Professional Documents
Culture Documents
BAB 4 (B) Compaction
BAB 4 (B) Compaction
BAB 4 (B) Compaction
Chapter 4
ROAD CONSTRUCTION Excavation
Earthwork Calculations Excavation increases the volume of material.
By:
Assoc. Prof. Dr. Mohamad Yusri Aman It is therefore necessary to use a bulking factor to determine the volume of
material that will be created by excavation.
Similarly a shrinkage factor is defined for the compaction of a soil at it's final
destination:
3 4
5 6
1
MASS HAUL DIAGRAM MASS HAUL DIAGRAM
Example 1
The table below shows ground levels and formation levels for a proposed road construction.
For a cut or fill on sloping ground
Embankments are to be built with side slopes of 1:2.5 and cuttings with slopes of 1:3. The
embankment crest width and cutting base width is 13 m. It may be assumed that the ground
Assuming a cut such as the one above, the cross sectional area is found firstly by is horizontal across the section.
calculating WL and WG:
b
WL = S nh
2
S n
b
S nh
2
WG =
S n
1 b b2
h (WL WG )
Thus Area = 2 2n 4n
(a) Construct a Mass Haul diagram for the project given the following:
Bulking Factor = 0.8
Shrinkage Factor = 1.0
A2
D
A1
(b) A river breaks up the project at chainage 1160m. Calculate the volumes of waste
material and borrow for this scenarios:
(i) Material cannot be moved across the river
M ASS HAUL DIAGRAM
M ASS HAUL DIAGRAM
50000
40000 150 280 500 740 1160 1280
Cumulative volume (cubic meter)
30000 50000
20000 40000
Cumulative volume (cubic meter)
10000 30000
0 20000
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
1500
-10000 10000
-20000 0
0
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
1500
-30000 -10000
-40000 -20000
-50000 -30000
-60000 -40000
-70000 -50000
-80000
-60000
-90000
-70000
Chainange (m) -80000
Fill Cut Cut Fill Fill Fill Cut
-90000
Chainange (m)
2
River (b) (ii) A Bailey bridge is constructed allowing material to be transported across the river
100
200
300
400
500
600
700
800
900
1000
1100
1200
1300
1400
1500
-10000
-20000
-30000
Borrow = 68,000 m3 -40000
Waste = 38,000 m3 -50000
-60000
-70000
-80000
-90000
Fill Cut Cut Fill Fill Fill Cut
Chainange (m)
Example 2
885.00 m
Existing
Ground
Distance (m) 150 130 220 240 540 220 Level
Cut (m3) 15,000 36,000 49,000 Proposed
Formation
Fill (m3) 15,000 36,000 79,000 Level
Haul (m3) 15,000 36,000 49,000
Borrow (m3)
Waste (m3)
The diagram above shows the proposed formation level and existing ground level for the construction of a
road.
1. Determine the volume of borrow or waste.
2. Verify your answer using a mass haul diagram.
(1) (2)
3
In-situ and On Site testing
METHODS OF MEASURING FIELD DENSITY
Soil Density Calculation
(1) SAND CONE / SAND REPLACEMENT
The volume of the test hole is obtained from
the loose sand required to fill the hole. The
sand used is uniform, medium sand that has
a constant loose density.
The difference between the mass of the
apparatus before and after the test is equal to
the mass of sand used to fill the test hole and
cone.
As the amount to fill the cone is constant,
therefore the mass in the test hole and the
volume of the test hole can be calculated.
19 20
21 22
4
SUBGRADE PREPARATION: Volumetric Calculations SUBGRADE PREPARATION: Volumetric Calculations
Borrow material:
Bulk density = 1.65 Mg/m3
(a)
Determine,
Dry density of borrow material dry = bulk / (1 + w) = 1.65 / (1 + 0.07) = 1.54 Mg/m3
(a)Volume of borrow material required for 1 cubic meter of
compacted road embankment
(b)Volume of additional water required for the entire volume of Compaction requirement: 97% of max. dry density:
embankment. 0.97 x 1.75 Mg/m3 = 1.70 Mg/m3
(c) Purchase and borrow pit material at site, haul 2 km round trip and spread
Soil inside truck is in loose condition, i.e. volume is the volume after excavation = RM 50/m3 x 275,000 m3
which is subjected to swelling (bulking).
= RM 13,750,000
Soil before excavation = 1.10 x 200,000 = 220,000 m3
Soil after excavation = 1.25 x 220,000 = 275,000 m3
Extra haul cost = RM 5/m3/km x 275,000 m3 x 3 km = RM 4,125,000
29 30
5
QUESTIONS??
Thank you …
31