RENCANA ANGGARAN BIAYA

( RAB )
PEKERJAAN : PEMBANGUNAN POS JAGA
LOKASI : YAPIS DOK V BAWAH JAYAPURA PAPUA
T.A : 2018

NO. URAIAN PEKERJAAN SATUAN VOLUME HARGA SAT Rp. JUMLAH Rp.

I PEKERJAAN PENDAHULUAN
1 Pek. Pengukuran dan pemasangan Bowplank M1 56 77,575.00 4,344,200.00
2 Pek.Pembersihan Lokasi dan Perataan M2 169 21,250.00 3,591,250.00
3 Pek. Galian Pondasi M3 26.14 94,625.00 2,473,876.00
4 Pek. Urugan Tanah Kembali M3 6.53 26,592.00 173,512.80
5 Pek. Urugan Pasir M3 1.54 397,850.00 610,779.32
6 Pek. Timbunan Pilihan M3 9.8 277,850.00 2,722,930.00
7 Pek. Urugan Pasir ( Bawah Tanah ) M3 2.45 397,850.00 974,732.50
JUMLAH 14,891,280.62

II PEKERJAAN PASANGAN BATU DAN PLESTERAN


1 Pas. Pondasi Batu Kali M3 11.7 1,154,675.00 13,514,316.20
2 Pas. Batu Kosong M3 4.79 615,750.00 2,948,211.00
3 Pas. Batu Tela 1 PC : 4 PSR M2 84.93 167,175.00 14,198,423.51
4 Pek. Plesteran 1 PC : 4 PSR, TEBAL 15 MM M2 169.86 68,785.00 11,684,026.46
5 Pek. Acian Semen M2 169.86 43,605.00 7,406,876.12
JUMLAH 49,751,853.29

III PEKERJAAN KAYU


1 Pas. Kusen Pintu dan Jendela Kayu M3 0.29 6,805,500.00 1,973,595.00
2 Pas. Pintu Panil Papan( Kayu Lengoa ) M2 3.44 745,500.00 2,564,520.00
3 Pas. Pintu Panil Papan Lapis Seng Plat BJLS 20 M2 1.72 705,500.00 1,213,460.00
4 Pas. Plafind Triplek 3 mm + Rangka Kayu M2 50.41 542,550.00 27,349,945.50
JUMLAH 33,101,520.50

IV PEKERJAAN RANGKA ATAP


1 Pas. Kontruksi Kuda Kuda Kayu M3 0.44 6,560,000.00 2,917,232.00
2 Pas. Gording Kayu 5/10 cm M3 0.3 5,285,000.00 1,587,614.00
3 Pas. Lisplank Papan 2 X 2/15 cm M 28 55,900.00 1,565,200.00
4 Pas. Talang Miring Senk Plat BJLS 20 M 28 133,951.25 3,750,635.00
5 Pas. Nok Genteng Metal Multiroof M 20 170,435.00 3,408,700.00
6 Pas. Atap Genteng Multiroof M2 50.41 249,580.00 12,581,327.80
7 Pas. Kaso + Reng Genteng Multiroof M2 50.41 68,325.00 3,444,263.25
JUMLAH 29,254,972.05

V PEKERJAAN BETON, PEMBESIAN DAN BEKISTING


1 Beton Tumbuk 1 PC : 3 PSR : 5 KRL M3 3.43 664,400.00 2,278,892.00
2 Beton Tumbuk 1 PC : 2 PSR : 3 KRL M3 3.36 1,661,075.00 5,587,856.30
3 Pembesian KG 198.77 16,821.14 3,343,504.32
4 Pas. Bekisting untuk Sloof M2 12.16 201,715.00 2,452,854.40
5 Pas. Bekisting untuk Kolom M2 7.74 419,458.23 3,248,284.50
6 Pas. Bekisting untuk Balok M2 17.94 429,358.23 7,700,969.14
JUMLAH 24,612,360.66

VI PEKERJAAN SANITER
1 Pas. Kloset Jongkok Kramik BH 1 938,900.00 938,900.00
2 Pas. Bak Mandi batu tela lapis Porsteling 0.30 M³ BH 1 2,594,743.60 2,594,743.60
3 Pas. Septiktank & Peresapan dari Beton 2 X 1,5 X 1,5 Ls 1 8,296,150.84 8,296,150.84
4 Pas. Pipa PVC Type AW 3/4" M 10 30,918.00 309,180.00
5 Pas. Pipa PVC Type AW 2" M 4 76,214.50 304,858.00
6 Pas. Pipa PVC Type AW 3" M 5 104,643.50 523,217.50
7 Pas. Kran Air Bersih 3/4" BH 2 94,150.00 188,300.00
8 Pas. Floor Drain/ Filter BH 1 68,775.00 68,775.00
JUMLAH 13,224,124.94

VII PEKERJAAN PENGANTUNG


1 Pas. Kunci Tanam BH 3 343,775.00 1,031,325.00
2 Pas. Engsel Pintu BH 3 46,913.75 140,741.25
3 Pas. Engsel Jendela Kupu-kupu BH 8 37,942.50 303,540.00
4 Pas. Grendel Pintu BH 3 70,885.00 212,655.00
5 Pas. Gerendel Jendela BH 8 70,885.00 567,080.00
JUMLAH 2,255,341.25

VIIII PEKERJAAN LANTAI DAN DINDING KERAMIK


1 Pas. Lantai Kramik 20 X 20 cm M2 8.91 333,999.00 2,975,931.09
2 Pas. Dinding Kramik 20 X 25 cm M2 2.55 283,765.00 723,600.75
3,699,531.84

IX PEKERJAAN PENGECATAN
1 Pek. Pengecatan Kusen Kayu M2 16.71 73,857.50 1,234,158.83
2 PEK. Vernis Kayu M2 4.65 59,302.50 275,827.79
3 PEK. Pengecatan Dinding M2 169.86 25,462.00 4,325,051.71
4 PEK. Pengecatan Felapond M2 50.41 25,462.00 1,283,539.42
JUMLAH 7,118,577.75

X PEKERJAAN LISTRIK
1 Pas. Lampu PHILIPS SL 14 What BH 7 309,512.50 2,166,587.50
2 Pas. Stop Kontak 230 VA BH 3 254,512.50 763,537.50
3 Pas. Saklar Tunggal BH 1 254,512.50 254,512.50
4 Pas. Saklar Ganda BH 2 249,512.50 499,025.00
5 Pas. Box Sekring/ Limit BH 1 294,512.50 294,512.50
JUMLAH 3,978,175.00
RENCANA ANGGARAN BIAYA
( RAB )
REKAFITULASI

NAMA PEKERJAAN : PEMBANGUNAN POS JAGA


LOKASI : YAPIS DOK V ATAS, KOTA JAYAPURA
TAHUN : 2018

NO. URAIAN PEKERJAAN JUMLAH Rp.

I PEKERJAAN PENDAHULUAN 14,891,280.62

II PEKERJAAN PASANGAN BATU DAN PLESTERAN 49,751,853.29

III PEKERJAAN KAYU 33,101,520.50

IV PEKERJAAN RANGKA ATAP 29,254,972.05

V PEKERJAAN BETON, PEMBESIAN DAN BEKISTING 24,612,360.66

VI PEKERJAAN SANITER 13,224,124.94

VII PEKERJAAN PENGANTUNG 2,255,341.25

VIIII PEKERJAAN LANTAI DAN DINDING KERAMIK 3,699,531.84

IX PEKERJAAN PENGECATAN 7,118,577.75

X PEKERJAAN LISTRIK 3,978,175.00

Coast 181,887,737.90
PPN (10%) 18,188,773.79
Realcoast 200,076,511.69
Dibulatkan 200,076,000.00
TERBILANG:
TERBILANG : Dua Ratus Juta Tujuh Puluh Enam Ribu Rupiah.

Jayapura 13 Desember 2018


CV. SEDERHANA

Direktur
.......................
DAFTAR HARGA SATUAN BAHAN DAN UPAH

PEKERJAAN : PEMBANGUNAN POS JAGA


LOKASI : YAPIS DOK V ATAS JAYAPURA
T.A : 2018

A UPAH KERJA SATUAN HARGA Rp.


1 Pekerja Org/Hr Rp. 120,000.00
2 Tukang Org/Hr Rp. 150,000.00
3 Kepala Tukang Org/Hr Rp. 165,000.00
4 Mandor Org/Hr Rp. 185,000.00

B HARGA BAHAN LOKAL


1 Batu Tela Bh Rp. 3,500.00
2 Paving Block / Cone Block Bh Rp. 6,000.00
3 Batu Apung Bh Rp. 25,000.00
4 Batu Alam/sisir (warna Hitam) Bh Rp. 30,000.00
5 Batu Kerawang (Roster) Bh Rp. 15,000.00
6 Batu bata merah Bh Rp.
7 Batu Gunung M3 Rp. 300,000.00
8 Sirtu M3 Rp. 200,000.00
9 Batu Kali M3 Rp. 300,000.00
10 Pasir Urug M3 Rp. 300,000.00
11 Pasir Pasangan M3 Rp. 300,000.00
12 Pasir Beton M3 Rp. 300,000.00
13 Batu pecah (1-2) M3 Rp. 450,000.00
14 Timbunan Pilihan M3 Rp. 200,000.00
15 Kayu Matoa (Balok) M3 Rp. 2,500,000.00
16 Kayu Matoa (Papan) M3 Rp. 2,500,000.00
17 Kayu Besi / Lenggoa (Balok / Papan) M3 Rp. 5,000,000.00
18 Kayu Ape dia 20 Cm M3 Rp. 1,750,000.00
19 Kayu Bakar M3 Rp. 500,000.00
20 Semen PC Kg Rp. 2,300.00
21 Semen Warna Kg Rp. 18,000.00
22 Tripleks 4 mm Lbr Rp. 65,000.00
23 Multipleks 6 mm Lbr Rp. 130,000.00
24 Teakwood 3MM (122 x 244) Lbr Rp. 135,000.00
25 Senk Gelombang BJLS 30 Lbr Rp. 65,000.00
26 Senk Plat BJLS 30 Lbr Rp. 85,000.00
27 Paku Senk Kg Rp. 25,000.00
28 Paku Biasa Kg Rp. 25,000.00
29 Paku Tripleks Kg Rp. 25,000.00
30 Paku Skrup Dos Rp. 45,000.00
31 Meni Kayu Kg Rp. 65,000.00
32 Meni Besi Kg Rp. 65,000.00
33 Cat Dinding Kg Rp. 26,000.00
34 Cat Kayu Kg Rp. 60,500.00
35 Cat Besi Kg Rp. 68,000.00

36 Cat Klir Batu Kg Rp. 85,000.00


36 Cat Alminium Kg Rp. 60,500.00
37 Cat Genteng / Seng Kg Rp. 130,000.00
38 Politur/Teak Oil Kg Rp. 60,000.00
39 Vernis Kg Rp. 60,000.00
40 Minyak Cat /Tenner Kg Rp. 45,000.00
41 Dempul Kayu Kg Rp. 65,000.00
42 Dempul Besi Kg Rp. 65,000.00
43 Plamur Besi Kg Rp. 50,000.00
44 Plamur Tembok Kg Rp. 27,500.00
45 Residu Kg Rp. 144,900.00
46 Kertas Amplas Lbr Rp. 5,000.00
47 Keramik Lantai 20 x 20 cm (warna) Dos Rp. 130,000.00
48 Keramik Lantai 30 x 30 cm (Warna) Dos Rp. 130,000.00
49 Keramik Lantai 40 x 40 cm (Warna) Dos Rp. 130,000.00
50 Keramik dinding 20 x 25 cm (warna) Dos Rp. 130,000.00
51 Plint Keramik 10 x 20 cm Dos Rp. 130,000.00
52 Kaca Bening 5 mm M2 Rp. 156,250.00
53 Kaca Riben 5 mm M2 Rp. 182,291.67
54 Kaca Cermin 5 mm M2 Rp. 225,694.44
55 Kaca Bening 16 mm M2 Rp. 2,256,944.44
56 Stang kaca naco 8 clip + kaca + tralis Set Rp. 225,050.00
57 Stang kaca naco 7 clip + kaca + tralis Set Rp. 205,000.00
58 Stang kaca naco 6 clip + kaca + tralis Set Rp. 185,000.00
59 Kunci Tanam 2 Slag ( Merk Union) Bh Rp. 265,000.00
60 Kunci Tanam 1 Slag ( Merk Union ) Bh Rp. 225,000.00
61 Engsel Pintu ( Merk Nikko-Japan ) Bh Rp. 20,000.00
62 Engsel Jendela ( Merk Nikko-Japan ) Bh Rp. 20,000.00
63 Grendel Pintu 3" Bh Rp. 35,000.00
64 Grendel Jendela Bh Rp. 35,000.00
65 Hak / Kait Angin (Lipat) Bh Rp. 65,000.00
66 Lem Kayu Kg Rp. 35,000.00
67 Lem Aibon Kg Rp. 45,000.00
68 Gerendel Besar 4" Bh Rp. 55,000.00
69 Kawat Bronjong 4 mm Kg Rp. 120,000.00
70 Kawat Duri Roll Rp. 285,000.00
71 Kawat Duri M Rp. 5,700.00
72 Kawat Ikat Kg Rp. 40,000.00
73 Kawat Ayakan M' Rp. 40,000.00
74 Kawat Harmonika Lebar 1,50 m M' Rp. 55,000.00
75 Has Nyamuk ( Besi ) M' Rp. 35,000.00
76 Kawat Raam M' Rp. 30,000.00
77 Kawat Las dos' Rp. 235,000.00
78 Baut mur 3/8" - 20 cm Bh Rp. 28,000.00
79 Baut mur kuda-kuda1/2" - 15 cm Bh Rp. 25,000.00
80 Beugel besi Strip 40.4 (sambungan Kayu) M' Rp. 85,000.00
81 Kabel NYM 2 x 1,5 mm Roll Rp. 525,000.00
82 Kabel NYM 2 x 2,5 mm Roll Rp. 775,000.00
83 Kabel NYM 3 x 1,5 mm Roll Rp. 603,750.00

84 Kabel NYM 3 x 2,5 mm Roll Rp. 862,500.00


85 Kabel NYA 1 x 1,5 mm Roll Rp. 300,000.00
86 Kabel NYA 1 x 2,5 mm Roll Rp. 375,000.00
87 MCB 6 A Bh Rp. 90,000.00
88 Sekring Box 1 Group Bh Rp. 75,000.00
89 Stop Kontak 220 Wat Merk Broco Bh Rp. 35,000.00
90 Saklar Tunggal Merk Broco Bh Rp. 35,000.00
91 Saklar Ganda Merk Broco Bh Rp. 30,000.00
92 Stop Kontak 220 Wat Biasa Bh Rp. 25,000.00
93 Saklar Tungga Biasa Bh Rp. 25,000.00
94 Saklar Ganda Biasa Bh Rp. 25,000.00
95 Fitting (Warna putih) Bh Rp. 30,000.00
96 Dop Light Philips (Besar) Bh Rp. 145,000.00
97 Dop Light Philips (Kecil) Bh Rp. 125,000.00
98 Lampu Philips SL 8 Wat Bh Rp. 55,000.00
99 Lampu Philips SL 14 Wat Bh Rp. 60,000.00
100 Lampu Philips SL 18 Wat Bh Rp. 65,000.00
101 Lampu Pijar 20, 40, 75 & 100 Wat Bh Rp. 6,325.00
102 Lampu TL Lengkap 20 wat Bh Rp. 94,875.00
103 Lampu TL Lengkap 2 x 20 wat Bh Rp. 275,000.00
104 Kloset Duduk KIA Set Rp. 2,500,000.00
105 Kloset Duduk Monoblok Lokal Set Rp. 1,600,000.00
106 Kloset Jongkok keramik Bh Rp. 300,000.00
107 Wastafel Set Rp. 3,500,000.00
108 Urinnoir KIA Bh Rp. 1,200,000.00
109 Wasbak Stanles Steel 1 Lubang Bh Rp. 1,500,000.00
110 Wasbak Stanles Steel 2 Lubang Bh Rp. 1,750,000.00
111 Bak Air Kotak 1 M3 Bh Rp. 850,000.00
112 Bak Air Siku 1 M3 Bh Rp. 750,000.00
113 Tandon plastik Profil 400 Liter Bh Rp. 782,000.00
114 Tandon plastik Profil 450 Liter Bh Rp. 920,000.00
115 Tandon plastik Profil 520 Liter Bh Rp. 1,300,000.00
116 Tandon plastik Profil 1.100 Liter Bh Rp. 2,702,500.00
117 Tandon plastik Profil 1.200 Liter Bh Rp. 3,450,000.00
118 Tandon plastik Profil 2.200 Liter Bh Rp. 4,542,500.00
119 Tandon plastik Profil 3.300 Liter Bh Rp. 6,325,000.00
120 Tandon plastik Profil 5.200 Liter Bh Rp. 11,500,000.00
121 Floor Drain/ Saringan Bh Rp. 50,000.00
122 Kran Air 1/2" Bh Rp. 60,000.00
123 Kran Air 3/4" Bh Rp. 75,000.00
124 Besi Beton Polos Kg Rp. 13,485.85
125 Besi Æ 6 (Polos) Kg Rp. 19,081.86
126 Besi Æ 8 (Polos) Kg Rp. 14,541.39
127 Besi Æ 10 (Polos) Kg Rp. 11,081.08
128 Besi Æ 12 (Polos) Kg Rp. 11,682.24
129 Besi Æ 16 (Polos) Kg Rp. 12,771.05
130 Besi Æ 19 (Polos) Kg Rp. 11,757.46
131 Pipa PVC dia 1/2" - 6M Btg Rp. 30,000.00
132 Pipa PVC dia 3/4" - 6M Btg Rp. 42,000.00

133 Pipa PVC dia 1" - 6M Btg Rp. 60,000.00


134 Pipa PVC dia 2" - 6M Btg Rp. 140,000.00
135 Pipa PVC dia 3" - 6M Btg Rp. 185,000.00
136 Pipa PVC dia 4" - 6M Btg Rp. 225,000.00
137 Lem PVC Bh Rp. 35,000.00
138 Pipa GIP dia 1/2" Btg Rp. 152,950.00
139 Pipa GIP dia 3/4" Btg Rp. 227,700.00
140 Pipa GIP dia 1" Btg Rp. 342,700.00
141 Pipa GIP dia 1,1/2" M' Rp. 420,900.00
142 Pipa GIP dia 2" Btg Rp. 547,400.00
143 Pipa GIP dia 3" Btg Rp. 885,500.00
144 Seal Type Rool Rp. 15,000.00
145 Drum Kosong Bh Rp. 300,000.00
146 Ijuk Kg Rp. 242,400.00
147 Pagar BRC 1.2 x 2.6 m + Plat Baja M2' Rp. 1,300,000.00
148 Kuas biasa Bh Rp. 25,000.00
149 Kuas roll Bh Rp. 35,000.00
150 Gypsum Board 9 mm Lbr Rp. 125,000.00
151 List Gypsum Board M' Rp. 65,000.00
152 List Kayu Profil M' Rp. 26,000.00
153 Genteng Metal Lbr Rp. 120,000.00
154 Nok Genteng Metal M' Rp. 70,000.00
155 Pegangan pintu (Door Holder) Bh Rp. 350,000.00
156 Reel pintu dorong dan Acc Pelengkap Bh Rp. 300,000.00
157 Kunci lemari Bh Rp. 40,000.00
158 minyak bekisting Ltr Rp. 15,000.00
159 Pintu Besi Baja (Rolling Door) M2 Rp. 2,500,000.00
160 Pintu Lipat (Bahan Plastik) M2 Rp. 1,300,000.00
161 Sunscreen Alluminium M2 Rp. 875,000.00
162 Rolling Door Alluminium M2 Rp. 1,500,000.00
163 Kusen / Profil Alluminium M Rp. 130,000.00
164 Skrup Fisher Bh Rp. 850
165 Sealant Tube Rp. 9,000.00
166 Besi Hollo □ 40.40.4 M1 Rp. 37,500.00
167 Besi Hollo □ 40.15.4 M1 Rp. 30,000.00
168 Besi Stainlees 2 inci M1 Rp. 750,000.00
169 Accecories Untuk Pagar / Tralis Bh Rp. 50,000.00
170 Sling Dia 10 mm M1 Rp. 105,000.00
171 Sling Dia 15mm M1 Rp. 120,000.00
172 Besi Plat t = 9 mm lbr Rp.
173 Plat Baja Polos t = 2 mm lbr Rp. 1,100,000.00
174 Besi Profil Canal 100.50.5 M1 Rp. 162,500.00
175 Stang Pemutar kg Rp.
176 Angker Baja 1" Bh Rp.
177 Pipa GIP 8" Bh Rp. 4,500,000.00

C SEWA PERALATAN DAN PERLENGKAPAN


1 Alat Pres Pipa PE /Hari Rp. 750,000.00
2 Alat pemotong besi 28 m /Hari Rp. 175,000.00
3 Paralatan Las /Hari Rp. 750,000.00
4 Peralatan Listrik /Hari Rp. 525,000.00
5 Peralatan Pertukangan /Hari Rp. 125,000.00
6 Kompresor /Hari Rp. 125,000.00
BACKUP DATA
( PEMBANGUNAN POS JAGA )

I PEKERJAAN PENDAHULUAN 7m
1 PENGUKURAN BOUPLANK
PEMASANGAN BOUPLANK 7m
panjang = 7m
lebar = 7m
keliling = 2x 7+ 7
= 28 m
panjang bouplank = keliling x 2
= 28 x 2
1300

VOLUME = 56 m

300
2 PEMBERSIHAN LAPANGAN 700

panjang = 13 m
lebar = 13 m

1300
700
VOLUME = 13 x 13
= 169 m2
300

3 pekerjaan galian
Luas = a+b x t
300 300

2
= 1 + 1.3 x 0.75 1.3
2
= 0.86 m2

Volume = luas x panjang pondasi 0.75


= 0.86 x 30.4
= 26.1 m3 1
sumbu tegak sumbu datar
a-h = 5.0 a-e = 5.0 a 2.5 b c 2.5 d
b-g = 1.5 a-f = 1.7
c-g = 3.0 a-g = 4.2 f
d-h = 5.0 a-h = 5.0 1.5
14.5 15.9 R. DAPUR
±0.00
Total Keseluruhan = sumbu tegak + sumbu datar R. ISTIRAHAT
= 14.5 + 15.9 ±0.00
-0.05
= 30.4 1.5

KM/
WC g

2.0

R. JAGA
h

1.7 0.8 2.5

4 PEK. URUGAN TANAH KEMBALI


Volume = 1/4 x galian pondasi
= 1/4 x 26.1
= 6.53 m3

7
700

5 PEK. URUGAN PASIR


di bawah lantai
tinggi urukan = 0.05 m
panjang = 7 m
lebar = 7 m
luas = p x l 7
= 7x 7

700
= 49 m2
volume = 0.05 x 49
= 2.45 m3

di bawah pondasi
luas = 0.05 m2 1.02
volume = 0.05 x 30.4
= 1.54 m3 0.05

6 PEK. TIMBUNAN PILIHAN


panjang = 7 m
lebar = 7 m 0.2 m
tinggi = 0.2 m
volume = p x l x t
= 7x 7x 0.2
= 9.8 m3

II PEKERJAAN PASANGAN BATU DAN PLESTERAN 0.3


1 PAS. PONDASI BATU KALI 1 PC : 4 PSR
lebar bawah = 0.8
lebar atas = 0.3
tinggi = 0.7
luas = 0.39 m2

volume = 0.39 x panjang pondasi 0.7


= 0.39 x 30.4
= 11.7 m3

0.8

2 PAS. BATU KOSONG/ ANSTAMPING


luas = 0.16 m2 1.08
volume = 0.16 x 30.4
= 4.79 m3

0.15 1.02
3 PAS. BATU TELA 1 PC : 4 PSR
panjang = panjang pas.pondasi luas kusen pintu, jendela dan ventilasi
= 30.4 m 1 luas ventilasi
tinggi = 3.3 m panjang = 0.45
luas = 100 m2 lebar = 0.25
= luas batu tela - luas total pintu jendela banyak = 20 bh
= 100 - 15.4 luas = 2.25 m2
= 84.9 m2 2 luas pintu
panjang = 2.15
lebar = 0.80
4 PEK. PLESTERAN 1 PC : 4 PSR, TEBAL 15 MM banyak = 3 bh
luas = PAS. BATU TELA 1 PC : 4 PSR x 2 luas = 5.16 m2
= 84.9 x 2 3 luas jendela
volume = 170 m2 panjang = 5.91
lebar = 1.35
5 PEK. ACIAN SEMEN luas = 7.98 m2
volume = PEK. PLESTERAN 1 PC : 4 PSR, TEBAL 15 MM total luas kusen pintu, jendela dan ventilasi
= 170 m2 = 15.4 m2
III PEKERJAAN KAYU
1 PAS. KUZEN PINTU DAN JENDELA KAYU
kusen pintu = 3
ukuran = 0.05 x 0.1 = 0.01 m2
panjang = 2.15 x 2+ 0.7 x 2
= 5.7 m
volume kusen pintu = 0.09 m3
kusen jendela panjang
total panjang = 26 m
ukuran = = 0.01 m2
volume kusen jendela = 0.13 m3

kusen ventilasi
banyak = 20 bh
= 0.05 x 0.1 x 0.25 + 0.45
= 0.004
volum 20 ventilasi = 20 x 0.004
= 0.07 m3

total volume kusen = 0.29 m3

2 PAS. PINTU PANIL PAPAN ( KAYU LENGOA)


total pintu = 2 bh
ukuran = 0.8 x 2.15
luas per pintu = 1.72 m2
volume 2 pintu = 3.44 m2

3 PAS. PINTU PANIL PAPAN LAPIS SENK PLAT BJLS 20


ukuran = 0.8 x 2.15
volume = 1.72 m2
4 PAS. PLAFOND TRIPLEKS 3 MM + RANGKA KAYU
panjang = 7.1 m
Pas.Plafond Triplek
lebar = 7.1 m 5mm
Rangka 60x120

volume = 50.4 m2
+3.00 Pas.Plafond Triplek
5mm
Rangka 60x120
+3.00
7.1

Pas.Plafond Triplek
5mm
Rangka 60x120
+3.00
5mm
Rangka 60x120
+3.00

Pas.Plafond Triplek
5mm
Rangka 60x120
+3.00

7.1

IV PEKERJAAN RANGKA ATAP


1 PAS. KONSTRUKSI KUDA - KUDA KAYU
ukuran = 0.05 x 0.1
luas = 0.01 m2

182,44
panjang k1 (1bh) = 3.7 + 11.2 + 6.06 + 1.82

91,74
0.53 x 2+ 0.68 x 2

53
0.91 x 2+ 1.23 x 2
302
= 29.5 m 560

panjang k2 ( 2 bh)
panjang = 5.46 + 3.6 + 0.87 + 1.16 + 1.63 + 1.5
= 28.4 m

163
8 7 ,2 5
148,71

panjang jurai 1 ( 2 bh) = 5.46 + 3.5 + 0.77 + 3+ 1.63 + 1.16


= 31 m
volume = luas x panjang total kuda-kuda 272,5

= 0.01 x 88.9
= 0.44 m3 TYPE KUDA - KUDA K2 (2 Bh) TY
S KALA 1 : 25 SKA

2 PAS. GORDING KAYU 5/10 CM


panjang = 5.32

4 8 0 ,4 1

6 5 4 ,1 8
1 3 4 ,5 6

3 0 7 ,2
12.3

4 8 0 ,4 1

6 5 4 ,1 8
1 3 4 ,5 6

3 0 7 ,2
16.3
26.2
total = 60.1
volume = luas x panjang gording
= 0.01 x 60.1
= 0.30 m3

3 PAS. LISPLANK PAPAN 2 X 2/20 CM


panjang = 7x 4
volume = 28 m
4 PAS. TALANG MIRING SENK PLAT BJLS 20
panjang = 7x 4
volume = 28 m

710
5 PAS. NOK GENTENG METAL MULTIROOF
panjang = 5x
volume = 20 m

6 PAS. ATAP GENTENG MULTIROOF


alas = 7.1
tinggi = 3.55
luas = axb
2
710
= 7.1 x 3.55
2
= 12.6 m2
volume = 12.6 x 4
= 50.4 m2

7 PAS. KASO + RENG GENTENG MULTIROOF

355
alas = 7.1

355
tinggi = 3.55
luas = axb
2
= 7.1 x 3.55
2
= 12.6 m2 710
volume = 12.6 x 4
= 50.4 m2

700

V PEKERJAAN BETON, PEMBESIAN DAN BEKISTING


1 BETON TUMBUK 1 PC : 3 PSR : 5 KRL
tinggi pasangan betonrumbuk = 0.07 m
panjang = 7m 7

700
lebar = 7m
luas = 49 m2
volume = 3.43 m3

7
2 BETON TUMBUK 1 PC : 2 PSR : 3 KRL
panjang balok dan slop = panjang pondasi x 2 sengkang ø6-200
= 30.4 x 2
= 60.8 m
luas = 0.15 x 0.2
= 0.03 m2 0.15 tulangan utama ø10
volume = 1.82 m3
350

0.2
350
kolom
banyak kolom = 11 bh
tinggi kolom = 3.5 m
luas = 0 m2
volume = 0 M3

volume total = 1.82 m3

3 PEMBESIAN DENGAN BESI POLOS ATAU BESI ULIR 0.2 sengkang ø6-200
pembesian slop
panjang per sengkang = 0.5 m
panjang pondasi = 30.4 m 0.2
= 152 bh
panjang sengkang slop = 76 m tulangan utama ø10
berat per meter = 0.22 kg
volume = 16.7 kg

banyak tulangan utama = 4 bh


panjang tulangan utama = 122 m
berat per meter = 0.62 kg
volume = 75.4 kg

pembesian kolom
panjang per sengkang = 0.5 m jumlah kolom = 11 bh
panjang kolom = 35.2 m tinggi kolom = 3.2 m
= 176 bh panjang kolom = 35.2 m
panjang sengkang kolom = 88 m 0.2
berat per meter = 0.22 kg
volume = 19.4 kg

banyak tulangan utama = 4 bh


panjang tulangan utama = 141 m
berat per meter = 0.62 kg
volume = 87.3 kg
volume total = 199 kg 0.22

4 PAS. BEKISTING UNTUK SLOOF


panjang slop = 30.4
ukran bekisting = 0.2 x 2
luas = 0.4 m
volume = 12.2 m2

5 PAS. BEKISTING UNTUK KOLOM slop


jumlah kolom = 11 bh
panjang bekisting = panjang kolom
per kolom = 3.2 x 4
= 12.8
0.2
ukuran bekisting = 0.22 m
volume 1 kolom = 2.82 m2
volume 11 kolom = 31 m2
tp bekisting yg dicor 1/2 dari kolom
= 7.74 m2 balok

6 PAS. BEKISTING UNTUK BALOK


panjang balok = 30.4 m
ukuran bekisting = 0.19 + 0.2 + 0.2
= 0.59 m 0.2
volume = 17.9 m2 0.19

VI PEKERJAAN SANITER
1 PAS. KLOSET JONGKOK KERAMIK
pas. Kloset jongkok keramik = 1 bh
volume = 1 bh
2 PAS. BAK MANDI BATU TELA LAPIS PORSELIN 0.30 M3
volume = 1 bh
3 PAS. SEPTIKTANK & PERESAPANNYA DARI BETON 2 X 1,5 X 1,5 M'
volume = 1 bh

4 PAS. PIPA PVC TYPE AW DIAMETER 3/4"


volume = 10 m
5 PAS. PIPA PVC TYPE AW DIAMETER 2"
volume = 4m
6 PAS. PIPA PVC TYPE AW DIAMETER 3"
volume = 5m
7 PAS. KRAN AIR BERSIH DIAMETER 3/4"
volume = 2 bh
8 PAS. FLOOR DRAIN/ FILTER =
volume = 1 bh

VII PEKERJAAN PENGANTUNG


1 PAS. KUNCI TANAM
volume = 3 bh
2 PAS. ENGSEL PINTU
volume = 3 bh

3 PAS. ENGSEL JENDELA KUPU - KUPU


volume = 8 bh
4 PAS. GRENDEL PINTU
volume = 3 bh

5 PAS. GRENDEL JENDELA =


volume = 8 bh

VIII PEKERJAAN LANTAI DAN DINDING KERAMIK


1 PAS. LANTAI KERAMIK 20 X 20 CM
panjang = 5.4 m
tinggi = 1.65 m
volume = 8.91 m2

2 PAS. DINDING KERAMIK 20 X 25 CM


panjang = 1.5 m
lebar = 1.7 m
volume = 2.55 m2

IX PEKERJAAN PENGECATAN
1 PEK. PENGECATAN KOSEN KAYU 3 X (BARU)
panjang kusen = 55.7 m
lebar = 0.05 m x 2= 0.1
tinggi = 0.1 m x 2= 0.2
volume = 16.7 m2

2 PEK. VERNIS KAYU


jendela
panjang daun jendela = 25.8
ukuran = 0.08 x 2+ 0.01 x 2
volume = 4.65 m2
pintu
banyak pintu = 3
ukuran = 0.81 x 2+ 0.02 x 2
volume = 4.98 m2

3 PEK. PENGECATAN DINDING BARU


volume = volume plasteran
= 170 m2

4 PEK. PENGECATAN PLAFOND BARU


volume = volume plapon
= 50.4 m2

X PEKERJAAN LISTRIK
1 PAS. LAMPU PHILIPS SL 14 WATT
volume = 7 bh No. SIMBOL KETERANGAN JUMLAH
2 PAS. STOP KONTAK 230 VA
1. Lampu XL 10 Watt 7
volume = 3 bh
3 PAS. SAKLAR TUNGGAL 2. Stop Kontak 3
volume = 1 bh 3. Saklar Ganda 2
4 PAS. SAKLAR GANDA 4. Saklar Tunggal 1
volume = 2 bh
5. Kabel NYM 2x2.5 mm
5 PAS. BOX SEKRING/ LIMIT
volume = 1 bh 6. Fuse Box 1