Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 7

EMPLOYER: CONSULTANT: CONTRACTOR:

M/S.Oman Tourism M/S.WS Atkins & Partners Overseas M/S.Larson &


Development Company Toubro Oman LLC
SAOC

Project No.: Document No.: Rev.: Date:

5073635 00 28/06/09

2nd ASIAN BEACH GAMES

METHOD STATEMENT FOR


BMS SYSTEM INSTALLATION

Prepared by: Reviewed by: Approved by: Approved by:

Mr.Nayankumar Mr. Mr.


(EMPLOYER’S
Dt. 28/06/09 Dt. Dt. REP.)
Dt.
INDEX

1.0 PURPOSE

2.0 INTRODUCTION

3.0 REFERENCES

4.0 DEFINITIONS

5.0 RESPONSIBILITIES

6.0 EQUIPMENT

7.0 PROCEDURE

8.0 SAFETY

9.0 DOCUMENTATION

Page 2 of 7
REVISION CONTROL SHEET

Sr. Rev. Issue Issue


Description
No. No. No. Date
1

Page 3 of 7
1.0 PURPOSE

The purpose of this method statement is to establish, monitor and control all
activities of chiller Building Management System installation Works.

2.0 INTRODUCTION

The procedure covers the installation & testing activities pertaining to HVAC
which are listed below for construction of "2nd Asian Beach Games 2010”.

- Building Management System

3.0 REFERENCES

3.1 Project Specification section 15910


3.2 Project Quality Plan
3.3 Approved construction drawing
3.4 Codes & standards

4.0 DEFINITIONS
4.1 Company : Oman Tourism Development Company SAOC
4.2 Consultant : WS Atkins & Partners Overseas
4.3 Contractor : Larson & Toubro Oman LLC

5.0 RESPONSIBILITIES:

Project consultant shall be responsible for coordination with Project engineer


and organization for the necessary resources & to ensure the works carried out
meeting the project quality requirement.

Project Engineer shall be responsible for planning & coordinating of day to day
work activities & notify the next day work plan to all concern including the
QA/QC Department.

QC Engineer / Inspector shall be responsible for overall coordination and


inspection of all Plumbing & Drainage activities. This includes but not limited to
notifying the Contractor and Coordination for all Inspection witness, prepare
stage wise inspection reports and get them signed by all concern personnel,
filing and indexing the same.

6.0 EQUIPMENT

Mechanical Tool Bag consisting of Measuring tape, Spirit level, Drill Machine &
Wire cutter, Disc cutter, Hex blade with mounting bracket etc.

Page 4 of 7
7.0 PROCEDURE

Procedures of above listed method statements in scope are described as below

7.1 BUILDING MANAGEMENT SYSTEM

1. Mark BMS location at site based on coordinated layout.

2. Check approved BMS schedule & approved shop drawings for correct Model of
BMS system.

3. Ensure that BMS system shall functioned the Operating, monitoring, data
evaluation, standerised forms, display function, management function, access
control, and commissioning & test function.

4. Ensure for necessary BMS control & monitoring outstations are available on
site.

5. Ensure for final connection of all BMS Field devices cabling including BMS
local area networks.

6. Check for the field cabling interface between all other system & BMS system.

7. Ensure that BMS shall control & monitor the building mechanical air handling
units, cooling plants using Direct Digital techniques.

8. Check for room thermostat, pressure switches, air flow switches, water flow
switches, level switches & detectors, humidity detectors, pressure detectors as
per approved drawing & specification & shall be interlocked to BMS.

9. Ensure that BMS shall interface with chiller control system to allow energisation
/deenesigation of chilled water system, selection of chiller sequence, primary
chilled flow temperature set point adjustment & to monitor faults on any chiller.

10. Ensure that all modulating & motorized control valves are selected as per
approved drawing & as per specifications.

11. Check for VAV boxes or FCU shall be accessed via floor layout graphics & shall
have local controller wired on LAN & communicate to BMS via LAN interface
unit.

12. Ensure that outstation shall be housed within wall or ceiling enclosures i.e. for
FCU, VAV boxes, Heater batteries etc.

13. Check for all termination BMS interface cabling at MCC termination strip in all
packaged equipment with self contained MCC’s.

Page 5 of 7
14. Check for the supply & connection of all control temperatures, humidity &
pressure detectors, damper actuators, and valve actuators within the ducts to
BMS system

15. Check for the level & routing of electrical cables passing through fire
compartments.

16. Ensure that the route of cable tray & cables is free from any disturbances.

17. The total BMS system shall be capable to operate & monitor the Air-handling
units, pump & booster sets, energy & water meters, chiller control system, heat
pump control system etc.

18. Ensure for Chiller are with flow switches, control board, sound reduction kit,
microprocessor based controllers for loading & unloading & digital display
module with BMS capability for future.

19. Check for controls of chillers that are with starter to limit starting current, short
cycling protection, temperature controller, freze up protection, thermostat,
circuits’ breakers, contactors, relay & field power & control wiring terminal
boxes.

20. Ensure free access to filter & motor for future maintenance.

21. Ensure that unit’s terminal box (Control Panel) free access to maintenance.

8.0 SAFETY

8.1 Effective supervision regarding safety shall be provided during HVAC activities.

8.2 Workers shall wear appropriate PPE while working on the slab & shall follow tall
the primary safety procedures.

8.3 Employees shall wear safety helmets, shoe, safety glass & over coat while
entering in to working premises.

8.4 Employees shall use movable scaffolding while working above 2.5 Meters with
proper safety belt.

8.5 Proper house keeping should be maintained.

Page 6 of 7
9.0 DOCUMENTATION

9.1 Inspection Request

9.2. Risk Assessment

- End of Document -

Page 7 of 7

You might also like