CIVIL - BILL OF QUANTITIES 03.08.

19

Detail Estimation for the Guest House and Common Rest Room

Material+L
S.No. Description of works Qty Unit Unit Amount
abour rate
SUB STRUCTURE
1 Earth work Excavation
Earth work excavation in hard soil after
clearing of vegetation and debris including
shoring,strutting, bailing, pumping out water 64.2 Cu.m Cu.m
and disposal, spreading/stacking the
excavated material.etc., included footing
excavation,alround plinth beam area.

2 Sand Filling (Backfilling of excavated area) 33.8 Cu.m Cu.m


3 100 mm thick P.C.C 1:4:8 filling in footing. 4.01 Cu.m Cu.m
4 75 mm thick P.C.C 1:4:8 in Plinth Beam. 2.90 Cu.m Cu.m
100mm thick P.C.C 1:2:4 - for flooring the
5 10.36 Cu.m Cu.m
entire area
75mm thk. Bed of dry Brick ballast of
6 40mm size wall rammed and consolidated 3.20 Cu.m Cu.m
and shall be ground with fine sand
50mm thk. P.C.C 1:2:4 Above plinth
7 2.10 Cu.m Cu.m
protection
SUPER STRUCTURE
8 Brick masonry
Upto Ground Floor Roof
i. Providing and laying 230mm thick brick
masonry work in CM 1:5 including all 37.9 Cu.m Cu.m
necessary scaffolding, curing etc
ii. Providing and laying 115mm thick brick
masonry work in CM 1:5.including all 8.4 Cu.m Cu.m
necessary scaffolding, curing etc.
Above Ground Floor Roof
i. Providing and laying 230mm thick brick
masonry work in CM 1:5 including all 37.4 Cu.m Cu.m
necessary scaffolding, curing etc.
ii. Providing and laying 115mm thick brick
masonry work in CM 1:5.including all 6.6 Cu.m Cu.m
necessary scaffolding, curing etc.
iii. Providing and laying 230mm thick brick
masonry work (Parapet wall) in CM 1:5 13.3 Cu.m Cu.m
including all necessary scaffolding, curing etc.
9 Cement plaster
Upto Ground Floor Roof
i. Providing & laying smooth cement plaster of
6mm thick in ratio 1:3 at all heights including
Scaffolding for ceiling & RCC surface etc 89.8 Sq.m Sq.m
complete.
Material+L
S.No. Description of works Qty Unit Unit Amount
abour rate
ii. Supplying and Providing 12 mm cement
plaster of mix: 1:6 (1 cement : 6 fine sand)for
all internal walls inclusive of providing and
fixing 150 mm wide chicken wire mesh at the
junctions of brick wall with R.C columns and 378.6 Sq.m Sq.m
beams with appropriate nails and also along
the places where the electrical Conduit pipes
are embedded in Brickwork.

iii. Supplying and Providing 18 mm cement


plaster 1:5 (1 cement: 5 coarse sand) and
mixed with approved water proofing
compound 2% by weight of cement and 199.4 Sq.m Sq.m
finished smooth on the external surface of
buildings for all heights and levels.
Upto First Floor Roof
i. Providing & laying smooth cement plaster of
6mm thick in ratio 1:3 at all heights including
Scaffolding for ceiling & RCC surface etc 83.8 Sq.m Sq.m
complete.
ii. Supplying and Providing 12 mm cement
plaster of mix: 1:6 (1 cement : 6 fine sand)for
all internal walls inclusive of providing and
fixing 150 mm wide chicken wire mesh at the
junctions of brick wall with R.C columns and 317.6 Sq.m Sq.m
beams with appropriate nails and also along
the places where the electrical Conduit pipes
are embedded in Brickwork.
iii. Supplying and Providing 18 mm cement
plaster 1:5 (1 cement: 5 coarse sand) and
mixed with approved water proofing
compound 2% by weight of cement and 157.9 Sq.m Sq.m
finished smooth on the external surface of
buildings for all heights and levels.
Parapet wall
i. Supplying and Providing 12 mm cement
plaster of mix: 1:6 (1 cement : 6 fine sand)for
all internal walls inclusive of providing and
fixing 150 mm wide chicken wire mesh at the
junctions of brick wall with R.C columns and 57.7 Sq.m Sq.m
beams with appropriate nails and also along
the places where the electrical Conduit pipes
are embedded in Brickwork.
Material+L
S.No. Description of works Qty Unit Unit Amount
abour rate
ii. Supplying and Providing 18 mm cement
plaster 1:5 (1 cement: 5 coarse sand) and
mixed with approved water proofing
compound 2% by weight of cement and 60.0 Sq.m Sq.m
finished smooth on the external surface of
buildings for all heights and levels.

Staircase
Supplying and Providing 18 mm cement 23.9 Sq.m Sq.m
plaster 1:5 (1 cement: 5 coarse sand) and
mixed with approved water proofing
compound 2% by weight of cement and
finished smooth on the external surface for
staircase
For Loft & Sunshade
Supplying and Providing 12 mm cement
plaster of mix: 1:6 (1 cement : 6 fine sand)for
all Sun shade slab, Loft slab etc.., 100.4 Sq.m Sq.m
complete.
10 Painting / white washing (2 coats)
Upto Ground Floor Roof
i. Supplying and applying single coat of ACE
paint including a coat of primer, necessary
scaffolding and surface preparation of etc for 89.8 Sq.m Sq.m
ceiling.
ii. Supplying & applying two coats of Acrylic
Premier Emulsion paint on new surface
including cleaning, applying a coat of
required primer, necessary surface preparation 378.6 Sq.m Sq.m
with Birla Wall Care Putty etc. complete for
internal surfaces.
iii. Supplying & applying two coats of Acrylic
Premier Emulsion paint on new surface
including cleaning, applying a coat of
required primer, necessary surface preparation 199.4 Sq.m Sq.m
with Birla Wall Care Putty etc. complete for
external surfaces.
Upto First Floor Roof
i. Supplying and applying single coat of ACE
paint including a coat of primer, necessary
scaffolding and surface preparation of etc for
83.8 Sq.m Sq.m
ceiling.
ii. Supplying & applying two coats of Acrylic
Premier Emulsion paint on new surface
including cleaning, applying a coat of
required primer, necessary surface preparation 317.6 Sq.m Sq.m
with Birla Wall Care Putty etc. complete for
internal surfaces.
Material+L
S.No. Description of works Qty Unit Unit Amount
abour rate
iii. Supplying & applying two coats of Acrylic
Premier Emulsion paint on new surface
including cleaning, applying a coat of
required primer, necessary surface preparation 157.9 Sq.m Sq.m
with Birla Wall Care Putty etc. complete for
external surfaces.
Parapet wall
i. Supplying & applying two coats of Acrylic
Premier Emulsion paint on new surface
including cleaning, applying a coat of
required primer, necessary surface preparation 57.7 Sq.m Sq.m
with Birla Wall Care Putty etc. complete for
internal surfaces.
ii. Supplying & applying two coats of Acrylic
Premier Emulsion paint on new surface
including cleaning, applying a coat of
required primer, necessary surface preparation 60.0 Sq.m Sq.m
with Birla Wall Care Putty etc. complete for
external surfaces.
For Loft & Sunshade
i. Supplying and applying single coat of ACE
paint including a coat of primer, necessary
scaffolding and surface preparation of etc for 100.4 Sq.m Sq.m
Sun shade slab and Loft slab

11 Pavior
Ground Floor
i. Providing and laying polished ceramic tiles
for flooring (Security cabin) of size 2’0”x2’0”
of Asian or equivalent, (colour to be
approved by the clients) over a bedding of
minimum 20mm thk.1:3 cement mortar & 76.2 Sq.m Sq.m
finishing of joints etc all complete. (Floor
area ) Preferred Brands - Somany (or)
Khajaria (or) Nitco and colour of tiles will
be chosen at the time of construction
First Floor
i. Providing and laying polished ceramic tiles
for flooring of size 2’0”x2’0” of Asian or
equivalent, (colour to be approved by the
clients) over a bedding of minimum 20mm
thk.1:3 cement mortar & finishing of joints 78.1 Sq.m Sq.m
etc all complete. (Floor area ) Preferred
Brands - Somany (or) Khajaria (or) Nitco
and colour of tiles will be chosen at the time
of construction
Material+L
S.No. Description of works Qty Unit Unit Amount
abour rate
Toilet Floor
i. Providing and laying of anti skid ceramic
tiles of Johnson make or equivalent over
a bedding of 1:3 cement mortar of 20 mm
thick, including finishing of joints etc all 19.3 Sq.m Sq.m
complete (toilet, sitout & service)(BC
32/SFT)

12 Weathering coarse
Weathering coarse 100mm thick and Terrace
flooring with Brickbat Coba and providing
89.8 Sq.m Sq.m
with water proofing chemical ( Brand - Nito
bond-SBR)
13 JOINERY ITEMS
i. Main Door -MD (1050 X 2100) 4 Nos Nos
ii. Door-D1 (900 X 2100) 5 Nos Nos
iii. Door-D2 (750 X 2100) 6 Nos Nos
iv. Window- W (1200 X 1200) 14 Nos Nos
v. Window- W1 (900 X 1200) 6 Nos Nos
vi. Ventilator- V (600 X 600) 6 Nos Nos
vii. European Water Closets-EWC 6 Nos Nos
viii. Wash Basin 6 Nos Nos
ix. Exhaust Fan QR Nos Nos
SHUTTERING QUANTITY
14 Providing and fixing plywood centering
and shuttering in RCC footings, columns,
portal column,beams, lintels, sunshades, 838.1 Sq.m Sq.m
portal frames, slabs, walls, drops, etc,
keeping the same in position.
CONCRETE QUANTITY
15 R.C.C. M-20 (1:1.5:3) Grade
Providing, mixing & placing in position for
all types of structures using 20 mm and down
sized graded coarse aggregate including
proper vibration,curing but excluding
formwork & reinforcement in foundation &
in super structure.( Preferred Brands of
Cement - Ultratech Cement)
i. Footing 12 Cu.m Cu.m
ii. Column 16 Cu.m Cu.m
iii. Plinth Beam 9 Cu.m Cu.m
iv. Slab 24 Cu.m Cu.m
v. Roof Beam 19.1 Cu.m Cu.m
vi. Staircase 8.7 Cu.m Cu.m
Total volume of concrete 88.4 Cu.m
Material+L
S.No. Description of works Qty Unit Unit Amount
abour rate
STEEL QUANTITY
16 Fe500 Steel - Reinforcement
Providing, fixing, straightening, cleaning,
cutting, bending, lifting, placing and tying in
position of reinforcement for rcc works in full
structures (insitu) with black annealed
binding wire of 18-20 gauge & ms rods
confirming to IS
i. Footing
Dia of Bar Y12 0.64 MT MT
ii. Column
Dia of Bar Y8 0.33 MT MT
Dia of Bar Y12 0.07 MT MT
Dia of Bar Y16 0.98 MT MT
Dia of Bar Y20 1.54 MT MT
iii. Plinth beam.
Dia of Bar Y8 0.33 MT MT
Dia of Bar Y12 0.38 MT MT
Dia of Bar Y16 0.38 MT MT
Dia of Bar Y20 0.15 MT MT
iv Roof Slab
Dia of Bar Y10 3.00 MT MT
v Roof Beam
Dia of Bar Y8 0.71 MT MT
Dia of Bar Y12 0.43 MT MT
Dia of Bar Y16 1.10 MT MT
Dia of Bar Y20 0.09 MT MT
Dia of Bar Y25 0.12 MT MT
vi. Staircase
Dia of Bar Y8 0.14 MT MT
Dia of Bar Y12 0.06 MT MT
Dia of Bar Y16 1.10 MT MT
vii Loft
Dia of Bar Y8 0.09 MT MT
viii Sunshade
Dia of Bar Y8 0.19 MT MT
viii Lintel Beam
Dia of Bar Y8 0.13 MT MT
Dia of Bar Y10 0.04 MT MT

For all works in the building ( Preferred


11.99 MT MT
Brands - Pulkit or Ponsuriya or SSI)