Practitioner Exam Questions

® 8
PRINCE2 Practitioner Resource Book

Question Part 2
6 B Answer

Whilst this is correct on its own “c” is correct because entry 5 is also in the
2a incorrect
wrong place.
Whilst this is correct on its own “c” is correct because entry 4 is also in the
2b incorrect
wrong place.
Both entry 4 and 5 are about roles and responsibilities and not Tools and
2c correct
techniques.
2d incorrect This is a responsibility.
Question Part

6 B Answer

3a incorrect Entry 6 These are relevant standards.


3b incorrect This relates to a responsibility and would not be noted under Standards.
3c incorrect This is a quality criterion.
3d correct This is a quality standard.
Question Part

6 B Answer

4a incorrect Entry 7 is a responsibility and correctly located.


4b incorrect Entry 8 is a responsibility and correctly located.
This is a responsibility of Project Assurance not the Project Manager (see
4c correct
C7.1).
4d incorrect See A above.