High Level Bridge: DPR of Construction of Across Malkua Deverbeli Road at RD - 1900 M

You might also like

Download as xls, pdf, or txt
Download as xls, pdf, or txt
You are on page 1of 23

DPR OF CONSTRUCTION OF

HIGH LEVEL BRIDGE


ACROSS
MALKUA DEVERBELI ROAD AT RD - 1900 M
ESTIMATE BASED ON S.O.R. FOR ROAD & BRIDGE WORKS

GENERAL DATA:-

1 NAME OF PIU: BALAGHAT

2 NAME OF BLOCK: LANJHI

3 NAME OF RIVER:

4 LENGTH OF BRIDGE: 200.00 M

5 TYPE OF BRIDGE: HIGH LEVEL

6 SPAN ARRANGEMENT: 8 SPAN (25.00 M T-BEAM GIRDER)


6 SPANS USED FOR TOTAL LENGTH OF 150.00M

7 LOADING: IRC CLASS 'A' TWO LANES OR IRC CLASS '70R' ONE LANE

8 RCC ABUTMENT AND PIER : ABUTMENTS: R.C.C. BOX TYPE M-30 (PILE FOUNDATION)
PIERS: R.C.C. SOLID CIRCULAR PIER M-30 (PILE FOUNDATION)

9 APPROACH ROAD: 192.00 M

ABSTRACT OF COST

COST OF BRIDGE : 43402785

COST OF APPROACH ROAD : 3401280

TOTAL : 46,804,065
ESTIMATE FOR HIGH LEVEL BRIDGE ACROSS
MALKUA DEVERBELI ROAD AT RD - 1900 M

8 SPANS @ 25.00 M . = 200.00 M.


ABUTMENTS(A1& A2) 2 X 5 = 10.00 M.
SOLID CIRCULAR PIERS & R.C.C. BOX TYPE ABUTMENTS (PILE FOUNDATION)

Ref. Of
S.No. Description Quantity Unit Rate Amount
C.S.R.

Clearing and Grubbing road. (Clearing and grubbing


road land including uprooting rank vegetation,grass
bushes,shrubs,saplings and trees girth up to 300mm,
removal of stumps of trees cut earlier and disposal of
2.2
unserviceable material and stacking of servieabale
material to be used or auctioned up to a lead of 1000
meters including removal and disposal of top organic soil
not exceeding 150mm in thikness.)

A In area of light jungle 0.34 hectare 27701 9418.3

1 12.1
Excavation for Structures (Earth work in excavation of
foundation of structures as per
drawing and technical specification, including setting out,
construction of shoring and
bracing, removal of stumps and other deleterious matter,
dressing of sides and bottom and backfilling with
approved material.)as per relevant clauses of section 300
& 2100 in

(I) A Ordinary soil Manual Means


12.1 (I)A(i) upto 3m. Depth 832 cu.m. 212 176384
12.1(I)A(ii) 3m. To 6m. depth 24 cu.m. 252 6048
12.2 Add extra as follows in the rates of the above items if
dewatering is resorted to
Ordinary soil
(a) UPTO 3 m depth 832 cu.m. 106 88192
(b) 3m. To 6m. depth 24 cu.m. 189 4536
2 12.8
Provdiing and laying Plain/Reinforced cement
concrete in open foundation including
form work shuttering etc. complete as per drawing
and technical specifications and as per relevant
clauses of sections 1500, 1700 & 2100 with .

A PCC Grade M15 10 cu.m. 4164 41640


3 12.13 Providing steel liner 10 mm thick for curbs and 6mm 40 tonne 60354 2414160
thick for steining of wells
including fabricating and setting out as per detailed
drawing as per section 1200 &
1900.
4 12.16 Bored cast-in-situ M35 grade R.C.C. pile excluding 351 metre 14707 5162157
reinforcement complete as per
drawing and technical specifications and removal of
excavated earth with all lifts and
lead upto 1000 m. (Pile diameter-1200 mm)as per
specification 1100, 1600 and 1700.
5 12.28 Pile load test on single vertical pile in accordance with 520 tonne 482 250640
IS:2911(Part-IV)
6 12.29 Cement concrete for reinforced concrete in pile cap
complete as per drawing and
Technical Specification and as per relevant clauses of
sections 1100, 1500 & 1700.
C (i) RCC Grade M30 (Using concrete mixer.) 489 cu.m. 5996 2932044
7 13.1 Levelling course for Pile cap PCC in M-15 below Pile 40 cu.m. 4004 160160
cap as per drawing and as per
section 1100 and 1700.
8 12.39 Supplying, fitting and placing un-coated HYSD bar 69 tonne 60354 4164426
reinforcement in foundation
complete as per drawing and technical specifications and
as per relevant clauses of
section 1600.
10 13.6
Providing and laying Plain/Reinforced cement
concrete in sub-structure or complete RCC Box
section as per drawing and technical specifications
and as per relevant clauses of sections 1500, 1700 &
2200 in (Height above average ground level)

13.6 (G) (i) Height upto 5m.(RCC Grade M30) Case I 246 cu.m. 6307 1551522
13.6 (G) (ii) Height beyond 5m. and upto 10m.(RCC Grade M30) 145 cu.m. 6485 940325
Case I
11 13.7 Supplying, fitting and placing HYSD bar reinforcement 42 tonne 60354 2534868
in sub-structure complete as per
drawing and technical specifications and as per relevant
clause of section 1600.
12 14.1 Furnishing and Placing Reinforced/Prestressed
cement concrete in super-structure as per drawing and
Technical Specification and as per relevant clauses of
sections 1500, 1700 and 2300 in
14.1 C (ii) RCC Grade M30 (For T -beam & Slab)
(a) Height upto 5m. 1303 cu.m. 7175 9349025
13 14.2 a) Supplying, fitting and placing HYSD bar 161 tonne 60354 9716994
reinforcement in super-structure
complete as per drawing and technical specifications as
per relevant clauses of
section 1600
14 12.9 Providing weep holes in Brick 15 metre 172 2580
masonry/Plain/Reinforced concrete abutment, wing
wall/return wall with 100 mm dia AC/PVC pipe, extending
through the full width of the structure with slope of 1V :
20H towards drawing foce. Complete as per drawing and
Technical specifications
15 12.1 143 cu.m. 577 82511
Back filling behind abutment, wing wall and return
wall complete as per drawing and
Technical specification and as per relevant clauses 305 of
specifications and as per appendix 6 of IRC-78.
A.Granular material

16 12.11
Providing and laying of Filter media with granular
materials/stone crushed aggregates
satisfying the requirements laid down in clause 2504.2.2.
of MoRTH specifications to a
thickness of not less than 600 mm with smaller size
towards the soil and bigger size towards the wall and
provided over the entire surface behind abutment, wing
wall and return wall to the full height compacted to a firm
condition complete as per drawing and technical
specification.
17 Inside granular filling in abt. 444 cu.m. 914 405816
18 12.12 368640 cu.cm. 0.6 221184
Supplying, fitting and fixing in position true to line
and level elastomeric bearing conforming to IRC: 83
(Part-II) section IX and clause 2005 of MoRTH
specifications complete including all accessories as per
drawing and Technical Specifications.

19 13.5 118 cu.m. 10.809 1275.462


Providing and laying Cement concrete wearing coat
M-30 grade including reinforcement complete as per
drawing and Technical Specifications and as per relevant
clauses of sections 1500, 1700 and clause 2702 of
specifications.

20 14.7 420 metre 2074 871080


Construction of RCC railing of M30 Grade in-situ with
20 mm nominal size aggregate,
true to line and grade, tolurence of vertical RCC post
not to exceed 1 in 500, centre to centre spacing
between vertical post not to exceed 2000 mm, leaving
adequate space between
vertical post for expansion, complete as per
approved drawings and technical specifications
and as per relevant clauses of sections 1500, 1600,
1700 and clause 2703 of specifications
(as per MoST specification drawing SD/201 or
SD/304)

21 13.9 Providing Drainage Spouts complete as per drawing 16 Nos. 1428 22848
and Technical specification and as per clause 2705 of
specifications.
22 13.10 9 cu.m. 4004 36036
Providing PCC M-15 Grade leveling course below
approach slab complete as per drawing and technical
specification and as per relevant clauses of section 1700

23 13.17 Reinforced cement concrete approach slab including 18 cu.m. 11926 214668
reinforcement and formwork complete as per drawing and
Technical specification and as per relevant clauses of
section 1500, 1600,
1700 and clause 2704 of specifications.
24 14.21 Strip Seal Expansion Joint (Providing and laying of a 76 metre 11590 880840
strip seal expansion joint catering tomaximum horizontal
movement upto 70 mm, complete as per approved
drawings and
standard specifications to be installed by the
manufacturer/supplier or their authorised
representative ensuring compliance to the manufacturer's
instructions for installation.)
25 14.24 Testing of span of bridge for deflection due to live load 77 tonne 905 69685
with platforms for loading arrangements apparaturs for
meaurement including unloading etc. complete as per
approved drawing.
26 14.26 Providing and fixing in position Marble Plates of size 2 Nos. 1521 3042
0.9 m. x 1.2 m. with inscribed details as per detailed
drawings.
27 10.2
Retro- reflectorised Traffic signs (Providing and fixing
of retro- reflectorised cautionary,
mandatory and informatory sign as per IRC :67 made of
encapsulated lens type reflective
sheeting vide clause 801.3, fixed over aluminium
sheeting, 1.5 mm thick supported on a mild steel angle
iron post 75 mm x 75 mm x 6 mm firmly fixed to the
ground by means of properly designed foundation with
M15 grade cement concrete 45 cm x 45 cm x 60 cm, 60
cm below ground level as per approved drawing)

ii 80 cm x 60 cm rectangular 2 Nos. 3898 7796


28 10.3 315 sqm 108 34020
Painting two coats after filling the surface with
synthetic enamel paint in all shades on new plastered
concrete surfaces and as per relevent clauses of section-
800 & I.R.C.-67 including cost of paint etc. complete.

29 10.7 Boundary pillar (Reinforced cement concrete M15 grade 84 each 454 38136
boundary pillars of standard
design as per IRC:25-1967, fixed in position including
finishing and lettering but excluding
painting)
30 15.1 Providing and laying boulders apron on river bed for
protection against scour with stone boulders weighing not
less than 40 kg each complete as per drawing and
Technical
specification.
14.9 Boulder laid dry without wire crates. 163 cum 1056 172128
28 Provision of Core boxes & Foundation core material 0
testing from geologist
28 EXTRA Provision of Barriers on both banks of Submersible L.S.
31 Bridge.
Cost Of Inauguration (Lump Sum) 5000
31 3.12 5400 cum 154 831600
Embankment Construction with Material Obtained
from Borrow Pits (Construction of
embankment with approved material CBR>5 obtained
from borrow pits with all lifts and leads, transporting to
site, spreading, grading to required slope and compacting
to meet requirement of table 300-2)

32 9.2
Laying Reinforced Cement Concrete Pipe
NP4/prestrssed concrete pipe on first class
bedding in single row . (Providing and Laying Reinforced
cement concrete pipe
NP4/prestrssed concrete pipe for culverts on first class
bedding of granular material (cost of
bedding included) in single row including fixing collar with
cement mortar 1:2 but excluding
excavation, protection works, backfilling, concrete and
masonry works in head walls and
parapets . )

(a) 1000 mm dia 0 meter 6998 0


TOTAL = 43402785
ESTIMATE BASED ON S.O.R. FOR ROAD & BRIDGE WORKS
ISSUED BY ENGINEER-IN-CHIEF M.P.P.W.D. BHOPAL
0
ESTIMATE FOR HIGH LEVEL BRIDGE ACROSS
MALKUA DEVERBELI ROAD AT RD - 1900 M
APPROACH ROAD ON DEBERVELI SIDE = 80 M (FLEXIBLE PAVEMENT)
APPROACH ROAD ON MALKUA SIDE = 112.0M (FLEXIBLE PAVEMENT)
TOTAL ROAD LENGTH = 80+112 = 192 M
Ref. Of
S.No. Description Quantity Unit Rate Amount
C.S.R.
FOR ROAD WIDTH=7.5 M
1 3.1 Excavation in Soil by Manual 230 cu.m. 122 28049
Means(Excavation for roadway in soil including
loading in truck for carrying of cut earth to
embankment site with all lifts and lead upto1000
metres.)
1 3.12 Embankment Construction with Material 5262 cu.m. 168 884016
Obtained from Borrow Pits (Construction of
embankment with approved material CBR>5
obtained from borrow pits with all lifts and leads,
transporting to site, spreading, grading to
required slope and compacting to meet
requirement of table 300-2)

2 4.2 Granular Sub-Base with Coarse Graded


Material ( Table:- 400- 2) (Construction of
granular sub-base by providing coarse graded
material, spreading in uniform layers with
motor grader on prepared surface, mixing by
mix in place method with rotavator at OMC, and
compacting with vibratory roller to achieve the
desired density, complete as per clause 401)

(ii) for grading - II material 118 cu.m. 943 111274


3 4.8 Water Bound Macadam (Providing, laying,
spreading and compacting stone aggregates of
specific sizes to water bound macadam
specification including spreading in uniform
thickness, hand packing, rolling with vibratory
roller 8-10 tonnes in stages to proper grade and
camber,applying and brooming requisite type of
screening/ binding Materials to fill up the
interstices of coarse aggregate, watering and
compacting to the required density.)

4.8 A (i) (a) Grading - II ( using screening type -A(13.2mm 54 cu.m. 1253 67662
agg)
4.8 A (ii) (a) Grading - III ( using screening type -B(11.2mm 54 cu.m. 1400 75600
agg)
4 5.1 Prime coat (Providing and applying primer coat 720 sqm 40 28800
with bitumen emulsion on prepared surface of
granular Base including clearing of road surface
and spraying primer at the rate of 0.75 kg/sqm
using mechanical means.)
5 5.2 Providing and applying tack coat with
bitumen emulsion using emulsion pressure
distributor on the prepared bituminous/granular
surface cleaned with mechanical broom and
as per relevant clauses of section-503.

(i) @ 0.25 kg per sqm (normal bituminous 720 sqm 14 10080


surfaces)
6 5.10 Open - Graded Premix Surfacing (Providing,
laying and rolling of open - graded premix
surfacing of 20 mm thickness composed of 13.2
mm to 5.6 mm aggregates either using
penetration grade bitumen or cut-back or
emulsion to required line, grade and level to
serve as wearing course on a previously
prepared base, including mixing in a suitable
plant, laying and rolling with a smooth wheeled
roller 8-10 tonne capacity, finished to required
level and grades.)

(i) Case - I: Mechanical method using Penetration 720 sqm 136 97920
grade Bitumen and HMP of appropriate
capacity not less than 75 tonnes/hour .
7 5.12 Seal Coat (Providing and laying seal coat
sealing the voids in a bituminous surface laid to
the specified levels, grade and cross fall using
Type A and B seal coats)
(ii) Type B (Providing and laying of premix sand 720 sqm 55 39600
seal coat with HMP of appropriate
capacity not less than 75 tonnes/ hours using
crushed stone chipping 6.7 mm size and
penetration bitumen of suitable grade.)

8 4.15 Construction of Shoulders with approved


material/selected soil i/c excavation all lifts &
leads i/c grading to required slope & camber of
4% and compacting using vibratory roller of
80 to 100 kN static weight to meet requirement
as per relevant clause of 400.

A Earthen Shoulders (CBR value >5) 98 cu.m. 186 18213


B Hard Shoulders (CBR value >12) 108 cum 223 24084
9 12.9 Provdiing and laying Plain/Reinforced
cement concrete in open foundation including
form work shuttering etc. complete as per
drawing and technical specifications and as per
relevant clauses of sections 1500, 1700 & 2100
with .

A PCC Grade M15 142 cu.m. 5080 721360


10 15.4 Providing and laying Pitching on slopes laid
over prepared filter media including boulder
apron laid dry in front of toe of embankment
complete as per drawing and Technical
specifications
A Stone/Boulder 437 cu.m. 2259 987357
11 15.5 Providing and laying Filter material underneath 219 cu.m. 1406 307265
pitching in slopes complete as per drawing
and Technical specification

APPROACH ROAD TOTAL 3401280


PART"A"- COST OF BRIDGE 43402785
PART"B"- COST OF APPROACH ROAD 3401280
TOTAL 46804065
ESTIMATE FOR HIGH LEVEL BRIDGE ACROSS
MALKUA DEVERBELI ROAD AT RD - 1900 M
8 SPANS @ 25.00 M . = 200.00 M.
ABUTMENTS(A1&
ABUTMENT(A2) 1 XA2) 2 X=510
10.00 = 10.00
M. M.
SOLID CIRCULAR PIERS & R.C.C. BOX TYPE ABUTMENTS (PILE FOUNDATION)

Ref.SO Description Quantities Total


R Nos.

12.1 A(I) EX. IN SOIL


(i) UPTO 3 M DEPTH
PIERS(RL 94.5)(P1 & P7) 2 X 5.10 X 5.10 X 2.65 137.85
PIERS(RL 91.5) ( P2, P3,P4, & P4) 5 X 5.10 X 5.10 X 2.70 351.14
ABUTMENT(A1 & A2) 2 X 8.40 X 6.80 X 3.00 342.72
TOTAL 831.71 832 Cum.
(ii) 3 M. TO 6 M DEPTH
ABUTMENT(A1 & A2) 2 X 8.40 X 6.80 X 0.21 23.99
TOTAL 23.99 24 Cum.
12.9 PCC M15 (Levelling Course)
BELOW ABUT. SLAB 2 X 7.50 X 4.30 X 0.15 9.68
TOTAL 9.68 10 Cum.

12.21 STEEL LINER IN PILE NOTE :- Weight of steel liner is 47 Kg/m2


PIERS(RL 94.5)(P1 & P7) 8 Xπ X 1.20 X 0.047 X 6.70 9.49
PIERS(RL 91.5) ( P2, P3,P4, & P4) 20 Xπ X 1.20 X 0.047 X 3.70 13.11
ABUTMENT(A1 & A2) 12 Xπ X 1.20 X 0.047 X 8.40 17.85
TOTAL 40.45 40 tonne

12.24 R.C.C. PILE GRADE M35


PIERS(RL 94.5)(P1 & P7) 8 X π /4 X 1.20 X 1.20 X 8.75 79.13
PIERS(RL 91.5) ( P2, P3,P4, & P4) 20 X π /4 X 1.20 X 1.20 X 5.75 130.00
ABUTMENT(A1 & A2) 12 X π /4 X 1.20 X 1.20 X 10.45 141.75
TOTAL 350.88 351 Cum.
12.36 PILE LOAD TEST ON SINGLE VERTICAL PILE
1 X 520 520.00
TOTAL 520.0 520 tonne
12.37 (C) R.C.C. IN PILE CAP (M-30)
PIERS(RL 94.5)(P1 & P7) 2 X 5.10 X 5.10 X 1.80 93.64
PIERS(RL 91.5) ( P2, P3,P4, & P4) 5 X 5.10 X 5.10 X 1.80 234.09
ABUTMENT(A1 & A2) 2 X 8.40 X 1.30 X 0.60 13.10
2 X 8.40 X 4.90 X 1.80 148.18
TOTAL 489.01 489 Cum.
12.38 PCC M15 FOR PILE CAP (Levelling Course)
PIERS(RL 94.5)(P1 & P7) 2 X 5.10 X 5.10 X 0.15 7.80
PIERS(RL 91.5) ( P2, P3,P4, & P4) 5 X 5.10 X 5.10 X 0.15 19.51
ABUTMENT(A1 & A2) 2 X 8.40 X 4.90 X 0.15 12.35
TOTAL 39.66 40 Cum.

12.39 HYSD BARS (FOUNDATION)


PIERS(RL 94.5)(P1 & P7) 2 X 4.64 PIER PILE CAP & PILE 9.28
PIERS(RL 91.5) ( P2, P3,P4, & P4) 5 X 3.97 PIER PILE CAP & PILE 19.85
ABUTMENT(A1 & A2) 2 X 20.08 ABUTMENT PILE CAP & PILE 40.15
TOTAL 69.28 69 tonne

13.5 SUB-STRUCTURE (RCC M30)


G (i) HEIGHT UPTO 5 M.
PIERS (7)Nos.
PIERS SHAFT
PIERS(RL 94.5)(P1 & P7) 2 Xπ/4 X 2.00 X 2.00 X 2.73 17.12
PIERS(RL 91.5) ( P2, P3,P4, & P4) 5 Xπ/4 X 2.00 X 2.00 X 5.00 78.54
SQUARE HEAD (P1 & P7) 2 X 2.00 X 2.00 X 0.50 4.00
PIER CAP (P1 & P7) 2 X 6.50 X 2.00 X 0.75 19.50
2 X 2 X 0.50 X 2.00 X 2.25 X 0.75 6.75
2 X 2.00 X 2.00 X 0.75 6.00
PEDESTAL (P1 & P7) 2 X 6 X 0.80 X 0.62 X 0.28 1.64
TOTAL 133.55 134 Cum.

ABUTMENTS (2 Nos.)
ABUTMENT(A1 & A2)
REAR WALL 2 X 8.40 X 0.25 X 5.00 21.00
FRONT WALL 2 X 8.40 X 0.25 X 5.00 21.00
INTERMEDIATE LONG WALL 2 X 1 X 8.40 X 0.20 X 5.00 16.80
SIDE WALL 2 X 4 X 2.46 X 0.25 X 5.00 24.63
INTERMEDIATE SHORT WALL 2 X 4 X 2.46 X 0.20 X 5.00 19.70
ABUTMENT CAP 2 X 8.40 X 0.90 X 0.50 7.56
PEDESTAL 2 X 3 X 0.80 X 0.62 X 0.50 1.49
TOTAL 112.18 112 Cum.
TOTAL (PIER+ ABUTMENT) : 245.73 246 Cum.

G (ii) Height 5m to10m (RCC M30)


PIERS (7)Nos.
PIERS(RL 91.5) ( P2, P3,P4, & P4) 5 Xπ/4 X 2.00 X 2.00 X 0.73 11.39
SQUARE HEAD (P2, P3 & P4) 5 X 2.00 X 2.00 X 0.50 10.00
PIER CAP (P2, P3 & P4) 5 X 6.50 X 2.00 X 0.75 48.75
5 X 2 X 0.50 X 2.00 X 2.25 X 0.75 16.88
5 X 2.00 X 2.00 X 0.75 15.00
PEDESTAL (P1 & P7) 2 X 6 X 0.80 X 0.62 X 0.23 1.34
PEDESTAL (P2, P3 & P4) 5 X 6 X 0.80 X 0.62 X 0.50 7.44
TOTAL 110.79 111 Cum.
ABUTMENT(A1 & A2)
REAR WALL 2 X 8.40 X 0.25 X 0.43 1.79
FRONT WALL 2 X 8.40 X 0.25 X 0.43 1.79
INTERMEDIATE LONG WALL 2 X 1 X 8.40 X 0.20 X 0.43 1.43
SIDE WALL 2 X 4 X 2.46 X 0.25 X 0.43 2.09
INTERMEDIATE SHORT WALL 2 X 4 X 2.46 X 0.20 X 0.43 1.67
ABUTMENT SLAB 2 X 8.40 X 5.00 X 0.30 25.20
TOTAL 33.97 34 Cum.
TOTAL (PIER + ABUTMENT) 144.76 145 Cum.
GRAND TOTAL 390.49 390 Cum.

13.6 HYSD BARS(SUB-STRUCTURE) 2 X 0.77 PIERS(RL 94.5)(P1 & P7) 1.546


5 X 1.14 PIERS(RL 91.5) ( P2, P3,P4, & P4) 5.675
7 X 2.77 PIER CAP 19.369
2 X 6.73 ABUTMENT(A1 & A2) 13.466
2 X 1.22 ABUTMENT CAP 2.438
42.49 42 Ton.
14.1 C(ii) SUPER-STRUCTURE (M-30)
(a) ABUTMENT
HEIGTH UPTO
CAP5 M. 2 X 8 (1.3+ 0.8) X 0.30 0.00
DECK SLAB(0.1 L TO 0.9 L) 8 X 20.2 X 4.19 (area see below) 677.64
DECK SLAB (0.0 L & 1.0 L) 8 X 2.00 X(5.655+4.185) X 2.38 187.35
X 2
INTERMEDIATE DIAPHRAGM 8 X 3.00 X 8.1 (area see below) 193.32
END DIAPHRAGM 8 X 2.00 X 11.8 (area see below) 188.40
KERB 2 X 210.00 X 0.45 X 0.30 56.70
TOTAL (CON. FOR SUPERSTRUCTURE) 1303.4 1303 Cum.
TOTAL(CONCRETE) 1303.4 1303 Cum.

HYSD BARS (SUPER-


14.2
STRUCTURE) 8 X 20.12 SLAB 160.98 161 Ton.

13.8 WEEP HOLES IN ABUTMENT 2 X 25.0 X 0.30 15.00 15 RMT

13.10 600mm TH. FILTER MEDIA 2 X 8.40 X 0.60 X 5.43 54.68


INSIDE GRANULAR FILLING IN 2 X 6 X 2.46 X 2.50 X 5.28 389.77
ABT.
444.45 444 Cum.
13.9 BACK FILLING BEHIND ABUTMENT
GRANULAR MATERIAL 2 X 8.40 X 0.50 X 5.43 X 3.1 142.73
142.73 143 Cum.

13.12 NEOPRENE BEARING 48 X 32.0 X 50.0 X 4.80 368640 368640 Cucm.


14.4 WEARING COAT ( 200 + 10.0) X 7.50 X 0.075 118.13 118 Cum.
14.7 RCC RAILING 2 X 210.0 420.00 420 RMT

14.9 PROVIDING DRAINAGE SPOUT 2 X8 16.00 16 Nos.


14.10 LEVELING COURSE BELOW
2 X 8.40 X 3.50 X 0.15 8.82
APPROCH SLAB
8.82 9 Cum.
14.11 APPROACH SLAB 2 X 8.40 X 3.50 X 0.30 17.64 18 Cum.

14.21 EXPANSION JOINT


STRIP SEAL 9 X 8.40 75.60 76 Nos.

14.24 TESTING OF SPAN 77.00 77 Ton.

14.26 MARBLE PLATE 2.00 2 Nos.


8.4(iv) PMGSY SIGN BOARDS (80cm x 60cm) 2.00 2 Nos.
8.7 PAINTING AFTER FILLING SURFA 2 X 210 X(0.45+0.3) 315.00 315 Sqm.
8.14 GUARD STONES 2 X 42 84.00 84 Nos.
15.1(a) BOULDER APRON 2 X 5.50 X 3.00 X 5.43 0.00 0 Cum.
AT ABUTMENT (EST) 2 X 2 X 0.50 X 5.0 X 5.00 X 3.26 163
2 X 0.60 X 1.0 X 8.40 0
(A2) 0 X 2 X 0.50 X 5.0 X 5.00 X 6.00 0
162.75 163 Cum.
EXTRA DIVERSION ROAD
3.12 EARTHWORK 300 X 12.0 X 1.50 5400 5400 Cum.
9.2 HUME PIPE 4 X 20.0 80.00 80 RMT
DISMENTELING 5.00 X 3.0 X 20.00 300 Cum.

SUPERSTRUCTURE AREA CALCULATIONS-:


6.9 X 0.0 =
2 X 0.2 X 0.75 =
2 X 0.5 X 0.05 X 0.75 =
S

SLAB (0.0 L & 1.0 L) 1 X 660.0 X 25.0 = 16500


1 X 90.0 X 20.0 = 1800
1 X 90.0 X 2.5 = 225
1 X 90.0 X 20.0 = 1800
1 X 90.0 X 2.5 = 225
6 X 30.0 X 5.0 = 900
3 X 60.0 X 195.0 = 35100
TOTAL 56550 cm2
5.66 m2

SLAB (0.1 L TO 0.9 L) 1 X 630.0 X 25.0 = 15750


1 X 105.0 X 20.0 = 2100
1 X 105.0 X 2.50 = 262.5
1 X 105.0 X 20.0 = 2100
1 X 105.0 X 2.50 = 262.5
6 X 30.00 X 5.00 = 900
3 X 30.00 X 170.0 = 15300
3 X 60.00 X 25.0 = 4500
6 X 15.00 X 7.50 675
TOTAL 41850 cm2
4.19 m2
INTERMEDIATE DIAPHRAGM 1 X 4.80 X 1.70 = 8.16
DEDUCT FILLETS 4 X 0.30 X 0.10 X 0.50 = 0.06
4 X 0.15 X 0.15 X 0.50 = 0.045
8.055 m2

END DIAPHRAGM 1 X 8.40 X 2.20 = 18.48


DEDUCT AREA AT 0.0 L = 5.655
DEDUCT END TRIANGLE. 2 X 0.70 X 1.50 X 0.50 = 1.05
11.775 m2
ESTIMATE FOR HIGH LEVEL BRIDGE ACROSS
MALKUA DEVERBELI ROAD AT RD - 1900 M

APPROACH ROAD ON DEBERVELI SIDE = 80 M (FLEXIBLE PAVEMENT)


APPROACH ROAD ON MALKUA SIDE = 112.0M (FLEXIBLE PAVEMENT)
TOTAL ROAD LENGTH = 80+112 = 192 M

FOR FLEXIBLE PAVEMENT


Ref.SOR Description Quantities Total
Nos.
FOR ROAD WIDTH=7.5 M
3.10 Excavation in soil (Estimated ) SEE EARTHWORK 230 230 Cum
3.12 Embankment in Filling CALCULATION REPORT 5262 5262 Cum
4.2 (ii) G.S.B 192 X 4.10 X 0.15 118.08 118 Cum
4.8 A (i) (a) WBM G- II 192 X 3.75 X 0.075 54.00 54 Cum
4.8 A (ii) (a) WBM G- III 192 X 3.75 X 0.075 54.00 54 Cum
5.1 Prime Coat 192 X 3.75 720 720 Sqm.
5.2 (i) Tack Coat 192 X 3.75 720 720 Sqm.
5.10 (i) OGPC 192 X 3.75 720 720 Sqm.
5.12(ii) Seal Coat 192 X 3.75 720 720 Sqm.
4.15 A Earthen Shoulder 2 X 192 X 1.700 X 0.15 97.92 98 Cum
4.15 B Hard Shoulder 2 X 192 X 1.875 X 0.15 108.00 108 Cum
12.9 A PCC M15 - *Toe Walls 134 X 0.80 107.2
**Drain 70 X 0.50 35
Total 142.2 142 Cum
15.4 A Pitching on Slope 2 X 210 X 6.71 X 0.30 437 437 Cum
15.5 Filter Media 2 X 210 X 6.71 X 0.15 219 219 Cum

* Toe wall - (in filling)


Area of Rectangular portion I = 2 x 0.3 x 0.6 = 0.36
Area of Rectangular portion II = 2 x 0.3 x 0.75 = 0.45
Total 0.8m2

** Drain - (in cutting)


2 x 2 x 0.15 x 0.6 = 0.36
2 x 0.45 x 0.15 =0.14
Total 0.5m2

PITCHING ON SLOPE
TO BIJADEHI SIDE = 2 X (80 + 6) X 8.253 X 0.3 = 425.87
TO DUDAR SIDE = 2 X (42 + 6) X 0.389 X 0.3 = 11.21

TOTAL 437.08
FILTER MEDIA
TO BIJADEHI SIDE = 2 X (80 + 6) X 8.253 X 0.15 = 212.94
TO DUDAR SIDE = 2 X (42 + 6) X 0.389 X 0.15 = 5.60
TOTAL 218.54
SOR
Proforma C (For Long Span Bridge only)
PRADHAN MANTRI GRAM SADAK YOJANA (PMGSY)
CHECK LIST FOR P.I.U. & S.T.A.
(For Indvidual Bridge works with length more than 15 m )
(To be filled by PIU)

1. Location State: M.P. District :- BALAGHAT Block:- LANJHI

2. Package No.:-

3. Name of the Road :- From: Deverbeli To: Malkua

4.Total Length of Road (Km):- KM

5. Name of Proposed Bridge (if any):- 0

6. Length of Proposed Bridge (Excluding Approaches):- 200.00 M

7. Width of Bridge in M:- 8.40 M

8. Throguh Route/Link Route Nos. as per core Network:-

(i) Is the road a part of Core Network

If Yes, SI no. of road CN-I IS no. of road CN - VI Yes/No

If Yes, Throguh/Link Route Number T- or L-

(ii) Name of the benefitted Habitation (s) (to be cross Sr. n. Name of Village Population
checked with CN-VI)with Population 1
2
3
4
5
6
7
8
Total 0

9. Whether the Road Proposal was sanction earlier: Yes/No

(i) If Yes, please mention the Phase, MoRD Sanction Letter No. And Date of sanction

Phase: MoRd sanction No.: Date:

Length: 0.00 KM ChainageFrom: 0 To: 0.00

(ii) Cost of the Road work sanctioned: Rs. Lakhs.

(iii) Whether any CD/ Causeway was sanctioned at or nearby location with the road proposal and
whether the same was constructed or not (if yes, the details there of with chainage:

(iv) Whether the roadwork has been completed or in progress and likely date of completion:

(v) If not, how the connectivity and movement of traffic was ensured:
Road proposal may be submitted.

(vi) Reasons for not proposing the Bridge at the time of submission of Road proposal:
Span Bridge only)

Yes/No

Population

0
SOR
10.Estimate Cost (Rs. In Lakhs)

Item Total Cost (Rs. In Lakhs) Cost per m


Approaches 34.01 0.18
Bridge Super Structure 190.66 0.95
Substructure & Foundation 197.00 0.98
Others 46.37 0.23
Total 468.04 2.35
MoRD Share State Share
(MoRD Shjare and State Share to be calculated as per the norms of MoRD/NRRDA

11. INDEX MAP (not to scale): Attached


Enroute Habitation Name / Chainage

Target Habitation
H1 H2

name
ROAD

Proposed Bridge Location CD3


Deverbeli 0 Malkua

12. Typical Sketch of proposed bridge showing schematic arrangement of spans

13. Typical Photographs of proposal Bridge Location:

(i) At Chainage
PHOTO

(ii) U/S of Bridge Site


PHOTO

(iii) D/S of Bridge Site


PHOTO

14. Type of Proposed Bridge:


(i) Submersible Structure like Vented Causeway or High Level Bridge
(ii) Box Culvert
(iii) Bridge with RCC Piers and Abutments

a. Type of Foundation : PILE FOUNDATION


b. Bearing Capacity at Foundation level 50 T/SQM
c. Arrengment of Spans
Total span (6X25.00M) No. of Vents 6 Clear Span of Vent 24 M

d. Critical Levels Road top Level(RTL) 105.80 m.


Average Ground Level (AGL) 101.779 m.
Nala Bed level(NBL) 97.95 m.
Ordinary Flood Level(OFL) 102.15 m.
Foundation Level(FL) 87.00 m.
Ht. of bridge h= (RTL-NBL) 7.850 m.
Ht. of bridge h= (RTL-FL) 18.80 m.
e. Catchment Area
(Catchment area should be based on hydological survey or from toposheet)
Catchment area served 30400 Hect
Annual Rainfall 1200 MM
Basis of Design Discharge 1248 CUMEC
Waterway Required 147.16 M
Waterway Provided 200.00 M
f. Scour Depth (m) 4.58 M
15. Cost Details
A. General Costs Cost Rs. 468.04 Lakhs
Cost of Preparation of DPR (Limited to 1% of total cost of Bridge)

B. Bridge Components (Estimate Attached) Grade


of
Description of Components Quantity Cost Rs.
Concr
ete
M-30&
Pile Foundations (RCC & Steel) 840 122.59 M-35
Abutments (RCC & Steel) 146 18.87 M - 30
Piers(RCC & Steel) 245 31.40 M - 30
Deck Slab(RCC & Steel) 1303 190.66 M - 30
Parapets/Railing 420 8.71
Wing Walls
Wearing Course 118 0.01 M - 30
Joints 76 8.81
Drainage 16 0.23
Bearings-Elastomeric or Roleer Bearing 368640 2.21
Earthwork(for approaches/Bridge) 856 1.82
Miscellaneous & Other Item 47.89
C. Road Component (for Approaches /Bridge)
Granular Sub base 118 1.113
Soil + Aggregate Mix
WBM Gr-II 54 0.68
WBM Gr-III/MPM 54 0.76
Prime Coat / Concrete sub - Base 720 0.29
Tack Coat / Cement Concrete Pavement 720 0.10
OGPC/Surface Dressing 720 0.98
Seal Coat 720 0.40
D. Protection works 29.65
E. Road Logo, Other Road Furniture 0.83
F. Cost Of Inauguration (Lump Sum) 0.05

Total Cost of the Project (Rs) 468.04 Lakhs


FOUR HUNDRED FOURTY
Total Cost of the Project (Rs) (In Words) LAKH SIXTY SEVEN
THOUSAND

16. Five Year Routine Maintenance Year Cost in Lakhs % Cost


I 0.702 0.15%
II 0.702 0.15%
III 0.936 0.20%
IV 1.170 0.25%
V 1.170 0.25%
Total Maintenance
cost 4.68

17. Whether the Bridge has Geometrics as per latest Circular of NRRDA: YES/NO
DO.# P- 17035/1/2007-Tech. 30 th September, 2010

18. Whether the Cost Estimats are as per standerd data analysis and S.S.R.

19. Sources and the lead distances of Materials are as under

Material Source Lead Dis. Material source Lead Dis.


Earth Cement
Murrum
(Subgrade Emulsion
)
Aggregate Bitumen
Sand Steel
Praptra - 1 Pradhan Mantri Gram Sadak Yojna

Details of Proposal for Bridge (span more than 50 m)

Approach Approach Water Total Cost of 50m Cost to Cost to


Water Way Cost water way be
S. District Block Name of Road Phase Name of Bridge Pavement Pavement Way be borne
NO. Length Cost Length Cost (In (In length (on by GOI. borne
Lakh) Lakh) prorata by State
(In 'm') (In Lakh) (In 'm') (8+10) basis) (8+12) (11-13)

1 2 3 4 5 6 7 8 9 10 11 12 13 14
HIGH LEVEL BRIDGE
BALAGHA ACROSS MALKUA
1 LANJHI Deverbeli TO Malkua 0 192.00 34.01 200.00 434.03 468.04 108.51 142.52 325.52
T DEVERBELI ROAD AT RD -
1900 M
Praptra - 2 Madhya Pradesh Rural Road Development Authority .Bhopal
Pradhan Mantri Gram Sadak Yojna
District wise Project Proposals

Proforma P-4 Proposed Bridge on already sanctioned Road Span > 50 Mtr

Old Name of Road Village getting Total


Village Proposed Pavement CD Works No of
S. (Sanction from starting for connectivity connected on populati Type of
way Total link
N Phase road ) Distt. Block point to on Proposal
Cost Route/T
O. Package connecting Served N/U hrought
No. Village (8+10)
Length (In Cost (Rs. No. of Cost (Rs.
Name Pop. Name Pop.
Kms) In Lakh) Works In Lakh)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
BALAG Deverbeli TO
1 0 0 LANJHI 0 0 0 N 0.192 34.01 1 434.03 468.04 0

0
HAT Malkua
dhya Pradesh Rural Road Development Authority .Bhopal
Pradhan Mantri Gram Sadak Yojna
District wise Project Proposals

P-4 Proposed Bridge on already sanctioned Road Span > 50 Mtr

Statu
s of
Road

19
Comp
lete
Praptra - 3 Madhya Pradesh Rural Road Development Authority .Bhopal
Pradhan Mantri Gram Sadak Yojna
District wise Project Proposals

Proforma P-4 Proposed Bridge on already sanctioned Road Span > 50 Mtr

Name of
No of
Road Total Type of Approach Pavement CD Works
Links
S.NO. District Block Name of Bridge (Previousl populatio proposal Total Cost
Route/Thr
y n served N/U oughth
sanction)
Length (In Cost (Rs. No. of Cost (Rs.
Kms) In Lakh) Works In Lakhs)
1 2 3 4 5 6 7 8 9 10 11 12 13
HIGH LEVEL BRIDGE
Deverbeli
BALAGHA ACROSS MALKUA
1 LANJHI TO 0 N 0.192 34.01 1.00 434.03 468.04 0.00
T DEVERBELI ROAD AT RD -
Malkua
1900 M
Praptra - 4 Madhya Pradesh Rural Road Development Authority .Bhopal
Pradhan Mantri Gram Sadak Yojna
District wise Project Proposals

Proforma P-4

Is the
proposal Is the
and proposal
Name of Length of
Extension Part of
Package Span (in Est. Total Road Road of Road Road
S.NO. District Block Name of Bridge Cost (Rs. (Previous Phase Previouse
No. mtr.) Already Taken up
In Lacs.) ely ly Taken up in Ealer In
Sanction) Sanction
in Phase……
Phase…… ……..
……..

1 2 3 4 5 6 7 8 9 10 11 12

HIGH LEVEL BRIDGE


Deverbeli
BALAGHA ACROSS MALKUA
1 0 LANJHI 200.00 468.04 TO 0 0 No. 0
T DEVERBELI ROAD AT RD -
Malkua
1900 M
Proposal of ……………….. Bridges

Cost as per Cost as per SOR


Cost
Approach Water ………………………. (Rs in Lac) Cost to ………………………..(Rs in Lac) Cost to Cost to Difference / %
S. Distr Blo Name of Pavemen Way Width 7.50 Mtr. Cost to borne by Width 5.50 Mtr. be borne by
N Phase Name of Bridge be borne State (11-
O. ict ck Road t Length Length by GOI borne State (11-
(m) (m) Approac 12) by GOI 17)
Bridge Total Bridge Approach Total Amt. in %
h

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
BALAGHAT

HIGH LEVEL BRIDGE


LANJHI

Deverbeli
ACROSS MALKUA
1 TO 0 192.00 200.00 434.03 34.01 468.04 108.51 359.53 378.28 32.84 411.12 127.41 340.63 56.92 13.85
DEVERBELI ROAD AT
Malkua
RD - 1900 M

You might also like