Professional Documents
Culture Documents
Contractors Entitlement To Additional Time - Cost-1
Contractors Entitlement To Additional Time - Cost-1
APRIL 2019
ENG. AHMED M. IBRAHIM
https://engamohd.blogspot.com
Sub-Clause # Clause Provisions EOT Additional Cost
1.9 Delayed If the Contractor suffers delay and/or incurs Yes Yes
Drawings or Cost as a result of a failure of the Engineer to
Instructions issue the notified drawing or instruction within
a time which is reasonable and is specified in
the notice with supporting details, the
Contractor shall give a further notice to the
Engineer and shall be entitled subject to Sub-
Clause 20.1 [Contractor’s Claims] to: (a) an
extension of time for any such delay, if
completion is or will be delayed, under Sub-
Clause 8.4 [ Extension of Time for Completion],
and (b) payment of any such Cost plus
reasonable profit, which shall be included in
the Contract Price.
2.1 Right of Access to If the Contractor suffers delay and/or incurs Yes Yes
the Site Cost as a result of a failure by the Employer to
give any right or possession within such time,
the Contractor shall give notice to the
Engineer and shall be entitled subject to Sub-
Clause 20.1 [Contractor’s Claims] to: a) an
extension of time for any such delay, if
completion is or will be delayed, under Sub-
Clause 8.4 [ Extension of Time for Completion],
and (b) payment of any such Cost plus
reasonable profit, which shall be included in
the Contract Price.
4.6 Co-operation The Contractor shall, as specified in the VO VO
Contract or as instructed by the Engineer,
allow appropriate opportunities for carrying
out work to: (a) the Employer’s Personnel, (b)
any other contractors employed by the
Employer, and (c) the personnel of any legally
constituted public authorities, who may be
employed in the execution on or near the Site
of any work not included in the Contract. Any
such instruction shall constitute a Variation if
and to the extent that it causes the
Contractor to incur Unforeseeable Cost.
Services for these personnel and other
contractors may include the use of
Contractor’s Equipment, Tempo
4.7 Setting Out If the Contractor suffers delay and/or incurs Yes Yes
Cost from executing work which was
necessitated by an error in these items of
reference, and an experienced contractor
could not reasonably have discovered such
error and avoided this delay and/or Cost, the
Contractor shall give notice to the Engineer
and shall be entitled subject to Sub- Clause
20.1 [ Contractor’s Claims] to: (a) an
extension of time for any such delay, if
completion is or will be delayed, under Sub-
Clause 8.4 [ Extension of Time for Completion],
and (b) payment of any such Cost plus
reasonable profit, which shall be included in
the Contract Price.