Professional Documents
Culture Documents
EPC Contracts
EPC Contracts
EPC Contracts
Construction (EPC)
Contracts –
Standard Documents
By:
R. K. Shekhawat
Sr. Professor (Projects)
IRICEN, PUNE
EPC Contract Bidding Process
Category Factor
Category 1 0.75
Category 2 0.50
Category 3 1
Category 4 0.75
The Authority shall provide ROW by the date specified for each part of the
Site referred to therein, but in no case later than 180 days of the
Appointed Date, and in the event of delay for any reason other than Force
Majeure or breach of this Agreement by the Contractor, it shall pay to the
Contractor, specified Damages.
The Authority may withdraw any part of Right of Way and the works
forming part of Agreement, upto 10% of the Contract Price.
If the Right of Way is not provided within 240 days of the Appointed
Date, for commencing construction on any part of the Site included in the
Appendix, the affected Works shall be deemed to be withdrawn unless the
Parties agree to the contrary, and such Works shall not be computed for
the purposes of the aforesaid ceiling of 10% of the Contract Price
hereunder.
Damages associated with obligations of Authority
• Damage for not providing ROW (Rs./day/m)
= 0.10 × C × 1/L × 1/N
C = Contract Price (Rs.), L = Length of Project (m),
N = Completion Period (days)
For 100 km long project with completion period of 1000
days & CP Rs. 600 Crore, damage works out to Rs.
6000/day/km.
• For ROB/RUB GAD approval, each ROB will be treated as 1
km of ROW for the purpose of damages.
• For Power/Traffic block, damage rate would be Rs.
1000/day for each hour of block not provided.
• Aggregate damages payable as above shall not exceed
2.5% of the contract price.
Damages associated with obligation of Contractor