PTL, LUDHIANA Rate Analysis

S. Particulars Brick Rate Amount Cement Rate Amount Sand Rate Amount Aggregate Rate
N.

1 P.C.C. 1:2:4 0.183 20.00 3.66 0.450 35.00 15.75 0.90 28.00

2 G.S.B. 1.25 28.00

3 P.C.C. 1:4:8 0.183 16.00 2.93 0.500 35.00 17.50 1.00 28.00

4 P.C.C. 1:5:10 0.183 16.00 2.93 0.500 35.00 17.50 1.00 28.00

5 R.C.C. 1:1.5:3 (Foundation) 0.230 18.00 4.14 0.440 35.00 15.40 0.88 28.00

6 R.C.C. 1:1.5:3 (Lintels / Beams) 0.230 18.00 4.14 0.440 35.00 15.40 0.88 28.00

7 Brick Work 1:5 (Foundation) 13.51 5.70 77.01 0.041 16.00 0.66 0.250 35.00 8.75

8 Brick Work 1:6 (Superstructure) 13.51 5.70 77.01 0.041 20.00 0.82 0.250 35.00 8.75
9 12mm Thick Cement Plaster 1:4

10 20mm Thick Cement Plaster 1:4

11 100mm Thick R.C.C. Flooring


Date : 21.06.19

Amount Total Labour Margin Total

25.20 44.61 25.00 17.40 87.00 3071.97

35.00 35.00 15.00 10.00 60.00

28.00 48.43 21.00 13.89 83.00

28.00 48.43 21.00 13.89 83.00

24.64 44.18 39.50 16.74 100.00

24.64 44.18 44.50 17.74 106.00

85.76 18.00 20.75 125.00

85.76 28.00 22.75 137.00