Activity ID Activity Name Original Remaining Actual Schedule % Start Finish Resources Budgeted Total Total Mar 10 Mar

Original Remaining Actual Schedule % Start Finish Resources Budgeted Total Total Mar 10 Mar 17 Mar 24 Mar 31 Apr 07 Apr 14 Apr 21 Apr 28 May 05 May 12 May 19
Duration Duration Duration Complete Cost Float M T W Thr Fri Sat S M T W Thr Fri Sat S M T W Thr Fri Sat S M T W Thr Fri Sat S M T W Thr Fri Sat S M T W Thr Fri Sat S M T W Thr Fri Sat S M T W Thr Fri Sat S M T W Thr Fri Sat S M T W Thr Fri Sat Sun M
58.00 45.00 13.00 0% 11-Mar-19 16-May-19 Rs.0.00 0.00 16-May-19, ICTPRM-1 ICTProjectScedule1
ICTPRM-1 ICTProjectScedule1
A
24.00 11.00 12.10 0% 11-Mar-19 A06-Apr-19 Rs.0.00 19.00 06-Apr-19, ICTPRM-1.1 Arcitectural
ICTPRM-1.1 Arcitectural
P1000 Start of Project 0.00 0.00 0.00 0% 26-Mar-19 Rs.0.00 0.00 Start of Project, 26-Mar-19
P1010 Creating Collaborative Environment 0.10 0.00 0.10 100% 11-Mar-19 A11 -Mar-19 A Rs.0.00 Creating Collaborative Environment
P1020 Ground Floor 3.00 0.00 3.00 100% 11-Mar-19 A14-Mar-19 A Rs.0.00 Ground Floor
P1030 First Floor 2.00 0.00 2.00 100% 14-Mar-19 A16-Mar-19 A Rs.0.00 First Floor
P1040 Second Floor 2.00 0.00 2.00 100% 16-Mar-19 A19-Mar-19 A Rs.0.00 Second Floor
P1050 Roof 2.00 0.00 2.00 100% 19-Mar-19 A21-Mar-19 A Rs.0.00 Roof
P1060 Design Elements 5.00 0.00 3.00 78% 21-Mar-19 A25-Mar-19 A Rs.0.00 Design Elements
P1070 Furniture/ Kitchens/ Toile ts/Stairs 5.00 5.00 0.00 0% 26-Mar-19* 30-Mar-19 Rs.0.00 19.00 Furniture/ Kitchens/ Toile ts/Stairs
P1090 Pergola/ External Work Including Landscaping 5.00 5.00 0.00 0% 26-Mar-19* 30-Mar-19 Rs.0.00 19.00 Pergola/ External Work Including Landscaping
P1100 Exterior Finishes 4.00 4.00 0.00 0% 01-Apr-19 04-Apr-19 Rs.0.00 19.00 Exterior Finishes
P1110 BOQ 2.00 2.00 0.00 0% 05-Apr-19 06-Apr-19 Rs.0.00 19.00 BOQ
43.00 30.00 13.00 0% 11-Mar-19 A29-Apr-19 Rs.0.00 0.00 29-Apr-19, ICTPRM-1.2 Structural
ICTPRM-1.2 Structural
P1120 Importing Collaborative Data 0.00 0.00 0.00 100% 11-Mar-19 A11 -Mar-19 A Rs.0.00 Importing Collaborative Data
P1130 R.C.C. Foundation Grid Designated 3.00 0.00 2.00 100% 11-Mar-19 A12-Mar-19 A Rs.0.00 R.C.C. Foundation Grid Designated
P1140 R.C.C. Coulmns to Top L evel Grid Designated 4.00 0.00 2.00 100% 13-Mar-19 A14-Mar-19 A Rs.0.00 R.C.C. Coulmns to Top L evel Grid Designated
P1150 R.C.C. Beams Framing Grid Designated 8.00 0.00 4.00 100% 15-Mar-19 A19-Mar-19 A Rs.0.00 R.C.C. Beams Framing Grid Designated
P1160 R.C.C. Slabs Level Designated 2.00 0.00 2.00 100% 20-Mar-19 A21-Mar-19 A Rs.0.00 R.C.C. Slabs Level Designated
P1170 Rebaring first placed in Pipe pierced Beams Freely 1.00 0.00 1.00 100% 22-Mar-19 A22-Mar-19 A Rs.0.00 Rebaring first placed in Pipe pierced Beams Freely
P1180 Rebaring in Foundations Grid Designated 2.00 2.00 0.00 0% 26-Mar-19 27-Mar-19 Rs.0.00 0.00 Rebaring in Foundations Grid Designated
P1190 Rebaring in Columns Grid Designated 5.00 5.00 0.00 0% 28-Mar-19 02-Apr-19 Rs.0.00 0.00 Rebaring in Columns Grid Designated
P1200 Rebaring in Beams Grid Designated 12.00 12.00 0.00 0% 03-Apr-19 16-Apr-19 Rs.0.00 0.00 Rebaring in Beams Grid Designated
P1210 Rebaring in Slabs Levels Designated 3.00 3.00 0.00 0% 17-Apr-19 19-Apr-19 Rs.0.00 0.00 Rebaring in Slabs Levels Designated
P1220 R.C.C. Additional Elements (Tanks Designated by Levels, Stairs, Ramps, R.C.C. Walls) 4.00 0.00 3.00 75% 22-Mar-19 A25-Mar-19 A Rs.0.00 R.C.C. Additional Elements (Tanks Designated by Levels, Stairs, Ramps, R.C.C. Walls)
P1230 Rebaring Additional Eleements 5.00 5.00 0.00 0% 20-Apr-19 25-Apr-19 Rs.0.00 0.00 Rebaring Additional Eleements
P1240 BOQ Elements related to non structural needs Ad ded 2.00 2.00 0.00 0% 26-Apr-19 27-Apr-19 Rs.0.00 0.00 BOQ Elements related to non structural needs Added
P1250 BOQ Schedules 1.00 1.00 0.00 0% 29-Apr-19 29-Apr-19 Rs.0.00 0.00 BOQ Schedules
28.00 17.00 9.00 0% 15-Mar-19 A16-Apr-19 Rs.0.00 11.00 16-Apr-19, ICTPRM-1.3 Electrical
ICTPRM-1.3 Electrical
P1260 BIM Environment Creation 0.00 0.00 0.00 100% 15-Mar-19 A15-Mar-19 A Rs.0.00 BIM Environment Creation
P1270 Families Arranged 2.00 0.00 5.00 100% 15-Mar-19 A20-Mar-19 A Rs.0.00 Families Arranged
P1280 Electrical Fixtures Ligting Plan 5.00 0.00 4.00 80% 21-Mar-19 A25-Mar-19 A Rs.0.00 Electrical Fixtures Ligting Plan
P1290 Wiring Ligting Plan 2.00 2.00 0.00 0% 03-Apr-19 04-Apr-19 Rs.0.00 11.00 Wiring Ligting Plan
P1300 Conduiting Lighting Plan 6.00 6.00 0.00 0% 05-Apr-19 11 -Apr-19 Rs.0.00 11.00 Conduiting Lighting Plan
P1310 Electrical Fixtures Power Plan 5.00 5.00 0.00 0% 28-Mar-19 02-Apr-19 Rs.0.00 Electrical Fixtures Power Plan
P1320 Wiring Power Plan 2.00 2.00 0.00 0% 03-Apr-19 04-Apr-19 Rs.0.00 11.00 Wiring Power Plan
P1330 Conduiting Power Plan 6.00 6.00 0.00 0% 05-Apr-19 11 -Apr-19 Rs.0.00 11.00 Conduiting Power Plan
P1340 BOQ Elements related to non electrical work 2.00 2.00 0.00 0% 12-Apr-19 13-Apr-19 Rs.0.00 11.00 BOQ Elements related to non electrical work
P1350 BOQ Schedules 2.00 2.00 0.00 0% 15-Apr-19 16-Apr-19 Rs.0.00 11.00 BOQ Schedules
39.00 14.00 12.00 0% 11-Mar-19 A24-Apr-19 Rs.0.00 4.00 24-Apr-19, ICTPRM-1.4 Plumbing
ICTPRM-1.4 Plumbing
P1360 BIM Environment Creation 0.00 0.00 0.00 100% 11-Mar-19 A11 -Mar-19 A Rs.0.00 BIM Environment Creation
P1370 Family Arranged 4.00 0.00 4.00 100% 11-Mar-19 A14-Mar-19 A Rs.0.00 Family Arranged
P1380 Fixtures + Manholes + Sinks + Toilets 8.00 0.00 6.00 87.5% 18-Mar-19 A23-Mar-19 A Rs.0.00 Fixtures + Manholes + Sinks + Toilets
P1390 Piping + Joining 10.00 10.00 0.00 0% 09-Apr-19 19-Apr-19 Rs.0.00 4.00 Piping + Joining
P1410 BOQ Schedules 4.00 4.00 0.00 0% 20-Apr-19 24-Apr-19 Rs.0.00 4.00 BOQ Schedules
17.00 17.00 0.00 0% 26-Mar-19 13-Apr-19 Rs.0.00 13.00 13-Apr-19, ICTPRM-1.5 Firefighting
ICTPRM-1.5 Firefighting
P1420 BIM Environment Creation 0.00 0.00 0.00 0% 26-Mar-19 26-Mar-19 Rs.0.00 13.00 BIM Environment Creation
P1430 Family Arranged 3.00 3.00 0.00 0% 26-Mar-19 28-Mar-19 Rs.0.00 13.00 Family Arranged
P1440 Fixtures 4.00 4.00 0.00 0% 29-Mar-19 02-Apr-19 Rs.0.00 13.00 Fixtures
P1450 Pipiing and Joining 6.00 6.00 0.00 0% 03-Apr-19 09-Apr-19 Rs.0.00 13.00 Pipiing and Joining
P1460 BOQ Schedules 4.00 4.00 0.00 0% 10-Apr-19 13-Apr-19 Rs.0.00 13.00 BOQ Schedules
3.50 0.00 3.50 0% 18-Mar-19 A21-Mar-19 A Rs.0.00 21-Mar-19 A, ICTPRM-1.6 ICT
ICTPRM-1.6 ICT
P1470 BIM Environment Creation 0.00 0.00 0.00 100% 18-Mar-19 A18-Mar-19 A Rs.0.00 BIM Environment Creation
P1480 Family Arranged 1.00 0.00 1.00 100% 18-Mar-19 A18-Mar-19 A Rs.0.00 Family Arranged
P1490 Fixtures 1.00 0.00 1.00 100% 19-Mar-19 A19-Mar-19 A Rs.0.00 Fixtures
P1500 Conduiting 1.00 0.00 1.00 100% 20-Mar-19 A20-Mar-19 A Rs.0.00 Conduiting
P1510 BOQ 0.50 0.00 0.50 100% 21-Mar-19 A21-Mar-19 A Rs.0.00 BOQ
15.00 15.00 0.00 0% 30-Apr-19 16-May-19 Rs.0.00 0.00 16-May-19, ICTPRM-1.7 Final Checks
ICTPRM-1.7 Final Checks
P1520 Checking Drawing, BOQ Schedules and Engineering Checking 5.00 5.00 0.00 0% 30-Apr-19 04-May-19 Rs.0.00 0.00 Checking Drawing, BOQ Schedules and Engineering Checking
P1530 Drafting Quality Checks and Guidance 5.00 5.00 0.00 0% 06-May-19 10-May-19 Rs.0.00 0.00 Drafting Quality Checks and Guidance
P1540 Print Drawings 5.00 5.00 0.00 0% 11-May-19 16-May-19 Rs.0.00 0.00 Print Drawings
P1550 Finish of Projects 0.00 0.00 0.00 0% 16-May-19 Rs.0.00 0.00 Finish of Projects,