Volume Satuan Kategori Biaya Harga Satuan (Rp )

Jumlah Biaya (Rp)


No Uraian Material Total
a b c d h=axd
BAHAN
1 Semen @. 50 Kg 26 Zak I-b Rp 65.000 Rp 1.690.000
2 Pasir Beton 6,8 M3 I-a Rp 200.000 Rp 1.360.000
3 Kerikil Beton 0,36 M3 I-a Rp 200.000 Rp 72.000
4 Kawat Harmonika 1.6 mm BWG 16 4,5 M2 I-b Rp 35.000 Rp 157.500
5 Batako 224 Bh I-b Rp 4.000 Rp 896.000
6 Besi Ø 10 mm 7 Btng I-b Rp 60.000 Rp 420.000
7 Besi Ø 6 mm 13 Btng I-b Rp 35.000 Rp 455.000
8 Batu Belah 3,276 M3 I-b Rp 280.000 Rp 917.280
9 Balok Kuda -Kuda 5/7 10 Bh I-a Rp 40.000 Rp 400.000
10 Balok Kasau 5/7 10 Bh I-a Rp 40.000 Rp 400.000
11 Kayu Papan Lapis 2/10 6 Bh I-a Rp 35.000 Rp 210.000
12 Papan Listplank Ulin 4 Kpng I-a Rp 65.000 Rp 260.000
13 Atap Seng 8 Lbr I-b Rp 70.000 Rp 560.000
14 Nok Atap Seng/ Bubungan 4 M1 I-b Rp 20.000 Rp 80.000
15 Cat Kilap 4 Kg I-b Rp 60.000 Rp 240.000
16 Klosed Jongkok 1 Bh I-b Rp 160.000 Rp 160.000
17 Pipa PVC Dia. 4 " 2 Btng I-b Rp 200.000 Rp 400.000
18 Pipa PVC Dia. 2 " 1 Btng I-b Rp 90.000 Rp 90.000
19 Lem dan Seal Tape 3 Bh I-b Rp 30.000 Rp 90.000
20 Pintu Plastik Kamar Mandi 1 Bh I-b Rp 300.000 Rp 300.000
21 Bak Air Biasa 1 Bh I-b Rp 350.000 Rp 350.000
22 Sepitank 2x2x2 m 1 Bh I-b Rp 2.500.000 Rp 2.500.000
23 Prasasti / Plakat KKN PPM UGM 1 Bh I-b Rp 250.000 Rp 250.000
TOTAL harga Per Unit WCU Rp 12.257.780

1 Mandor / Kepala Kerja 5 Hok Rp 65.000 Rp 325.000


2 Tukang 20 Hok Rp 60.000 Rp 1.200.000 RAB WC UMUM
3 Pekerja 20 Hok Rp 55.000 Rp 1.100.000
TOTAL Rp 2.625.000