Method Statement For Dredging and Reclamation: Revision Record
Method Statement For Dredging and Reclamation: Revision Record
Issued for
01 Construction / 27-10-2018 S2R JAB JAB
Issued for Use
VO
Revision Description Date VO Checked VO Approved
Originator
Revision record
Revision Number Description Date
00 Issued for Construction / Issued for Use 01-10-2018
01 Issued for Construction / Issued for Use 27-10-2018
This document is the property of Van Oord Group. This document or any part thereof is CONFIDENTIAL and may not be made
known, copied, multiplied, or used in any other way without the permission of Van Oord Group.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 2 of 36
Table of contents
Content
1 Introduction ....................................................................................................................................... 4
1.1 Introduction .............................................................................................................................. 4
1.2 Abbreviations and Definitions .................................................................................................. 4
1.3 Area Plan ................................................................................................................................. 4
1.4 Scope of Work ......................................................................................................................... 5
2 Organization ..................................................................................................................................... 5
2.1 Organogram............................................................................................................................. 6
2.2 Responsibilities ........................................................................................................................ 6
3 Mobilization and site preparation ................................................................................................... 11
3.1 General .................................................................................................................................. 11
3.2 Site preparation works ........................................................................................................... 11
4 Activities ......................................................................................................................................... 12
4.1 Marine Equipment ................................................................................................................. 12
4.2 Land Based Equipment ......................................................................................................... 13
4.3 Survey.................................................................................................................................... 13
4.4 Dredging of marine basin and reclamation using CSD ......................................................... 15
4.4.1 Introduction ........................................................................................................................ 15
4.4.2 Dredging Suitable Material ................................................................................................ 15
4.4.3 Cutting Principle................................................................................................................. 15
4.4.4 Dredging Process .............................................................................................................. 16
1.1.1 Positioning and moving of the CSD ................................................................................... 16
1.1.2 Dredging Control................................................................................................................ 16
1.1.3 Cutting and discharging of the material ............................................................................. 17
4.4.5 Work Method – Reclamation ............................................................................................. 19
5 Working Cutting Plan...................................................................................................................... 19
5.1 Volumes ................................................................................................................................. 20
5.2 Activities ................................................................................................................................. 21
5.2.1 Dredging ............................................................................................................................ 21
5.2.2 Reclamation Preparations ................................................................................................. 21
5.2.3 Reclamation Sequence ..................................................................................................... 23
6 Quality ............................................................................................................................................ 24
7 Health and Safety ........................................................................................................................... 24
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 3 of 36
Figures
Figure 1 – Reclamation Work Area ..................................................... ……………………………….. 05
Figure 2 – Preliminary Drain Plan ......................................................................................................... 11
Figure 3– Floating Pipeline assembling area ........................................................................................ 12
Figure 4 - Cutter Suction Dredger ......................................................................................................... 12
Figure 5 - Land based equipment on the reclamation ........................................................................... 13
Figure 6 - Survey vessel ........................................................................................................................ 14
Figure 7 – Preconstruction survey ………………………………………………………………………….. 15
Figure 8 - Dredging cut .......................................................................................................................... 16
Figure 9 – Detail of screen dredge computer ........................................................................................ 17
Figure 10 – Ladder and cutter-head ...................................................................................................... 18
Figure 11 - Box Cut Method .................................................................................................................. 19
Figure 12 - Reclamation Process .......................................................................................................... 19
Figure 13 – Cutting plan ..................................................................................................................... 20
Figure 14 - Dredging area ..................................................................................................................... 21
Figure 15 - Typical bund cross section .................................................................................................. 21
Figure 16 – Water boxes & water flow .................................................................................................. 22
Figure 17 - Stage 1 ................................................................................................................................ 23
Figure 18 - Stage 2 ................................................................................................................................ 23
Tables
Table 1 - Area plan .................................................................................................................................. 4
Table 2 - Reclamation Volumes ............................................................................................................ 20
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 4 of 36
1 Introduction
1.1 Introduction
The Anaklia Development Consortium (ADC) has been appointed by the Government of Georgia to develop
a deep-sea port in Anaklia, Georgia. The Anaklia Port property is located just south of the Enguri River and
the village of Anaklia on the Black Sea, and just north of Kolkheti National Park in the Samegrelo-Zemo
Svaneti Region of the Republic of Georgia.
The Anaklia Deep Water Black Sea Port will have the capacity to accept vessels of 10,000 TEU and will be
able to handle mixed cargo containers, dry bulk and liquids.
MS Method Statement
RA Risk Assessment
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 5 of 36
2 Organization
This chapter describes the personnel involved in the realization of the scope of works covered under this
method statement and provides information on the organization, roles and responsibilities.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 6 of 36
2.1 Organogram
Project
Manager
Secretary QHSE
Project Works
Chief surveyor
Controller Manager
2.2 Responsibilities
The specific tasks and responsibilities of the project staff, crew and labor directly involved in the activities
covered under this method statement are described below and in the appendix Work Instruction in case
applicable.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 7 of 36
Is responsible for his/her team including planning the aims, objectives and
priorities of their work area and communicating this to the team members and to
colleagues as appropriate
To control and assign supervision to areas of work
To control and report construction activities including progress against the
program
To control and report actual cost of work done against budgeted cost of work
To approve time sheets
Leads by example; gets people to do what is necessary by having them to follow
his/her example
Ensures that project personnel is aware of their duties as stated in the project
plans
To ensure that work is carried out in accordance with approved drawings,
procedures, specifications and Method Statements
To ensure that equipment on site is in proper condition and maintained during the
construction and that inspection log books are maintained
Responsibilities: To ensure all supervisors and foremen have received the required work
instructions or method statements
Prepare work programs for forthcoming operations
Liaising with Superintendents (onshore and near-shore) and Package Manager /
Project Manager
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 8 of 36
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 9 of 36
Responsibilities: General
Responsibilities: Provide safe working conditions for all workers under their supervision.
Provide workers with instruction in safe work procedures. Supervisors shall
require employees to use personal protective equipment, as appropriate, as part
of their routine duties, e.g., hard hats, goggles, masks, respirators, safety glasses
or other items deemed necessary.
Correct work site conditions, which are liable to cause or have caused accidents.
Undertake the investigation of accidents, incidents, or near misses to determine
the underlying causes. Report in detail to the Superintendent and complete the
required report forms on a timely basis.
Provide a good example for employees by always directing and performing work
in a safe manner.
Conduct regular inspections for unsafe practices and conditions and ensure
prompt corrective action to eliminate causes of accidents.
Work in cooperation with other project supervisory personnel to determine safe
practices, enforce their observance, develop procedures for dealing with
violations and develop other general safety and accident prevention measures.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 10 of 36
Provide each employee with information about the hazards of his/her job and
how to avoid them.
Maintain housekeeping standards and assign definite cleaning and organizing
responsibilities to individuals.
Enforce all established safety legislation and work methods. Provide a minimum
of one toolbox meeting a week with their crew and record minutes on the
prescribed form
Roles and Responsibilities Master
Responsibilities: General
Final responsibility for the safety of the ship, it’s crew and all personnel on board
Implement and maintain the QHSE system on board
Has the authority to stop all operations which are not executed in a safe manner
and/or endangering the vessel and its crew.
Report incidents to the Project Manager
Responsible for understanding and complying with the applicable procedures,
applicable regulations and Risk Assessments
To perform visual inspections
Maintaining the vessel specific HAZID/RA
Maintaining vessel specific JSA documentation
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 11 of 36
3.1 General
The vessels will be mobilized to Poti Port where the custom and immigration formalities will be performed.
After the documentation is finalized the marine equipment will sail to the Anaklia work site. Some auxiliary
equipment (pipelines, containers, spares etc) will be mobilized to Poti by vessel and transported by road to
site, and some equipment will be transported directly over the road to site from the Netherlands.
The dredging and the reclamation area will be cleared of obstructions by the client so the Contractor will
be able to start the construction work for the bunds and the installation of the PVD’s.
The floating pipeline will be assembled on the beach near Anaklia and will be installed on the site prior to
the arrival of the dredging vessel.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 12 of 36
4 Activities
Cutter Suction Dredger (CSD) Athena – Self-propelled vessel that uses a rotating cutter head to
loosen the material in the seabed (‘cutting’). The Athena is 130 m long, with a total installed power
of 24,650 kW. Along with its sister vessel the Artemis, it's among the most modern and powerful
self-propelled cutter suction dredgers in the world.
The Cronus or similar. This multicat will act as an assistance vessel to the primary marine
equipment: fulfilling duties such as crew transfer, delivery of stores and spares. Furthermore the
vessel will install the floating pipelines and anchors.
The Rijnstroom and Midyia. This workboats will act as an assistance vessel to the primary marine
equipment: fulfilling duties such as crew transfer and delivery of stores. The workboats may be
deployed in other operations as dictated by the project: inspection of buoys, conducting survey,
towing of pipelines/barges.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 13 of 36
- All marine based equipment will have communication equipment covering the requirements under
Section 35 20 23 3.01 A Bridge-to-Bridge Communication.
- Transfer of personnel and materials will take place by using the jetty in front of area A and/or Palm
Beach Docking. Fendering will be placed in front of the jetty. In the event of high wave conditions
an alternative might be the use of a small boat sailing from the estuary for boat to boat transfer.
For all personnel transfer using either jetty or boat lifejackets must be used during transfer.
- Bunkering of marine equipment will take place by bunker barge. A bunker barge will arrive on site
from Turkey and the Athena will be supplied with fuel and fresh water while all dredging operations
are stopped. It might be necessary to conduct these operations inside International Waters.
- Bunkering of Cronus, Rijnstroom and Midyia will take place alongside the Athena or in Port / Jetty.
Hydraulic excavators – CAT 330 to CAT 349 or similar – The excavators will be used for the moving
and placement of the reclamation pipelines and for the placement and control of sand whilst the
discharge process is underway.
Wheel loaders – CAT 966 to 980 or similar – The wheel loaders will transport the reclamation
pipelines around the site. They will also tidy the work area, levelling off of the sand and providing
general assistance where needed onsite.
Bulldozers – CAT D6 to D8 or similar – The bulldozers will be used on the reclamation for the
spreading and levelling of the discharge material and for the construction of the bunds.
4.3 Survey
During the fieldwork of the Feasibility phase, survey monuments (benchmarks) have been installed around
the site that are well documented, coordinated and agreed upon between parties.
Horizontal Control is UTM Zone 37 based on WGS’84 and Vertical Control is BZ (Baltic Zero).
A survey team will ensure that both reclamation and dredging activities will be performed to the lines and
levels indicated on the Drawings.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 14 of 36
The main survey equipment that will be installed on both ships and land based equipment are GNSS (GPS)
rover receivers, that make will use of a base station which will be installed close to the working areas. This
combination provides both horizontal and vertical centimeter level accuracies.
Monitors or displays will present the location and height of the working units with respect to the lines and
levels (design).
Rijnstroom or Midyia will be used as survey vessel to perform the hydrographic surveys. A bathymetric
survey system including a multibeam, motion sensor, heading device system will be installed on the vessel.
Topographic surveys will be performed by GNNS (GPS) rover receivers. Depending on the terrain a
combination of survey techniques with the GNSS antenna on a pogo stick, placed on a backpack or
mounted on a vehicle (quad) will be used.
Preconstruction Surveys:
Prior to commencement reclamation works topographical surveys will be carried out to determine the actual
status of reclamation areas. This survey will be witnessed by an independent surveyor. Prior to
commencement of the dredging, bathymetric lanes of the borrow pit will be checked to verify that the
Bathymetry from 2016 is still applicable.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 15 of 36
Progress surveys:
Progress surveys will be executed at a regular basis on request of the Operation team, and are used to get
an overview of the progress of the works both on land and on water.
Post Surveys:
To demonstrate compliance with the Drawings and Specifications and as base for interim payments, Post
surveys will be executed. Post surveys of the final levels will be used in the As-Built drawings. Post surveys
of the reclamation will be witnessed by an independent surveyor.
A CSD is equipped with powerful side winches mounted either side at the bow of the dredger. This enables
sideways dredging movement of the CSD.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 16 of 36
Once a full swing is completed an hydraulic cylinder will push the CSD forward by 1.0 – 1.5 mtr and the
next swing can be made. This hydraulic cylinder is fixed to the CSD and pushes against the spud pole.
The cutter position monitoring system works with angle transducers measuring the angle of the ladder to
determine the depth of the cutter head relative to the pontoon. A pressure transducer provides the depth of
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 17 of 36
the pontoon at that location. A computer calculates the relative x, y and z coordinates of the cutter head
and makes it available to the survey system and dredge computer.
The survey computer determines that actual pontoon position with input from a gyrocompass, DGPS/RTK
system and tide level in combination with information from the cutter position monitoring system. The results
are presented on displays for the dredge operator.
The information on the displays include a top view with the outline and position of the dredger and the cutter
head on a background of bathymetric data. Centre lines, slope lines, obstacles such as buoys and cables
are shown in this view. Also a cross profile of the cut with the actual seabed, dredged depth and cutter
position will be shown. Further, the survey computer determines and displays variables such as the actual
offset of the cutter from the centerline, the depth of the cutter head amongst others.
Most operations such as dredge depth and swing speed of the cutter, rpm’s of the cutter head and pumps
can be controlled by the dredge computer. An interface between the survey computer and the dredge
computer enables control of the dredge process to pre-defined levels.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 18 of 36
At the back of the cutter head a pipeline is placed that is connected to the dredge pumps located inside the
dredger. While the cutter head is cutting the soil the suction power of the pumps will suck the material away
that falls inside the cutter head. The soil will be mixed with water and the mixture will be around 25% soil
and 75% water. The pump will generate enough velocity to suck the material away from the cutter head
and pump it towards the shore. A total of three pumps are installed.
The dredging works will commence deepening the basin to a depth up to -8m BZ to create enough water
depth for the dredger to freely dredge the area till final depth.
The “Box cut” method will be applied and subsequently natural slopes will develop.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 19 of 36
Dredged material will be pumped from CSD to the allocated reclamation areas utilizing a floating pipeline
connected to the dredger, which is connected to a submerged pipeline and a pipeline on shore.
Winds, waves and currents may affect the floating pipeline during dredging and pumping operations. It may
then be necessary to utilize anchors to restrain the area of occupancy of the floating pipeline and to keep
it reasonably stretched to prevent the pipe line from snapping. The anchoring set will be a number of Delta
Flipper anchors. They will be set out at both sides of the floating pipeline. The length of wire will be
approximately 35 meters.
The shore pipeline consists of 12 meter long steel pipes with flanges. Bolts through these flanges connect
the pipes. On the reclamation area the pipeline will be extended each time the required level is reached
within the relevant area; as appropriate the pipeline can be diverted in order to raise the neighboring areas.
Dredged material protruding above the water level will be spread and levelled with the assistance of a
suitable number of bulldozers. Pipelines will be extended when the area around the pipeline in use has
reached the required fill level. Extension of the pipeline will be done by connecting a new length of
pipeline with the assistance of an excavator and or wheel-loader.
Containment bunds (further partitioning the overall reclamation area) will be constructed using dredged fill
for flow direction and the transportation of the dredged material. The return water will freely drain off into
open water through a water box.
The (progress of the) reclamation works will be frequently monitored by means of a combination of
hydrographic surveys and topographic surveys (above water level). Results of these surveys will be
presented in bathymetric and topographic charts.
The dredging plan is prepared in such a way as to ensure that the dredging operation is executed in a
safe and controlled manner and to optimize productivity. The dredging plan will be adjusted during the
execution according with the circumstances .
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 20 of 36
5.1 Volumes
A dredging area of 91.4 ha has been defined by ADC in the near shore (fig.12) of the work area, and the
current seabed varies from -2m BZ until -8m BZ. A layer of average 6 to 6.5m needs to be dredged to have
sufficient reclamation material to supply the entire volume of the 4.500.000 m3. This layer can be dredged
in one time or in two times. There are some thin lenses of clayey material within the dredging area and
deeper from surface there is in general more fines in the borrow material. The required layer will be dredged
and during the dredging the material will be mixed to an homogeneous mixture and pumped ashore.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 21 of 36
5.2 Activities
5.2.1 Dredging
The CSD will dredge the area to at least -8m to create enough water depth for the vessel to move forward
towards the shore.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 22 of 36
Furthermore the shore pipeline will be bolted together for the two areas, and water boxes will be installed
to let the excess water off the reclamation. The water boxes will be installed in the bunds and regulate the
water level inside the reclamation.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 23 of 36
Stage 1:
Once the dredger arrived first Reclamation area A,B,C will be reclaimed to a level of approx. 2.5m to create
a base for the PVD installation in the inaccessible areas from area B and C. The pumping maximum
distance will be approx. 2,000m from the dredger to the reclamation.
Figure 17 - Stage 1
Stage 2:
Area D will be reclaimed to a level of approx. 2.5m to create a base for the PVD installation in that area.
The pumping maximum distance will be approx. 2,500m from the dredger to the reclamation.
Figure 18 - Stage 2
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 24 of 36
Stage 3:
Reclamation areas A,B and C will be reclaimed to final level. So Reclamation Areas A,B and C will be
completed during this stage. While in Reclamation area D the PVD will be installed in the elevated area
(approx. +2.5m).
Stage 4:
In stage 4 Reclamation area D will be reclaimed till final level.
It should be noted that there will be overlap between the stages. This will mean that there will be relocation
between the areas frequently in order to guarantee continuity for the dredging vessel.
Weather forecast and wave measurements will be used for dredging workability.
Should dust become a problem than water will be sprayed on the reclamation in order to avoid dust or loss
of sand.
6 Quality
This chapter describes all quality aspects directly related to the scope of work covered under this method
statement.
For the overall project information on the quality aspects reference is made to the Project Quality Plan
As part of this method statement an Inspection and Test Plan (ITP) will be prepared in line with the
Project Quality Plan. Further reference is made to the ITP (VOMS-2.04-TE-03-09-03) in the
appendices.
Following are the activity which will be done to support reclamation work process:
For the overall project information on health and safety reference is made to the Project Health Safety and
Security Management Plan.
The Risk Assessment(s) will be discussed and communicated to persons involved prior to the start of works
and fully documented. Attending persons will be asked to sign the Risk Assessment to confirm their
attendance and understanding of the briefing.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 25 of 36
If compaction problems will occur we will deal with. If excessive fine layer will be found the impact will be
assessed on the final works.
Reference is made to the Risk Assessment form (VOMS-PR2.04-TE-03-09-03) related to the scope of work
covered under this method statement in the appendices.
Mandatory PPE
Certain specific tasks and activities covered under this Method Statement may require personnel to wear
job specific PPE.
The type of job specific PPE to be used will be indicated in the Risk Assessment and Work Instruction in
the appendices and/or the JSA prepared prior to the start of the work.
8 Environment
For the overall project environmental information reference is made to the Project Environmental
Management Plan.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 26 of 36
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 27 of 36
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 28 of 36
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 29 of 36
MIDYIA
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 30 of 36
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 31 of 36
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 32 of 36
……………………..
1.
2.
3.
4.
5.
6.
7.
8.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 33 of 36
1 2
Inspection and Test Plan (ITP) for Legend “Verification by” Legend “Inspection by”
WM – Works Manager HP – Hold point
……………… (Method Statement)
SI – Superintendent WP – Witness point
CS – Chief Surveyor MP – Monitor point
MV – Master of Vessel DR – Document review point
QC – QC Inspector
9.
10.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 34 of 36
……………………..
1.
2.
3.
4.
5.
6.
7.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 35 of 36
Inspection and Test Plan (ITP) for 1 Legend “Verification by” 2 Legend “Inspection by”
……………… (Method Statement) WM – Works Manager HP – Hold point
SI – Superintendent WP – Witness point
CS – Chief Surveyor MP – Monitor point
MV – Master of Vessel DR – Document review point
QC – QC Inspector
Inspection method / Acceptance Inspection by 2
No. Activity / description Frequency Verification by1 Records Executed
standard Criteria VO Subcon Client
8.
9.
10.
VO-P1-DR00-CM-MS-0002 # Rev. 01
Anaklia Deep Water Black Sea Port Issued For Construction Use
Dredging and Reclamation
Method Statement for Dredging and Reclamation Page 36 of 36
Client Date
Project Location
Activity/Phase
Originator Signature
Reviewed by Signature
Approved by Signature
1-Introduction
1.1 Task Objectives
2-Procedure
Item Task Description Resp. Check
1.1
2.1
VO-P1-DR00-CM-MS-0002 # Rev. 01