Doc. No.

01/TRNSPWR/GTS/V/18
PT. Gamatara INSPECTION WELDING EXAMINATION
Transocean Revision -
Shipyard
REPORT Date 04-Mei-18

OWNER : PT. TRANS POWER MARINE Date of Inspection : 03 Mei 2018


REPORT

SURFACE CONDITION √ WELDED GROUND FLUSH OTHER ( )

STAGE OF EXAM √ AFTER WELDING AFTER HYDROSTATIC OTHER ( )

WELDING PROCESS GTAW √ SMAW OTHER ( )

SCOPE OF BASE METAL BACK CHIPING √ WELD PART

EXAMINATION √ EDGE PREP REPAIRED WELD OTHER ( )

CURRENT 70-110 √ SMAW √ FILLER METAL 4 mm √ LEAK TEST


Ampere
SKL-SPI AWS A5.1 ESAB E-6013 √ DIESEL FUEL+LIME

√ DWELL TIME : 45 MINUTES

WELDING THICKNESS JUDGEMENT TYPE OF


MATERIAL REMARK
INDICATION (MM) ACCEPTED REJECTED DISCOUNTINUITY
Top Side Frame 5 12 √ ABS Heat no.SK 24395
Top Side Frame 5-6 12 √ ABS Heat no.SK 24395

PREPARED BY, CHECKED BY

MOH. GUFRON F.Gunadi


Quality Control Staff Quality Control Manager
PT. Gamatara INSPECTION WELDING REPORT
Transocean Owner : PT. Trans Power Marine Location : Graving Dock C
Shipyard Project : FC Joshua Doc. No : 01/TRNSPWR/GTS/V/18
Part : Replate Lambung Date : 04/05/2018

PHOTO BEFORE WELDING PROCESS

TOP SIDE FRAME 0-4 TOP SIDE FRAME 0-4

TOP SIDE FRAME 5-6 TOP SIDE FRAME 5-6


PT. Gamatara INSPECTION WELDING REPORT
Transocean Owner : PT. Trans Power Marine Location : Graving Dock C
Shipyard Project : FC Joshua Doc. No : 01/TRNSPWR/GTS/V/18
Part : Replate Lambung Date : 04/05/2018

PHOTO AFTER WELDING PROCESS

TOP SIDE FRAME 5-6 TOP SIDE FRAME 5-6 CAPING 3 mm

TOP SIDE FRAME 5-6 CAPING 3 mm TOP SIDE FRAME 5-6


PT. Gamatara INSPECTION WELDING REPORT
Transocean Owner : PT. Trans Power Marine Location : Graving Dock C
Shipyard Project : FC Joshua Doc. No : 01/TRNSPWR/GTS/V/18
Part : Replate Lambung Date : 04/05/2018

PHOTO AFTER WELDING PROCESS

TOP SIDE FRAME 5-6 TOP SIDE FRAME 5-6

TOP SIDE FRAME 5-6 TOP SIDE FRAME 5-6


PT. Gamatara INSPECTION WELDING REPORT
Transocean Owner : PT. Trans Power Marine Location : Graving Dock C
Shipyard Project : FC Joshua Doc. No : 01/TRNSPWR/GTS/V/18
Part : Replate Lambung Date : 04/05/2018

PHOTO AFTER WELDING PROCESS

TOP SIDE FRAME 5-6 NO LEAK TOP SIDE FRAME 5-6 NO LEAK

TOP SIDE FRAME 5-6 NO LEAK TOP SIDE FRAME 5-6 NO LEAK