Professional Documents
Culture Documents
Method Statement Piping Works
Method Statement Piping Works
For
Piping Works at Site
TABLE OF CONTENTS
1. PURPOSE
2. SCOPE
3. REFERENCES
4. DEFINITIONS
5. RESPONSIBILITIES
6. SEQUNCE OF WORKS
7. QA/QC
8. RESOURCE
9. HSE REQUIMENTS
Page 2 of 12
1.0 Purpose:
The purpose of this methodology is to provide a systematic control and direction for the
activity for the installation of piping at site. This method statement provides the expectation to
execute work in safe, eco-friendly manner and in compliance to the ELCREST/NPDC
and Quality requirements.
2.0 Definitions
Client - ELCREST/NPDC
QHSE - Quality, Health, Safety & Environment
QCI - Quality Control Inspector
ITP - Inspection and Test Plan
WPS - Welding Procedure Specification
NDT - Non Destructive Testing
PWHT - Post Weld Heat Treatment
3.0 Responsibilities
TECHRON ENERGY shall arrange all the resources deemed necessary for carrying out the
works related to the piping installations. In addition to the above TECHRON ENERGY will
also ensure that adequate safety precautions are put in place in order to carry out the job in a
safe manner.
Construction Manager:
The Construction Manager is responsible in executing the works as per ELCREST/NPDC
procedure and approved method statement.
Page 3 of 12
Supervisor/ Foreman:
Ensure that welding equipment, baking oven, quiver are in good condition.
Ensure welding is done as per the approved WPS and approved for construction
drawings and in line with ELCREST/NPDC HSE requirements.
Ensure that weld maps / spool drawings are available.
Coordinate with QC personnel to study the cause of any reported weld defects and
arrange to take corrective and preventive action.
Adhere to the ELCREST/NPDC HSE requirements.
Comply with ELCREST/NPDC PTW requirements.
QC Inspector:
Carry out the inspection as per the Inspection and test plan.
Approving/ rejecting the item based on inspection.
Submitting the quality records to the client and getting their approval.
Responsible to keep records of all inspection related activities & Material traceability.
Adhere to the HSE requirements.
HSE Officer:
Advise the construction crew on HSE aspects and ensure their safety.
Arrange through Job performer for tool box talk covering risk assessment in language
understandable by workers.
Cross checking certified material devices and equipments are used.
Do weekly, monthly HSE audit.
Ensure appropriate safety measures are taken as per the risk assessment and controlled
documents.
Ensure that all staff adhere to the HSE plan and HSE requirements.
Page 4 of 12
4.0 Sequence of Works
4.1 PTW Issuance
A Hot Work permit will be issued to carry out the works, along with the permit will be
the attached crane certificate, approved method statement, risk assessment, and
approved drawings shall also be attached.
Page 5 of 12
Lifting of the pipe spools shall be done by using either a HIAB or Crane. Third Party
certified slings and riggers shall be used during the lifting operations. All lifting tools
and tackles shall be color coded based on the current color code.
Once the spools are lifted into position, the fabricator/pipe fitter shall ensure that proper
alignment is achieved, lengths of spools are correct as per the piping layout and
isometric sheet prior to either bolting the spools together or welding any field joints.
Welding and grinding of field joints shall be carried out inside a closed habitat made
of fire retardant material. Any live facilities will be covered with the fire retardant
blanket as an additional precaution.
Welding shall be done as per the approved procedure, specification and approved for
construction drawings.
Approved welders for the specific WPS shall be used for welding.
Welded surfaces shall be clean and free from grease, oil, paint or other foreign material
which are detrimental to welding.
When the weather does not permit satisfactory workmanship welding shall not be done,
on site in windy condition the pipe ends shall be closed to prevent through draughts
during welding. Suitable covering using tarpaulin (fire retardant) shall be provided.
Welding shall not be done when the weld surface is wet or when the area is exposed to
rain and strong windy conditions. Preheating to be done properly during cold weather.
Page 6 of 12
The support will then be placed in position, aligned, and tack welded. Once tack
welding is completed, the alignment will be rechecked and final welding will be carried
out.
Welding shall be done based on the approved welding procedure for structural steel.
4.6 Scaffolding
Scaffolding if required shall be erected by qualified personnel in a safe and suitable
manner.
Scaffolding above 2 m in height shall be inspected by a scaffolding inspector and a
scaff-tag shall be signed and provided on the scaffolding near the ladder. No one shall
use the scaffolding without the scaff-tag being approved.
Scaffolding material to be used shall be in good conditions, brass hammer shall be used
to assemble and tighten the scaffolding locks.
Page 7 of 12
5.0 QA/QC
5.1 Weld Identification
Each weld shall be uniquely identified with the joint number and welder number.
After completing the weld the welder shall mark the joint no: & welder no: near the
weld using paint or indelible crayon.
After welding each spool the line no, spool no & etc shall be marked / tagged on the
spool and stocked over wooden sleepers or other suitable material above ground.
Page 8 of 12
5.4 Weld Separation
Circumferential welds (Girth welds):
Distance between weld shall be measured between the adjacent edges of the cap passes.
Circumferential butt welds (Girth welds) shall be separated by maximum possible distance.
However between fittings, short pipe lengths may be required. In this case, butt welds shall
not be within 75 mm of adjacent girth weld for nominal pipe sizes of 75 mm and above.
For pipe sizes less than 75mm nominal, girth weld shall not be within the greater of 4 times
the wall thickness or one pipe diameter of adjacent girth welds. Girth welds closer than the
above limit shall require approval of the client and may require PWHT solely at the
discretion of the company.
Branch / Nozzle / attachment welds.
Branch / nozzle and other pressure attachment welds shall have minimum 3” distance to
adjacent pressure welds. Non pressure containing attachment welds shall be separated by
2” from adjacent pressure containing welds.
Longitudinal seams of adjacent pipes shall be separated by at least 4”.
Page 9 of 12
6.0 Resources
Welding machine
Grinding machine
Preheating torches with propane gas cylinders
Holding ovens/baking ovens
PWHT equipment
Hiab, Crane, trailer
Cutting tools
Generator
Page 10 of 12
8.0 Emergency contacts
TO BE ASSIGNED.
Page 11 of 12