EMPLOYER: CONSULTANT: CONTRACTOR:

M/S.Oman Tourism M/S.WS Atkins & Partners Overseas M/S.Larson &


Development Company Toubro Oman LLC
SAOC

Project No.: Document No.: Rev.: Date:

5073635 00 24/06/09

2nd ASIAN BEACH GAMES

METHOD STATEMENT FOR


CONDENSATE DRAIN

Prepared by: Reviewed by: Approved by: Approved by:

Mr.Nayankumar Mr. Mr.


(EMPLOYER’S
Dt. 24/06/09 Dt. Dt. REP.)
Dt.

Page 1 of 6
INDEX

1.0 PURPOSE

2.0 INTRODUCTION

3.0 REFERENCES

4.0 DEFINITIONS

5.0 RESPONSIBILITIES

6.0 EQUIPMENT

7.0 PROCEDURE

8.0 SAFETY

9.0 DOCUMENTATION

Page 2 of 6
REVISION CONTROL SHEET

Sr. Rev. Issue Issue Description


No. No. No. Date
1

Page 3 of 6
1.0 PURPOSE

The purpose of this method statement is to establish, monitor and control all
activities before concrete work to do condensate drain as per the HVAC
requirements.

2.0 INTRODUCTION

The procedure covers the activities pertaining to providing sleeves & openings
as per project requirements for construction of "2 nd Asian Beach Games 2010".

3.0 REFERENCES

3.1 Project Specification section 15720 & 15730


3.2 Project Quality Plan
3.3 Approved construction drawing / Builders Work Drawing
3.5 Codes & standards

4.0 DEFINITIONS

4.1 Company : Oman Tourism Development Company SAOC


4.3 Consultant : WS Atkins & Partners Overseas
4.4 Contractor : Larson & Toubro Oman LLC

5.0 RESPONSIBILITIES:

Project Manager shall be responsible for coordination with Project engineer and
organization for the necessary resources & to ensure the works carried out
meeting the project quality requirement.

Project Engineer shall be responsible for planning & coordinating of day to day
work activities & notify the next day work plan to all concern including the
QA/QC Department.

QC Engineer / Inspector shall be responsible for overall coordination and


inspection of all HVAC sleeves & openings. This includes but not limited to
notifying the Contractor and Coordination for all Inspection Witness and Hold
Points, prepare stage wise inspection reports and get them signed by all
concern personnel, filing and indexing the same.

6.0 EQUIPMENT

Mechanical tool kit with primary tools (i.e. Measuring Tape, Hammer, Spirit
level, wire cutter, Hex blade with mounting bracket etc.)

Page 4 of 6
7.0 PROCEDURE

7.1 Check and ensure all drawings used for installation are latest and approved for
construction.

7.2 Mark the drainage pipe routing and support location as per approved drawing.

7.3 Check the co – ordination of piping layout with other services and decide pipe
route with minimum bends / offsets.

7.4 Check for the proper U-trap is provided wherever shown in the approved
drawing.

7.5 Check and ensure sufficient clearance around pipe for applying insulation

7.6 Cut proper size of the length and debar. Put proper size of insulation.

7.7 Ensure to apply proper glue at the joint of rubber tube insulation.

7.8 Provide proper masonry support for roof condensate piping.

7.9 Drill the holes for fixing Supports

7.10 Fix the Anchor fasteners, threaded rods and supports, Threaded rod length
shall be sufficient to allow for leveling of piping

7.11 Cut the pipes accurately to measurement determined at site

7.12 Prepare the pipe ends according to the type of joints, and fix it properly.

8.0 SAFETY

8.1 Effective supervision regarding safety shall be provided during HVAC activities.

8.2 Workers shall wear appropriate PPE while working on the slab & shall follow tall
the primary safety procedures.

8.3 Employees shall wear safety helmets, shoe, safety glass & over coat while
entering in to working premises.

8.4 Employees shall use movable scaffolding while working above 2.5 Meters with
proper safety belt.

8.5 Proper house keeping should be maintained.

Page 5 of 6
9.0 DOCUMENTATION

9.1 Inspection Request

9.2. Risk Assessment

- End of Document -