Professional Documents
Culture Documents
Elevator Installation Cash Flow
Elevator Installation Cash Flow
Elevator Installation Cash Flow
SCOPE OF WORKS
MAY JUNE JULY AUGUST SEPTEMBER
Preliminaries 30 days
Receipt of Notice to Proceed (NTP) 7 days
PHASE 1 PHASE 1
Receipt of PO and Down Payment 7 days
Process Design and Engineering 7 days
Issuance and Approval of drawing 7 days
PHASE 2
Procurement 120 days
Delivery 35 days
Turn over of Shaf 1 day
PHASE 3
Installation of Mechanical Parts 44 days
Installation of Electrical Parts 17 days
PHASE 4
Testing and Commissioning 24 days
Final Adjustment 5 days
Issuance of Permit to Operate 1 day
Hand Over 1 day
Retention 1 day
IMPORTATION
EXPENSES
11,219,342.26
EQUIPMENT
IMPORTED
PHP
CASH FLOW PLAN
3,240,000.00
LOCAL PORTION
PHP
14,459,342.26
TOTAL AMOUNT OF
PAYMENT
PHP
LOCAL POR
CASH FLOW IMPORTED EQUIPMENT IMPORTATION EXPENSES Insta
PHASE 1
30% Down Payment of Imported Equipment upon confirmation of order PHP 11,219,342.26
30% Down Payment of Local Portion upon Confirmation of order PHP
PHASE 2
PHASE 3
PHASE 2
PHASE 3
Installation and Permits)
LOCAL PORTION (Supplied Materials,
LEGEND
PHP 35,527,915.27 PHP 26,178,465.27 PHP 9,349,450.00
ON SITE WORKS
PHASE DURATION
P 2,592,000.00
P 648,000.00
P 1,944,000.00
P 1,296,000.00
P 1,080,000.00
P 10,800,000.00
JUNE
PHASE 4
JULY
PHP 57,547,257.53
PHP 10,800,000.00
PHP 37,397,807.53
PHP 9,349,450.00
ESCALATOR INSTALLATION CASH FLOW
SCOPE OF WORKS
MAY JUNE JULY AUGUST SEPTEMBER
Preliminaries 30 days
Receipt of Notice to Proceed (NTP) 7 days
PHASE 1 PHASE 1
Receipt of PO and Down Payment 7 days
Process Design and Engineering 7 days
Issuance and Approval of drawing 7 days
PHASE 2
Procurement 120 days
Delivery 35 days
Turn over of Shaf 1 day
PHASE 3
Installation of Mechanical Parts 39 days
Installation of Electrical Parts 20 days
PHASE 4
Testing and Commissioning 24 days
Final Adjustment 5 days
Issuance of Permit to Operate 1 day
Hand Over 1 day
Retention 1 day
IMPORTATION
EXPENSES
8,539,753.90
EQUIPMENT
IMPORTED
PHP
CASH FLOW PLAN
1,200,000.00
LOCAL PORTION
PHP
9,739,753.90
TOTAL AMOUNT OF
PAYMENT
PHP
LOCAL POR
CASH FLOW IMPORTED EQUIPMENT IMPORTATION EXPENSES Insta
PHASE 1
30% Down Payment of Imported Equipment upon confirmation of order PHP 8,539,753.90
30% Down Payment of Local Portion upon Confirmation of order PHP
PHASE 2
PHASE 3
PHASE 2
PHASE 3
Installation and Permits)
LOCAL PORTION (Supplied Materials,
LEGEND
PHP 27,042,552.42 PHP 19,926,092.42 PHP 7,116,460.00
ON SITE WORKS
PHASE DURATION
P 840,000.00
P 760,000.00
P 200,000.00
P 600,000.00
P 400,000.00
P 4,000,000.00
JUNE
PHASE 4
JULY
PHP 43,182,306.32
PHP 7,600,000.00
PHP 28,465,846.32
PHP 7,116,460.00