ID Task Name Duration Start Finish Oct 27, '19

T W T F S S M T
1 Area Kolam Dewasa & Anak 3 days? Thu 10/24/19 Mon 10/28/19
2 Layout Kolam 1 day Fri 10/25/19 Fri 10/25/19
3 Potongan Kolam 1 day? Fri 10/25/19 Fri 10/25/19
4 Detail Kolam 1 day Fri 10/25/19 Fri 10/25/19
5 3D Kolam 1 day? Mon 10/28/19 Mon 10/28/19
6 Detai Ruang Pompa 1 day? Mon 10/28/19 Mon 10/28/19
7 Koposit Instalasi Pipa 1 day? Thu 10/24/19 Thu 10/24/19
8 Wearing Diagram 1 day? Thu 10/24/19 Thu 10/24/19
9 Scematic Diagram 1 day? Thu 10/24/19 Thu 10/24/19
10 Area Onsen 1 day? Mon 10/28/19 Mon 10/28/19
11 Layout Onsen 1 day Mon 10/28/19 Mon 10/28/19
12 Potongan Onsen 1 day? Mon 10/28/19 Mon 10/28/19
13 Detail Onsen 1 day? Mon 10/28/19 Mon 10/28/19
14 Detail Ruang Pompa 1 day? Mon 10/28/19 Mon 10/28/19
15 3D Onsen 1 day? Mon 10/28/19 Mon 10/28/19
16 Weaing Diagram 1 day? Mon 10/28/19 Mon 10/28/19
17 Scematic Diagram 1 day? Mon 10/28/19 Mon 10/28/19

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Shcedule Shop Drawing
Summary Manual Summary Rollup Progress
Date: Wed 10/23/19
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1