Professional Documents
Culture Documents
Forecast Cash Flow
Forecast Cash Flow
Forecast Cash Flow
Salihudin Hassim
FORECAST CASH FLOW Ptofesor Ma<lga
Jabatan Keir.r ruteiaan Arram
Falct:lti Kcjurtlteraarr
{.hrivrlsi.ti ?utta t':1al:'.;::"*r
4.? iOi) ::er r:tur3. SaidlE()l'
Tendering Process
Pre-contract Activity
Exploring opportunities
Deciding whether to participate in the tender or not
Buying tender document
Estimating base cost
Determining tender price
o Analyzingtenderdocument
o Getting quotation from suppliers and sub-contractors.
o Evaluating the quotations.
o Determining fix cost and overhead cost.
o Planning execution schedule
o Forecasting cash flow
o Analyzing financial cost
o Analyzingmarket price among competitors
o Finalizing final tendei price
o Strategizing price distribution to improve cash floil maximizing potential
gain from possible variation.
Filling up tender document
Checking tender documenf
o To avoid possible calculation error
o To a.void from being disqualified because of non conformance of tender
requirement.
Submitting complete tender document before closing of tender.
-
- Background of S'O
Price'
Good Practice for Preparation of Tender
Bill of Quantity.
o Contractor shall verify the quantity with the drawing if the quantity is stated
as provisional.
o If the final figure differ a lot with the actual work, it will definitely effect the
cost/ profitability of the project.
Market Price
- Based on supply and demand
- Influence by economic situation.
- Depend on competitors' strategy
- Change from time to time
Fair Price
- base cost r financial cost rover head + reasonable profit
depend on the company's capability, skill and efficiency to execute the project
Company's rating amongst the vendors, sub-cons, suppliers will influence the base
cost and financial cost.
To be able to construct at the lowest reasonable price, lhe company must:
o Have the right skill and experience of the compariy's staff
o Employ the most efficient construction method
o Have proper work schedule
o Get the full support from the sub-cons, suppliers and vendors
o Get cooperation from the s.o and authorities
o Have good rePutation.
The contractor must have the knowledge of the following information before deciding on the
tender price:
- base cost
o material
o machineries
o labour
- preliminaries
o mobiliZation
o contractual requirement such as bond and insurance
o maintenance of site office
o supervisoryteam
o temporary facilities such as assess road, temporary diversion etc.
o entertainment
o etc
- fix over-head cost
o tendering cost
o office maintenancs
o office staff
o licensing
o etc
- profit
o relationshiP with client
o companY's strategY
o market condition
o comPetitors
The above data will be analyzed with the work schedule to estimate:
cash flow
required working capital
financial cost
opportunity cost
=-F-
Working Capital
It is very important for the contractor to know the estimated wor|ing capital for a project as to
avoid financial problems during construction.
Estimated amount of required working capital can only be prepared if the contractor has done
his forecast cash flow. To be able to do the forecast cash flow, the contractor need to know:
- estimated cash-irV income
- estimated cash-out/ expenditur
- Work schedule
- Method of construction
- Work Breakdown Structure
Terms of payment with sub-con, labour, supplier etc.
focus on cost for every item/ activity of the project to be incurred at site.
- Based cost
- Tabular form.
- Profit and over-head are excluded
, Work Schedule
- Information on when to start and the duration of each activity.
- Relationship between activities
- Resources for each activity.
- Person I team responsible for the activity.
Presented in Gantt Chart and CPM
Cost Curve
- Combination of direct cost data and work schedule.
- Cost of work distributed through all activities along the time scale in work schedule.
- Only include direct field cost which is considered as direct cost.
- In the form of s-curve
Production Curve
Modified cost curve which represent total tender cost
Based cost r overhead + profit * other indirect cost
Indirect cost include insurance, bond, supervision, tax, entertainment etc.
Adjusted weighted value for all items for the contractor's / owner convenience.
Served as basis for progress payment.
Adjustment shall not change total tender price.
Modified production curve.
Scheduling
- Identify all activities to be done.
- Decide how the activities are going to be carried out'
o Own labour
o Sub- labour
o Sub-con
- Determine the time taken to complete each activity based on the available resources.
- Prepare CPM
- Transfer to Gantt Chart.
Ex.
Activity Duration (davs) Precedence Activity
A 5 none
B 12 none
a
D -) A
F 4 B&A
E 10 F &D
G 8 A&B
Fig 3
I tBt
F
E
A
D -
5 10 15 20 25
:29453 I 25500
:1.155
week 1 2 3 4 5 o
Cumulative Cost 3500 7500 14500 22500 25000 25500
Cumulative' Prod uction 4043 8663 16748 25988 28875 29453
value
10
Production Curve vs Cost curve
25000
.q
o
(5 20000
o
'E 15000
E
10000
5000
0
34
Period (week)
11
- Value of items/works listed in the tender documents will be used as a base for
progress valuation and rate ofvariation order.
- Corting for certain items are suppose to be hidden and need to be distributed for
paSrment pu{pose.
o Overhead
o Profit
o Lobbying cost
o Risk
o etc
Unequal distribution is done for strategic reasons (manipulation) to increase the
potential profit or improve the cash flow of the project.
,Client will counter the manipulation during price rationalizationprocess.
Price manipulation can be risky if the scope of work change.
Cash flow can be improved by employing 'front loading' strategy.
Ex.
B alance of c ontrac t t7 82
:-ifoo li ;rt
:29453 - 9818
: RM 19635
Weight factor for balance of work
:17671 .l 19635
:0.9
12
(RM) (RM)
E 5775 0.9 5198
F 4620 0.9 4158
G 9240 0.9 8315
k7571
l3
qrnlative Fno*.rtim Qne vs Arrrddi\re Oolffid Val rc
/ O,I1e n,
(
36m0
.H 3oooo
e25000
g 20m0
.='15000
B room
C
E 50m
0
'r
"4F
kiod (upd0
t4
Cash lncome Curve
Ddlation (week) 1 .2 3 4 5 6 7
Production Value 4851 5545 7624 831 5 2598 520 0
Cumulative Production Value 4851 10396 1 8020 26335 28933 29453 29453
10% retention fund 485 1040 18A2 2634 2893 2945 0
Pavment due 4366 9356 16216 23701 26040 26s08 29453
15
lncome curve vs Contract Value Cunve
35000
30000
25000
.g
o
(E
G
20000
= {
E) 1 5000
E'
E 1 0000
5000
'4
Duration
16
Cash Requirement Planning.
- Cash is required to pay the direct labour, material, sublhbour, sub-contract etc.
- Each group has is own terms and conditions.
- Terms and conditions are usually clearly written in the contract form.
- Common practice in the industry will become the guideline if no formal agreement
is signed.
- Late payment will cause
o Delay
i. o LAD
o Termination
o Legal claim
- Estimate of the amount of cash and the time to ensure that the allocation is ready
when it is needed
L7
For the above example, assume that
Cost Schedule
)uration (days) 1C 1l 2C 2l 3C
rveek 1 2 3 4 5 6
abour (A) 1000 (D)1500 (G) 3000 (G) 5000
natrerial (B) 2500 (B) 2500 (B) 1000
3ub-con (fl 3000 (n 1000
Vendor (E) 2000 (E) 2500 (E) 500
fotal cost 3500 4000 7000 8000 2500 500
lumulative Cost 3500 7500 14500 2250A 25000 25500
18
35000
30000
25000
20000
1 5000
1 0000
5000
0
t9
Cost Incurred Schedule
Cash Requirement
//eek 1 I A E
€
20
I
I
Cash-flow
- the difference between cash received and cash out.
1'
- financing ,
o intemal source
o external financing
- negotiating better terms and conditions
- repackaging
Cash-flow schedule
luration 1 2 3 4 5 6 7
lash Received 4366 4990 6862 7483 2339 3413
lumulative cash received 4366 9356 16218 23701 26040 29453
]ash pavment 3500 4000 4000 7700 2900 2500 900
lumulative Cash oavmeit 3500 7500 1 1500 19200 22100 24640 25500
lash flow -3500 366 990 -838 4583 -161 2513
lumulative cash flow -3500 -3134 -2144 -2982 1601 1440 3953
2l
Cash ln vs Gash Out
.q
I zoooo
.E
(s
=
=E''
P tsooo
E
Duration (week)
22