AB gaudiness to carry out the offshore work

Fig.1

Crane 250te

Fig.2

The scope of work shall be carried out in accordance to the below steps.
1. Back fill the cliff (beach area1)as shown in fig.2 which is highlighted with red color to ensure a
suitable access for the mobile crane (250te) and make the loading arms and destruct offshore
materials reachable rather than use a ship crane .This area should be removed later on once the
target get finished .
2. Back fill the cliff (beach area 3) as shown in fig.2 to ensure a significant yard for scaffolding
erection to destruct the pipe expansion loops which are laid on the sea as shown in fig.1.this
area also has to be removed later on .
3. Use area 2 as shown in fig.2 as a temporary laydown area for the offshore destructed materials.
4. All the demolition work for the platform and trestle as shown in fig.1 to be carried out in the
same manner as the onshore.
*we believe this way to execute the offshore works will be faster ,easier and noncosty We
preferred to go through the back filling of cliff as long as the current scope of others also has a
back filling works .