Minutes of Site Progress and Technical Meeting 79: Project No. MOM. No. Page 1 of 2
Minutes of Site Progress and Technical Meeting 79: Project No. MOM. No. Page 1 of 2
AGENDA :
NEXT MEETING
Date : Wednesday 23rd October 2019 /
11.00am
Agenda :
Progress of Work
Participants :
AEC, MBCC, FALCON,EMT,EAS
1
0 0 7 9
PROJECT: Palm furnished apartments 2B+G+8 Floor +9th (P.H +pool)
CLIENT : H.E SHAIKH MOHAMMED BIN ALI BIN RASHID AL NUAIMI Project No. MOM. No.
Consultant: M/s AL ABBASI ARCH & Eng. Consultants Page 2 of 2
2
0 0 7 9
PROJECT: Palm furnished apartments 2B+G+8 Floor +9th (P.H +pool)
CLIENT : H.E SHAIKH MOHAMMED BIN ALI BIN RASHID AL NUAIMI Project No. MOM. No.
Consultant: M/s AL ABBASI ARCH & Eng. Consultants Page 3 of 2
3 MEP
1. Wiring works completed for 1-8th floors at studios, 1&2 bed room also started with
provided ID, 1-8 floors completed, IR to be done..
2. Drainage high level for 7 floors completed, 8th- partially completed, B1 and B2 HL 80%
completed, vertical pipe and WC opening closing started with concrete material. G.F
to 2nd floor completed, 3rd in progress.
3. PPR connection in wet area high level 1st floor 90% completed, 2nd floor pressure test
remaining, and 3rd floor 90% completed, 4th floor started, corridor balance.
4. 8th floor shaft diversion completed. PPR 2 risers completed with pressure test, 1st to
4th floor completed, 5th 60%. Transfer line PPR pipes for B1and B2 -70% done.
5. Fire alarm cable and emergency works are in progress IR completed for 9 floors, B1
emergency completed, B2 80% completed.
6. LPG detection cable started at ground floor high level. 85% completed.
7. EMT started their 2nd fix at basements; F.F Main line at B1-95%, B2 -85% completed.
Branches at B1-90%, B2-85% completed, GSM cable tray B2-95%, B1 40%.B2 pressure
completed. Main line from pump room at B1 and B2 90% completed. Power cable tray
at B1 60% completed
8. Firefighting works started, sprinkler riser work completed up to 8 th floor, 2nd FHR riser
completed up to 8th floor, main header branches works at 1st to 8th floor completed
with pressure test, 9th floor 50% completed.
9. Containment work for low current in progress, 2nd to 7th floor cable pulling 80% done,
CCTV structuring cable work completed for 1 to 8 floors. 6-8 coring work remaining.
10. FCU cable received and MIR approved, connections will be started.
11. GRMS sample and technical details are submitted on 9/10, selection of services and
finalization needed from client.
12. Electrical Service room and telephone riser completed for 1-8 floors, IR approved,
branches at 2, 3 and 4th floor started.
13. EMT submitted the variation supporting details with updated letter by today, 16/10.
14. EMT informed that the FIC inspection request to DM has been submitted, breakdown
for the invoice has been sent to EAS by mail.
15. EMT reminded that estimation for all MEP services have to be paid by the client as
soon as possible. Updated estimate will be sent by EMT if any change in final amount.
16. EMT raised their concern regarding the delay in the payments.
17. EMT raised their concern about any change in completed concealed mixer works in
bathroom survey report have been made and will be submitted as a RFI for approval.
18. Solar panels are delivered at the site and MIR approved.
4 LIFT
1. Passenger lift 1&2 is decided as fire lift and proper signage to be provided by MBCC.
2. Melco agreed to do the hook work for scissor lift and get the 3 rd party certificate.
3. Melco requested MBCC to complete the jam grouting works to proceed other works,
4. Cabin installation for service lift completed.
5. MIR for scissor lift approved.
6. AEC asked MBCC to finish the scissor lift civil works to start the Lift installation works.
3
0 0 7 9
PROJECT: Palm furnished apartments 2B+G+8 Floor +9th (P.H +pool)
CLIENT : H.E SHAIKH MOHAMMED BIN ALI BIN RASHID AL NUAIMI Project No. MOM. No.
Consultant: M/s AL ABBASI ARCH & Eng. Consultants Page 4 of 2
5 General:
1. Material and shop drawing log sheet to be submitted week.
2. Monthly report and look ahead program submitted by all parties.