Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 120

Name of Project: Provision of Water System

A. Location:
Barangay: Nagotgot, Pawa, Hologan, Balabagon
Municipality: Manito
Province: Albay
Region: 5

B. Design Parameters:

Demand:
Particular Description Data Unit
Number of Household Actual number of household beneficiaries 1770 HH
Average Household Size 5 No.
Total Population (No. of HH)(Ave. HH Member) 8,850.00 No.
Average Population Growth Rate Percent annualy 3%
Growth rate factor 1+Growth rate^lifespan 1.55796742
Design Project Life No. of years 15 Years
Design Population PP(1+GR)^Life Span 13,788.01 No.
Average Daily Water Demand Ave. daily consumption per capita 100 Liter
per Capita per Day average demand per day
PCWC ADD/24x60x60) 0.00115741
Average Daily Demand (ADD) (Design population)(ADW DCD) 1,378,801 Liter
Average Demand per Second ADD/24x60x60) 15.958 LPS

Supply:

Type of Source: Spring (Pumped)


Number of Sources:
Spring Discharge: 25.00 lps

Water Quality: Result Remarks (Pass/Fail)


Bacteriological (result/standard)
Physical
Chemical

Note:
If water quality failed in the bacteriological test, request treatment plan from RHU
252.85714
Water Consumption Pattern per Hour per HH

PCWC = 100 liter


R = ASF ÷ ADD

Ave. HH Size = 5 members


R = 1.5665783123

Ave. Consumption per 500 liter Use: 1/4 of the average


HH=
daily demand
Reservoir Size if
R>1: 448.11 cu.m.

Adopted Result: 1/4 of the average daily demand

Operational Size = 448.11


Emergency = 114.90
Reservoir Size = 563.01
Reservoir Dimensions:
Note: Dimensions are inside Dimensions

If Rectangular: If Cylindrical:
Dimension = 8.2573145 m Height = 3
length= 15 m Less:
width= 15 m dead volume: 0.2
height= 3m freeboard: 0.2
Less: Radius = (Vol/(∏h))^.5
dead volume: 0.2 m 7.4067959941
freeboard: 0.2 m Diameter = 17

Volume: 585 cu.m Volume: 590.164588


Ratio Storage Capacity

inadequate source
< 1.0 use mass diagram

1/4 of the average


1.0-3.0 daily demand

1/8 of the average


3.0-4.0 daily demand
no storage facility
> 4.0 required

Time to fill
Reservoir
m If rectangular:
6.50
m If cylindrical:
m 6.56

m
m
Pipeline Section Household Peak Available Pipe
Section Node Length Served Flow Head Diameter
from to (L) (HH) (Q) (Hr+elev.h) (D)
(m) (no.) (lps) (m) (mm)
1 2 3 4 5 6 7 8
1 A A1 2,000.00 Reservoir 15.9583468 94.31 150
2 A1 B 2,380.00 Reservoir 15.9583468 142.99 100
3 B C 1,240.00 1770 39.895867 60.42 150
4 C D 2,800.00 400 9.016015142 92.56 100
2 C E 1,714.50 1370 30.87985186 95.48 150
3 E F 2,960.51 500 11.27001893 103.03 100
4 E G 860.00 520 11.72081969 52.43 100
5 G H 2,968.45 400 9.016015142 110.57 100
6 G I 969.28 120 2.704804543 131.93 50

Column Description
1 Pipe section under consideration
2-3 Node under consideration
4 Length of pipe section under consideration (meter)
5 Number of household served
6 Computed Peak Flow = 2.5*Average Flow (liter per second)
Average Flow = 2.5 x GRF x N x Average Household Size x PCWC / 86,400
Where:
GRF= Growth Rate Factor
N= Number of households served by pipe section
PCWC= Per Capita Water Consumption
7 Residual Head from Junction plus Difference in elevation between nodes under consideration (meter)
8 Nominal pipe diameter taken from commercially available pipe sizes(mm)
9 Pipe material (GI or Plastic)
10 Absolute Roughness (G.I.=.15, Plastic = .0015)
11 Reynolds Number = (Water Density x Velocity x Diameter)/Water Viscosity
12 Friction Factor = Rough pipes in turbulent flow
13 Actual Head loss for the considered section computed using Darcy Weisbach Fomula
14 Residual Head = Avalable Head - Head Loss
15 Remarks = Pass/Fail (Transmission > 10.0 m., Distribution > 3.0 m.)
Pipe Absolute Reynolds Friction Actual Residual
Material Roughness Number Factor Headloss Head Pressure Airflow
Remarks
(e) (Re) (f) (Hf) (Hr) (PSI) (SCFM)
(mm) (m) (m)
9 10 11 12 13 14 15 16 17
Plastic 0.01 135187.96 0.0172605 9.5628 84.75 pass 120.58 0.6762764
Plastic 0.01 202781.94 0.0163546 81.8793 61.11 pass 86.95 0.6762764
Plastic 0.01 337969.91 0.0148422 31.8639 28.56 pass 40.63 1.6906911
Plastic 0.01 114566.07 0.0180009 33.8424 58.71 pass 83.54 0.3820771
Plastic 0.01 261592.53 0.0154316 27.4425 68.03 pass 96.80 1.308614
Plastic 0.01 143207.59 0.0173111 53.7675 49.27 pass 70.10 0.4775964
Plastic 0.01 148935.89 0.0171962 16.7813 35.65 pass 50.73 0.4967002
Plastic 0.01 114566.07 0.0180009 35.8783 74.69 pass 106.28 0.3820771
Plastic 0.01 68739.642 0.0202818 38.0152 93.92 pass 133.63 0.1146231
Node Elev Section Distance HH
A 369.98 A-A1 2000 Reservoir
A1 272.67 A1-B 2380 Reservoir
B 214.43 B-C 1240 1770
C 154.01 C-D 2800 400 A
C-E 1714.5 1370
D 90.01
E 87.09 E-F 2960.51 500
E-G 860 520
F 52.09
G 102.69 G-H 2968.45 400
G-I 969.28 120
H 27.77
I 6.41
F
A
Pawa
500 HH

C
B
E
Nagotgot
750 HH

D
H

Hologon
400 HH

G I
Balabagon
120 HH
Schedule of Valves along Pipe Line
Station Pipe Connection Fitting
6" dia flange
0+000 (intake box)
6" dia stub end

6" x 1" Saddle Clamp


0+880
1" dia. X 12" GI Nipple

6" x 1" Saddle Clamp


1+460
1" dia. X 12" GI Nipple
6" x 1" Saddle Clamp
1+900
1" dia. X 12" GI Nipple
4" x 1" Saddle Clamp
2+880
1" dia. X 12" GI Nipple
4" x 1" Saddle Clamp
3+680
1" dia. X 12" GI Nipple
6" x 1" Saddle Clamp
4+400 (reservoir)
1" dia. X 12" GI Nipple
Section CD
4" x 2" Saddle Clamp
0+100
2" dia. X 36" GI Nipple
4" x 1" Saddle Clamp
0+560
1" dia. X 12" GI Nipple
0+900 4" x 1" Saddle Clamp
1" dia. X 12" GI Nipple
1+500 4" x 1" Saddle Clamp
2+120 4" x 2" Saddle Clamp
2" dia. X 36" GI Nipple
1" dia. X 12" GI Nipple
2+360 4" x 1" Saddle Clamp
1" dia. X 12" GI Nipple
1" dia. X 12" GI Nipple
SECTION CE
0+600 4" x 2" Saddle Clamp
2" dia. X 36" GI Nipple
0+700 4" x 1" Saddle Clamp
1" dia. X 6" GI Nipple
0+880 4" x 1" Saddle Clamp
1" dia. X 6" GI Nipple
Section EF
0+200 4" x 2" Saddle Clamp
2" dia. X 36" GI Nipple
0+380 4" x 1" Saddle Clamp
1" dia. X 6" GI Nipple
0+860 4" x 2" Saddle Clamp
2" dia. X 36" GI Nipple
0+970 4" x 1" Saddle Clamp
1" dia. X 6" GI Nipple
1+540 4" x 1" Saddle Clamp
1" dia. X 6" GI Nipple
1+920 4" x 1" Saddle Clamp
1" dia. X 12" GI Nipple
2+180 4" x 1" Saddle Clamp
1" dia. X 6" GI Nipple
2+880 4" x 1" Saddle Clamp
1" dia. X 6" GI Nipple
Section EG
1+280 4" x 1" Saddle Clamp
1" dia. X 6" GI Nipple
1+400 4" x 2" Saddle Clamp
2" dia. X 36" GI Nipple
1+780 4" x 1" Saddle Clamp
1" dia. X 6" GI Nipple
es along Pipe Line Summary
Valve Type Valve Type Number
1/16" Orifice Air Release Valve w/ I"
6" dia mechanical gate valve inlet; CWP=175 PSI 16
1" Air/Vacuum Valve w/ 1" inlet; CWP
= 300 3
1/16" Orifice Air Release Valve w/ I" inlet; 5/64" Orifice Combination Air Valve
CWP=175 PSI w/ I" inlet; CWP=300 PSI 1
2" Diameter 90 deg, Angle Valve (Blow
Off) 6
1/16" Orifice Air Release Valve w/ I" inlet; 6" Mechanical Gate Valve
CWP=175 PSI 2
4" Screw Type Gate Valve 2
5/64" Orifice Combination Air Valve w/ I" 4" Mechanical Gate Valve
inlet; CWP=300 PSI 2

1/16" Orifice Air Release Valve w/ I" inlet;


CWP=175 PSI

1/16" Orifice Air Release Valve w/ I" inlet;


CWP=175 PSI

1" Air/Vacuum Valve w/ 1" inlet; CWP = 300

on CD
2" dia. 90 deg angle valve (blow-off)

1/16" Orifice Air Release Valve w/ I" inlet;


CWP=175 PSI

1/16" Orifice Air Release Valve w/ I" inlet;


CWP=175 PSI

1/16" Orifice Air Release Valve w/ I" inlet;


CWP=175 PSI
2" dia. 90 deg angle valve (blow-off)

1/16" Orifice Air Release Valve w/ I" inlet;


CWP=175 PSI

ON CE
2" dia. 90 deg angle valve (blow-off)

1/16" Orifice Air Release Valve w/ I" inlet;


CWP=175 PSI
1/16" Orifice Air Release Valve w/ I" inlet;
CWP=175 PSI

on EF
2" dia. 90 deg angle valve (blow-off)

1/16" Orifice Air Release Valve w/ I" inlet;


CWP=175 PSI

2" dia. 90 deg angle valve (blow-off)

1/16" Orifice Air Release Valve w/ I" inlet;


CWP=175 PSI

1/16" Orifice Air Release Valve w/ I" inlet;


CWP=175 PSI

1" Air/Vacuum Valve w/ 1" inlet; CWP = 300

1/16" Orifice Air Release Valve w/ I" inlet;


CWP=175 PSI

1/16" Orifice Air Release Valve w/ I" inlet;


CWP=175 PSI

on EG
1/16" Orifice Air Release Valve w/ I" inlet;
CWP=175 PSI

2" dia. 90 deg angle valve (blow-off)

1" Air/Vacuum Valve w/ 1" inlet; CWP = 300


Pipe Fittings
Node Pipe Fitting Quantity
A (Intake) 6" x 12" dia GI nipple 3
6" x 12" dia GI nipple 1
6" dia 90 degree GI elbow 3
2" dia. X 36" GI Nipple 3
2" dia 90 deg GI elbow 4
4" x 36" dia GI nipple 2
6" Sleeve Type Coupling 1
B(reservoir) 4" Sleeve Type Coupling 1
4" Sleeve Type Coupling 2
4" Flange Type Tee 1
4" Flange Type 90 deg. Elbow 1
4" Flange Type 90 deg. Elbow 2
4" Flange Type Tee 1
4" Sleeve Type Coupling 1
4" x 6" Reducer/Expander 1
6" dia Flange Type Tee 1
6"x 6 meters HDPE Pipe 5
6" dia 90 degree GI elbow 2
Node C 6" x 4" HDPE Tee (Butt fused) 1
Node D 4" dia End Cap 1
Node E 6" x 4" HDPE Tee (Butt fused) 1
Node F 4" dia End Cap 1
Node G 6" x 4" HDPE Reducer 1
4" dia HDPE Tee (Butt fused) 1
Node H 4" dia End Cap 1
Node I 4" dia End Cap 1
Component
Overflow
Outlet Pipe
Overflow
Airvent
Airvent
Drain
Outlet Pipe
Inlet Pipe
Diversion Pipe
Inlet Pipe
Inlet Pipe
Diversion Pipe
Outlet Pipe
Outlet Pipe
Diversion Pipe
Diversion Pipe
Diversion Pipe
Outlet Pipe
Section CD
Section CD
Section EF
Section EF
Section GI
Section GH
Section GH
Section GI
Summary
Description Quantity
6" x 12" dia GI nipple 4
6" dia 90 degree GI elbow 5
2" dia. X 36" GI Nipple 3
2" dia 90 deg GI elbow 4
4" x 36" dia GI nipple 2
6" Sleeve Type Coupling 1
4" Sleeve Type Coupling 4
4" Flange Type Tee 2
4" Flange Type 90 deg. Elbow 3
4" x 6" Reducer/Expander 1
6" dia Flange Type Tee 1
6"x 6 meters HDPE Pipe 5
6" x 4" HDPE Tee (Butt fused) 2
4" dia End Cap 4
4" dia HDPE Tee (Butt fused) 1
6" x 4" HDPE Reducer 1
BILL OF QUANTITIES

No. of Crew/
ITEM NO. ITEM DESCRIPTION QUANTITY UNIT Labor

I INTAKE STRUCTURE
I - 1. Clearing and Grubbing 225.00 sq.m.
Length 15.00 m
Width 15.00 m
Estimated Quantity 225.00 sq.m.
A. Labor
Productivity Rate:
150.00 sq. m./ man-day
Laborer 2.00 day/s 2.00
Foreman 2.00 day/s 1.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
I - 2. Diversion of Water 1.00 lot
A. Materials
Empty Cement Bags 200.00 pc/s
Sub-Total
B. Labor
Laborer 6.00 day/s 6.00
Foreman 6.00 day/s 1.00
Sub-Total
C. Equipment
15 hp Diesel Powered Water Pump 6.00 day/s 1.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
I - 3. Layout 1.00 lot
A. Materials
2 x 2 Coco Lumber 80.00 bdf
2 x 3 Coco Lumber 120.00 bdf
Nylon String #80 1.00 kg
Asstd. CW Nails 5.00 kg
Sub-Total
B. Labor
Foreman 2.00 day/s 1.00
Skilled Laborer 2.00 day/s 2.00
Laborer 2.00 day/s 2.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
I - 4. Excavation 5.76 cu.m.
Intake Box Base
Length 12.00 m
Width 0.80 m
Depth 0.60 m
Volume 5.76 cu.m.
Estimated Quantity 5.76 cu.m.
A. Labor
Productivity Rate:
1.50 cu.m. per m-day
Foreman 5.00 day/s 1.00
Skilled Laborer 5.00 day/s 4.00
Laborer 5.00 day/s 10.00

Direct Cost
Profit
OCM
Tax
Total Item Cost
I - 5. Handlaid Boulder 18.90 cu.m.
Length 3.50 m
Width 12.00 m
Depth 0.45 m
18.90 cu.m.
A. Materials
0.15-0.20 m. dia. Boulders 20.00 cu.m.
Sub-Total
B. Labor
Productivity Rate
3.00 cu.m. per m-day
Foreman 2.00 day/s 1.00
Skilled Laborer 2.00 day/s 2.00
Laborer 2.00 day/s 4.00
Sub-Total
C. Hauling
0.15-0.20 m. dia. Boulders 982.80 cans
-52 cans per cu.m.
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
I - 6. Concrete Works 3.49 cu.m.
Footing
Length 12.00 m
Width 0.45 m
Depth 0.20 m
Volume 1.08 cu.m.
Intake Box Slab
Length 4.00 m
Width 1.15 m
Depth 0.15 m
Volume 0.69 cu.m.
Intake Box Wall
Length 5.70 m
Width 0.70 m
Depth 0.15 m
Volume 0.60 cu.m.
Intake Box Floor and Apron
Length 5.00 m
Width 1.50 m
Depth 0.15 m
Volume 1.13 cu.m.
Estimated Quantity 3.49 cu.m.

A. Materials
Portland Cement Type 1 55.00 bags
Washed Sand 3.00 cu.m.
Washed Gravel 3/4 6.00 cu.m.
Waterproofing Compound 55.00 packs
Plastic Pail 10.00 pc/s.
Water Drum 1.00 pc/s.
Sub-Total
B. Labor
Productivity Rate:
2.50 cu.m. per gang - day
Foreman 3.00 day/s 1.00
Skilled Laborer 3.00 day/s 2.00
Laborer 3.00 day/s 8.00
Sub-Total
C. Equipment
1 Bagger Concrete Mixer 3.00 day/s 1.00
Sub-Total
D. Hauling
Portland Cement Type 1 55.00 bags
Washed Sand 156.00 cans
Washed Gravel 3/4 312.00 cans
1 Bagger Concrete Mixer (Mob and Demob) 1.00 Unit
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
I - 7. RSB Works 427.20 kgs.
A. Materials
12 mm. dia. X 6.0 m. def. bars 80.00 pc/s
Ga. 16 Tie Wire 9.00 kgs
Hacksaw Blade 10.00 pc/s
Sub-Total
B. Labor
Productivity Rate Cut,Place,Bend
80.00 kgs. Per - mday
Foreman 6.00 day/s 1.00
Skilled Laborer 6.00 day/s 1.00
Laborer 6.00 day/s 1.00
Sub-Total
C. Hauling
12 mm. dia. X 6.0 m. def. bars 80.00 pcs
Ga. 16 Tie Wire 1.00 lot
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
I - 8. Form Works 44.80 sq.m.
A. Materials
2 x 2 x 12 Coco Lumber 200.00 bdf.
2 x 3 x 12 Coco Lumber 420.00 bdf.
2 x 4 x 12 Coco Lumber 400.00 bdf.
Asstd. CW Nails 40.00 kgs
1/2" thk. Marine Plywood 15.00 pc/s
Sub-Total
B. Labor
Productivity Rate: Fab., Inst., Rem.
3.50 sq.m. per gday
Foreman 7.00 day/s 1.00
Skilled Laborer 7.00 day/s 4.00
Laborer 7.00 day/s 4.00
Sub-Total
C. Hauling
2 x 2 x 12 Coco Lumber 50.00 pc/s
2 x 3 x 12 Coco Lumber 70.00 pc/s
2 x 4 x 12 Coco Lumber 50.00 pc/s
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
I - 9. Pipe Fittings 1.00 lot
A. Materials
6" (0.20m) dia. Mechanical Gate Valve Flange Type 1.00 unit
6" (0.20m) dia. Flange with gasket (GI) 1.00 pc/s
6" (0.20m) dia. Nipple 1.00 pc/s
2" dia. GI Pipe (6.0m) 1.00 pc/s
2" GI Elbow 90 deg 2.00 pc/s
6" dia. HDPE Pipe SDR 9 (6.0m) 2.00 pc/s
6" dia. Elbow (buttfused) 1.00 pc/s
4" floor drain 1.00 pc/s
Sub-Total
B. Labor
Foreman 4.00 day/s 1.00
Skilled Laborer 4.00 day/s 2.00
Laborer 4.00 day/s 2.00
Sub-Total
C. Fabrication of Outlet Pipes 1.00 lot
Sub-Total
D. Hauling 1.00 lot
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost

II PIPE LINES
II-1. Clearing and Grubbing 8,946.37 sq.m.
Length 17,892.74
Width 0.50
Area 8,946.37
A. Labor
Productivity Rate:
150.00 sq. m./ man-day
Laborer 12.00 day/s 5.00
Foreman 12.00 day/s 1.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
II-2.Excavation 7,157.10 cu.m.
Length 17,892.74 m
Width 0.50 m
Depth 0.80 m
Estimated Quantity 7,157.10 cu.m.
A. Labor
Productivity Rate:
1.00 cu.m. per m-day
Foreman 120.00 day/s 1.00
Laborer 120.00 day/s 60.00
Sub-Total
B. Equipment
Concrete Cutter 10.00 day/s 1.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
II-3. Pipe Laying 17,900.00 m
Estimated Quantity
A. Materials
6" dia HDPE Pipe SDR 11 4,955.00 m
4" dia HDPE Pipe SDR 11 11,970.00 m
2" dia HDPE Pipe SDR 11 975.00 m
6" x 12" dia GI nipple 4 pcs
6" dia 90 degree GI elbow 5 pcs
2" dia. X 36" GI Nipple 3 pcs
2" dia 90 deg GI elbow 4 pcs
4" x 36" dia GI nipple 2 pcs
6" Sleeve Type Coupling 1 pcs
4" Sleeve Type Coupling 4 pcs
4" Flange Type Tee 2 pcs
4" Flange Type 90 deg. Elbow 3 pcs
4" x 6" Reducer/Expander 1 pcs
6" dia Flange Type Tee 1 pcs
6"x 6 meters HDPE Pipe 5 pcs
6" x 4" HDPE Tee (Butt fused) 2 pcs
4" dia End Cap 4 pcs
4" dia HDPE Tee (Butt fused) 1 pcs
6" x 4" HDPE Reducer 1 pcs
Sub-Total
B. Labor
Productivity Rate
2.00 Units per m-day
Foreman 5.00 day/s 1.00
Skilled Laborer 5.00 day/s 2.00
Laborer 5.00 day/s 4.00
Sub-Total
C. Hauling
Pipes and Fittings 1.00 lot
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
II-4. Installation of Valves 26.00 sets
A. Materials
1/16" Orifice Air Release Valve w/ I" inlet; CWP=175 16 set
PSI
1" Air/Vacuum Valve w/ 1" inlet; CWP = 300 3 set
5/64" Orifice Combination Air Valve w/ I" inlet;
1 set
CWP=300 PSI
2" Diameter 90 deg, Angle Valve (Blow Off) 6 set
6" Mechanical Gate Valve 2 pc
4" Screw Type Gate Valve 2 pcs
4" Mechanical Gate Valve 2 pcs
6" dia flange w/ bolt and nut 4 pcs
6" dia stub end 2 pcs
6" x 1" Saddle Clamp 4 pcs
1" dia. X 12" GI Nipple 20 pcs
4" x 2" Saddle Clamp 6 pcs
2" dia. X 36" GI Nipple 6 pcs
4" x 1" Saddle Clamp 16 pcs
Sub-Total
B. Labor
Productivity Rate
4.00 Sets per m-day
Foreman 7.00 day/s 1.00
Skilled Laborer 7.00 day/s 2.00
Laborer 7.00 day/s 4.00
Sub-Total
C. Hauling
Valves and Fittings 1.00 lot
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
II-5. Valve Box 26.00 Units
A. Materials
6"CHB 650.00 pcs
Portland Cement 65.00 bags
Washed Sand 10.00 cu.m.
10 mm dia. RSB 85.00 pcs
Ga. Tie Wire 10.00 kgs
Plastic Pail 5.00 pcs
Water Drum 1.00 pc
Sub-Total
B. Labor
Productivity Rate
2.00 units per day
Foreman 13.00 day/s 1.00
Skilled Laborer 13.00 day/s 2.00
Laborer 13.00 day/s 4.00
Sub-Total
C. Equipment
1 Bagger Concrete Mixer 13.00 day/s 1.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
III RESERVOIR
III- 1. Clearing and Grubbing 256.00 sq.m.
Length 16.00 m
Width 16.00 m
Estimated Quantity 256.00 sq.m.
A. Labor
Productivity Rate:
150.00 sq. m./ man-day
Laborer 1.00 day/s 2.00
Foreman 1.00 day/s 1.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
III- 2. Layout 1.00 lot
A. Materials
2 x 2 Coco Lumber 80.00 bdf
2 x 3 Coco Lumber 120.00 bdf
Nylon String #80 1.00 kg
Asstd. CW Nails 5.00 kg
Sub-Total
B. Labor
Foreman 1.00 day/s 1.00
Skilled Laborer 1.00 day/s 2.00
Laborer 1.00 day/s 2.00

Direct Cost
Profit
OCM
Tax
Total Item Cost
III - 3. Excavation 32.70 cu.m.
Length 16.00 m
Width 16.00 m
Depth 0.70 m
Estimated Quantity 32.70 cu.m.
A. Labor
Productivity Rate:
1.00 cu.m. per m-day
Foreman 5.00 day/s 1.00
Skilled Laborer 5.00 day/s 2.00
Laborer 5.00 day/s 8.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
III - 4. Boulder Fill 51.20 cu.m.
Length 16.00 m
Width 16.00 m
Depth 0.20 m
51.20 cu.m.
A. Materials
0.15-0.20 m. dia. Boulders 52.00 cu.m.
Sub-Total
B. Labor
Productivity Rate
3.00 cu.m. per m-day
Foreman 5.00 day/s 1.00
Skilled Laborer 5.00 day/s 2.00
Laborer 5.00 day/s 4.00
Sub-Total
C. Hauling
0.15-0.20 m. dia. Boulders 2,704.00 cans
-52 cans per cu.m.
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
III- 5. Concrete Works 178.50 cu.m.
Foundation
Length 16.00 m
Width 16.00 m
Depth 0.30 m
Volume 76.80 cu.m.
Reservoir Slab
Length 14.10 m
Width 14.50 m
Depth 0.10 m
Volume 20.45 cu.m.
Reservoir Wall
Length 57.20 m
Depth 3.10 m
Thickness 0.25 m
Volume 44.33 cu.m.
Beam
Length 15.50 m
Width 0.25 m
Depth 0.40 m
Number 8.00
Volume 12.40 cu.m.
Column
Height 3.50 m
Width 0.25 m
Length 0.35 m
Number 16.00
Volume 4.90 cu.m.
Service Path Walk
Length 66.00 m
Width 1.20 m
Thickness 0.10 m
Volume 7.92 cu.m.
Valve Box
Length 9.00 m
Width 2.60 m
Thickness 0.10 m
Volume 11.70 cu.m.
ESTIMATED QUANTITY 178.50 cu.m.
A. Materials
Portland Cement Type 1 2,141.94 bags
Washed Sand 90.00 cu.m.
Washed Gravel 3/4 179.00 cu.m.
Waterproofing Compound 2,141.94 packs
Plastic Pail 30.00 pc/s.
Water Drum 10.00 pc/s.
Sub-Total
B. Labor
Productivity Rate:
2.50 cu.m. per gang - day
Foreman 9.00 day/s 1.00
Skilled Laborer 9.00 day/s 8.00
Laborer 9.00 day/s 32.00
Sub-Total
C. Equipment
1 Bagger Concrete Mixer 9.00 day/s 4.00
Sub-Total
D. Hauling
Portland Cement Type 1 2,141.94 bags
Washed Sand 4,680.00 cans
Washed Gravel 3/4 9,308.00 cans
1 Bagger Concrete Mixer (Mob and Demob) 4.00 Unit
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
III - 6. RSB Works 15,491.20 kgs.
A. Materials
16 mm. dia. X 6.0 m. def. bars 720.00 pc/s
12 mm. dia. X 6.0 m. def. bars 1,510.00 pc/s
10 mm. dia. X 6.0 m. def. bars 170.00 pc/s
Ga. 16 Tie Wire 250.00 kgs
Sub-Total
B. Labor
Productivity Rate Cut,Place,Bend
80.00 kgs. Per - mday
Foreman 33.00 day/s 1.00
Skilled Laborer 33.00 day/s 6.00
Laborer 33.00 day/s 6.00
Sub-Total
C. Equipment
Bar Cutter 33.00 day/s 1.00
Sub-Total
D. Hauling
16 mm. dia. X 6.0 m. def. bars 720.00 pc/s
12 mm. dia. X 6.0 m. def. bars 1,510.00 pc/s
10 mm. dia. X 6.0 m. def. bars 170.00 pc/s
Ga. 16 Tie Wire 250.00 lot
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
III - 7. Form Works 746.25 sq.m.
A. Materials
2 x 2 x 12 Coco Lumber 1,600.00 bdf.
2 x 3 x 12 Coco Lumber 3,360.00 bdf.
2 x 4 x 12 Coco Lumber 3,200.00 bdf.
Asstd. CW Nails 200.00 kgs
1/2" thk. Phenolic Board 100.00 pc/s
Sub-Total
B. Labor
Productivity Rate: Fab., Inst., Rem.
3.50 sq.m. per gday
Foreman 27.00 day/s 1.00
Skilled Laborer 27.00 day/s 32.00
Laborer 27.00 day/s 32.00
Sub-Total
C. Hauling
2 x 2 x 12 Coco Lumber 400.00 pc/s
2 x 3 x 12 Coco Lumber 840.00 pc/s
2 x 4 x 12 Coco Lumber 800.00 pc/s
Asstd. CW Nails 200.00 kgs
1/2" thk. Marine Plywood 100.00 pc/s
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
IV COMMUNAL FAUCETS 250.00 Units
IV - 1. Concrete Works 47.50 cu.m.
A. Materials
Portland Cement 500.00 bags
Washed Sand 50.00 cu.m.
Washed Gravel 3/4" 50.00 cu.m.
Plastic Container ( Capacity 20 lit ) 100.00 pc/s
Sub-Total
B. Labor
Foreman 16.00 day/s 1.00
Skilled Laborer 16.00 day/s 8.00
Common Laborer 16.00 day/s 8.00
Sub-Total
C. Equipment
1 Bagger Concrete Mixer 16.00 day/s 1.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
IV - 2. RSB 1850.00 kgs.
A. Materials
10mm dia. x 6.0m RSB 500.00 pc/s
#16 G.I. Tie Wire 50.00 kg
Sub-Total
B. Labor
Foreman 24.00 day/s 1.00
Skilled Laborer 24.00 day/s 2.00
Common Laborer 24.00 day/s 2.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
IV - 3. Form Works 1.00 lot
A. Materials
2" x 3" x 12' Coco Lumber 600.00 bdf
2" x 2" x 12' Coco Lumber 400.00 bdf
1/4 thk. 4' x 8' Marine Plywood 50.00 pc/s
#3'' CWN 100.00 kg
#2'' CWN 100.00 kg
Sub-Total
B. Labor
Foreman 15.00 day/s 1.00
Skilled Laborer 15.00 day/s 2.00
Common Laborer 15.00 day/s 2.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
IV - 4. Pipe Fittings 1.00 lot
A. Materials
6" x 1/2" Saddle Clamp 70.00 pc/s
4" x 1/2" Saddle Clamp 180.00 pc/s
1/2" HDPE Pipe SDR 13.5 1,500.00 m
1/2''dia. X 6m GI. Pipe S-40 50.00 pc/s
1/2'' dia. HDPE to GI. Male adapter 250.00 pc/s
1/2'' dia. Brass Faucet 250.00 pc/s
1/2'' dia. X 10 '' G.I Nipple 250.00 pc/s
1/2'' dia. 90 deg. GI. Elbow 500.00 pc/s
1/2'' dia. GI. Coupling 500.00 pc/s
Sub-Total
B. Labor
Foreman 16.00 day/s 1.00
Skilled Laborer 16.00 day/s 8.00
Common Laborer 16.00 day/s 8.00
Sub-Total
C. Equipment
Pipe Threader 125.00 day/s 1.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
SUMMARY
I INTAKE BOX
II PIPELINES
III RESERVOIR
IV COMMUNAL FAUCETS
TOTAL
A DIRECT COST
MATERIALS
EQUIPMENT
LABOR
SKILLED
UNSKILLED
TOTAL ESTIMATED COST
MATERIALS LABOR EQUIPMENT
RATE PER SKILLED UNSKILLED
DAY/ UNIT TOTAL
COST
738,355.99

550.00 2,200.00 2,200.00


300.00 600.00 600.00
2,800.00
2,800.00
252.00
224.00
393.12
3,669.12

5.00 1,000.00 1,000.00


1,000.00

550.00 19,800.00 19,800.00


300.00 1,800.00 1,800.00
21,600.00

1,500.00 9,000.00 9,000.00


9,000.00
31,600.00
2,844.00
2,528.00
4,436.64
41,408.64

20.00 1,600.00
20.00 2,400.00
80.00 80.00
75.00 375.00
4,455.00 4,455.00

550.00 1,100.00 1,100.00


450.00 1,800.00 1,800.00
300.00 1,200.00 1,200.00
4,100.00
8,555.00
769.95
684.40
1,201.12
11,210.47

550.00 2,750.00 2,750.00


450.00 9,000.00 9,000.00
300.00 15,000.00 15,000.00
26,750.00
26,750.00
2,407.50
2,140.00
3,755.70
35,053.20

1,000.00 20,000.00 20,000.00


20,000.00

550.00 1,100.00 1,100.00


450.00 1,800.00 1,800.00
300.00 2,400.00 2,400.00
5,300.00

150.00 147,420.00 147,420.00

147,420.00
172,720.00
15,544.80
13,817.60
24,249.89
226,332.29

300.00 16,500.00
1,000.00 3,000.00
1,000.00 6,000.00
150.00 8,250.00
200.00 2,000.00
1,000.00 1,000.00
36,750.00 36,750.00

550.00 1,650.00 1,650.00


450.00 2,700.00 2,700.00
300.00 7,200.00 7,200.00
11,550.00

2,000.00 6,000.00 6,000.00


6,000.00

150.00 8,250.00
150.00 23,400.00
150.00 46,800.00
2,000.00 2,000.00
80,450.00 80,450.00
134,750.00
12,127.50
10,780.00
18,918.90
176,576.40

235.00 18,800.00
80.00 720.00
100.00 1,000.00
20,520.00 20,520.00

550.00 3,300.00 3,300.00


450.00 2,700.00 2,700.00
300.00 1,800.00 1,800.00
7,800.00

50.00 4,000.00
100.00 100.00
4,100.00 4,100.00
32,420.00
2,917.80
2,593.60
4,551.77
42,483.17

20.00 4,000.00
20.00 8,400.00
20.00 8,000.00
75.00 3,000.00
950.00 14,250.00
37,650.00 37,650.00

550.00 3,850.00 3,850.00


450.00 12,600.00 12,600.00
300.00 8,400.00 8,400.00
24,850.00
50.00 2,500.00
50.00 3,500.00
50.00 2,500.00
8,500.00 8,500.00
71,000.00
6,390.00
5,680.00
9,968.40
93,038.40

40,000.00 40,000.00
1,950.00 1,950.00
500.00 500.00
2,200.00 2,200.00
150.00 300.00
11,235.24 22,470.48
3,093.00 3,093.00
150.00 150.00
70,663.48 70,663.48

550.00 2,200.00 2,200.00


450.00 3,600.00 3,600.00
300.00 2,400.00 2,400.00
8,200.00
1,000.00 1,000.00 1,000.00
1,000.00
3,000.00 3,000.00 3,000.00
3,000.00
82,863.48
7,457.71
6,629.08
11,634.03
108,584.30

27,617,420.31

300.00 18,000.00 18,000.00


550.00 6,600.00 6,600.00
24,600.00
24,600.00
2,214.00
1,968.00
3,453.84
32,235.84

550.00 66,000.00 66,000.00


300.00 2,160,000.00 2,160,000.00
2,226,000.00

2,000.00 20,000.00 20,000.00


20,000.00
2,246,000.00
202,140.00
179,680.00
315,338.40
2,943,158.40
18,248,022.95

1,659.75 8,224,061.25
750.75 8,986,477.50
235.00 229,125.00
500.00 2,000.00
800.00 4,000.00
300.00 900.00
150.00 600.00
500.00 1,000.00
6,000.00 6,000.00
4,000.00 16,000.00
800.00 1,600.00
500.00 1,500.00
500.00 500.00
2,000.00 2,000.00
11,235.24 56,176.20
4,573.00 9,146.00
1,000.00 4,000.00
2,707.00 2,707.00
1,980.00 1,980.00
17,549,772.95 17,549,772.95

550.00 2,750.00 2,750.00


450.00 4,500.00 4,500.00
300.00 6,000.00 6,000.00
13,250.00

685,000.00 685,000.00 685,000.00


685,000.00
18,248,022.95
1,642,322.07
1,459,841.84
2,562,022.42
23,912,209.27

10,000.00 160,000.00
10,000.00 30,000.00
10,000.00 10,000.00
3,500.00 21,000.00
40,000.00 80,000.00
5,000.00 10,000.00
29,000.00 58,000.00
2,700.00 10,800.00
1,400.00 2,800.00
1,375.00 5,500.00
100.00 2,000.00
936.00 5,616.00
400.00 2,400.00
736.00 11,776.00
409,892.00 409,892.00

550.00 3,850.00 3,850.00


450.00 6,300.00 6,300.00
300.00 8,400.00 8,400.00
18,550.00

10,000.00 10,000.00 10,000.00


10,000.00
438,442.00
39,459.78
35,075.36
61,557.26
574,534.40

20.00 13,000.00
300.00 19,500.00
1,000.00 10,000.00
150.00 12,750.00
80.00 800.00
200.00 1,000.00
1,000.00 1,000.00
58,050.00 58,050.00

550.00 7,150.00 7,150.00


450.00 11,700.00 11,700.00
300.00 15,600.00 15,600.00
34,450.00

2,000.00 26,000.00 26,000.00


26,000.00
118,500.00
10,665.00
9,480.00
16,637.40
155,282.40
5,588,561.16

550.00 1,100.00 1,100.00


450.00 450.00 450.00
1,550.00
1,550.00
139.50
124.00
217.62
2,031.12

20.00 1,600.00
20.00 2,400.00
80.00 80.00
75.00 375.00
4,455.00 4,455.00

550.00 550.00 550.00


450.00 900.00 900.00
300.00 600.00 600.00
2,050.00
6,505.00
585.45
520.40
913.30
8,524.15

550.00 2,750.00 2,750.00


450.00 4,500.00 4,500.00
300.00 12,000.00 12,000.00
19,250.00
19,250.00
1,732.50
1,540.00
2,702.70
25,225.20

1,500.00 78,000.00 78,000.00


78,000.00

550.00 2,750.00 2,750.00


450.00 4,500.00 4,500.00
300.00 6,000.00 6,000.00
13,250.00

50.00 135,200.00 135,200.00


135,200.00
226,450.00
20,380.50
18,116.00
31,793.58
296,740.08

300.00 642,582.00
1,000.00 90,000.00
1,000.00 179,000.00
150.00 321,291.00
200.00 6,000.00
1,000.00 10,000.00
1,248,873.00 1,248,873.00

550.00 4,950.00 4,950.00


450.00 32,400.00 32,400.00
300.00 86,400.00 86,400.00
123,750.00

2,000.00 72,000.00 72,000.00


72,000.00

50.00 107,097.00
50.00 234,000.00
50.00 465,400.00
1,000.00 4,000.00
810,497.00 810,497.00
2,255,120.00
202,960.80
180,409.60
316,618.85
2,955,109.25

390.00 280,800.00
235.00 354,850.00
150.00 25,500.00
80.00 20,000.00
400,350.00 400,350.00

550.00 18,150.00 18,150.00


450.00 89,100.00 89,100.00
300.00 59,400.00 59,400.00
166,650.00

500.00 16,500.00 16,500.00


16,500.00

20.00 14,400.00
15.00 22,650.00
10.00 1,700.00
300.00 75,000.00
113,750.00 113,750.00
697,250.00
62,752.50
55,780.00
97,893.90
913,676.40

20.00 32,000.00
20.00 67,200.00
20.00 64,000.00
75.00 15,000.00
1,200.00 120,000.00
298,200.00 298,200.00

550.00 14,850.00 14,850.00


450.00 388,800.00 388,800.00
300.00 259,200.00 259,200.00
662,850.00

10.00 4,000.00
15.00 12,600.00
20.00 16,000.00
300.00 60,000.00
50.00 5,000.00
97,600.00 97,600.00
1,058,650.00
95,278.50
84,692.00
148,634.46
1,387,254.96
1,656,385.40

300.00 150,000.00
1,000.00 50,000.00
1,000.00 50,000.00
200.00 20,000.00
270,000.00 270,000.00

550.00 8,800.00 8,800.00


450.00 57,600.00 57,600.00
300.00 38,400.00 38,400.00
104,800.00

2,000.00 32,000.00 32,000.00


32,000.00
406,800.00
36,612.00
32,544.00
57,114.72
533,070.72

150.00 75,000.00
80.00 4,000.00
79,000.00 79,000.00

550.00 13,200.00 13,200.00


450.00 21,600.00 21,600.00
300.00 14,400.00 14,400.00
49,200.00
128,200.00
11,538.00
10,256.00
17,999.28
167,993.28

20.00 12,000.00
20.00 8,000.00
495.00 24,750.00
75.00 7,500.00
75.00 7,500.00
59,750.00 59,750.00

550.00 8,250.00 8,250.00


450.00 13,500.00 13,500.00
300.00 9,000.00 9,000.00
30,750.00
90,500.00
8,145.00
7,240.00
12,706.20
118,591.20

1,099.00 76,930.00
658.00 118,440.00
24.50 36,750.00
380.00 19,000.00
55.00 13,750.00
185.00 46,250.00
70.00 17,500.00
80.00 40,000.00
80.00 40,000.00
408,620.00 408,620.00

550.00 8,800.00 8,800.00


450.00 57,600.00 57,600.00
300.00 38,400.00 38,400.00
104,800.00

1,000.00 125,000.00 125,000.00


125,000.00
638,420.00
57,457.80
51,073.60
89,778.80
836,730.20

738,355.99
27,617,420.31
5,588,561.16
1,656,385.40
35,600,722.86 23,054,918.43 1,013,650.00 2,792,650.00 306,500.00
3,806,300.00

35,600,722.86
Republic of the Philippines
DEPARTMENT OF AGRICULTURE
PHILIPPINE RURAL DEVELOPMENT PROJECT

MUNICIPALITY OF MANITO, ALBAY

SUB-PROJECT PROGRAM OF WORKS


(For Level II Potable Water Supply)

PROJECT IDENTIFICATION NO.: PRDP-IB-R04A-


Project Title : Construction of PWS Level II, Eastern Cluster, Manito, Albay

Category : Potable Water Supply


Brgy/Mun/Province : Nagotgot, Hologan, Pawa, Balabagon
Total Project Cost : Php 0.00
Physical Target : 0.00 kms. of pipelines, intake box, reservoir and 250 communal fauctes
Project Duration : 275 c.d. inclusive of 30 unworkable days
Implementation Mode : By Contract
Project Description: Equipment Needed: Equipment Needed:
Owned Leased Description Owned Leased Description
Construction of Intake box 2 cu.m. 1 Bar Cutter
Construction of Reservoir 585 cu.m. 1 Pipe Threader
Installation of Pipelines 17.9 kms 1 Con. Mixer
1 Dump Truck
(Transmission and Distribution) 1 Stake Truck
Public Faucet (PF) 250 unit

Item No. Scope of Work % Weight Quantity Unit

I INTAKE STRUCTURE 97.75%


I - 1. Clearing and Grubbing 0.00% 225.00 sq.m.
0 0.37% 0.00 0
Foreman 0.24% 6.00 0
2 x 2 Coco Lumber 0.21% 80.00 bdf
0 1.48% 0.00 0
0 4.64% 0.00 0
0 0.00% 0.00 0
1 Bagger Concrete Mixer 0.79% 3.00 day/s
Productivity Rate 0.00% 0.00 0
0 1/2" thk. Marine Plywood 1.89%
0 4.98% 0.00 0
2 x 3 x 12 Coco Lumber 0.46% 70.00 pc/s
2" GI Elbow 90 deg 0.04% 2.00 pc/s
0 0.26% 0.00 0
2" dia HDPE Pipe SDR 11 30.33% 975.00 m
0 Foreman 0.36%
Skilled Laborer 0.60% 5.00 day/s
0 3165.69% 0.00 0
6" x 1" Saddle Clamp 0.73% 4.00 pcs
0 2.46% 0.00 0
B. Labor 0.00% 0.00 0
0 0.36% 0.00 0
0 2.40% 0.00 0
0 Depth 0.00%
Number 0.00% 8 0
Width 0.00% 3 m
Water Drum 1.32% 10 pc/s.
Portland Cement Type 1 14.18% 2142 bags

Breakdown of Estimated SOURCE OF FUND


Project Cost WB DA Grant CASH (LGU)
A. Direct Cost 13,200.00 1,650.00 1,650.00
Equipment 13,200.00 1,650.00 1,650.00
Labor - - -
Materials - - -
B. Indirect Cost 1,338,943.12 167,367.89 167,367.89
OCM 50,202.00 6,275.25 6,275.25
Contractor's Profit 557,800.00 69,725.00 69,725.00
Taxes 730,941.12 91,367.64 91,367.64
C. Project Cost 1,352,143.12 169,017.89 169,017.89
D. Percentage 80% 10% 10%
Prepared by: Reviewed by:

Technical Staff Municipal Engineer

Recommending Approval: Approved by:

MPDC Municipal Mayor


munal fauctes

Technical Personnel:
No. Description
1 Civil Engineer
1 Foreman
28 Skilled Laborers
50 Unskilled Laborer
100 Common Laborers

Unit Cost Total

738,355.99
- -
#DIV/0! 2,800.00
300.00 1,800.00
20.00 1,600.00
#DIV/0! 11,210.47
#DIV/0! 35,053.20
#DIV/0! -
2,000.00 6,000.00
#DIV/0! -
14,250.00
#DIV/0! 37,650.00
50.00 3,500.00
150.00 300.00
#DIV/0! 1,968.00
235.00 229,125.00
2,750.00
900.00 4,500.00
#DIV/0! 23,912,209.27
1,375.00 5,500.00
#DIV/0! 18,550.00
#DIV/0! -
#DIV/0! 2,702.70
#DIV/0! 18,116.00
-
- -
- -
1,000.00 10,000.00
50.00 107,097.00
755,355.99
Total Cost

₱16,500.00
16,500.00
0.00
0.00
₱1,673,678.90
62,752.50
697,250.00
913,676.40
₱1,690,178.90
100%

Municipal Engineer

Municipal Mayor
ACTIVITY ANNOTATION PREDECESSOR DURATION (DAYS)
I INTAKE STRUCTURE A -
I - 1. Clearing and Grubbing A1 NONE 2.00
I - 2. Diversion of Water A2 A1 6.00
I - 3. Layout A3 A2 2.00
I - 4. Excavation A4 A3 5.00
I - 5. Handlaid Boulder A5 A6 2.00
I - 6. Concrete Works A6 A7,A8 3.00
I - 7. RSB Works A7 A3 6.00
I - 8. Form Works A8 A3 7.00
I - 9. Pipe Fittings A9 A6 4.00
II PIPE LINES B
II-1. Clearing and Grubbing B1 A3 12.00
II-2.Excavation
Transmission B2a B3a 30.00
Distribution B2b C2 90.00
II-3. Pipe Laying
Transmission B3a B1,A6 5.00
Distribution B3b B2b 15.00
II-4. Installation of Valves
Transmission B4a B3a 2.00
Distribution B4b B3b 5.00
II-5. Valve Box B5 B4b,B4a 13.00
III RESERVOIR C
III- 1. Clearing and Grubbing C1 B3a 2.00
III- 2. Layout C2 C1 1.00
III - 3. Excavation C3 C2 5.00
III - 4. Boulder Fill C4 C3 5.00
III- 5. Concrete Works C5 C4,C6,C7 9.00
III - 6. RSB Works C6 C2 33.00
III - 7. Form Works C7 C2 27.00
IV COMMUNAL FAUCETS D
IV - 1. Concrete Works D1 D2,D3,D4 16.00
IV - 2. RSB D2 B4b 24.00
IV - 3. Form Works D3 B4b 15.00
IV - 4. Pipe Fittings D4 B4b 16.00

Qty Unit Cost


I INTAKE STRUCTURE
I - 1. Clearing and Grubbing 225.00 sq.m. -
I - 2. Diversion of Water - 0 2,800.00
I - 3. Layout 6.00 day/s 1,800.00
I - 4. Excavation 80.00 bdf 1,600.00
I - 5. Handlaid Boulder - 0 11,210.47
I - 6. Concrete Works - 0 35,053.20
I - 7. RSB Works - 0 -
I - 8. Form Works 3.00 day/s 6,000.00
I - 9. Pipe Fittings - 0 -
II PIPE LINES
II-1. Clearing and Grubbing - 0 37,650.00
II-2.Excavation 70.00 pc/s 3,500.00
Transmission
Distribution
II-3. Pipe Laying 2.00 pc/s 300.00
Transmission
Distribution
II-4. Installation of Valves - 0 1,968.00
Transmission
Distribution
II-5. Valve Box 975.00 m 229,125.00
III RESERVOIR
III- 1. Clearing and Grubbing 5.00 day/s 4,500.00
III- 2. Layout - 0 23,912,209.27
III - 3. Excavation 4.00 pcs 5,500.00
III - 4. Boulder Fill - 0 18,550.00
III- 5. Concrete Works - 0 -
III - 6. RSB Works - 0 2,702.70
III - 7. Form Works - 0 18,116.00
IV COMMUNAL FAUCETS
IV - 1. Concrete Works 8.00 0 -
IV - 2. RSB 2.60 m -
IV - 3. Form Works 10.00 pc/s. 10,000.00
IV - 4. Pipe Fittings 2,141.94 bags 107,097.00
24,409,681.65

Physical Accomplishment Periodic


Cumulative
Financial Accomplishment Periodic
Cumulative
0 0 0 2
A1 0 2 A2 2 8 A3 8 10 A4 10
2 0 2 6 2 8 2 8 10 5 12

1
A7 10
6 11

0
A8 10
7 10
S A= ANNOTATION
A ES EF t= TIME/DURATION 2
t LS LF S= SLACK B1 10
ES= EARLY START 12 12
EF= EARLY FINISH
LS= LATE START
LF= LATE FINISH

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
%RW
0.00% 0 0
0.01% ### ### ### ### ### ###
0.01% ### ###
0.01% ### ### ### ###
0.05%
0.14% 0 0 0
0.00% 0 0 0 0 0 0
0.02% ### ### ### ### ### ### ###
0.00%

0.15% 0 0 0 0 0 0 0 0 0 0
0.01%
0.00%
0.00%
0.00%
0.00%
0.00%
0.01%
0.00%
0.00%
0.94%

0.02%
97.96%
0.02%
0.08%
0.00%
0.01%
0.07%

0.00%
0.00%
0.04%
0.44%
100.00%
0 0 ### ### ### ### ### ### ### ### 0 0 0 0 0 0 0 0 0 0
- 0.0076% 0.0472% 0.1458% 0.1931%
- 0.0076% 0.0549% 0.2007% 0.3938%
- 1,866.67 11,522.62 35,595.11 47,129
- 1,866.67 13,389.29 48,984.40 96,113
190
A5 20 22
2 210 212

0 0
15 A6 17 20 A9 20 24
17 3 17 20 4 20 24

16
17

17
17

0 168
22 B3a 24 29 B4a 29 31
24 5 24 29 2 197 199

0
B2a 29 59
30 29 59

0
C1 59 61
2 59 61

21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
0 0

0 0 0 0

0 0

### ### ### ### ###1E-06 ### ### ### ### ### ### ### ###

### ### ### ### ###

0 0 0 0 ### ### ### ### ### ### ### ### ### ###1E-06 ### ### ### ### ### ### ### ###
0.1931% 0.0004% 0.0007% 0.0007% 0.0007%
0.3938% 0.3942% 0.3949% 0.3956% 0.3963%
47,129.27 104.17 175.00 175.00 1
96,113.67 96,217.84 96,392.84 96,567.84 96,7
27
B5 172 185
13 199 212

0
D2 172
24 172
0 0 0
B2b 62 152 B3b 152 167 B4b 167 172 9
90 62 152 15 152 167 5 167 172 D3 172
15 181

8
D4 172
16 180
0 103 131
C2 61 62 C3 62 67 C4 67 72
1 61 62 5 165 170 5 198 203

103
C6 67 100
33 170 203

109
C7 67 94
27 176 203

44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65
### ### ### ### ### ### ### ### ### ### ###1E-06 ### ### ### ###
### ### ###

### ###

###9E-05
97.96%
### ### ###

### ### ### ### ### ### ### ### ### ### ###1E-06 ### ### ### ### ###9E-05 0.9796 ### ### ###
0.0007% 0.0007% 0.0121% 97.9897%
0.3963% 0.3970% 0.4092% 98.3989%
175.00 175.00 2,958.12 23,918,975.94
96,742.84 96,917.84 99,875.96 24,018,851.90
0
F 212 212
0 212 212

0
196 D1 196 212
196 16 196 212

187
196

188
196
103
C5 100 109
9 203 212

66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89
1E-06 ### ### ###1E-06 1E-06 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###

5E-05 ###
0 0 0 0 0

### ###3E-06 3E-06 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
### ###3E-05 3E-05 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###

5E-05 ### 0 0 0 0 0 ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
897% 0.0966% 0.0192% 0.0192% 0.0192%
989% 98.4955% 98.5147% 98.5340% 98.5532%
23,918,975.94 23,589.31 4,692.18 4,692.18 4,692.18
24,018,851.90 24,042,441.21 24,047,133.39 24,051,825.57 24,056,517.75
90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###

0 0 0 0 0 0 0 0 0
### ### ### ### ### ### ### ### ### ### ###
### ### ### ### ###

### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
.0192% 0.0137% 0.0021% 0.0007% 0.0007%
8.5532% 98.5669% 98.5690% 98.5697% 98.5704%
4,692.18 3,350.25 502.60 175.00 175.00
24,056,517.75 24,059,868.00 24,060,370.60 24,060,545.60 24,060,720.60
114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###

### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
0007% 0.0007% 0.0007% 0.0007% 0.0007%
5704% 98.5711% 98.5718% 98.5725% 98.5733%
175.00 175.00 175.00 175.00 175.00
24,060,720.60 24,060,895.60 24,061,070.60 24,061,245.60 24,061,420.60
137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159
### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###

### ### ### ### ### ### ###

### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ### ###
0.0007% 0.0007% 0.0007% 0.0005% 0.0004%
98.5733% 98.5740% 98.5747% 98.5752% 98.5756%
175.00 175.00 175.00 118.33 90.00
24,061,420.60 24,061,595.60 24,061,770.60 24,061,888.93 24,061,978.93
160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182
### ### ### ### ### ### ### ###

### ### ### ### ###


0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0
### ### ### ### ### ### ### ### ### ###
0 0 0 0 0 0 0 0 0 0

### ### ### ### ### ### ### ### ### ### ### ### ### 0 0 0 0 0 0 0 0 0 0
0.0004% 0.0015% 0.2093% 0.6141% 0.5419%
98.5756% 98.5770% 98.7863% 99.4005% 99.9424%
90.00 356.14 51,095.03 149,911.38 132,28
24,061,978.93 24,062,335.07 24,113,430.10 24,263,341.48 24,395,62
183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204
0 0 0

0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0
### ### ### ### ###
0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0.5419% 0.0576% 0.0000% 0.0000%
99.9424% 100.0000% 100.0000% 100.0000%
132,286.38 14,053.79 - -
24,395,627.85 24,409,681.65 24,409,681.65 24,409,681.65
205 206 207 208 209 210 211 212
0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0
0.0000% 0.0000%
100.0000% 100.0000%
- -
24,409,681.65 24,409,681.65
BILL OF QUANTITIES

No. of Crew/
ITEM NO. ITEM DESCRIPTION QUANTITY UNIT Labor

I INTAKE STRUCTURE
I - 1. Clearing and Grubbing 225.00 sq.m.
Length 15.00 m
Width 15.00 m
Estimated Quantity 225.00 sq.m.
A. Labor
Productivity Rate:
150.00 sq. m./ man-day
Laborer 2.00 day/s 2.00
Foreman 2.00 day/s 1.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
I - 2. Diversion of Water 1.00 lot
A. Materials
Empty Cement Bags 200.00 pc/s
Sub-Total
B. Labor
Laborer 6.00 day/s 6.00
Foreman 6.00 day/s 1.00
Sub-Total
C. Equipment
15 hp Diesel Powered Water Pump 6.00 day/s 1.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
I - 3. Layout 1.00 lot
A. Materials
2 x 2 Coco Lumber 80.00 bdf
2 x 3 Coco Lumber 120.00 bdf
Nylon String #80 1.00 kg
Asstd. CW Nails 5.00 kg
Sub-Total
B. Labor
Foreman 2.00 day/s 1.00
Skilled Laborer 2.00 day/s 2.00
Laborer 2.00 day/s 2.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
I - 4. Excavation 5.76 cu.m.
Intake Box Base
Length 12.00 m
Width 0.80 m
Depth 0.60 m
Volume 5.76 cu.m.
Estimated Quantity 5.76 cu.m.
A. Labor
Productivity Rate:
1.50 cu.m. per m-day
Foreman 5.00 day/s 1.00
Skilled Laborer 5.00 day/s 4.00
Laborer 5.00 day/s 10.00

Direct Cost
Profit
OCM
Tax
Total Item Cost
I - 5. Handlaid Boulder 18.90 cu.m.
Length 3.50 m
Width 12.00 m
Depth 0.45 m
18.90 cu.m.
A. Materials
0.15-0.20 m. dia. Boulders 20.00 cu.m.
Sub-Total
B. Labor
Productivity Rate
3.00 cu.m. per m-day
Foreman 2.00 day/s 1.00
Skilled Laborer 2.00 day/s 2.00
Laborer 2.00 day/s 4.00
Sub-Total
C. Hauling
0.15-0.20 m. dia. Boulders 982.80 cans
-52 cans per cu.m.
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
I - 6. Concrete Works 3.49 cu.m.
Footing
Length 12.00 m
Width 0.45 m
Depth 0.20 m
Volume 1.08 cu.m.
Intake Box Slab
Length 4.00 m
Width 1.15 m
Depth 0.15 m
Volume 0.69 cu.m.
Intake Box Wall
Length 5.70 m
Width 0.70 m
Depth 0.15 m
Volume 0.60 cu.m.
Intake Box Floor and Apron
Length 5.00 m
Width 1.50 m
Depth 0.15 m
Volume 1.13 cu.m.
Estimated Quantity 3.49 cu.m.

A. Materials
Portland Cement Type 1 55.00 bags
Washed Sand 3.00 cu.m.
Washed Gravel 3/4 6.00 cu.m.
Waterproofing Compound 55.00 packs
Plastic Pail 10.00 pc/s.
Water Drum 1.00 pc/s.
Sub-Total
B. Labor
Productivity Rate:
2.50 cu.m. per gang - day
Foreman 3.00 day/s 1.00
Skilled Laborer 3.00 day/s 2.00
Laborer 3.00 day/s 8.00
Sub-Total
C. Equipment
1 Bagger Concrete Mixer 3.00 day/s 1.00
Sub-Total
D. Hauling
Portland Cement Type 1 55.00 bags
Washed Sand 156.00 cans
Washed Gravel 3/4 312.00 cans
1 Bagger Concrete Mixer (Mob and Demob) 1.00 Unit
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
I - 7. RSB Works 427.20 kgs.
A. Materials
12 mm. dia. X 6.0 m. def. bars 80.00 pc/s
Ga. 16 Tie Wire 9.00 kgs
Hacksaw Blade 10.00 pc/s
Sub-Total
B. Labor
Productivity Rate Cut,Place,Bend
80.00 kgs. Per - mday
Foreman 6.00 day/s 1.00
Skilled Laborer 6.00 day/s 1.00
Laborer 6.00 day/s 1.00
Sub-Total
C. Hauling
12 mm. dia. X 6.0 m. def. bars 80.00 pcs
Ga. 16 Tie Wire 1.00 lot
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
I - 8. Form Works 44.80 sq.m.
A. Materials
2 x 2 x 12 Coco Lumber 200.00 bdf.
2 x 3 x 12 Coco Lumber 420.00 bdf.
2 x 4 x 12 Coco Lumber 400.00 bdf.
Asstd. CW Nails 40.00 kgs
1/2" thk. Marine Plywood 15.00 pc/s
Sub-Total
B. Labor
Productivity Rate: Fab., Inst., Rem.
3.50 sq.m. per gday
Foreman 7.00 day/s 1.00
Skilled Laborer 7.00 day/s 4.00
Laborer 7.00 day/s 4.00
Sub-Total
C. Hauling
2 x 2 x 12 Coco Lumber 50.00 pc/s
2 x 3 x 12 Coco Lumber 70.00 pc/s
2 x 4 x 12 Coco Lumber 50.00 pc/s
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
I - 9. Pipe Fittings 1.00 lot
A. Materials
6" (0.20m) dia. Mechanical Gate Valve Flange Type 1.00 unit
6" (0.20m) dia. Flange with gasket (GI) 1.00 pc/s
6" (0.20m) dia. Nipple 1.00 pc/s
2" dia. GI Pipe (6.0m) 1.00 pc/s
2" GI Elbow 90 deg 2.00 pc/s
6" dia. HDPE Pipe SDR 9 (6.0m) 2.00 pc/s
6" dia. Elbow (buttfused) 1.00 pc/s
4" floor drain 1.00 pc/s
Sub-Total
B. Labor
Foreman 4.00 day/s 1.00
Skilled Laborer 4.00 day/s 2.00
Laborer 4.00 day/s 2.00
Sub-Total
C. Fabrication of Outlet Pipes 1.00 lot
Sub-Total
D. Hauling 1.00 lot
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost

II PIPE LINES
II-1. Clearing and Grubbing 8,946.37 sq.m.
Length 17,892.74
Width 0.50
Area 8,946.37
A. Labor
Productivity Rate:
150.00 sq. m./ man-day
Laborer 12.00 day/s 5.00
Foreman 12.00 day/s 1.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
II-2.Excavation 7,157.10 cu.m.
Length 17,892.74 m
Width 0.50 m
Depth 0.80 m
Estimated Quantity 7,157.10 cu.m.
A. Labor
Productivity Rate:
1.00 cu.m. per m-day
Foreman 120.00 day/s 1.00
Laborer 120.00 day/s 60.00
Sub-Total
B. Equipment
Concrete Cutter 10.00 day/s 1.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
II-3. Pipe Laying 17,900.00 m
Estimated Quantity
A. Materials
6" dia HDPE Pipe SDR 11 4,955.00 m
4" dia HDPE Pipe SDR 11 11,970.00 m
2" dia HDPE Pipe SDR 11 975.00 m
6" x 12" dia GI nipple 4 pcs
6" dia 90 degree GI elbow 5 pcs
2" dia. X 36" GI Nipple 3 pcs
2" dia 90 deg GI elbow 4 pcs
4" x 36" dia GI nipple 2 pcs
6" Sleeve Type Coupling 1 pcs
4" Sleeve Type Coupling 4 pcs
4" Flange Type Tee 2 pcs
4" Flange Type 90 deg. Elbow 3 pcs
4" x 6" Reducer/Expander 1 pcs
6" dia Flange Type Tee 1 pcs
6"x 6 meters HDPE Pipe 5 pcs
6" x 4" HDPE Tee (Butt fused) 2 pcs
4" dia End Cap 4 pcs
4" dia HDPE Tee (Butt fused) 1 pcs
6" x 4" HDPE Reducer 1 pcs
Sub-Total
B. Labor
Productivity Rate
2.00 Units per m-day
Foreman 5.00 day/s 1.00
Skilled Laborer 5.00 day/s 2.00
Laborer 5.00 day/s 4.00
Sub-Total
C. Hauling
Pipes and Fittings 1.00 lot
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
II-4. Installation of Valves 26.00 sets
A. Materials
1/16" Orifice Air Release Valve w/ I" inlet; CWP=175 16 set
PSI
1" Air/Vacuum Valve w/ 1" inlet; CWP = 300 3 set
5/64" Orifice Combination Air Valve w/ I" inlet;
1 set
CWP=300 PSI
2" Diameter 90 deg, Angle Valve (Blow Off) 6 set
6" Mechanical Gate Valve 2 pc
4" Screw Type Gate Valve 2 pcs
4" Mechanical Gate Valve 2 pcs
6" dia flange w/ bolt and nut 4 pcs
6" dia stub end 2 pcs
6" x 1" Saddle Clamp 4 pcs
1" dia. X 12" GI Nipple 20 pcs
4" x 2" Saddle Clamp 6 pcs
2" dia. X 36" GI Nipple 6 pcs
4" x 1" Saddle Clamp 16 pcs
Sub-Total
B. Labor
Productivity Rate
4.00 Sets per m-day
Foreman 7.00 day/s 1.00
Skilled Laborer 7.00 day/s 2.00
Laborer 7.00 day/s 4.00
Sub-Total
C. Hauling
Valves and Fittings 1.00 lot
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
II-5. Valve Box 26.00 Units
A. Materials
6"CHB 650.00 pcs
Portland Cement 65.00 bags
Washed Sand 10.00 cu.m.
10 mm dia. RSB 85.00 pcs
Ga. Tie Wire 10.00 kgs
Plastic Pail 5.00 pcs
Water Drum 1.00 pc
Sub-Total
B. Labor
Productivity Rate
2.00 units per day
Foreman 13.00 day/s 1.00
Skilled Laborer 13.00 day/s 2.00
Laborer 13.00 day/s 4.00
Sub-Total
C. Equipment
1 Bagger Concrete Mixer 13.00 day/s 1.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
III RESERVOIR
III- 1. Clearing and Grubbing 256.00 sq.m.
Length 16.00 m
Width 16.00 m
Estimated Quantity 256.00 sq.m.
A. Labor
Productivity Rate:
150.00 sq. m./ man-day
Laborer 1.00 day/s 2.00
Foreman 1.00 day/s 1.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
III- 2. Layout 1.00 lot
A. Materials
2 x 2 Coco Lumber 80.00 bdf
2 x 3 Coco Lumber 120.00 bdf
Nylon String #80 1.00 kg
Asstd. CW Nails 5.00 kg
Sub-Total
B. Labor
Foreman 1.00 day/s 1.00
Skilled Laborer 1.00 day/s 2.00
Laborer 1.00 day/s 2.00

Direct Cost
Profit
OCM
Tax
Total Item Cost
III - 3. Excavation 32.70 cu.m.
Length 16.00 m
Width 16.00 m
Depth 0.70 m
Estimated Quantity 32.70 cu.m.
A. Labor
Productivity Rate:
1.00 cu.m. per m-day
Foreman 5.00 day/s 1.00
Skilled Laborer 5.00 day/s 2.00
Laborer 5.00 day/s 8.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
III - 4. Boulder Fill 51.20 cu.m.
Length 16.00 m
Width 16.00 m
Depth 0.20 m
51.20 cu.m.
A. Materials
0.15-0.20 m. dia. Boulders 52.00 cu.m.
Sub-Total
B. Labor
Productivity Rate
3.00 cu.m. per m-day
Foreman 5.00 day/s 1.00
Skilled Laborer 5.00 day/s 2.00
Laborer 5.00 day/s 4.00
Sub-Total
C. Hauling
0.15-0.20 m. dia. Boulders 2,704.00 cans
-52 cans per cu.m.
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
III- 5. Concrete Works 178.50 cu.m.
Foundation
Length 16.00 m
Width 16.00 m
Depth 0.30 m
Volume 76.80 cu.m.
Reservoir Slab
Length 14.10 m
Width 14.50 m
Depth 0.10 m
Volume 20.45 cu.m.
Reservoir Wall
Length 57.20 m
Depth 3.10 m
Thickness 0.25 m
Volume 44.33 cu.m.
Beam
Length 15.50 m
Width 0.25 m
Depth 0.40 m
Number 8.00
Volume 12.40 cu.m.
Column
Height 3.50 m
Width 0.25 m
Length 0.35 m
Number 16.00
Volume 4.90 cu.m.
Service Path Walk
Length 66.00 m
Width 1.20 m
Thickness 0.10 m
Volume 7.92 cu.m.
Valve Box
Length 9.00 m
Width 2.60 m
Thickness 0.10 m
Volume 11.70 cu.m.
ESTIMATED QUANTITY 178.50 cu.m.
A. Materials
Portland Cement Type 1 2,141.94 bags
Washed Sand 90.00 cu.m.
Washed Gravel 3/4 179.00 cu.m.
Waterproofing Compound 2,141.94 packs
Plastic Pail 30.00 pc/s.
Water Drum 10.00 pc/s.
Sub-Total
B. Labor
Productivity Rate:
2.50 cu.m. per gang - day
Foreman 9.00 day/s 1.00
Skilled Laborer 9.00 day/s 8.00
Laborer 9.00 day/s 32.00
Sub-Total
C. Equipment
1 Bagger Concrete Mixer 9.00 day/s 4.00
Sub-Total
D. Hauling
Portland Cement Type 1 2,141.94 bags
Washed Sand 4,680.00 cans
Washed Gravel 3/4 9,308.00 cans
1 Bagger Concrete Mixer (Mob and Demob) 4.00 Unit
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
III - 6. RSB Works 15,491.20 kgs.
A. Materials
16 mm. dia. X 6.0 m. def. bars 720.00 pc/s
12 mm. dia. X 6.0 m. def. bars 1,510.00 pc/s
10 mm. dia. X 6.0 m. def. bars 170.00 pc/s
Ga. 16 Tie Wire 250.00 kgs
Sub-Total
B. Labor
Productivity Rate Cut,Place,Bend
80.00 kgs. Per - mday
Foreman 33.00 day/s 1.00
Skilled Laborer 33.00 day/s 6.00
Laborer 33.00 day/s 6.00
Sub-Total
C. Equipment
Bar Cutter 33.00 day/s 1.00
Sub-Total
D. Hauling
16 mm. dia. X 6.0 m. def. bars 720.00 pc/s
12 mm. dia. X 6.0 m. def. bars 1,510.00 pc/s
10 mm. dia. X 6.0 m. def. bars 170.00 pc/s
Ga. 16 Tie Wire 250.00 lot
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
III - 7. Form Works 746.25 sq.m.
A. Materials
2 x 2 x 12 Coco Lumber 1,600.00 bdf.
2 x 3 x 12 Coco Lumber 3,360.00 bdf.
2 x 4 x 12 Coco Lumber 3,200.00 bdf.
Asstd. CW Nails 200.00 kgs
1/2" thk. Phenolic Board 100.00 pc/s
Sub-Total
B. Labor
Productivity Rate: Fab., Inst., Rem.
3.50 sq.m. per gday
Foreman 27.00 day/s 1.00
Skilled Laborer 27.00 day/s 32.00
Laborer 27.00 day/s 32.00
Sub-Total
C. Hauling
2 x 2 x 12 Coco Lumber 400.00 pc/s
2 x 3 x 12 Coco Lumber 840.00 pc/s
2 x 4 x 12 Coco Lumber 800.00 pc/s
Asstd. CW Nails 200.00 kgs
1/2" thk. Marine Plywood 100.00 pc/s
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
IV COMMUNAL FAUCETS 250.00 Units
IV - 1. Concrete Works 47.50 cu.m.
A. Materials
Portland Cement 500.00 bags
Washed Sand 50.00 cu.m.
Washed Gravel 3/4" 50.00 cu.m.
Plastic Container ( Capacity 20 lit ) 100.00 pc/s
Sub-Total
B. Labor
Foreman 16.00 day/s 1.00
Skilled Laborer 16.00 day/s 8.00
Common Laborer 16.00 day/s 8.00
Sub-Total
C. Equipment
1 Bagger Concrete Mixer 16.00 day/s 1.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
IV - 2. RSB 1850.00 kgs.
A. Materials
10mm dia. x 6.0m RSB 500.00 pc/s
#16 G.I. Tie Wire 50.00 kg
Sub-Total
B. Labor
Foreman 24.00 day/s 1.00
Skilled Laborer 24.00 day/s 2.00
Common Laborer 24.00 day/s 2.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
IV - 3. Form Works 1.00 lot
A. Materials
2" x 3" x 12' Coco Lumber 600.00 bdf
2" x 2" x 12' Coco Lumber 400.00 bdf
1/4 thk. 4' x 8' Marine Plywood 50.00 pc/s
#3'' CWN 100.00 kg
#2'' CWN 100.00 kg
Sub-Total
B. Labor
Foreman 15.00 day/s 1.00
Skilled Laborer 15.00 day/s 2.00
Common Laborer 15.00 day/s 2.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
IV - 4. Pipe Fittings 1.00 lot
A. Materials
6" x 1/2" Saddle Clamp 70.00 pc/s
4" x 1/2" Saddle Clamp 180.00 pc/s
1/2" HDPE Pipe SDR 13.5 1,500.00 m
1/2''dia. X 6m GI. Pipe S-40 50.00 pc/s
1/2'' dia. HDPE to GI. Male adapter 250.00 pc/s
1/2'' dia. Brass Faucet 250.00 pc/s
1/2'' dia. X 10 '' G.I Nipple 250.00 pc/s
1/2'' dia. 90 deg. GI. Elbow 500.00 pc/s
1/2'' dia. GI. Coupling 500.00 pc/s
Sub-Total
B. Labor
Foreman 16.00 day/s 1.00
Skilled Laborer 16.00 day/s 8.00
Common Laborer 16.00 day/s 8.00
Sub-Total
C. Equipment
Pipe Threader 125.00 day/s 1.00
Sub-Total
Direct Cost
Profit
OCM
Tax
Total Item Cost
SUMMARY
I INTAKE BOX
II PIPELINES
III RESERVOIR
IV COMMUNAL FAUCETS
TOTAL
A DIRECT COST
MATERIALS
EQUIPMENT
LABOR
SKILLED
UNSKILLED
TOTAL ESTIMATED COST
MATERIALS LABOR EQUIPMENT
RATE PER SKILLED UNSKILLED
DAY/ UNIT TOTAL
COST
738,355.99

550.00 2,200.00 2,200.00


300.00 600.00 600.00
2,800.00
2,800.00
252.00
224.00
393.12
3,669.12

5.00 1,000.00 1,000.00


1,000.00

550.00 19,800.00 19,800.00


300.00 1,800.00 1,800.00
21,600.00

1,500.00 9,000.00 9,000.00


9,000.00
31,600.00
2,844.00
2,528.00
4,436.64
41,408.64

20.00 1,600.00
20.00 2,400.00
80.00 80.00
75.00 375.00
4,455.00 4,455.00

550.00 1,100.00 1,100.00


450.00 1,800.00 1,800.00
300.00 1,200.00 1,200.00
4,100.00
8,555.00
769.95
684.40
1,201.12
11,210.47

550.00 2,750.00 2,750.00


450.00 9,000.00 9,000.00
300.00 15,000.00 15,000.00
26,750.00
26,750.00
2,407.50
2,140.00
3,755.70
35,053.20

1,000.00 20,000.00 20,000.00


20,000.00

550.00 1,100.00 1,100.00


450.00 1,800.00 1,800.00
300.00 2,400.00 2,400.00
5,300.00

150.00 147,420.00 147,420.00

147,420.00
172,720.00
15,544.80
13,817.60
24,249.89
226,332.29

300.00 16,500.00
1,000.00 3,000.00
1,000.00 6,000.00
150.00 8,250.00
200.00 2,000.00
1,000.00 1,000.00
36,750.00 36,750.00

550.00 1,650.00 1,650.00


450.00 2,700.00 2,700.00
300.00 7,200.00 7,200.00
11,550.00

2,000.00 6,000.00 6,000.00


6,000.00

150.00 8,250.00
150.00 23,400.00
150.00 46,800.00
2,000.00 2,000.00
80,450.00 80,450.00
134,750.00
12,127.50
10,780.00
18,918.90
176,576.40

235.00 18,800.00
80.00 720.00
100.00 1,000.00
20,520.00 20,520.00

550.00 3,300.00 3,300.00


450.00 2,700.00 2,700.00
300.00 1,800.00 1,800.00
7,800.00

50.00 4,000.00
100.00 100.00
4,100.00 4,100.00
32,420.00
2,917.80
2,593.60
4,551.77
42,483.17

20.00 4,000.00
20.00 8,400.00
20.00 8,000.00
75.00 3,000.00
950.00 14,250.00
37,650.00 37,650.00

550.00 3,850.00 3,850.00


450.00 12,600.00 12,600.00
300.00 8,400.00 8,400.00
24,850.00
50.00 2,500.00
50.00 3,500.00
50.00 2,500.00
8,500.00 8,500.00
71,000.00
6,390.00
5,680.00
9,968.40
93,038.40

40,000.00 40,000.00
1,950.00 1,950.00
500.00 500.00
2,200.00 2,200.00
150.00 300.00
11,235.24 22,470.48
3,093.00 3,093.00
150.00 150.00
70,663.48 70,663.48

550.00 2,200.00 2,200.00


450.00 3,600.00 3,600.00
300.00 2,400.00 2,400.00
8,200.00
1,000.00 1,000.00 1,000.00
1,000.00
3,000.00 3,000.00 3,000.00
3,000.00
82,863.48
7,457.71
6,629.08
11,634.03
108,584.30

27,617,420.31

300.00 18,000.00 18,000.00


550.00 6,600.00 6,600.00
24,600.00
24,600.00
2,214.00
1,968.00
3,453.84
32,235.84

550.00 66,000.00 66,000.00


300.00 2,160,000.00 2,160,000.00
2,226,000.00

2,000.00 20,000.00 20,000.00


20,000.00
2,246,000.00
202,140.00
179,680.00
315,338.40
2,943,158.40
18,248,022.95

1,659.75 8,224,061.25
750.75 8,986,477.50
235.00 229,125.00
500.00 2,000.00
800.00 4,000.00
300.00 900.00
150.00 600.00
500.00 1,000.00
6,000.00 6,000.00
4,000.00 16,000.00
800.00 1,600.00
500.00 1,500.00
500.00 500.00
2,000.00 2,000.00
11,235.24 56,176.20
4,573.00 9,146.00
1,000.00 4,000.00
2,707.00 2,707.00
1,980.00 1,980.00
17,549,772.95 17,549,772.95
550.00 2,750.00 2,750.00
450.00 4,500.00 4,500.00
300.00 6,000.00 6,000.00
13,250.00

685,000.00 685,000.00 685,000.00


685,000.00
18,248,022.95
1,642,322.07
1,459,841.84
2,562,022.42
23,912,209.27

10,000.00 160,000.00
10,000.00 30,000.00
10,000.00 10,000.00
3,500.00 21,000.00
40,000.00 80,000.00
5,000.00 10,000.00
29,000.00 58,000.00
2,700.00 10,800.00
1,400.00 2,800.00
1,375.00 5,500.00
100.00 2,000.00
936.00 5,616.00
400.00 2,400.00
736.00 11,776.00
409,892.00 409,892.00

550.00 3,850.00 3,850.00


450.00 6,300.00 6,300.00
300.00 8,400.00 8,400.00
18,550.00

10,000.00 10,000.00 10,000.00


10,000.00
438,442.00
39,459.78
35,075.36
61,557.26
574,534.40
20.00 13,000.00
300.00 19,500.00
1,000.00 10,000.00
150.00 12,750.00
80.00 800.00
200.00 1,000.00
1,000.00 1,000.00
58,050.00 58,050.00

550.00 7,150.00 7,150.00


450.00 11,700.00 11,700.00
300.00 15,600.00 15,600.00
34,450.00

2,000.00 26,000.00 26,000.00


26,000.00
118,500.00
10,665.00
9,480.00
16,637.40
155,282.40
5,588,561.16

550.00 1,100.00 1,100.00


450.00 450.00 450.00
1,550.00
1,550.00
139.50
124.00
217.62
2,031.12

20.00 1,600.00
20.00 2,400.00
80.00 80.00
75.00 375.00
4,455.00 4,455.00
550.00 550.00 550.00
450.00 900.00 900.00
300.00 600.00 600.00
2,050.00
6,505.00
585.45
520.40
913.30
8,524.15

550.00 2,750.00 2,750.00


450.00 4,500.00 4,500.00
300.00 12,000.00 12,000.00
19,250.00
19,250.00
1,732.50
1,540.00
2,702.70
25,225.20

1,500.00 78,000.00 78,000.00


78,000.00

550.00 2,750.00 2,750.00


450.00 4,500.00 4,500.00
300.00 6,000.00 6,000.00
13,250.00

50.00 135,200.00 135,200.00

135,200.00
226,450.00
20,380.50
18,116.00
31,793.58
296,740.08

300.00 642,582.00
1,000.00 90,000.00
1,000.00 179,000.00
150.00 321,291.00
200.00 6,000.00
1,000.00 10,000.00
1,248,873.00 1,248,873.00

550.00 4,950.00 4,950.00


450.00 32,400.00 32,400.00
300.00 86,400.00 86,400.00
123,750.00

2,000.00 72,000.00 72,000.00


72,000.00

50.00 107,097.00
50.00 234,000.00
50.00 465,400.00
1,000.00 4,000.00
810,497.00 810,497.00
2,255,120.00
202,960.80
180,409.60
316,618.85
2,955,109.25

390.00 280,800.00
235.00 354,850.00
150.00 25,500.00
80.00 20,000.00
400,350.00 400,350.00

550.00 18,150.00 18,150.00


450.00 89,100.00 89,100.00
300.00 59,400.00 59,400.00
166,650.00

500.00 16,500.00 16,500.00


16,500.00

20.00 14,400.00
15.00 22,650.00
10.00 1,700.00
300.00 75,000.00
113,750.00 113,750.00
697,250.00
62,752.50
55,780.00
97,893.90
913,676.40

20.00 32,000.00
20.00 67,200.00
20.00 64,000.00
75.00 15,000.00
1,200.00 120,000.00
298,200.00 298,200.00

550.00 14,850.00 14,850.00


450.00 388,800.00 388,800.00
300.00 259,200.00 259,200.00
662,850.00

10.00 4,000.00
15.00 12,600.00
20.00 16,000.00
300.00 60,000.00
50.00 5,000.00
97,600.00 97,600.00
1,058,650.00
95,278.50
84,692.00
148,634.46
1,387,254.96
1,656,385.40

300.00 150,000.00
1,000.00 50,000.00
1,000.00 50,000.00
200.00 20,000.00
270,000.00 270,000.00

550.00 8,800.00 8,800.00


450.00 57,600.00 57,600.00
300.00 38,400.00 38,400.00
104,800.00
2,000.00 32,000.00 32,000.00
32,000.00
406,800.00
36,612.00
32,544.00
57,114.72
533,070.72

150.00 75,000.00
80.00 4,000.00
79,000.00 79,000.00

550.00 13,200.00 13,200.00


450.00 21,600.00 21,600.00
300.00 14,400.00 14,400.00
49,200.00
128,200.00
11,538.00
10,256.00
17,999.28
167,993.28

20.00 12,000.00
20.00 8,000.00
495.00 24,750.00
75.00 7,500.00
75.00 7,500.00
59,750.00 59,750.00

550.00 8,250.00 8,250.00


450.00 13,500.00 13,500.00
300.00 9,000.00 9,000.00
30,750.00
90,500.00
8,145.00
7,240.00
12,706.20
118,591.20

1,099.00 76,930.00
658.00 118,440.00
24.50 36,750.00
380.00 19,000.00
55.00 13,750.00
185.00 46,250.00
70.00 17,500.00
80.00 40,000.00
80.00 40,000.00
408,620.00 408,620.00

550.00 8,800.00 8,800.00


450.00 57,600.00 57,600.00
300.00 38,400.00 38,400.00
104,800.00

1,000.00 125,000.00 125,000.00


125,000.00
638,420.00
57,457.80
51,073.60
89,778.80
836,730.20

738,355.99
27,617,420.31
5,588,561.16
1,656,385.40
35,600,722.86 23,054,918.43 1,013,650.00 2,792,650.00 306,500.00
3,806,300.00

35,600,722.86
ACTIVITY ANNOTATION PREDECESSOR DURATION (DAYS)
I INTAKE STRUCTURE A -
I - 1. Clearing and Grubbing A1 NONE 2.00
I - 2. Diversion of Water A2 A1 6.00
I - 3. Layout A3 A2 2.00
I - 4. Excavation A4 A3 5.00
I - 5. Handlaid Boulder A5 A6 2.00
I - 6. Concrete Works A6 A7,A8 3.00
I - 7. RSB Works A7 A3 6.00
I - 8. Form Works A8 A3 7.00
I - 9. Pipe Fittings A9 A6 4.00
II PIPE LINES B
II-1. Clearing and Grubbing B1 A3 12.00
II-2.Excavation
Transmission B2a B3a 30.00
Distribution B2b C2 90.00
II-3. Pipe Laying
Transmission B3a B1,A6 5.00
Distribution B3b B2b 15.00
II-4. Installation of Valves
Transmission B4a B3a 2.00
Distribution B4b B3b 5.00
II-5. Valve Box B5 B4b,B4a 13.00
III RESERVOIR C
III- 1. Clearing and Grubbing C1 B3a 2.00
III- 2. Layout C2 C1 1.00
III - 3. Excavation C3 C2 5.00
III - 4. Boulder Fill C4 C3 5.00
III- 5. Concrete Works C5 C4,C6,C7 9.00
III - 6. RSB Works C6 C2 33.00
III - 7. Form Works C7 C2 27.00
IV COMMUNAL FAUCETS D
IV - 1. Concrete Works D1 D2,D3,D4 16.00
IV - 2. RSB D2 B4b 24.00
IV - 3. Form Works D3 B4b 15.00
IV - 4. Pipe Fittings D4 B4b 16.00
Finish F A5,B5,C5,D1 Critical Path - 212 Days

Qty Unit Cost


I INTAKE STRUCTURE
I - 1. Clearing and Grubbing 225.00 sq.m. 3,669.12
I - 2. Diversion of Water - 0 41,408.64
I - 3. Layout 6.00 day/s 11,210.47
I - 4. Excavation 80.00 bdf 35,053.20
I - 5. Handlaid Boulder - 0 226,332.29
I - 6. Concrete Works - 0 176,576.40
I - 7. RSB Works - 0 42,483.17
I - 8. Form Works 3.00 day/s 93,038.40
I - 9. Pipe Fittings - 0 108,584.30
II PIPE LINES
II-1. Clearing and Grubbing - 0 32,235.84
II-2.Excavation 70.00 pc/s 2,943,158.40
Transmission
Distribution
II-3. Pipe Laying 2.00 pc/s 23,912,209.27
Transmission
Distribution
II-4. Installation of Valves - 0 574,534.40
Transmission
Distribution
II-5. Valve Box 975.00 m 155,282.40
III RESERVOIR
III- 1. Clearing and Grubbing 5.00 day/s 2,031.12
III- 2. Layout - 0 8,524.15
III - 3. Excavation 4.00 pcs 25,225.20
III - 4. Boulder Fill - 0 296,740.08
III- 5. Concrete Works - 0 2,955,109.25
III - 6. RSB Works - 0 913,676.40
III - 7. Form Works - 0 1,387,254.96
IV COMMUNAL FAUCETS
IV - 1. Concrete Works 8.00 0 533,070.72
IV - 2. RSB 2.60 m 167,993.28
IV - 3. Form Works 10.00 pc/s. 118,591.20
IV - 4. Pipe Fittings 2,141.94 bags 836,730.20
35,600,722.86

Physical Accomplishment Periodic


Cumulative
Financial Accomplishment Periodic
Cumulative
A1 A2 A3 A4

A7

A8

S A= ANNOTATION
A ES EF t= TIME/DURATION
t LS LF S= SLACK B1
ES= EARLY START
EF= EARLY FINISH
LS= LATE START
LF= LATE FINISH

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20
%RW
0.01% ### ###
0.12% 0 0 0 0 0 0
0.03% 0 0
0.10% 0 0 0 0
0.64%
0.50% 0 0 0
0.12% 0 0 0 0 0 0
0.26% 0 0 0 0 0 0 0
0.31%

0.09% ### ### ### ### ### ### ### ### ### ###
8.27%
0.00%
0.00%
67.17%
0.00%
0.00%
1.61%
0.00%
0.00%
0.44%

0.01%
0.02%
0.07%
0.83%
8.30%
2.57%
3.90%

1.50%
0.47%
0.33%
2.35%
100.00%
### ### 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
- 0.0878% 0.2490% 0.5261% 1.3016%
- 0.0878% 0.3369% 0.8629% 2.1645%
- 31,274.88 88,656.05 187,281.43 463,379
- 31,274.88 119,930.93 307,212.36 770,591
A5

A4 A6 A9

A7

A8

B1 B3a B4a

B2a

C1

21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40 41 42 43
0 0

0 0 0 0

### ###

0 0 0 0 0 0 0 0 0 0 0 0 0 0

0.03 0 0 0 0

0 0 0 0 0.03 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
1.3016% 16.8608% 0.4134% 0.4134% 0.4134%
2.1645% 19.0254% 19.4387% 19.8521% 20.2654%
463,379.47 6,002,578.64 147,157.92 147,157.92 147,1
770,591.83 6,773,170.47 6,920,328.39 7,067,486.31 7,214,6
B5

D2

B2b B3b B4b


D3

D4

C2 C3 C4

C6

C7

44 45 46 47 48 49 50 51 52 53 54 55 56 57 58 59 60 61 62 63 64 65
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0

0 0

###3E-05
0.02%
0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 ###3E-05 0.0002 0 0 0
0.4134% 0.4134% 0.8084% 0.3591%
20.2654% 20.6788% 21.4872% 21.8463%
147,157.92 147,157.92 287,799.84 127,825.15
7,214,644.23 7,361,802.15 7,649,602.00 7,777,427.15
F

D2 D1

D3

D4

C5

66 67 68 69 70 71 72 73 74 75 76 77 78 79 80 81 82 83 84 85 86 87 88 89
0 0 0 0 0 0.001 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0
0 0 0 0.002 0

0 0 0 0.001 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0.001 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0.005 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
91% 2.3715% 1.7459% 1.7459% 1.7459%
463% 24.2178% 25.9637% 27.7096% 29.4555%
127,825.15 844,277.92 621,559.78 621,559.78 621,559.78
7,777,427.15 8,621,705.07 9,243,264.85 9,864,824.64 10,486,384.42
90 91 92 93 94 95 96 97 98 99 100 101 102 103 104 105 106 107 108 109 110 111 112 113
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01


0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0 0 0 0


.7459% 1.4573% 2.5690% 5.9472% 1.3357%
9.4555% 30.9128% 33.4819% 39.4290% 40.7647%
621,559.78 518,800.16 914,597.52 2,117,230.75 475,503.39
10,486,384.42 11,005,184.57 11,919,782.09 14,037,012.84 14,512,516.24
114 115 116 117 118 119 120 121 122 123 124 125 126 127 128 129 130 131 132 133 134 135 136
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
3357% 0.4134% 0.4134% 0.4134% 0.4134%
7647% 41.1780% 41.5914% 42.0047% 42.4181%
475,503.39 147,157.92 147,157.92 147,157.92 147,157.92
14,512,516.24 14,659,674.16 14,806,832.08 14,953,990.00 15,101,147.92
137 138 139 140 141 142 143 144 145 146 147 148 149 150 151 152 153 154 155 156 157 158 159
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0.03 0.03 0.03 0.03 0.03 0.03 0.03

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0.03 0.03 0.03 0.03 0.03 0.03 0.03


0.4134% 0.4134% 0.4134% 13.5713% 20.1503%
42.4181% 42.8315% 43.2448% 56.8161% 76.9665%
147,157.92 147,157.92 147,157.92 4,831,494.49 7,173,662.78
15,101,147.92 15,248,305.84 15,395,463.76 20,226,958.25 27,400,621.03
160 161 162 163 164 165 166 167 168 169 170 171 172 173 174 175 176 177 178 179 180 181 182
0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03

0 0 0 0 0
0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0

0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0


20.1503% 17.0225% 1.3668% 1.3339% 1.3003%
76.9665% 93.9890% 95.3558% 96.6897% 97.9900%
7,173,662.78 6,060,128.66 486,597.84 474,877.42 462,93
27,400,621.03 33,460,749.69 33,947,347.54 34,422,224.96 34,885,15
183 184 185 186 187 188 189 190 191 192 193 194 195 196 197 198 199 200 201 202 203 204
0 0 0

0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0 0 0 0
0 0 0 0 0
0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
1.3003% 0.4340% 0.2658% 0.5615%
97.9900% 98.4240% 98.6898% 99.2513%
462,932.62 154,495.67 94,632.72 199,901.52
34,885,157.59 35,039,653.26 35,134,285.98 35,334,187.50
205 206 207 208 209 210 211 212
0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0
0.5615% 0.1872%
99.8128% 100.0000%
199,901.52 66,633.84
35,534,089.02 35,600,722.86

You might also like