, particularly true of pre-
will be wide cracks at great distances. stressed concrete with pretensioned
To distribute the cracks and limit the steel.
1500 °p
1175
initial. stress Opi =1395 (N /mm2)
940
E 1400
695
E M
(kNm)
1300
a,
Mcr
1200
e- Mae
1175
N 940
^'
LA
1100 695
N
c 1000
_
U)
U,
v
L
Fig. 18. Relation between degree of prestress K and stress (r, in prestressing steel under
three different loads.
166
L
0
c deformations
M
z
C cri
ds dp
I
us2
Fig. 19. Derivation of steel stresses under M. ES
S.Cr
3DC
E
E
z 25C kN
1175
CD 20(
L.
d 15C
a 940 .
0
0 1DC
a
C
St
U
C
C
_55C
0.2 04 0.6 Q8 1.0
degree of prestress x
the crack width can be limited to 0.05 strength) and location of the bars in the
mm by using bars with 0 k = 6 mm. This structural section. Raising the load
is, of course, not a suitable diameter for above the value corresponding to the
practical use. If bars with rt k = 10 mmn cracking moment causes the steel to in-
are used, the crack width is limited crease, a fact that must he considered.
to about 0.08 mm, while 16 mm and 25 This can be done by assuming that, at
mm bars limit the crack widths to about higher steel stress values, the crack
0.10 mm and 0.15 mm, respective- width increases proportionately to the
lv. steel stress.
Thus, crack width associated with In the case of members loaded in
elongations can he controlled by a suit- bending, it is usually possible to apply
able choice of deformed bar diameter, the rules for crack width calculation
reinforcement cross-sectional area for which are given in various codes of
the given concrete quality (specified practice.
CONCLUSION
168
B-22.5
■■MMMENNE ONNUM■■■
3rOk
2
E
a 2
a,
E
D1
L
■►^^\►N\►\ M\NZ
0
1D
•
■■■■\i■■■■^1i■■■■rte
■■■■■■■■■■■■■■■■■■
Fig. 21. Relation between bar diameter d., steel stress o$, cr , and crack width w.
Concrete cube strength is 22.5 Nlmm 2 (cylinder strength is 18 NImm2 or 2.61 ksi).
one commonly applied to reinforced tensile zone, the stresses in the prestress-
concrete structures eccentrically loaded ing steel crossing the crack increase. By
in compression. The compressive force using the simplified method of analysis
externally applied to the section is the and design, this effect can be taken into
effective prestressing force which can account as well as bond behavior differ-
be determined from the initial prestress- ences between post-tensioned prestress-
ing force in the same way as with fully ing cables and reinforcing steel an-
prestressed designs. chored by bond.
If the stress in the reinforcing steel is In conclusion, it has been shown that
known, the bar diameters of that steel the procedure for designing partially
can he chosen, within the limits used in prestressed concrete structures is no
actual practice, so that crack width limit more difficult than the design of fully
requirements can be fulfilled. However, prestressed or conventionally reinforced
to do this, it may be necessary to adapt members. Partial prestressing offers
the reinforcement cross-sectional area to many distinct advantages which can be
suit individual cases. used to produce more efficient and im-
As a result of cracking in the flexural aginative concrete structures.
ACKNOWLEDGMENT
The author wishes to express his ap- Technology, The Netherlands, for re-
preciation to Mr. J. Brakel, senior scien- viewing and checking the original man-
tific officer of Delft University of uscript.
170
APPENDIX - NOTATION
A, = cross-sectional area of con- = shrinkage strain from t = 0 tot
crete =00
At, = cross-sectional area of pre- r1 = coefficient = n p 0, l(1 + n p)
stressing steel K = degree of prestress K =
A, cross-sectional area of non- MD er I Mn +L
prestressed reinforcing steel p = A:+p /A,
= modulus of elasticity of con- p^ = ABA,
crete pv = An/A,
E„ = E, = modulus of elasticity of a cz = concrete stress at top fiber
steel (compressive zone)
MA = bending moment due to dead o cz = concrete stress at bottom fiber
load Crro = concrete stress at t = 0
Mme' = bending moment of decom- 6^ a – concrete stress at t = x
pression = concrete stress, mean value at
'WD+L = maximum bending moment t=-(P„+Ma)
M„ = ultimate bending moment CrV
, = initial stress in prestressing
N = normal force steel (t = 0)
P! = initial prestressing force U„ = steel stress in reinforcement
I
stressed reinforcement = bar diameter of prestressing
tk = permissible tensile strength steel
(upper value) of concrete A cr, = stress increase in prestressing
.1 = internal lever arm steel due to cracking of con-
n = modular ratio crete
t = time A U,,« = stress increase in normal
U) = crack width reinforcement due to cracking
7 = safety factor for ultimate load of concrete