Professional Documents
Culture Documents
Irece Vol 9 N 3
Irece Vol 9 N 3
Irece Vol 9 N 3
net/publication/327289313
CITATIONS READS
0 500
4 authors, including:
Suprapto Siswosukarto
Universitas Gadjah Mada
49 PUBLICATIONS 34 CITATIONS
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
The Study of Wooden Clamps for Strengthening of Connection on Bamboo Truss Structure View project
All content following this page was uploaded by Suprapto Siswosukarto on 19 September 2018.
International Review of
Civil Engineering
(IRECE)
Contents
Editor-In-Chief:
Prof. K. M. Liew
Chair Professor of Civil Engineering
Department of Civil and Architectural Engineering
City University of Hong Kong
Hong Kong SAR
Editorial Board:
Abrams Daniel P. (U.S.A.) University of Illinois
Ansal Attila (Turkey) Bogaziçi University
Banthia Nemkumar (Canada) University of British Columbia
Berke Philip (U.S.A.) University of North Carolina at Chapel Hill
Cai Steve C. S. (U.S.A.) Louisiana State University
Chan Siu-Lai (Hong Kong) The Hong Kong Polytechnic University
Dey Subhasish (India) Indian Institute of Technology
Dhakal Rajesh P. (New Zealand) University of Canterbury
Folić Radomir (Yugoslavia) University of Novi Sad
Kappos Andreas (Greece) Aristotle Univ of Thessaloniki
Kovler Konstantin (Israel) Israel Institute of Technology
Liew Jat Yuen Richard (Singapore) National University of Singapore
Mang Herbert (Austria) Vienna University of Technology
Sapountzakis Evangelos J. (Greece) National Technical University of Athens
Tan Kiang Hwee (Singapore) National University of Singapore
Tenek Lazarus (Greece) Aristotle University of Thessaloniki
Triantafillou Thanasis (Greece) University of Patras
Ye J. (U.K. ) University of Leeds
The International Review of Civil Engineering (IRECE) is a publication of the Praise Worthy Prize S.r.l..
The Review is published bimonthly, appearing on the last day of January, March, May, July, September, November.
Published and Printed in Italy by Praise Worthy Prize S.r.l., May 31, 2018.
This journal and the individual contributions contained in it are protected under copyright by Praise Worthy Prize S.r.l. and the following
terms and conditions apply to their use:
Single photocopies of single articles may be made for personal use as allowed by national copyright laws.
Permission of the Publisher and payment of a fee is required for all other photocopying, including multiple or systematic copying, copying
for advertising or promotional purposes, resale and all forms of document delivery. Permission may be sought directly from Praise
Worthy Prize S.r.l. at the e-mail address:
administration@praiseworthyprize.com
Permission of the Publisher is required to store or use electronically any material contained in this journal, including any article or part of
an article. Except as outlined above, no part of this publication may be reproduced, stored in a retrieval system or transmitted in any form
or by any means, electronic, mechanical, photocopying, recording or otherwise, without prior written permission of the Publisher. E-mail
address permission request:
administration@praiseworthyprize.com
Responsibility for the contents rests upon the authors and not upon the Praise Worthy Prize S.r.l..
Statement and opinions expressed in the articles and communications are those of the individual contributors and not the statements and
opinions of Praise Worthy Prize S.r.l.. Praise Worthy Prize S.r.l. assumes no responsibility or liability for any damage or injury to
persons or property arising out of the use of any materials, instructions, methods or ideas contained herein.
Praise Worthy Prize S.r.l. expressly disclaims any implied warranties of merchantability or fitness for a particular purpose. If expert
assistance is required, the service of a competent professional person should be sought.
International Review of Civil Engineering (I.RE.C.E.), Vol. 9, N. 3
ISSN 2036 - 9913 May 2018
Abstract – Poboya Mountains is one of the gold mines located in Palu city. Miners conduct
quarrying and slope slicing to extract gold ores every day, resulting in changes on slope stability.
The research is to determine rock mass classification and slope stability of metamorphic rocks.
The research conducted at Poboya Gold Mine, it geographically located at central of Sulawesi
province. The classification of rock mass carried out through a field survey and a laboratory
testing, and then determined according to methods of RMR and SMR. The results showed that for
gneiss at location 1, it obtained values of 60-69 for RMR and SMR as well. Meanwhile, for schist
at location 2, the obtained values are 56-71 for RMR and 57-79 for SMR. Schist at location 3 has
values of 65-75 for RMR and 69-79 for SMR, and schist at location 4 have values of 56-70 for
RMR and 59-85 for SMR. Referring to the rock mass classification results, it can be concluded
that slopes location at Poboya with a good quality of rock mass is at schist of location 3.
Generally, slopes considered stable, hence there will be no landslides, and if landslide occurs, it
will merely occurs on small blocks. Copyright © 2018 Praise Worthy Prize S.r.l. - All rights
reserved.
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved https://doi.org/10.15866/irece.v9i3.13889
91
S. Ramadhani, A. Rifa’i, K. B. Suryolelono, W. Wilopo
92
S. Ramadhani, A. Rifa’i, K. B. Suryolelono, W. Wilopo
TABLE I
ROCK MASS CLASSIFICATION AT GNEISS LITHOLOGY (LOCATION 1)
UCS RQD Spacing Discontinuity Conditions RMR SMR
Lithology Length Separation Ground Water F1 F2 F3 F4
MPa (%) (m) Roughness Infilling Weathering Total Class Total Class
(m) (mm)
Gneiss-1 31 96 0.3 0.2 0.5 SR NO HW CD 61 67 99
69 II 0 69 II
Rating 4 20 10 6 4 3 6 1 15 0.15 1 0
Gneiss-2 31 94 0.2 1 0.8 SR NO HW CD 97 81 113
65 II 0 65 II
Rating 4 20 8 4 4 3 6 1 15 0.15 1 -6
Gneiss-3 31 89 0.2 1.6 0 SR NO HW CD 112 89 121
63 II 0 63 II
Rating 4 17 8 4 5 3 6 1 15 0.15 1 -25
Gneiss-4 31 78 0.1 1 0.5 SM NO HW CD 12 89 121
60 II 0 60 II
Rating 4 17 8 4 4 1 6 1 15 0.15 1 -25
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
93
S. Ramadhani, A. Rifa’i, K. B. Suryolelono, W. Wilopo
TABLE II
ROCK MASS CLASSIFICATION AT SCHIST LITHOLOGY (LOCATION 2)
UCS RQD Spacing Discontinuity Conditions RMR SMR
Ground
Lithology Length F1 F2 F3 F4
MPa (%) (m) Separation(mm)Roughness Infilling Weathering Water Total Class Total Class
(m)
Schist-1 41 86 0.2 0.6 3 SR NO MW CD 64 51 -12
63 II 0 72 II
Rating 4 17 8 6 1 3 6 3 15 0.15 1 -60
Schist-2 41 94 0.3 0.7 1.3 SR NO MW CD 143 51 -12
68 II 0 77 II
Rating 4 20 10 6 1 3 6 3 15 0.15 1 -60
Schist-3 41 91 0.2 1.2 20 SR SF>5 MW CD 58 76 13
57 III 0 57 III
Rating 4 20 8 4 0 3 0 3 15 0.15 1 0
Schist-4 41 97 0.4 0.7 5.5 SR NO MW CD 123 64 1
67 II 0 69 II
Rating 4 20 10 6 0 3 6 3 15 0.4 1 -6
Schist-5 41 98 0.5 1.8 1 SR SF>5 MW CD 115 46 -17
60 III 0 69 II
Rating 4 20 10 4 1 3 0 3 15 0.15 1 -60
Schist-6 41 58 0.1 0.4 1 SR NO MW CD 89 81 18
59 III 0 60 III
Rating 4 13 8 6 1 3 6 3 15 0.15 1 0
Schist-7 41 86 0.2 0.6 0 SR SF>5 MW CD 133 39 -24
61 II 0 69 II
Rating 4 17 8 6 5 3 0 3 15 0.15 1 -60
Schist-8 41 91 0.2 0.1 0 SR NO MW CD 73 60 -3
70 II 0 78 II
Rating 4 20 8 6 5 3 6 3 15 0.15 1 -50
Schist-9 41 74 0.1 0.5 1 SR NO MW CD 115 29 -34
59 III 0 63 II
Rating 4 13 8 6 1 3 6 3 15 0.15 1 -60
Schist-10 41 89 0.2 1 2 SR NO MW CD 28 77 14
61 II 0 61 II
Rating 4 17 8 4 1 3 6 3 15 0.4 1 0
Schist-11 41 71 0.2 0.3 0.7 SR SF>5 MW CD 133 62 -1
56 III 0 64 II
Rating 4 13 8 6 4 3 0 3 15 0.15 1 -50
Schist-12 41 92 0.2 1.2 15 SR SF>5 MW CD 94 39 -24
57 III 0 65 II
Rating 4 20 8 4 0 3 0 3 15 0.15 1 -60
Schist-13 41 96 0.3 2.1 70 SR SF>5 MW CD 101 72 9
59 III 0 60 III
Rating 4 20 10 4 0 3 0 3 15 0.15 1 -6
Schist-14 41 99 0.9 1.2 5 SR NO MW CD 107 39 -24
71 II 0 79 II
Rating 4 20 15 4 1 3 6 3 15 0.15 1 -60
Schist-15 41 95 0.3 0.5 30 SR SF>5 MW CD 116 68 5
61 II 0 62 II
Rating 4 20 10 6 0 3 0 3 15 0.15 1 -6
Schist-16 41 93 0.23 0.2 1 SR SF>5 MW CD 69 41 -22
62 II 0 70 II
Rating 4 20 10 6 1 3 0 3 15 0.15 1 -60
Results of RMR value weighting obtained that for with rock mass classification from good to fair.
gneiss at location 1 as in Table I, for schist at location 2 The largest RMR value is in schist-7, and this is
shown in Table II, for schist at location 3 presented in influenced by smaller separation value, hence, the quality
Table III and for schist at location 4 presented in Table of schist-7 according to a width aperture has a better
IV. quality. The greatest RMR value for all locations found
The results are as follows: in schist lithology at location 3, and this is affected by
1. Gneiss: the large value of compressive strength, RQD value is
For gneiss lithology at location 1, RMR value ranges dominantly large, average spacing of discontinuities is
from 60-69, included in rock mass of class II and class III great, no infilling and underground water condition of the
with rock mass classification from good to fair. The discontinuity field is dry.
greatest RMR value is in gneiss-1, and this is influenced Based on the above results, then the best rock mass
by the large value of RQD and spacing among quality from four location is what found in schist
discontinuity fields. lithology at location 3, for it dominantly has the greatest
2. Schist: value of RMR.In addition to that, it was found in blocks
For schist lithology at location 2, RMR value ranges all locations having a poor rock mass quality which is a
from 56-71, included in rock mass of class II and class III small RMR value.
with rock mass classification from good to fair. The
largest RMR value is in schist-14, and this is influenced
V.2. Slope Mass Rating (SMR)
by the large value of RQD, spacing among discontinuity
fields and no discontinuity aperture filler. SMR value is obtained based on the equation [20],
For schist lithology at location 3, RMR value ranges [17].
from 65-75, included in rock mass of class II with a good Results of SMR value calculation for gneiss lithology
rock mass classification. The largest RMR value is in at location 1 can be seen in Table I, for schist lithology at
schist-9 based on a smaller separation value, hence, the location 2 described in Table II, for schist lithology at
quality on schist-9 which is referred to a width aperture location 3 shown in Table III, and for schist lithology at
has a better quality. location 4 can be found as well on Table IV.
For schist lithology at location 4, RMR value ranges Referring to the obtained results according to location
from 56-70, included in rock mass class II and class III and lithology can be deliberated as following:
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
94
S. Ramadhani, A. Rifa’i, K. B. Suryolelono, W. Wilopo
TABLE III
ROCK MASS CLASSIFICATION AT SCHIST LITHOLOGY (LOCATION 3)
UCS RQD Spacing Discontinuity Conditions RMR SMR
Ground
Lithology Length F1 F2 F3 F4
MPa (%) (m) Separation(mm)Roughness Infilling Weathering Water Total Class Total Class
(m)
Schist-1 66 99 0.6 3 1 SR NO MW CD 86 69 129
67 II 0 71 II
Rating 7 20 10 2 1 3 6 3 15 0.15 1 -25
Schist-2 66 97 0.4 1.1 10 SR NO MW CD 84 76 136
68 II 0 72 II
Rating 7 20 10 4 0 3 6 3 15 0.15 1 -25
Schist-3 66 95 0.3 0.9 1.43 SR NO MW CD 70 85 145
71 II 0 75 II
Rating 7 20 10 6 1 3 6 3 15 0.15 1 -25
Schist-4 66 99 0.6 1.1 3 SR NO MW CD 202 35 95
69 II 0 69 II
Rating 7 20 10 4 1 3 6 3 15 0.4 1 0
Schist-5 66 98 0.5 0.8 5 SR NO MW CD 99 78 138
71 II 0 75 II
Rating 7 20 10 6 1 3 6 3 15 0.15 1 -25
Schist-6 66 97 0.4 1.1 10 SR NO MW CD 81 70 130
68 II 0 72 II
Rating 7 20 10 4 0 3 6 3 15 0.15 1 -25
Schist-7 66 91 0.2 0.7 10 SR NO MW CD 100 60 120
68 II 0 69 II
Rating 7 20 8 6 0 3 6 3 15 0.15 1 -6
Schist-8 66 99 0.6 1 1 SR NO MW CD 221 64 124
65 II 0 69 II
Rating 7 20 10 0 1 3 6 3 15 0.15 1 -25
Schist-9 66 97 0.4 0.9 0 SR NO MW CD 70 74 134
75 II 0 79 II
Rating 7 20 10 6 5 3 6 3 15 0.15 1 -25
TABLE IV
ROCK MASS CLASSIFICATION AT SCHIST LITHOLOGY (LOCATION 4)
UCS RQD Spacing Discontinuity Conditions RMR SMR
Ground
Lithology Length F1 F2 F3 F4
MPa (%) (m) Separation(mm)Roughness Infilling Weathering Water Total Class Total Class
(m)
Schist-1 81 94 0.2 1.6 4 SR NO MW CD 92 67 126
67 II 0 71 II
Rating 7 20 8 4 1 3 6 3 15 0.15 1 -25
Schist-2 81 87 0.2 2 5 SR SF>5 MW CD 149 68 127
58 III 0 62 II
Rating 7 17 8 4 1 3 0 3 15 0.15 1 -25
Schist-3 81 85 0.1 0.6 0.5 SR NO MW CD 30 66 125
69 II 0 79 II
Rating 7 17 8 6 4 3 6 3 15 0.4 1 -25
Schist-4 81 96 0.3 1 5 SR NO MW CD 53 60 119
69 II 0 70 II
Rating 7 20 10 4 1 3 6 3 15 0.15 1 -6
Schist-5 81 80 0.1 1.1 10 SR SF>5 MW CD 118 69 128
57 III 0 61 II
Rating 7 17 8 4 0 3 0 3 15 0.15 1 -25
Schist-6 81 99 0.6 1.5 5 SR NO MW CD 162 72 131
69 II 0 73 II
Rating 7 20 10 4 1 3 6 3 15 0.15 1 -25
Schist-7 81 95 0.3 0.9 0 SR NO MW CD 29 81 140
70 II 0 85 II
Rating 7 20 10 6 5 3 6 3 15 0.4 1 -25
Schist-8 81 17 0.1 1 2.5 SR SF>5 MW CD 135 57 116
58 III 0 59 III
Rating 7 17 8 4 5 3 0 3 15 0.15 1 -6
Schist- 9 81 64 0.1 0.7 3 SR SF>5 MW CD 35 61 120
56 III 0 57 III
Rating 7 13 8 6 1 3 0 3 15 0.15 1 -6
Schist-10 81 98 0.5 1.2 3.5 SR NO MW CD 66 66 125
69 II 0 73 II
Rating 7 20 10 4 1 3 6 3 15 0.15 1 -25
Schist-11 81 94 0.3 1 2 SR SF>5 MW CD 168 36 95
63 II 0 63 II
Rating 7 20 10 4 1 3 0 3 15 0.15 1 0
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
95
S. Ramadhani, A. Rifa’i, K. B. Suryolelono, W. Wilopo
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
96
S. Ramadhani, A. Rifa’i, K. B. Suryolelono, W. Wilopo
[17] Abbas, S. M. and Konietzky, H., Rock mass classification Ahmad RifRifa’i
a’i was born on July 12, 1969. In
systems. Introduction to Geomachincs
Geomachincs, (Departement
Departement of Rock 1988 he continued his civil engineering
Mechanics, Technical University Freiberg (ebook), 2014) education at the faculty of Engineering,
[18] Barton, N., Some new Q Q-val
value
ue correlations to assist in site Universitas Gadjah Mada, Indonesia. He
design,, International journal of Rock
characterization and tunnel design achieved his bachelor's degree in 1993. In 1994
Mechanics and Mining Sciences. Vol. 39 (Issue 2) 2):: 185–216
185 216, he continued his Master's, Geotechnics, Institute
February 2002
2002. Teknologi Bandung, Indonesia and earned his
doi:https://doi.org/10.1016/S1365
doi:https://doi.org/10.1016/S1365 1609(02)00011
https://doi.org/10.1016/S1365-1609(02)00011
1609(02)00011-4 master's degree in 1996. His doctorate was
[19] Romana,
Romana, M., New adjustment ratings for application of obtained in 2002 at The Swiss Federal Institute of Technology of
Bieniawski
Bie niawski classification to slope, In:: Proceedings of the Lausanne (EPFL), Switzerland. Research interest in soil mechanics,
international symposium on role of rock mechanics (pp. 49-53 49 53). tunneling, and the foundation has res
resulted
ulted in several publications in the
Zacatecas, Mexico, September 1985 1985. form of international journals. Dr. Ahmad Rifai is a member of the
[20] Romana, M., Sero
Seron,
n, J. B., and Montalar, E., SMR Geo Geomechanics
mechanics Indonesian Soil Engineers Association (HATTI) and International
Classification: Application, Experience and Validation
Validation, Inn: 10th Society for Soil Mechani
Mechanics
cs and Geotechnical Engineering (ISSMG)
(ISSMG).
ISRM
SRM Congress 2003 Jan 1. International Society for Rock E mails:: ahmad.rifai@ugm.ac.id,
E-mail ahmad.rifai@ugm.ac.id kabulbasah@yahoo.com
Mechanics
Mechanics, January 20032003.
Kabul Basah Suryolelono was born on 13
March 1947. a bachelor's degree in civil
Authors’ information engineering faculty of engineering Universitas
Gadjah Mada. the master's education earned the
1
Doctoral Candidate, Department of Civil and Environmental Dip. HE at IIHE Delft, The Netherlands, and
Engineering, Faculty of Engineering, Gadjah Mada University, doctoral education at the UniUniversity
versity Joseph
Yogyakarta 55281, Indonesia.
Indonesia Fourier Grenoble
Grenoble,, France.Research interest in
2
Geotechnics special soil reinforcement, Ground
Department of Civil and Environmental Engineering, Faculty of water flow, Dam (soil mechanics) has prod
produced
uced several publications in
Engineering, Gadjah Mada University,
University, Yogyaka
Yogyakarta
rta 55281, Indonesia.
the form of international journals. Prof Kabul Basah Suryolelono is a
3 member of the Soil Engineering Associatio
Associationn of Indonesia (HATTI) and
Department of Geological and Center for Disaster Mitigation and
Internation
International
al Geosynthetic Society (IGS)
(IGS).
Technological Innovation (GAMA
(GAMA-InaTEK)
InaTEK) Gadjah Mada University,
Yogyakarta 55281, Indonesia.
Indonesia
Wahtu Wilopo was born on 19 Nov 1975 1975.. A
Sriyati Ramadhani (corresponding author) was bachelor's degree in geological engineering
born on September 25, 19751975,, at Yogyakarta,
Yogyakarta faculty of engineering Gadjah Mada University
s achieved her graduate
Indonesia. In 2002 she (1999) The
(1999). he master's education earned at Mining
education in civil engineering, Faculty of Engineering Faculty, Chulalongkorn University,
Engineering, Tadulako University,
University Palu, Thailand (2004) and doctoral education at the
Indonesia. In 2003 shehe pursued her master's Kyushu University, Japan
Japan.. Research interest in
degree in Geotechnical Engineering in civil Geological engineering, especially concerning
engineering faculty of Gadjah Mada University about hydrogeology, hydro geochemistry, environmental geology,
and earned hers master's degree in 2006
2006.. Since 2005 sshe
he was appointed Groundwater geology,
Groundwater geology disaster risk reduction, early warning system,
as a permanent lecturer at the Department of Civil Engineering of debris flow and landslide. He has produced several publi
publications
cations in the
Gadjah Mada University,
University, Indonesia. She is currently studying doctor
doctoral
al form of international journals. He is serving for Head of Central
postgraduate at Gadjah Mada University
University, Yogyakarta Indonesia. Laboratory, Gadjah Mada University · Department of Geological
Several studies have been conducted, among others, concerning slopes Engineering, Engineering geology, hydrogeology and disaster
stability which has produced publications in the form of journals. management, Indonesia, Yogyakarta
Yogyakarta.
Sriyati Ramadhani is a member of the Geotechnical Engineering E-mail:
E mail: wwilopo@gmail.com
Association of Indonesia (HATTI) as well as the Association of
Technical Manpower of Indonesia (ASTTI)
(ASTTI).
E-mail:
mail: sriyatiramadhani@mail.ugm.ac.id
97
International Review of Civil Engineering (I.RE.C.E.), Vol. 9, N. 3
ISSN 2036 - 9913 May 2018
Indriati Martha Patuti1, Ahmad Rifa’i2, Kabul Basah Suryolelono2, Suprapto Siswosukarto2
Abstract – Crib wall is one type of retaining wall that is often done for slope reinforcement.
Usually made of pre-cast concrete beams mounted interlocked-hooks with considerable
construction costs. Based on that it is necessary to research the construction of slope
reinforcement with low cost and easy in its implementation. The purpose of this research is
to design crib wall by utilizing the local material. The research location is the slope of Trans
Sulawesi-Pantai Selatan Street, precisely the slope of the road in Muara Bone Village (Bone
Subdistrict) and Oluhuta Village (Kabila Bone Subdistrict), Bone Bolango Regency. Crib
wall material used is timber obtained from around the research area. Slope stabilization
analysis was performed using limit equilibrium with the help of Slide3 2017. The results of
external and internal stability analysis showed that the slopes with the construction of timber
crib walls in stable condition (Factor of Safety, FS>1.5). It is expected that the crib wall
model can be an alternative to stabilize the roadside slopes in Bone Bolango Distr ict, due to
the cheaper construction cost compared to other conventional retaining wall construction .
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved.
Keywords: Timber Crib Walls, Slope Stability, Factor of Safety, Limit Equilibrium Methods,
Counterweight of Slopes
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved https://doi.org/10.15866/irece.v9i3.14050
98
I. M. Patuti, A. Rifa’i, K. B. Suryolelono, S. Siswosukarto
I. Introduction
and:
Landslide events frequently occur in mountainous
areas such as Bone Bolango District. That becomes a
challenging task because it has repeatedly been done to
improve the stability of the slope. During this method
commonly used is the reinforcement of slopes with the
conventional retaining wall, which is the wall of a stone- The resultant earth pressure will be given by
clutch. Also, this retaining wall, such as reinforcement of , which will act at 1/3 of height from the
concrete walls, is often used for slope reinforcement. bottom of the wall. In general, the factor of safety against
Construction costs are quite expensive. Based on this slipping can be given by the equation:
it is necessary to model slope retrofitting using local
materials. Utilization of materials in crib wall design is
expected to reduce the cost of construction, in addition to (2)
a natural building.
The occurrence of the landslide in Bone Bolango
The factor of safety against overturning is defined as:
regency, especially the roadside slope of Trans Sulawesi-
Pantai Selatan Street caused by the geological condition
and local topography. The structure of the rock easily (3)
landslides with a very steep hill. Andesite rocks on the
slopes of Oluhuta Village, Kabila Bone subdistrict, have
been destroyed and weathered due to the discontinuity. where Mr=sum of resisting moment; Ms=sum of
This zone is a zone passed by active fault [1], [2]. moment leading to overturning. The maximum and
Several studies have been conducted by researchers on minimum stresses at wall base are given by:
the design and analysis of crib walls as done by [3]-[9]
and so on. References [5] and [8] research the numeric (4)
simulation of crib wall, while [6] and [7] investigate the
failure of the crib wall. The studies of 3D equilibrium
limit method analysis have also been widely used, as did where =sum of vertical forces; A and B=area and
by [11]-[18]. This 3D analysis is a development of 2D breadth of wall base; e=eccentricity [19]. The safety of a
analysis. single crib element against the detachment from the crib
system will be checked. In this case it is required to
check the strength of joints. In case of inclined walls, the
II. Literature Review lifting up of crib elements can be happened in two ways
II.1. Crib Walls [4]:
a. From vertical and horizontal forces (Fig. 1(b)). If
Crib walls are gravity retaining walls, a structure built A,B= self-weights of crib elements and soil trapped
up of longitudinal and transverse elements to form a between crib layers in case of inclined crib wall, then
series of rectangular cells into which infill is placed. Crib total pressure on each side of crib elements can be
constructed from interlocking, precast, concrete calculated as follows:
components.
They are filled with free draining material and earth
backfill to eliminate the hazards of hydrostatic pressure
(5)
building up behind the wall. Crib wall elements can be
made of concrete, steel, bamboo, or wood [4]. The spaces
between the interlocking are filled with a granular
material, i.e., sand, or aggregate [6]. Failure for the wall
will be by one of the following modes:
1. Sliding and overturning of wall
2. The overstress on foundation (bearing capacity
failures)
3. Sliding and overturning of crib elements
4. Overloading of crib elements and shearing of joints
The coefficient of active lateral pressures used in this
analysis are calculated using the following equation after
Coulomb’s earth pressure theory [4]: For vertical walls:
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
99
I. M. Patuti, A. Rifa’i, K. B. Suryolelono, S. Siswosukarto
(11)
and:
(6) (13)
The safety factor against the lifting up of crib The example of cribwall models as shown in Fig. 2,
elements at earth side will be given by: Fig. 3 and Fig. 4.
(7)
(8)
and:
(9)
In the above equation, and j and for II.2. Three-Dimension of Limit Equilibrium Analysis
practical purpose, kB j can be assumed as 0.5 [21]. For Three-dimensional slope stability analysis are
each of these cases a global factor of safety of 1.5 extension of general 2-D limit equilibrium method [23]-
will be required. [24]. The basic definition of these inter-column force
According to monolithic theory, the maximum functions was similar to that proposed by Morgenstern
compression at the outer side of crossing point is given and Price [13].
by:
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
100
I. M. Patuti, A. Rifa’i, K. B. Suryolelono, S. Siswosukarto
TABLE II
THE PROPERTIES OF SOIL AND ROCK IN OLUHUTA VILLAGE
Layer 1 Layer 2 Fill
Parameters
(Clayey sand) (Andesite) material
Water content, w (%) 12.17 1.18 0.61
Bulk unit weight, b (kN/m3) 19.24 24.41 25.30
Cohesion, c’ (kN/m2) 12.95 520.00 343.00
Angle of internal friction, ’ (o) 30.00 53.00 50.00
Young’s modulus, E (kN/m2) 1,64E+04 1.23E+07 2,39E+07
Poisson’s ratio,µ 0.15 0.30 0.28
TABLE III
Fig. 4. Cross-section through a typical crib wall [6] THE PROPERTIES OF TIMBER
Parameters Average Values
Slide3 2017 is a brand new 3-dimensional limit Moisture content, m (%) 15.13
Density, (kN/m3) 5.17
equilibrium method for slope stability program created Compressive strength, Fc’// (kN/mm2) 22.37
by Rocscience. With Slide3 most of the analysis features Shear Strength, Fv’// (kN/mm2) 2.83
found in our very popular 2D program Slide are now Young’s modulus, E (kN/m2) 10,549
available in full 3D, including complex geology,
anisotropic materials, loading, and support. Slide3 offers
a wide variety of strength models for soil and rock, IV. Result and Discussion
including Mohr-Coulomb, undrained, tremendous IV.1. Numeric Simulation of The Natural Slope
strength, anisotropic, generalized Hoek-Brown,
SHANSEP, and more. These strength criteria allow the The analysis was conducted in Muara Bone and
model all commonly encountered material types in slope Oluhuta Village, Bone Bolango Regency. The slip
stability analysis [20]. surface described non-circular shape. The results of
stability analysis and slope behavior in the locations are
illustrated in Fig. 5 and Fig. 6.
III. Research Method
The objects of the research were the road side slope in
Muara Bone Village (Bone Subdistrict) and Oluhuta
Village (Kabila Bone Subdistrict), Bone Bolango
Regency. The samples of soil/rock were the undisturbed
and disturbed sample that obtained on the dry season.
The crib walls used local materials, namely timber
(coconut woods). The physical and mechanical properties
of the soil/rock and timber discovered based on the
laboratory test results were presented in Table I, Table II,
and Table III.
TABLE I
THE PROPERTIES OF SOIL AND ROCK IN MUARA BONE VILLAGE
Layer 2
Layer 1 Fill
Parameters (Volcanic Fig. 5. Results of analysis of natural slope stability
(Silty sand) material
Breccia) in Muara Bone Village
Water content, w (%) 29.4 0.81 0.61
Bulk unit weight, b (kN/m3) 14.82 25.42 25.30
Cohesion, c’ (kN/m2) 0 190.00 343.00
The results by GLE method show that the natural
Angle of internal friction, ’ (o) 37.00 50.00 50.00 slopes in Muara Bone Village was unstable/critics
Young’s modulus, E (kN/m2) 890 9.26E+06 2,39E+07 (FS=0.35<1.5). The factor of safety (FS) in Oluhuta
Poisson’s ratio, µ 0.35 0.25 0.28 Village was 1.542. The condition of slope was stable, but
during the rainy season (water content of clayey sand,
The test carried by American Standard Test Materials w=20%), this slope was unstable, FS=1). Slope
(ASTM). The timber characteristics corrected again by instability caused by geological conditions with slopes
SNI 7973-2013 [22]. In the case, used the load resistance forming material have experienced weathering and the
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
101
I. M. Patuti, A. Rifa’i, K. B. Suryolelono, S. Siswosukarto
geometry of the slope is so steep. Moreover, triggered by The angle of inclination of earth pressure
rainfall is high enough to cause a reduction in shear (=2/3=30o). The bearing capacity for gravel, permit=
strength and pore water pressure increase. 300 kN/m2.
Fig. 9. The geometry and forces acting on the timber crib walls
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
102
I. M. Patuti, A. Rifa’i, K. B. Suryolelono, S. Siswosukarto
References
[1] I. M. Patuti, A. Rifa'i and K. B. Suryolelono, Mechanism and
Characteristics of The Landslides in Bone Bolango Regency,
Gorontalo Province, Indonesia, International Journal of Geomate,
Vol. 12 (Issue 29): 1-8, January 2017.
[2] I. M. Patuti, A. Rifa'I, K. B. Suryolelono and S. Siswosukarto,
(b) Oluhuta Village (Kabila Bone Subdistrict) The Effect of Water Content Change in Pluto-Volcanic
Subsurface Slope Stability Based on Limit Equilibrium and Finite
Figs. 10. Result of the analysis slope stability of timber crib walls Element Method, 1st Warmadewa University International
Conference Architecture and Civil Engineering, pp 198-205,
Warmadewa University, Bali, October 2017.
V. Conclusion [3] M. S. Acharya and F. Florineth, Vegetated Bamboo Crib Wall - A
Suitable Alternative to Stabilise Road Side Slopes in Nepal,
Based on the analysis done with the equilibrium limit European Geosciences Union 2006, Vienna, Austria, 2006.
method, the following conclusions have been drawn from [4] M. S. Acharya, Analytical Approach to Design Vegetative Crib
Walls, Geotechnical and Geological Engineering, Vol. 35 (Issue
this study:
162): 1-14, August 2017.
1. Based on numerical simulation with the limit [5] J. P. Fernandes and N. Guiomar, Simulating the Stabilization
equilibrium method, the safety factor of natural slope Effect of Soil Bioengineering Interventions in Mediterranean
in the research area illustrates that during the dry Environments Using Limit Equilibrium Stability Models and
Combinations of Plant Species, Ecological Engineering, Vol. 88,
season, the slopes in Muara Bone was unstable
pp. 122-142, December 2016.
FS=0.352. In Oluhuta Village, factor of safety in the [6] G. D. Lehmer and C. G. Ekwueme, Description and Analysis of
dry season tends to be safe, which amounted to 1.542 Crib Wall Failures, Fifth Forensic Engineering Congress, pp.
but during the rainy season, the slopes in Oluhuta 414-423, Washington D.C., 2009.
[7] L. Shaw-Shong, L. Peir-Tien and L. Fang-Liang, Failure
Village was unstable, FS=1.0.
Investigation of Crib Wall, Piled Reinforced Concrete Wall and
2. The analysis of the crib walls describe the crib wall Geosynthetic Reinforced Soil Wall, The 17th Southeast Asian
designs have safety factor that qualifies (FS>1.5), Geotechnical Conference, pp 1-4,Taiwan, May 2010.
both external and internal stability. External stability [8] G. Bella, M. Barbero, F. Barpi, M. Borri-Brunetto and D. Peila,
An innovative Bio-Engineering Retaining Structure for
analysis of the crib wall describe the value of the
Supporting Unstable Soil, Journal of Rock Mechanics and
safety factor against bearing capacity failure, sliding Geotechnical Engineering, Vol. 9,(Issue 2):247-259, 2017
and overtuning failure sequentially hazard was 1.85; [9] G. Tardíoa and S. B. Mickovski, Implementation of Eco-
1.87; and 4.92. The results of the analysis of internal Engineering Design into Existing Slope, Ecological Engineering,
Vol. 92, pp. 138-147, 2016
stability with the limit equilibrium method (by Slide [10] W. H. Roth and A. Delnik, Numerical Modeling of a Crib-wall
3D) represents the average value of a safety Failure, Fourth International Conference on Case Histories in
factoragainst shear failure of timber crib wall in Geotechnical Engineering 9, pp 746-754, St. Louis, Missouri,
Oluhuta Village, and Muara Bone Village March 1998.
[11] G. Liu, X. Zhuang and Z. Cui, Three-Dimensional Slope Stability
sequentially were 2.91 and 9.78. The value of safety
Analysis Using Independent Cover Based Numerical Manifold
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
103
I. M. Patuti, A. Rifa’i, K. B. Suryolelono, S. Siswosukarto
and Vector Method, Engineering Geology, Vol. 225(Issue 225), member of the Geotechnical Engineering Association of Indonesia
pp. 83-95, February 2017. (HATTI).
[12] D. Park and R. L. Michalowski, Three-Dimensional Stability E-mail: ipatuti@yahoo.com
Analysis of Slopes in Hard Soil/Soft Rock with Tensile Strength
Cut-Off, Engineering Geology, Vol. 229, pp. 73-84, November Ahmad Rifa’i (corresponding author) was born
2017. on July 12, 1969. In 1988 he continued his Civil
[13] L. Zhang, M. D. Fredlund, D. G. Fredlun and H. Lu, Comparison Engineering education at the Faculty of
of 2-D and 3-D Slope Stability Analysis for Unsaturated Soil Engineering, GadjahMada University,
Slopes,Geo Regina, Canada, 2014. Indonesia. He achieved his bachelor's degree in
[14] K. Lim, A. Li and A. Lyamin, Three-Dimensional Slope Stability 1993. In 1994 he continued his Master's
Assesment of Two-Layered Undrained Clay, Computers and Geotechnics, Institute of Technology Bandung,
Geotechnics, Vol. 70, pp. 1-17, July 2015 Indonesia and earned his master's degree in
[15] L. Zhang, F. D. Fredlund, D. G. Fredlund, H. Lu and G. Wilson, 1996. His doctorate was obtained in 2002 at The Swiss Federal Institute
The Influence of The Unsaturated Soil Zone on 2-D and 3-D of Technology of Lausanne (EPFL), Switzerland. Research interest in
Slope Stability Analysis, Engineering Geology, Vol. 193, pp. 374- soil mechanics, tunnelling, and the foundation has resulted in several
383, 2015. publications in the form of international journals. Dr. Ahmad Rifa’i is a
[16] A. Ahmed, K. Ugai and Q. Q. Yang, Assessment of 3D Slope member of the Indonesian Soil Engineers Association (HATTI) and
Stability Analysis Methods Based on 3D Simplified Janbu and International Society for Soil Mechanics and Geotechnical Engineering
Hovland Methods, International Journal of Geomechanics, Vol. (ISSMG).
12(Issue 2): 81-89,March 2012. E-mail: ahmad.rifai@ugm.ac.id
[17] D. Dong-ping, L. Liang and Z. Lian-Heng, LEM for Stability
Analysis of 3D Slopes with General-Shaped Slip Surfaces, Kabul Basah Suryolelono was born on
International Journal of Geomechanic, Vol. 17 (Issue 10): 1-12, February 11, 1946. A bachelor's degree in Civil
2017. Engineering Faculty of Engineering,
[18] X. Zhou and H. Cheng, Analysis of Stability of Three- GadjahMada University. The master's education
Dimensional Slopes using the Rigorous Limit Equilibrium earned the Dip. HE at IIHE Delft, The
Method, Engineering Geology, Vol. 160 (Issue 27): 21-33, June Netherlands, and doctoral education at the
2013. University of Joseph Fourier, Grenoble,
[19] J. A. Ortigao and A. S. Sayao, Handbook of Slope Stabilisation, France.His research interest on geotechnics
1st ed., (Berlin, SpringerVerlag, 2004). special soil reinforcement, groundwater flow, dam (soil mechanics) has
[20] RocScience, Slide3D Limit Equilibrium Slope Stability for Civil produced several publications in the form of international journals.
Applications, Roc News Summer 2-017, 2017. Prof. Kabul Basah Suryolelono is a member of the Soil Engineering
[21] Brandl H., Tragverhalten und Dimensionierung von Association of Indonesia (HATTI) and International Geosynthetic
Raumgitterstützmauern (Krainerwänden) (Vienna, Austria, Society (IGS).
Bundesministerium für Bauten und Technik, Straßenforschung E-mail. kabulbasah@yahoo.com
Heft 141, 1980, pp 115–220).
[22] Badan Standardisasi Nasional, SNI 7973: Spesifikasi Desain untuk Suprapto Siswosukarto was born on 7April
Konstruksi Kayu (Jakarta, Badan Standardisasi Nasional,2013). 1965. A bachelor's degree in Civil Engineering
[23] Taleb, H., Berga, A., Finite Element Analysis of Slope Stability Faculty of Engineering, GadjahMada
Reinforced with Pile, (2017) International Review of Civil University, and doctoral school at Civil
Engineering (IRECE), 8 (1), pp. 25-33. Engineering, University of Leeds, England.
doi:https://doi.org/10.15866/irece.v8i1.11147 Research interest in bamboo and wood structure
[24] Taleb, H., Berga, A., Slope Stability Analysis with Interaction of has produced several publications in the form of
Frictional Contact, (2017) International Review of Civil international journal.
Engineering (IRECE), 8 (4), pp. 167-176. E-mail: suprapto_siswosukarto@ugm.ac.id
doi:https://doi.org/10.15866/irece.v8i4.11535
Authors’ information
1
Doctoral Candidate, Department of Civil and Environmental
Engineering, Faculty of Engineering, GadjahMada University,
Yogyakarta 55281, Indonesia.
2
Department of Civil and Environmental Engineering, Faculty of
Engineering, GadjahMada University, Yogyakarta 55281, Indonesia.
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
104
International Review of Civil Engineering (I.RE.C.E.), Vol. 9, N. 3
ISSN 2036 - 9913 May 2018
W. Hamid, A. Waterman
Abstract – Cost overruns problem is still a critical issue despite many improvements are being
made in the management of construction projects. Therefore, this research aims to identify the
main causes of cost overruns in construction industry in developing countries and to make a
critical analysis with the ones in the United Kingdom. In addition, some existing studies regarding
cost estimation and cost overruns have been reviewed by the authors. In order to carry that out, in
this research the authors used a secondary data collection such as books, journals, international
standard and some Internet information through few search engines, like Google scholar, Science
direct, Emerald Insight etc. Besides that, a qualitative research method has been used to review
considerable number of books, articles, website, journals etc. In the findings, it has been
concluded that the major common causes of cost overruns in construction projects in developing
countries and in the United Kingdom were: change in design, inflation, increasing of the
material’s price, project complexity, change in the project scope and inadequate contract and
procurement method. The reasons behind each of these factors and how to minimize them have
been critically explained. Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved.
Keywords: Cost Estimation, Cost Overrun, Cost Control, Cost Management, Cost in
Construction
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved https://doi.org/10.15866/irece.v9i3.14525
105
W. Hamid, A. Waterman
in the future. For instance, the contribution of investing types of projects especially construction industry. It is
in education, such as new schools will improve the UK stated that cost overrun occurs when the final project cost
economically. Excellence [11] stated that the growth in is exceeding the estimated cost throughout the initiation
construction sector over the past few years has resulted in and planning stages of the project [15]. This issue
a strong business confidence and in new opportunities indicates a difference between the project budget and the
with private house building output currently at a high overall financial project cost. Cost overrun represents a
level. Ashworth and Perera [12] stated the important failure to perform the cost discipline in projects. Olawale
need of understanding the cost control and construction and Sun [16] realized that, despite using many project
economics for many reasons. For example, the control techniques, cost overrun exists when construction
requirements of the client today are more complicated, projects are unable to meet the cost requirements.
with a tendency towards modern designs, materials, In construction industry, stakeholders (clients,
techniques and construction methods. Therefore, more contractors and consultants) take the project cost
effective control system is required from the initiation management as their responsibility and this is due to the
stage to the completion stage. The designer has a wide impact of both direct and indirect cost on the project
range of options to choose from and this leads to variety [17]. Shehu et [15] clarified that when the estimating is
in construction. Therefore, the traditional methods accurate, it represents an excellent foundation to
sometimes are unable to cope in this environment to implement project monitoring, whilst, inaccurate cost
attain value for money. Moreover, contractors have lost estimating affects both clients and contractors. Inaccurate
lots of their profits in the last decade. Therefore, they are estimating could be over or underestimated cost. An
more conscious about cost now in an attempt to rectify overestimated cost is unacceptable to the client during
losses as much as possible. Finally, there is more the feasibility stage, while the underestimated cost can be
expectation on achieving better cost control in enhanced. In the last situation, clients and contractors
construction projects and this is due to the essential tools will experience financial losses based on the contractual
and techniques desirable to achieve greater accuracy of conditions [18]. However, Enshassi et al. [19] stated that
estimate. Bergeron and St-Arnaud [13] stated that an cost overrun can be in the excess of the total cost. The
accurate estimation can assist the project manager to cost overrun rate can be calculated and compared by
have an effective resources allocation and risk dividing the contract amount change over the original
management. At the same time, an effective estimation contract amount during the award stage [20].
can also increase enterprises success and, therefore, it Jackson [21] mentioned few projects as examples of
can save a lot of money. projects that were implemented and that presented cost
Many researchers have discussed the failure of overruns in the United Kingdom. The first project is the
construction projects, and yet there is no one who has Scottish parliament building which is considered as an
agreed method of measuring project success. However, extremely high cost project in the United Kingdom. The
there are three various measures suggested by Morris and main causes for cost overruns in this project were:
Hough [14] to identify whether the project is successful inflation change, delay in the designs, issues of one of
or not. Firstly, they conditioned that the project should be the underground stations under the building and
functioned technically and financially. Secondly, the approvals of costs. The British Library is another project
researchers suggested measures on the project that experienced cost overruns which was completed in
management which indicates if the schedule and budgets 1998 and the final budget overran more than the triple of
goals have been achieved. Finally, an evaluation should its original budget, due to the change in staff and their
be carried out on the contractors’ performance to show if responsibilities. The last example, given by Jackson [21],
it provides beneficial services for the project. Therefore, is The Guy's House which exceeded its original budget
there is no unique path of identifying the project success. twice due to different causes such as, change in design
However, cost estimation is a critical issue to be taken significantly, construction requirements changes and
into account in the success or failure of project. Smith [3] delays in construction. Flyvbjerg and Stewart [22]
considered that the process of cost estimating is very indicated another example of cost overruns which is
important as it enables construction companies to represented by The Olympic Games 2012. The project
determine what their direct costs will be, and to provide a exceeded its initial cost by approximately two billion
`bottom line’ cost below which it would not be pound, due to many causes, for instance, issues with the
economical for them to carry out the work. contractor regarding the price negotiation, and inaccurate
In summary, cost estimation in construction is estimating of budget and resources.
reviewed. In addition, the main reasons for cost overruns
in the UK and in the developing countries are intensively
discussed. II.2. Cost Performance in Construction Projects
Construction is a dynamic industry due to the risks
and uncertainties in its budgets, technologies and process
II. Cost in Construction that the it faces [23]. These project’s complexities,
II.1. Overview of Cost Overrun uncertainties and the rising of stakeholders create
difficulties in cost management in construction projects.
Cost overrun is a very common problem in different
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
106
W. Hamid, A. Waterman
Thus, this leads to project’s delay and cost overrun approval of construction which caused delays. Despite
[24]. Construction projects often have poor reputation some similar causes of cost overruns in the previous
due to the widespread cost and time overruns [25]. studies, Table I shows some variations in these studies.
Construction sector still faces challenges despite lot of
TABLE I
improvements have been made [26]. Overruns in projects
MAIN CAUSES OF COST OVERRUNS IN NIGERIA (TAKEN FROM OKPALA
cost exist when the project cost at the final stage AND ANIEKWU, 1988; ELINWA AND BUBA, 1993)
becomes greater than the initial estimation [27]. Though, Okpala and Aniekwu Elinwa and Buba
Main causes of cost overruns
the original estimation is continuously changing (1988) (1993)
throughout the project execution. Due to this reason, Financial issues Payment for
implemented works
Avotos [27] stated that it is essential to consider and
Shortage in materials
calculate the possible cost overrun of the project. Fluctuations in price
According to Flyvbjerg, et al. [28] the initial cost has to Poor contract management
be made when a decision of starting building is taken. Increasing of materials’ prices
However, Love, et al. [29] supported the saying that cost Fraudulent practices
Poor planning
overrun should be established to compare the initial high cost of machineries
budget with the final budget at the completion stage.
Le-Hoai, et al. [30] also stated that the cost overrun In further studies, Chang [38] identified three causes
size may different from a project to another, depending that contribute to cost and schedule increases: the
on many factors such as the project size, its location and owner's control, the beyond control and the consultant’s
its type. For instance, Eden et al. [31] said that private control. These findings were based on an analysis of case
projects have larger cost overruns larger public projects. study of engineering design projects in California.
At the same time, Koushki, et al. [20] and Frimpong et Flyvbjerg et al. [39] mentioned that cost overruns
al. [32] indicated that cost overruns are more significant causes can be similar to most developing countries due to
and more common in large projects than in small ones. similar roots of problems that these countries have in
This idea has been supported later by Gkritza and Labi construction projects. An example that supported
[33], who pointed out that cost overrun is more frequent Flyvbjerg et al. [39] is the study which was carried out
with long-term projects. In contrast, Odeck [34] believed by Kaming et al. [40]. The authors conducted some
that due to the attention that project managers pay to the interviews with 31 project managers of skyscrapers
management of large projects, they can have fewer cost projects in Indonesia to define the major causes that
overruns comparing to the small projects. affect overruns in projects’ cost and time. It has been
concluded that the shortage of materials because of the
II.3. Causes of Cost Overruns in Construction Projects inaccurate planning and estimating, the materials' price
in Developing Countries increment, the ineffective management of contractors,
the works complexity and the bad climate were the most
In this section, the main causes of cost overruns are important reasons for cost overruns in Indonesian
presented, representing results from different studies, projects. Moreover, Frimpong et al. [32] have reached to
throughout the periods of cost overruns in different similar results in another developing country. The
construction projects in different countries. In general, authors wanted to determine the main factors that caused
these factors, that have an effect on cost performance of delays and cost overruns in the groundwater project in
the project and cause cost overruns, are present from the Ghana, by sending 125 questionnaires to the consultants,
estimating stage to the final stage of the project [35]. The the owners and the contractors. These factors were: the
aim of presenting factors that cause cost overruns is to increase in the materials’ cost, payments problems with
understand them, and therefore, to minimize the impact the agencies, poor management of contractors, inaccurate
and create strategic plans to face uncertainties in all cost estimation and poor technical performance. It can be
project stages [26]. seen that these reasons for delays and cost overruns are
Elinwa and Buba [36] conducted a different similar to those in developing countries. Fig. 1 shows
questionnaire taking into account the causes of cost these reasons. More recently, Le-Hoai et al. [30] obtained
overruns which were listed by Okpala and Aniekwu [37]. similar results in a research conducted in Vietnam
In this study, 150 questionnaires were also delivered through 285 questionnaires sent to professionals of large
to professionals in three various areas in north Nigeria. projects in the country. The study came to similar results
The main cause of cost overruns that has been of those obtained from the study in the state of Kuwait.
identified was the materials cost; the researchers This is because that the financial problems of contractors,
highlighted: the increasing of materials’ prices, the poor supervision, owners’ financial resources and
fraudulent practices, the poor planning and the high cost changes in design were also part of the five more
of machineries. This study upheld the previous ones of frequent factors that caused cost overruns in Vietnam. By
the authors [36], [37], but at the same time, the authors reviewing some studies, it has been shown that the main
added others causes for cost overruns which were the causes of cost overruns in developing countries are
lack of geotechnical research before commencing the similar in construction sector which supported the idea
construction stage and the complicated process of proposed by Flyvbjerg, et al. [39].
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
107
W. Hamid, A. Waterman
TABLE II
Unexpected Inaccurate Poor
weather
SUMMARY OF STUDIES ABOUT COST OVERRUNS
estimating technical
IN CONSTRUCTION PROJECTS
skills
Main causes of cost Okpala and
Elinwa and Buba (1993)
overruns Aniekwu (1988)
-Owner's financial constraints
Fig. 1. Main reasons for cost overruns (taken from Frimpong, et al., -Financial difficulties of
2003; Kaming, et al., 1997) contractors
Koushki, et al. (2005) Kuwait -Contractors did not meet the
Chen and Hsu [41] highlighted fourteen significant specifications of the job
causes influencing cost for engineering consulting firms -Delays caused by design
-Changes and change orders
in Taiwan, from a survey of 118 professionals working in -Lack of supervision
engineering consulting companies. -Owners’ financial resources
The most important factors were: the project size, the -Financial difficulties of
Le-Hoai, et al. (2008) Vietnam
project duration, the project contract and the description contractors
-Changes in the design
of both repayment plan and cash flow. A year later, Le- -Poor project management
Hoai et al. [30] researched construction industry in Asia -Shortages of materials
and Africa, through interviewing 87 Vietnamese -High cost of materials
construction professionals. This resulted in seven -Lack of experience
Enshassi, et al. -Poor technical knowledge of
categories of principal factors including market and (2009)
Gaza (Palestine)
workers
estimate, incompetence, design, poor and slow -Lack of skilled leaders in the
constraint, workers, government and capability of project managerial jobs
finance.
-Bad climate
Enshassi, et al., [19] carried out a study in Gaza to -Changes in the scope of the
determine the main reasons for cost overruns in project
construction projects in occupied Palestine. The authors Kaliba, et al. (2009) Zambia -Inflation
distributed 120 questionnaires among consultants, -Schedule delays
-Poor technical and
owners and contractors. The results showed that the main administrative knowledge
reasons were: shortages of materials, high cost of
materials and lack of experience and poor technical Jergeas and Ruwanpura [43] have reinforced their
knowledge of workers. The authors indicated an previous study by conducting another study to find the
important factor which was not been mentioned in main causes of cost and schedule overruns in oil sand
previous studies. This factor is the lack of skilled leaders megaprojects in Canada. The study included a survey of
in the project managerial jobs, which can affect the eighty-seven professionals from different nations and it
relationship with the client, in addition to the effect of was concluded to have similar causes of cost overruns to
poor performance. In the same year, Kaliba et al. [42] those determined by Flyvbjerg et al., [39]. The main
explored the main causes of cost overruns in Zambian causes were: the insufficient knowledge in the project
road construction projects. The study was a mix of case and its complexity, the poor strategies in managing the
studies, questionnaires and interviews in this country. project, the inaccurate costs estimation and the poor
According to the study and unlike previous studies, planning when dealing the design changes and
the major cause for cost overruns in Zambia was the bad implementation requirements, the poor information of
climate. On the other hand, other causes were frequent to changes in currencies exchange rates and the health and
the research conducted in other developing countries. For safety risks. Fig. 2 shows common causes of cost
instance, changes in the project scope, inflation, schedule overruns in Megaprojects of construction
delays and poor technical and administrative knowledge. Table II shows that more researches have been
A summary of the main causes of cost overruns of conducted during the past years and this focus was more
these studies is shown in Table II. Few years ago, Jergeas on developing countries than developed countries.
and Ruwanpura [43] have defined megaprojects as Although it is essential and useful to review those studies
construction projects whose budget is more than one to understand main causes of cost overruns because
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
108
W. Hamid, A. Waterman
construction projects have almost similar features in the to be out of original budgets. Rosenfeld [47] investigated
world. However, these causes cannot be general for all about the root-cause analysis concerning cost overruns in
countries because some of these factors are specific for the construction projects globally and identified 15
each country [16]. Newly, some studies, carried out few possible root causes; three of them were determined to be
years ago, will be analyzed. core. The factors included continuous changes of
requirements, tender prices that are unrealistic, tender
documents that are premature, and definitions by project
owners. Finally, Twana [48] identified that the volatility
of the construction industry together with the high level
of risk exposure signify some of the factors and have an
effect on the cost in Kurdistan region. The discovery of
factors that cause construction project cost overrun
continues to evolve with numerous findings and
positions. It can be seen that developing countries have
common causes of cost overruns in construction industry,
Despite there are many studies that have been carried
out and there are still cost overruns problems in
construction projects. Researchers used a combination of
both qualitative and quantitative methods which involve
numerous ranges of previous studies, interviews and
surveys. A critical analysis of the major causes in
developing countries and those in the United Kingdom
and why these causes occur, is presented after reviewing
some studies on construction projects in the United
Kingdom.
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
109
W. Hamid, A. Waterman
managers or directors (71.82%) and project managers gives credibility to this study. It can be looked at as a
11.80%. Moreover, about 84% of the participants had reliable study about construction projects in the UK due
more than 16 years of experience. to the high response average and it represents various
viewpoints of project stakeholder such as clients,
TABLE III
contractors and consultants. A critical analysis of the
ROLES AND YEARS OF EXPERIENCE OF RESPONDENTS (TAKEN FROM
OLAWALE, 2010) major causes in developing countries and those in the
Years of experience of United Kingdom and why these causes occur is presented
Roles Percentage Percentage
respondents in the next section.
Director/senior
71.82% 0-5 4.54%
management
Commercial II.5. Further Critical Analysis for Cost Overrun
2.73% 6-10 2.73%
manager Causes in Developing Countries and
Contracts manager 1.82% 11-15 8.18%
Project manager 11.80% 16-20 18.18% United Kingdom (Discussion)
Quantity surveyor 1.82% 21-25 18.18%
Construction
It can be seen that developing countries have common
1.82% >25 48.18% causes of cost overruns in construction industry. Despite
manager
Others 8.18% > there are many studies that have been carried out, there
are still cost overruns problems in construction projects.
Olawale et al. [16] interviewed some of the Researchers used a combination of both qualitative
participants during the second stage of the study, which and quantitative methods which involve numerous ranges
was an interview of 30 minute with each practitioner. As of previous studies, interviews and surveys. By analyzing
a result, 15 professionals agreed to be interviewed. Most the main causes in most developing countries, it can be
of the interviewees were contractors and three of them recognized that inflation is the shared factor that cause
were working in consultancy firms. Generally, cost overruns in these countries. However, some studies
interviewees had more than 20 years of experience. were carried out in the 1980s, and therefore, inflation is
Moreover, the questionnaire and the interviews listed not necessarily still having the same impact as a cause
20 factors that caused cost overruns which was a result of for cost overruns in some counties. For instance,
reviewing past literature. The participants were told to Durdyev et al. [44] stated that inflation has the least
give a rank for these factors in order of importance. In impact on construction costs in comparison to other
addition, the respondents were given the opportunity to factors due to significant economic change between the
mention extra causes of cost overruns during the 1980s and the 2000s.
interview and questionnaires [16]. The author listed 20 When noticing the causes of cost overrun in
factors which were considered the main reasons that developing countries and in the United Kingdom, it can
inhibit the control of cost in a construction project in the be shown that there is a similarity in the major causes
UK, as well as the main factors that cause cost overruns, which are change in design, inflation, increasing of the
by using the Relative Importance Index [RII]. These material’s price, project complexity, change in the
factors are shown in Table IV. with the RII for each of project scope and inadequate contract and procurement
the factors. method. The reasons behind each of these factors can be
critically clarified: a change in design can be caused by
TABLE IV different reasons such as design errors or clients request
ROLES AND YEARS OF EXPERIENCE OF RESPONDENTS (TAKEN FROM for change and such reasons require extra works.
OLAWALE, 2010)
Therefore, it causes time and cost overruns. In
Cost overruns causes Rank RII
Change in design 1 0.94 addition, and from the researcher’s experience in a
Risks and uncertainties 2 0.89 construction project, it can be added that insufficient
Inaccurate time estimation 3 0.86 investigation of the site status can be another reason for
Poor performance of subcontractors and suppliers 4 0.82 design change. Undoubtedly, this affects the overall
Works complexity 5 0.81
Conflicts and disputes between parties in the project 6 0.81 project cost.
Contradictions in contract documentation 7 0.8 The second important and shared cause of cost
Misinterpretation of Contract and requirement 8 0.8 overruns in developing countries and the UK is Inflation.
Prices inflation 9 0.79 However, some studies were carried out in the 1980s,
Financial and payment issues for completed works 10 0.78
Poor training and experience of project management 11 0.77 and therefore, inflation is not necessarily still having the
Lack of skills of workers 12 0.69 same impact as a cause for cost overruns in some
Unexpected climate conditions 13 0.68 counties. For instance, Durdyev et al., [44] stated that
Dependency on imported materials 14 0.65 inflation has the least impact on construction costs in
Poor planning 15 0.62
Fluctuation in interest rate 16 0.59 comparison to other factors due to significant economic
Fluctuation of exchange rate currencies 17 0.58 change between the 1980s and the 2000s. Unlike in
Weak regulations and controls 18 0.58 developing countries, inflation came at the middle of the
Project fraud and corruption 19 0.55 causes list and not as a major reason for cost overruns.
However, inflation can be a major factor that may
The research has been carried out by a PhD student in affect the UK construction industry after the Brexit from
one of the UK’s most prestigious universities, which
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
110
W. Hamid, A. Waterman
the European Union. Further research after this event economics for many reasons such as the client
should be conducted to find out the potential impact of requirements are more complicated. Thus, effective
the brexit on the construction industry. In relation to the control system is required from the initiation stage to the
inflation, increasing of the material’s price was another completion stage. Another reason is the tendency
important factor for cost overruns. The main reason for towards modern designs, materials, techniques and
the impacts of these two causes is that the construction construction methods to attain value for money. A
project often can remain for years until completion. secondary data collection such as books, journals,
Therefore, labours, materials cost, equipment etc. may international standard and some Internet information
change time to time. were used in this research through using search engines,
The complexity of a work can be also seen as a like Google scholar, Science direct, Emerald Insight etc.
common factor for cost overruns. This is due to the fact Besides that, qualitative research method was used to
that projects with high level of complexity result in review a considerable number of books, articles, website,
complex estimation, plans, schedules and stakeholders’ journals etc.
diversity. Those stakeholders have various interests in It has been reviewed how cost estimation is essential
the project, and to integrate their interest it may take time to the contract tendering process in construction industry
due to the excepted dispute can occur, therefore, because it provides the funds required for the project.
influencing the project and causing cost overrun. Inaccurate cost estimating could have a significant
Complexity can be also affected by inflation and the impact on contracting business [3]. Therefore, this could
increasing of materials prices due to the long time that lead to cost overruns when the final project cost exceeds
complex projects need to be completed. During the the estimated cost [15]. Le-Hoai et al. [30] stated that
project time, a potential inflation may occur and there inappropriate practice of construction management
can also be a change in the materials prices. The change usually contributes to cost overrun.
in the project scope can be a main cause of cost overruns The main objective of the research is to identify cost
because the project scope involves all project schedule, overruns causes and its impact on construction industry
plans, estimation and quality. Therefore, any change in in developing countries and those in the United
these aspects means more time and resources are Kingdom. It is shown that there is a similarity in the
required, and therefore, more costs against the estimated main causes of cost overruns. After reviewing many
budget. Also, poor scope may result in conflict and studies, which were conducted in different developing
dispute among project parties which this leads to spend countries about cost overruns in construction projects, it
time and money to some conflict and dispute techniques is found that there are various causes for cost overruns
such as litigation and arbitration. All the mentioned depending on the country. Olawale et al. [16] listed 20
reasons can lead to project cost overrun. Finally, factors which were considered the main reasons that
inadequate contract and procurement method. inhibit the control of cost in a construction project in the
Contracts touch all business aspects such as terms of UK. Generally, it can be concluded that the major
payment and pricing. Therefore, contracts should specify common causes of cost overruns in construction projects
each aspect of the project work, otherwise, a dispute may in developing countries and in the United Kingdom were:
be found and dispute techniques like arbitration and change in design, inflation, increasing of the material’s
negotiations need to be established in order to solve this price, project complexity, change in the project scope
dispute. This process can take time and at the end and inadequate contract and procurement method. The
additional costs will be added to the initial budget. In the reasons behind each these factors and what can be done
same context, unclear ambiguous clauses in the contract to reduce them can be critically clarified below.
may also be a reason for dispute, thus, this generates cost It can be seen that developing countries have common
overruns in a project. Furthermore, it is worthwhile causes of cost overruns in construction industry, despite
noting that selecting contract and procurement method is many studies have been carried out and there are still
critical to the project success. Choosing the low bid cost overruns problems in construction projects.
without considering the contractor’s experience and Researchers used a combination of both qualitative
his/her technical capability to manage the project may and quantitative methods which involve numerous ranges
lead to time and cost overruns. What can be done for of previous studies, interviews and surveys. By looking
these causes is explained in the conclusion section. at the main causes in most developing countries, it can be
recognized that inflation is the shared factor that cause
cost overruns in these countries. However, some studies
III. Conclusion were carried out in the 1980s, and therefore, inflation has
Construction industry has been playing a major role in not still necessarily the same impact as a cause for cost
today’s economy for many countries, especially overruns in some counties. For instance, Durdyev, et al.,
developed ones [9]. The main critical issue in [44] stated that inflation has the least impact on
construction projects is that most projects often have construction costs in comparison to other factors due to
failure of either time or cost overruns [14]. Therefore, significant economic change between the 1980s and the
Ashworth and Perera [12] state the importance of an 2000s. It can be shown that the major causes of cost
understanding of cost control and construction overrun in developing counties and in the United
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
111
W. Hamid, A. Waterman
Kingdom, are change in design, inflation, increasing of also change in the materials prices. To reduce the impact
the material’s price, project complexity, change in the of complexity on the project cost, it is advised to
project scope and inadequate contract and procurement implement few steps such as a detailed work breakdown
method. The reasons behind each of these factors can be structure, good planning, milestones and ensure a high
critically clarified below. communication in the team. These steps can be essential
A change in design can be caused by different reasons for the project success.
such as design errors or clients request for change and The change in the project scope can be a main cause
such reasons require extra works. Therefore, it causes of cost overruns because the project scope involves all
time and cost overruns. In addition, and from the project schedule, plans, estimation and quality.
researcher’s experience in a construction project, it can Therefore, any change in these aspects means more
be added that insufficient investigation of the site status time and resources are required, and therefore, more
can be another reason for design change. Undoubtedly, costs against the estimated budget. Also, poor scope may
this affects the overall project cost. In order to control result in conflict and dispute among project parties which
design changes, the main step to take is to hire this leads to spend time and money to some conflict and
professional people with high skills and applying dispute techniques such as litigation and arbitration. All
competent techniques during the project. In addition, the mentioned reasons can lead to project cost overrun.
effective communication with the design team and Since change is inevitable in a project and in order to
integrating the process of design that is appropriately achieve a proper project scope, it is important to create
planned, investigating and reviews, and taking sufficient an appropriate change management plan that can be used
time for corrections can assist to achieve effective by the project’s stakeholders to satisfy their need during
outcomes and therefore, overcome the cost overruns the project. In addition, establishing KPI in the milestone
problem. Furthermore, those professionals should form and identify the successful key factor in
establish planning, controlling and monitoring to raise conjunction with the client will measure the success of
the performance of the project during the project life achieving the project scope.
cycle. Finally, ensuring a proper investigation of site to
take all site circumstances into consideration in the
design to acquire the best cost effective design choices. Acknowledgements
Inflation is the shared factor that caused cost overruns I am deeply grateful for the Higher Committee for the
in these countries. However, according to some studies, Development of Education in Iraq (HCDE) for providing
carried out in the 1980s, inflation is not necessarily still me a great opportunity and supporting me financially to
having the same impact as a cause for cost overruns in study a master’s degree in construction project
some countries. For instance, Durdyev, et al. [44] stated management at The University of Manchester in the UK.
that inflation has the least impact on construction costs in This article is a part of my dissertation in my master’s
comparison to other factors due to significant economic degree 2016.
change between the 1980s and the 2000s. Unlike in
developing countries, inflation came at the middle of the
causes list and not as a major reason for cost overruns. References
However, inflation can be a major factor that may [1] Rezaian, A., 2011. Time-Cost-Quality-Risk of Construction and
affect the UK construction industry after the Brexit from Development Projects or Investment. Middle-East Journal of
the European Union. Further research after this event Scientific Research, 10(2), pp. 218-223.
should be conducted to find out the potential impact of [2] Al-Shanti, Y., 2003. A Cost Estimate System for Gaza Strip
Construction Contractors, Palestine, Master thesis in construction
the Brexit on the construction industry. In relation to the management, The Islamic University of Gaza Strip.
inflation, increasing of the material’s price was another [3] Akintoye, A., 2000. Analysis of factors influencing project cost
important factor for cost overruns. The main reason for estimating practice. Construction Management & Economics,
the impacts of these two causes is that the construction 18(1), pp.77-89.
[4] Cook, A. E., (1991). Construction Tendering: Theory and
project often can remain for years until completion. Practice. London: B T Batsford Limited, P. 57.
Therefore, labors, materials cost, equipment etc. may [5] Richardson, D., 2014. Productivity in the construction industry.
change from time to time. Work complexity can be also [6] Jrade, A. and Alkass, S., 2007. Computer-integrated system for
seen as a common factor for cost overruns. This is due to estimating the costs of building projects. Journal of Architectural
Engineering, 13(4), pp.205-223.
the fact that projects with high level of complexity result
[7] Smith, A. J. (1995) Estimating, Tendering and Bidding for
in complex estimation, plans, schedules and Construction, Macmillan, London
stakeholders’ diversity. Those stakeholders have various [8] Erkoyuncu, J. A., Durugbo, C., Shehab, E., Roy, R., Parker, R.,
interests in the project, and to integrate their interest it Gath, A. and Howell, D., 2013. Uncertainty driven service cost
estimation for decision support at the bidding stage. International
may take time due to the excepted dispute can occur,
Journal of Production Research, 51(19), pp.5771-5788
therefore, influencing the project and causing cost [9] Takim, R. (2005). A Framework for Successful construction
overrun. Complexity can be also affected by inflation and Project Performance. Glasgow Caledonian University.
the increasing of materials prices due to the long time [10] UK Contractors Group. (2009). Construction in the UK Economy:
that complex projects need to be completed. During the The Benefits of Investment.
[11] Excellence, C., 2009. UK Industry Performance Report Based on
project time, there is potential inflation may occur and the UK Construction Industry Key Performance Indicators.
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
112
W. Hamid, A. Waterman
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
113
International Review of Civil Engineering (I.RE.C.E.), Vol. 9, N. 3
ISSN 2036 - 9913 May 2018
Abstract – Multipurpose rule curves are suitable guide lines to operate multipurpose reservoirs
during a considered time period. This study applied the conditional genetic algorithm and
reservoir simulation model by considering multipurpose objective functions. 25 years of historic
inflow data (1992-2016) and 50 years of future inflow (2017-2066) under climate change scenario
B2 data and land use change data for the Man Oon Reservoir in Thailand have been considered.
The extreme inflow, the future inflow and the synthetic inflow of reservoirs were used in evaluating
the obtained rule curves. The situations of water shortage water excess as well as stored water at
the end of the wet season were shown. The results showed that the multipurpose rule curves with
objective function of minimized average excess spill water, can mitigate flood situations more than
the other rule curves, furthermore it is possible to have more stored water at the end of wet season
than water stored when using the other rule curves. Copyright © 2018 Praise Worthy Prize S.r.l. -
All rights reserved.
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved https://doi.org/10.15866/irece.v9i3.14532
114
R. Hormwichian, J. Tongsiri, A. Kangrang
operating system are available water (calculated from the stops [14]-[15].
water balance concept) and downstream water demands. The integrating conditional genetic algorithm and
Monthly release is estimated by considering the reservoir simulation model to search optimal rule curves
monthly available water with release criteria, operating is described in Fig. 2.
policies and reservoir rule curves. For this study, the
reservoir operation model was created following the GA Searching
concept of water balance. The reservoir operation model Set initial population of rule curves
is used under physical reservoir data, inflow data, water
demand, hydrological data, standard operating rule and
water balance equation as presented in Fig. 1 and Eq. (1): Input Data Reservoir Simulation
GA generating
-Water demand the new rule curves
-Water balance
-Historic inflow -Considering rule curves
W S 1 I P E DS (1) -Future inflow parameters
-Calculate water release
Reproduction
where W is the available water during month , S-1 is the -Selection
-crossover
stored water at the end of month -1; I is the monthly -mutation
inflow to the reservoir, P is the precipitation during Evaluation
multi-objective functions
month , E is the average value of the evaporation loss
and DS is the minimum reservoir storage capacity. LRC
No
represents the lower rule curves during month and Criteria
URC represents the upper rule curves during month. satisfied?
Yes
Release
Stop GA
1 Obtain the multi-objective rule curves
1
Fig. 2. Conditional Genetic Algorithm with Reservoir Simulation
1 to search Rule Curves
1
Firstly, the minimum average excess spill water per
Available water year ( U ) is set as the objective function of the searching
procedure subject to the constraints on the simulation
model as in the following:
Fig. 1. Standard Operating Rule
1 n
Then, monthly release of water from the reservoir (R) Min U ( Xi )
Sp v (2)
will be used to calculate the multi-objective functions in n v 1
the searching procedure, such as average excess release
12
of water per year, frequency of water shortage as well as
the maximum of the water stored at the end of the wet
if R D ,then Spv R D (3)
1
season, etc. These objective functions will be recorded
and used in the CGA model. The details of each Else Spv 0
objective function will be described in the next section.
where n is the total number of considered years, Sp is
the excess spill water during year (a year in which
II.2. Conditional Genetic Algorithm releases are higher than the target demand) and i is the
with Reservoir Simulation iteration number.
Firstly, the conditional genetic algorithm was created Secondly, the maximum of the average stored water at
with the reservoir simulation model. The procedure starts the end of the wet season ( N ) is set as the objective
from creating initial population of rule curves, boundary function of the searching procedure subject to the
search, probable crossover and mutation, and stopping constraints on the simulation model as in the following:
criteria. Then, the population initial rule curves were sent
to reservoir simulation model to operate considering 1 n
input data. The monthly release was calculated using Max N ( Xi )
SN v (4)
initial rule curves. Then, the monthly release water was n v 1
used to calculate objective function and to evaluate the
initial rule curves to accept in first generation. Also, the where n is the total number of considered years, SN is
new accepted rule curves will be used to replace the the stored water at the end of the month of November
initial population. This procedure is repeated until the during year (November is the last month of the wet
new accepted rule curves are appropriate, then the search season in Thailand) and i is the iteration number.
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
115
R. Hormwichian, J. Tongsiri, A. Kangrang
1,200
Historic Inflow (1992-2016) Future Inflow (2017-2066)
1,000
800
Inflow (MCM)
600
400
200
0
1992
1994
1996
1998
2000
2002
2004
2006
2008
2010
2012
2014
2016
2018
2020
2022
2024
2026
2028
2030
2032
2034
2036
2038
2040
2042
2044
2046
2048
2050
2052
2054
2056
2058
2060
2062
2064
2066
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
116
R. Hormwichian, J. Tongsiri, A. Kangrang
III. Results and Discussion different objective functions. The optimal future rule
curves of each case were obtained. All the obtained
III.1. Historic Rule Curves with future rule curves were plotted with the current rule
Multi-Objective Function curves as shown in Fig. 7. They indicated that the rule
The 25 years of monthly historic inflow data, monthly curve patterns of all cases are similar when compared to
data of evaporation, rainfall, irrigation, domestic and the current rule curves.
industrial water requirements and monthly environmental Fig. 7 also shows the optimal future rule curves of the
conservation were used in the reservoir simulation model Nam Oon reservoir using minimize excess spill water
connecting with CGA while considering different (RC4-min spill-future), using maximize store water at the
objective functions. end of wet season (RC5-max store-future), using multi
Then, the optimal historic rule curves of each case objectives of maximize store and minimize spill (RC7-
were obtained. These obtained rule curves of all the cases multi future) as well as when compared with the current
were plotted to be compared with the current rule curves rule curves (RC1). The obtained rule curves also
as shown in Fig. 6. They indicated that the rule curve indicated that the storage capacity of upper rule curves of
patterns in all cases were similar to the current rule CGA models for both objective functions are higher than
curves. The patterns of the obtained curves are similar to the upper rule curves of the current ones, whereas their
the patterns of other reservoirs in Thailand from other lower levels are slightly different. Hence, they can reduce
studies [8]-[9], [19]-[20] because of the seasonal inflow the spill water and keep the storage capacity full at the
effect. Fig. 6 also presents the optimal historic rule end of the rainy season. This will help to alleviate water
curves of the Nam Oon reservoir using minimize excess shortages in the next year, as seen in other studies [21]-
spill water (RC2-min spill-historic), using maximize [22].
store water at the end of wet season (RC3-max store-
historic), using multi objectives of maximize store and III.3. Efficiency of Rule Curves Under Synthetic
minimize spill (RC6-multi historic) as well as compared Inflow Conditions
to the current rule curves (RC1).
The obtained rule curves also indicated that the upper The efficiency of the obtained rule curves from all
levels of CGA models for both objective functions are cases of searching were evaluated by the operating
higher than the upper level of the current rule curves, reservoir simulation considering the synthetic inflow
whereas the lower level of them is slightly different. data. 1,000 samples of synthetic inflow were generated
Hence, they can increase the storage water for the next from the historic inflow over 50 years.
dry season. This will help to alleviate water shortages in Table I shows the situations of the water shortage
the next year, as it can be seen in other studies [21]-[22]. using both multi-objective rule curve and the current rule
curves. They indicated that the average magnitudes of the
water shortages using CGA rule curves are lower than
III.2. Future Rule Curves with the magnitudes using the current rule curves
Multi-Objective Functions (17.208±8.126 million cubic meters (MCM)/year for
The 25 years future inflow period 2017-2041 under average water shortage of CGA compared to water
the B2 scenario and the other monthly information, like shortages of current rule curves that are 41.586 ±6.258
in the former section, were used in the reservoir MCM/year).
simulation model connecting with CGA considering two
600
Normal high water storage (520 MCM)
Storage Capacity (MCM)
500
400
300
RC1-current RC2-min spill-historic RC3-max store-historic RC6-multi historic
200
100
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
117
R. Hormwichian, J. Tongsiri, A. Kangrang
The frequencies and the duration times of the water end of the wet season when using CGA rule curves are
shortages using CGA rule curves are lower than the higher than the stored level when using the current rule
frequencies and the duration times of the current rule curves. They found that the stored level when using
curves. RC3-max store-historic is the highest with
Table II presents the situations of excess spill water 425.996±6.258 MCM, because of the searching objective
when using each multi-objective rule curve and the function effect. The high capacity at the end of the wet
current rule curves. The results indicated that the average season surely guarantees the storage of a great amount of
magnitudes of excess release using the CGA rule curves water for the following dry season.
are less than the magnitudes using the current rule curves
(66.471±18.241 MCM/year for average excess water of TABLE III
MAXIMUM STORED WATER AT END OF WET SEASON USING 1,000
CGA compared to the excess spills of the current rule
SAMPLES OF SYNTHETIC INFLOW FOR EACH MULTI-OBJECTIVE FUTURE
curves of 90.509 ±19.573 MCM/year). The frequencies RULE CURVE
and the duration times of the excess spill water using the Rule curves Stored water at the end of November (MCM)
CGA rule curves are lower than the frequencies and the 323.307
RC1 (current)
duration times using the current rule curves. 13.364
319.307
RC2-min spill-historic
TABLE I 17.384
SITUATIONS OF WATER SHORTAGE OF SYSTEMS CONSIDERING 1,000 425.996
RC3-max store-historic
SAMPLES OF SYNTHETIC INFLOW FOR EACH MULTI-OBJECTIVE 6.258
RULE CURVE 325.145
Magnitude RC4-min spill -future
Frequency Duration (year) 17.277
Rule curves (MCM/year) 368.699
(times/year) RC5-max store-future
Average Maximum Average Maximum 9.836
0.971 41.586 130.189 18.238 21.056 317.641
RC1 (current) RC6-multi-historic
0.032 6.258 36.162 6.990 4.693 14.640
RC2-min spill- 0.281 17.208 116.854 1.818 2.968 323.899
historic 0.103 8.126 29.775 0.684 1.405 RC7-multi-future
17.020
RC3-max 1.000 128.288 144.549 25.000 25.000
store-historic 0.000 3.774 3.685 0.000 0.000
RC4-min spill - 0.493 18.880 114.844 2.445 4.918 III.4. Efficiency of Multi-Objective Future Rule Curves
future 0.108 8.145 28.606 0.866 2.054
Under Future Inflow Conditions
RC5-max 1.000 100.800 106.000 25.000 25.000
store-future 0.000 1.206 4.967 0.000 0.000 For the future situation, the obtained rule curves of all
RC6-multi- 1.000 42.778 102.147 25.000 25.000 case searches were used to operate the reservoir system
historic 0.000 4.645 39.238 0.000 0.000
for evaluating the efficiency by considering 25 years of
RC7-multi- 0.361 18.769 119.361 2.039 3.647
future
future inflow under B2 scenario. Table IV shows the
0.106 8.280 28.797 0.734 1.598
situations of water shortage when using each future rule
Note: = average,= standard deviation
curve and the current rule curves. They indicated that the
TABLE II average magnitudes of the water shortages using the
SITUATIONS OF EXCESS SPILL WATER OF SYSTEMS CONSIDERING 1,000 CGA future rule curves are lower than the magnitudes
SAMPLES OF SYNTHETIC INFLOW FOR EACH MULTI-OBJECTIVE using the current rule curves (6.380 MCM/year for the
RULE CURVE
average water shortages of CGA compared to the
Magnitude
Rule curves
Frequency
(MCM/year)
Duration (year) shortage with the current rule curves of 24.600
(times/year) MCM/year). The frequencies and the duration of water
Average Maximum Average Maximum
0.676 90.509 356.605 3.376 7.017 shortages using the CGA rule curves are lower than with
RC1 (current)
0.100 19.573 74.965 1.402 2.960 the current rule curves. The results also indicate that
RC2-min spill- 0.543 66.471 328.849 2.537 5.166 situations of water shortage when using the future rule
historic 0.112 18.241 83.273 0.846 2.160 curves (RC5-max store-future) are lower because these
RC3-max 0.935 170.380 414.268 12.543 17.018 rule curves attempt to keep the water at the maximum
store-historic 0.052 21.709 64.248 6.713 5.451
level at the end of the wet season following the searching
RC4-min spill 0.555 67.614 325.539 2.581 5.233
-future 0.112 18.205 80.325 0.906 2.183
objective function. Table V shows the situations of the
RC5-max 0.880 155.300 373.173 11.000 18.000 excess spill water when using both multi-objective future
store-future 0.074 22.888 70.750 5.022 5.081 rule curve and current rule curves. The results indicated
RC6-multi- 0.670 92.679 374.179 3.589 7.311 that the average magnitudes of the excess release using
historic 0.109 20.965 80.586 1.527 3.079 the CGA rule curves are lower than the magnitudes using
RC7-multi- 0.554 67.785 327.092 2.539 5.189 the current rule curves (180.958 MCM/year for average
future 0.110 18.148 79.683 0.842 2.141 excess water for CGA compared to the excess spills of
Note: = average ,= standard deviation the current rule curves that are 199.661 MCM/year). The
frequency and the duration time of the excess spill water
Table III shows the stored water at the end of the wet
using the CGA rule curves are lower than the frequency
season (November) using every multi-objective rule
and the duration using the current rule curves.
curve. The results indicated that the stored water at the
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
118
R. Hormwichian, J. Tongsiri, A. Kangrang
600
Normal high water storage (520 MCM)
400
300
RC1-current RC4-min spill-future RC5-max store-future RC7-multi future
200
100
TABLE V
SITUATIONS OF EXCESS SPILL WATER OF SYSTEMS USING FUTURE
IV. Conclusion
INFLOW FOR EACH MULTI-OBJECTIVE FUTURE RULE CURVE
This study applied conditional genetic algorithm
Magnitude
Rule curves
Frequency
(MCM/year)
Duration (year) (CGA) with reservoir simulation model to search the
(times/year) multi-objective rule curves of the Nam Oon Reservoir,
Average Maximum Average Maximum
RC1-current 0.920 199.661 923.360 11.500 24.000 SakonNakhon province, Thailand. There were two
RC2-min spill- objective functions applied to search optimal rule curves;
0.820 181.317 923.360 5.125 17.000
historic
RC3-max
(1) minimize average excess water spill and (2)
0.980 267.581 923.360 24.500 25.000 maximize store water at the end of wet season. The 25
store-historic
RC4-min spill
0.840 180.958 923.360 6.000 17.000
years of future inflow were created by the SWAT model
-future considering both climate change of scenario B2 and land
RC5-max
store-future
0.960 266.358 923.360 16.000 24.000 use change of Agri-map. The 25 years of future inflow
RC6-multi- and 1,000 samples of synthetic inflow were used to
0.920 207.504 923.360 11.500 24.000
historic simulate the reservoir system for evaluating the
RC7-multi- performance of rule curves. The results showed that the
0.860 182.551 923.360 6.143 17.000
future
obtained rule curves from CGA with objective function
of minimize average excess water spill are more suitable
Table VI shows the stored water at the end of the wet for reservoir operation than the current rule curves in
season (November) when using each multi-objective both the historic situation and the future situation.
future rule curve. The results indicated that the stored Furthermore, the frequency and the magnitude of
water at the end of the wet season when using CGA rule excess water releases when using the newly obtained rule
curves are higher than the stored level when using the curves are lower than those of current rule curves. For
current rule curves. It has also been found that the stored the obtained rule curves from CGA with objective
level when using RC5-max store-future had the highest function of maximize store water at the end of wet season
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
119
R. Hormwichian, J. Tongsiri, A. Kangrang
are more suitable for reservoir operation than the current [12] Ilavarasan, E., Thambidurai, P., Genetic Algorithm for Task
Scheduling on Distributed Heterogeneous Computing System,
rule curves in both the historic situation and the future
(2015) International Journal on Engineering Applications (IREA),
situation too. In addition, the frequency, magnitude of 3 (4), pp. 108-117. Retrieved from:
excess water releases and stored water at the end of wet https://www.praiseworthyprize.org/jsm/index.php?journal=irea&p
season when using the newly obtained rule curves are age=article&op=view&path%5B%5D=0306r
[13] Soepangkat, B., Norcahyo, R., Pamuji, D., Lusi, N., Multi-
less than those of current rule curves. These conclude Objective Optimization in End Milling Process of ASSAB XW-
that the CGA models considering future inflows are 42 Tool Steel with Cryogenic Coolant Using Grey Fuzzy Logic
effective for searching optimal rule curves for future and Backpropagation Neural Network-Genetic Algorithm
situations. Whereas the maximum stored water at the end (BPNN-GA) Approaches, (2018) International Review of
Mechanical Engineering (IREME), 12 (1), pp. 42-54.
of the wet season is an effective objective function for
doi: https://doi.org/10.15866/ireme.v12i1.14123
searching optimal rule curves for storing water for the [14] R. Hormwichian, A. Kangrang, and A. Lamom, A conditional
next dry season. genetic algorithm model for searching optimal reservoir rule
curves, Journal of Applied Sciences, vol. 9, no. 19, pp. 3575-
3580, 2009.
Acknowledgements [15] H. Prasanchum, and A. Kangrang, Optimal reservoir rule curves
under climatic and land use changes for Lampao Dam using
This research was financially supported by genetic algorithm, KSCE Journal of Civil Engineering, vol. 22,
no. 1, pp. 351–364. 2018
Mahasarakham University Grant 2018; the authors would [16] J. Supakosol, and A. Kangrang, Assessment of soil loss and
like to acknowledge Mahasarakham University. nutrient depletion due to climate change impact in the SongKhram
Basin, Thailand, International Journal of Ecology &
Development, vol. 32, no.2, pp. 53-66, 2017.
References [17] IPCC, Summary of policymakers: Emission scenarios: A special
report of IPCC workgroup III of the Intergovernmental Panel on
[1] S. K. Jain, M. K. Goel, and P. K. Agarwal, Reservoir operation Climate Change, 2000.
study of sabamati system, India, Journal of Water Resources [18] A. W. Alansi, M. S. M. Amin, G. Abdul Halim, H. Z. M. Shafri,
Planning and Management, vol. 124, no. 1, pp. 31–38, 1998. and W. Aimrun, Validation of SWAT model for stream flow
[2] M. Azizipour, V. Ghalenoei, M. H. Afshar, and S. S. Solis, simulation and forecasting in Upper Bernam humid tropical river
Optimal operation of hydropower reservoir systems using weed basin, Malaysia, Hydrology and Earth System Sciences, vol. 6, no.
optimization algorithm, Water Resources Management, vol. 30, 6, pp. 7581–7609, 2009.
no. 11, pp. 3995–4009, 2016. [19] A. Kangrang, H. Prasanchum, R. Hormwichian, Future runoff
[3] C. Chaleeraktrakoon, and A. Kangrang, Dynamic programming under land use and climate changes in the Nam Oonana Basin,
with the principle of progressive optimality for searching rule Thailand, International Journal of Ecology & Development, vol.
curves, Canadian Journal of Civil Engineering, vol. 34, pp. 170- 32, no. 3, pp. 53-66, 2017.
176, 2007. [20] P. S. Ashofteh, O. B. Haddad, and H. A. Loáiciga, Evaluation of
[4] F. J. Chang, L. Chen, and L. C. Chang, Optimizing the reservoir climatic-change impacts on multiobjective reservoir operation
operating rule curves by genetic algorithms, Hydrological with multiobjective genetic programming, Journal of Water
Processes, vol. 19, pp. 2277-2289, 2005. Resources Planning, Vol.141, no.11, pp. 04015030, 2015.
[5] A. Kangrang, S. Compliew, and R. Hormwichian, Optimal [21] C. Chiamsathit, A. J. Adeloye, and B. S. Soundharajan, Assessing
reservoir rule curves using simulated annealing, Proceedings of competing policies at Ubonratana reservoir, Thailand,”
the Institution of Civil Engineers-Water Management, vol. 164, Proceeding of the Institution of Civil Engineering–Water
no. WM1, pp. 27–34, 2011. Management, vol. 167, no. 10, pp. 551–560, 2015.
[6] R. Hormwichian, A. Kangrang, A. Lamom, C, Chaleeraktrakoon, [22] X. Guo, T. Hu, C. Wu, T. Zhang, and Y. Lv, Multi-objective
and P. Patamatamkul, Coupled-operations model and a optimization of the proposed multi-reservoir operating policy
conditional differential evolution algorithm for improving using improved NSPSO, Water Resources Management, vol. 27,
reservoir management, International Journal of Physical no. 7, pp. 2137–2153, 2013.
Sciences, vol. 7, no. 42, pp. 5701-5710, 2012. [23] Si Tayeb, M., Fizazi, H., A Dual-Level Hybrid Approach for
[7] A. Kangrang, and C. Lokham, Optimal reservoir rule curves Classification of Satellite Images, (2017) International Review of
considering conditional ant colony optimization with simulation Aerospace Engineering (IREASE), 10 (1), pp. 42-49.
model, Journal of Applied Sciences, vol. 13, no. 1, pp. 154-160, doi:https://doi.org/10.15866/irease.v10i1.11191
2013. [24] Kassem, A., El-Bayoumi, G., Habib, T., Kamalaldin, K.,
[8] A. Kangrang, and R. Homwichian, Optimal reservoir rule curves Improving Satellite Orbit Estimation Using Commercial Cameras,
using conditional shuffled frog leaping algorithm and simulation, (2015) International Review of Aerospace Engineering (IREASE),
International Journal of Earth Sciences and Engineering, vol. 6, 8 (5), pp. 174-178.
no. 6, pp. 1392-1399, 2013. doi:https://doi.org/10.15866/irease.v8i5.8279
[9] A. Kangrang, W. Pakoktom, W. Nualnukul, and C. [25] Ghazli, A., Hadj Said, N., Alipacha, A., Mobile Phone Security
Chaleeraktrakoon, Adaptive Reservoir Rule Curves by Based New Strong Genetic Stream Cipher Design, (2017)
Optimization and Simulation, Proceedings of the Institution of International Journal on Communications Antenna and
Civil Engineers-Water Management, vol. 170, no. WM5, pp. 219- Propagation (IRECAP), 7 (4), pp. 334-341.
230, 2017. doi:https://doi.org/10.15866/irecap.v7i4.10693
[10] B. Ming, J-X. Chang, O. Huang, Y-M. Wang, and S-Z. Huang [26] Abdul Malek, N., Mat Ramli, N., Abdullah, K., Null Positioning
Optimal operation of multi-reservoir system based on cuckoo of Dipole Antenna Array Considering Coupling Effect, (2017)
search algorithm, Water Resources Management, vol. 29, no. 15, International Journal on Communications Antenna and
pp. 5671–5687. 2015. Propagation (IRECAP), 7 (5), pp. 370-377.
[11] Omar, H., Zaky, E., Ibrahim, G., Elsawy, A., An Algorithm Based doi:https://doi.org/10.15866/irecap.v7i5.11718
Levenberg Marquardt Method with Genetic Algorithm for [27] Zongo, O., Oonsivilai, A., Comparison between Harmony Search
Solving Continuation Problems, (2013) International Journal on Algorithm, Genetic Algorithm and Particle Swarm Optimization
Numerical and Analytical Methods in Engineering (IRENA), 1 in Economic Power Dispatch, (2015) International Review of
(1), pp. 20-30. Retrieved from: Electrical Engineering (IREE), 10 (2), pp. 286-292.
https://www.praiseworthyprize.org/jsm/index.php?journal=irena& doi:https://doi.org/10.15866/iree.v10i2.5361
page=article&op=view&path%5B%5D=11624
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
120
R. Hormwichian, J. Tongsiri, A. Kangrang
[28] Phanendra Babu, N., Suresh Babu, P., Siva Sarma, D., A Reliable
Wide--Area
Wide Area Measurement System Using Hybrid Genetic Particle
Swarm Optimization (HGPSO), (2015) International Re Review
view of
Electrical Engineering (IREE)
(IREE),, 10 (6), pp. 747
747-763.
763.
doi:https://doi.org/10.15866/iree.v10i6.7127
Authors’ information
Rattana Hormwichian received her Ph.D. in
Civil Engineering from Mahasarakham
University, Thailand in 2014
2014. She is currently
an Assistant
A stant Professor at the Faculty of
Engineering at Mahasarakham University,
Thailand. Her research interests include water
resource management and optimization
techniques.
Jedsada
Jedsada Tongsiri received his B.Eng. degree in
Civil Engineering ffrrom
m Kasetsart University,
University,
Thailand in 2000. He is currently aaM.Eng
M.Eng
M.Eng.
student in Civil Engineering at Mahasarakham
University, Thailand.
121
International Review of Civil Engineering (I.RE.C.E.), Vol. 9, N. 3
ISSN 2036 - 9913 May 2018
Abstract – The phenomenon of clays swelling is the cause of possible disorders dependent on the
movement of the soil. The technique of the stabilization to improve such a soil state using cement
and lime is utilized all around the world. The stabilization of the soil can be a very important
solution because it brings important modifications to their geotechnical properties. This document
aims to study the influence of the lime and the cement on the geotechnical properties of the
expansive soil. The studied mechanical properties are the plasticity, the compaction, the
unconfined compression strength, the free swell and the shear strength characteristics of the soil
with varying proportions of lime and cement, Properties of the untreated soil were determined.
The percentages of lime and cement added are respectively 2 %, 4 %, 6 % and 8 % by the dry
weight of the soil. The untreated soil values were used as points of comparison. The obtained
results show a significant reduction in the plasticity index and in the percentage of free swell of
expansive soil with the increase of the quantity of lime and cement. Also it has been found that the
addition of lime and cement increases the optimum moisture content, the unconfined compression
strength, and the shear strength of the soil. The soil used in this research was taken in the zone of
Me’daourouch, near the city of Souk Ahras. This research work studied in particular three
aspects, Such as the effect of admixtures cement and lime, the effect of the variation of the
percentage of admixtures and the effect of curing time after mixing of admixtures on the
stabilization. Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved.
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved https://doi.org/10.15866/irece.v9i3.14457
122
S. Djouimaa, S. Madani, M. Hidjeb
lime and cement. In order to illustrate the effect of cao, the Ca++ provided by cement and lime can replace
adding cement and lime on the geotechnical behaviour of the Na+ in the expansive soil, which leads to the
the expansive soil. The soil was subjected to a series of stabilization of the clay. Normal Proctor tests were
tests such as atterberg limit compaction characteristics, carried out according to standard NF P94-093, which will
free swell, shear strength and unconfined compressive study the influence and the relation between the dry unit
strength, furthermore, the influence of the curing time is weight of the soil as well as the water content.
investigated.
TABLE I
PROPERTIES OF THE STUDIED SOIL For the natural soil the optimum water content
Properties obtained is of 15.8 % (Fig. 5). The optimum water
Φ<80 µm 96,8 content and the maximum dry unit weight of the natural
Nature water content (%) 21,5 and treated specimens were determined by using the
Liquid limit (%) 51
standard Proctor compaction test, in a standard
Plastic limit (%) 22
Plasticity index (%) 29 cylindrical mould, whose dimensions were 101 mm in
Optimum water content OMC (%) 15,8 diameter and 100 mm in height. Unconfined compressive
maximum dry unit weight MDD (t/m3) 01,89 strength tests were carried out on the natural and treated
CaCo3 Soil (%) 01,86 soil according to the appropriate French standard NF P
CaCo3Cement (%) 62,2
CaCo3lime (%) 88,00 94-077.
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
123
S. Djouimaa, S. Madani, M. Hidjeb
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
124
S. Djouimaa, S. Madani, M. Hidjeb
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
125
S. Djouimaa, S. Madani, M. Hidjeb
(a)
(b)
TABLE III
COHESION AND ANGLE OF INTERNAL FRICTION TESTED AT DIFFERENT
Fig. 12. Unconfined compressive strength of soil CURING DURATION
With various additions of lime Cement Lime
Angle of internal friction
content content Cohesion (kPa)
(degree)
This result indicates that the curing period influences (%) (%)
the strength of the samples treated with lime or cement, 7 days 14 days 28 days 7 days 14 days 28 days
so that the increase in treatment time increases the - 2 66,9 83,7 125,6 21,5 23,2 27,2
- 4 91,5 109,7 165,8 23,4 26,5 31,4
unconfined compressive strength of the treated soil. - 6 129,4 153,2 203,6 28,6 32 38,3
Because of the influence of the cementitious - 8 164,2 189,5 248,7 32,1 34,9 42,7
compounds the unconfined compressive strength 2 - 69,2 89,7 157,8 23,9 25,1 29,4
increases with the curing time by increasing in the lime 4 - 99,3 117,4 183,1 27,1 29,9 33,8
6 - 135,8 161,1 221,8 33,2 35,4 40,1
values which is due to the pozzolanic reaction. The effect 8 - 172,5 218,7 263,2 38,4 40,3 45,1
of the treatment with cement is better than the one of
lime. The variation of internal friction angle with cement
and lime content, illustrated in Figs. 16 and 17, is similar
III.4. Variation of Shear Strength Parameters to the one of cohesion in Figs. 14 and 15. The maximum
internal friction angle is also observed at 8% cement and
The values of the cohesion and the internal friction 8% lime content. An increase in the cohesion from a
angle of the samples treated at 7, 14, 28 days are given in value of 157 kPa to a value of 263 kPa at 28 days of
Table III. curing during with cement is presented in Fig. 14. The
The two stabilizers lead to an increase in the shear effect of the treatment with lime is quite slow compared
strength parameters; this increase is due to the formation to the one of cement and it does not exceed 249 kPa in
of cementation compounds dependent on the addition of long term, the angle of friction of the soil treated with
the different percentage of cement and limes that makes lime and cement presents the same behavior of cohesion
the connection between the grains of clays increase and in Figs. 16 and 17. The internal friction angle increases
consequently there is more shear strength. also with the time. The results of the direct shear tests are
The maximum of cohesion is observed with the 8% of the same for the cohesion and the internal friction angle;
cement and the 8% of lime content (Table III) which they depend on the type of treatment and the curing
represents a good adherence between the grains. period.
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
126
S. Djouimaa, S. Madani, M. Hidjeb
Fig. 16. Effect of curing time and percentage of cement on the angle of
internal friction of treated soil
Fig. 19. Swell versus time graphics for different cement contents
with 7days cure
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
127
S. Djouimaa, S. Madani, M. Hidjeb
Fig. 22. Swell versus time graphics for different lime contents
with 7 days cure
Fig. 23. Swell versus time graphics for different lime contents
with 28 days cure
TABLE IV
VARIATION OF SWELLING PERCENTAGE WITH PERCENT CEMENT, LIME
AND CURING TIME
specimens % Change in dH/H
Without curing 7days curing 28days curing
A 0,0 0,0 0,0
98%A+2%Cement 36,6 46,7 58,8
96%A+4%Cement 43,5 50,4 65,9
93%A+6%Cement 49,3 56,9 69,7
Fig. 21. Swell versus time graphics for different
90%A+8%Cement 57,1 60,1 73,8
lime contents without cure
98%A+2%Lime 22,8 26,8 40,9
96%A+4%Lime 31,8 35,4 54,3
93%A+6%Lime 44,8 48,6 54,9
III.6. Effect of Curing on the Swelling Percentage 90%A+8%Lime 53,6 56,5 57,3
Fig. 24 shows a significant decrease in the percentage
in the swelling of soils treated with cement or lime. It is This is due to an exchange reaction as well as an
also noted that this improvement in the percentages of adsorption of non-exchanged calcium ions, and the
swelling of the treated soil is due to the increase of the formation of a cementing agent, which binds the particles
curing time between them, and thus limiting the increase in volume
of clays.
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
128
S. Djouimaa, S. Madani, M. Hidjeb
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
129
S. Djouimaa, S. Madani, M. Hidjeb
Authors’ Information
Sarah Djouimaa is an Assistant Professor in
Dept. of Civil Engineering University of
Mohamed Cherif Messaadia Souk-Ahras
Algeria. She received a degree in civil
engineering from Constantine university of
Science and Technologie in 2006 and a master’s
degree in geotechnical option from the
University of 20 August 1955, Skikda, Algeria
in 2009, she is a member of the Management, Maintenance and
Rehabilitation of Urban Infrastructures, Laboratory. Her research
interests include swelling and soil treatment.
Copyright © 2018 Praise Worthy Prize S.r.l. - All rights reserved International Review of Civil Engineering, Vol. 9, N. 3
130
International Review of Civil Engineering
(IRECE)
Aims and scope
The International Review of Civil Engineering (IRECE) is a peer-reviewed journal that publishes original theoretical papers,
applied papers, review papers and case studies on all fields of civil engineering.
The scope of the Journal encompasses, but is not restricted to the following areas: infrastructure engineering; transportation
engineering; structural engineering (buildings innovative structures environmentally responsive structures bridges stadiums
commercial and public buildings, transmission towers, television and telecommunication masts, cooling towers, plates and shells,
suspension structures, smart structures, nuclear reactors, dams, pressure vessels, pipelines, tunnels and so on); earthquake,
hazards, structural dynamics, risks and mitigation engineering; environmental engineering; structure-fluid-soil interaction; wind
engineering; fire engineering; multi-scale analysis; constitutive modeling and experimental testing; construction materials;
composite materials in engineering structures (use, theoretical analysis and fabrication techniques); novel computational modeling
techniques; engineering economics.
The Editorial policy is to maintain a reasonable balance between papers regarding different research areas so that the Journal will be
useful to all interested scientific groups.
The Journal also publishes short communications and discussions, book reviews, and a diary on international events related to any
aspect of civil engineering.
Contributions may consist of invited tutorials or critical reviews; original scientific research papers (regular paper); letters to the
Editor and research notes which should also be original presenting proposals for a new research, reporting on research in progress
or discussing the latest scientific results in advanced fields.
All papers will be subjected to a fast editorial process.
Any paper will be published within two months from the submitted date, if it has been accepted.
www.praiseworthyprize.org/jsm/?journal=irece
Manuscripts should be sent on-line or via e-mail as attachment in .doc and .pdf formats to:
editorialstaff@praiseworthyprize.com
Subscription rates: