Professional Documents
Culture Documents
Analysis, Design, and Detailing of Shear Walls and MRFs
Analysis, Design, and Detailing of Shear Walls and MRFs
Analysis, Design, and Detailing of Shear Walls and MRFs
FACULTY OF ENGINEERING
Project Title: Analysis, Design, and Detailing of Shear Walls and MRFs
Semester: Spring
____________________________
Student Signature
Table of Content
ii
Model Modifications
Conclusion
b. Conclusion ................................................................................................................................ 60
iii
List of Tables
List of Figures
iv
Figure 8 – X – Direction Applied Load ............................................................................................ 25
Figure 14 – Shear Wall Section (Uniform Reinforcement Hand Calculations) (4th Floor) .......................... 43
Figure 15 – Shear Wall Section (Uniform Reinforcement ETABS) (4th Floor) ........................................ 43
Figure 16 – Shear Wall Section (T/C Reinforcement ETABS) (4th Floor) ............................................... 43
v
Figure 32 – C30x70 Rebar Rendered View ...................................................................................... 54
vi
This Page Intentionally Left Blank
vii
Project Plans, Structural Elements, and Material Details
This report covers the design of a 6 story building structural system. The building consists of a
basement 3 meters high and 5 floors each 3.25 meters high. There is also a roof extension (3 m) to
allow access to the roof top. The basement is surrounded by 25 cm retaining walls. The building is
expected to resist seismic loads using a dual system (to be verified later) made up of shear walls and a
This building is located in seismic zone 3 and soil classification is Sb. Seismic analysis and designs
will be done in accordance to UBC ‘97 and ACI 318M - 14. All modeling will be done using ETABS
NOTE:
difference is the
wall thickness
changes from 25
cm to 20 cm after
-1-
c. Elevation View (with Dimensions)
-2-
Concrete Unit Weight (g) = 2500 Kg/cm3
Dummy beams (B20x20) will be used in the ETABS model for load transferring purposes, but
will have no effect on the building mass by assigning them a modified concrete material.
Façade Claddings = 750 Kg/m2 (per surface area of wall and include 1 m skirt on roof top)
Staircase Equivalent Loads = 2.5 tons DL and 1.5 tons LL as point loads on 4 corners of stairwell
NOTE: Some of these loads where not included in the original ETABS model and are not reflected in the
floor weight, Ta, and Tb calculations. They were added later for the purpose of shear wall and
MRF designs.
-3-
The following load combinations are used in this building structure (for strength design):
All other details can be found in the completed ETABS model corresponding to this project.
e. Project Requirements
The following requirements will all be covered throughout the rest of this report in the sequence listed
below.
Calculate the Equivalent Static Seismic Force (Base Shear) for the building manually using Ta,
Get the floor displacements of the CM from ETABS, and re-calculate the Equivalent Static
Seismic Force (Base Shear) for the building using Tb manually, and compare it with ETABS
Verify if the Seismic loads resisting system can be classified as a Dual System in both directions,
-4-
Design the structural wall on Axis D, using Interaction Diagram Charts, and provide complete
wall reinforcement details (longitudinal and horizontal). Compare reinforcement with ETABS
using the "Uniform Reinforcing Design" concept and "Simplified T and C" Concept.
Verify the cross sections of all beams and columns, and propose changes if necessary.
Provide complete reinforced concrete design of the Moment Resisting Frame members on Axis 5,
for the first floor with application of all ACI 318M - 14 chapter 18 regulations.
R = 8.5 (Assuming both directions are Dual System – Shear Walls and SMRF)
-5-
c. Floor Weights (ETABS)
After modeling the entire structure on ETABS and applying all the required loads and seismic
-6-
d. Floor Weights (Hand Calculations)
-7-
-8-
-9-
- 10 -
- 11 -
e. Base Shear and Force Distribution using Ta (ETABS)
The following results are obtained from ETABS using only Ta as the fundamental period. The results
are seen for the X and Y directions even though both directions have the same values.
- 12 -
- 13 -
f. Base Shear and Force Distribution using Ta (Hand Calculations)
- 14 -
- 15 -
These results are from an excel spreadsheet
- 16 -
g. Building Deflections due to Ta (ETABS)
The following data is obtained from the ETABS model report and are based on the seismic loads due
to Ta. These values are the displacement of each floor’s center of mass in the X and Y directions.
- 17 -
Figure 7 – ETABS Model Deformation (Mode 3)
Next, we need to calculate all the inelastic drifts and check if they are within the allowable limits
- 18 -
Y – Direction Drift Check
Floor Elastic Drift (m) Inelastic Drift (m) Inelastic Drift Limit (m) OK / NOT OK
Roof Extension 0.002158 0.01284 0.08125 OK
Roof Top 0.001858 0.011055 0.08125 OK
4th Floor 0.002234 0.013292 0.08125 OK
3rd Floor 0.002479 0.01475 0.08125 OK
2nd Floor 0.002396 0.014256 0.08125 OK
1st Floor 0.001678 0.009984 0.08125 OK
Ground Floor 0.000158 0.00094 0.08125 OK
Basement - - - -
It is seen that this structure does not have any inelastic drift problems in both directions and so no
modifications are required to be done to the deformations. The deformations in table 3 will now be used
It is also worth noting that the structure also does not have any torsional irregularity (Type 1 –
Plan Irregularity) in either direction on any floor and so there is no need to increase the accidental
The following results are obtained from ETABS using the programs calculated T as the fundamental
period (either Ta or Tb, based on ETABS calculations). The results are seen for the X and Y directions
- 19 -
- 20 -
- 21 -
i. Base Shear and Force Distribution using Tb (Hand Calculations)
- 22 -
- 23 -
- 24 -
Seismic Loads Resisting System
In order to determine the frame participation ratio so that the seismic resisting system can be classified
as dual or shear walls we need to create a modified ETABS model of the building by removing all applied
loads, seismic effects, and entire basement floor. The center of rigidity is identified (XCR = 8.7934 m and
YCR = 6.9294 m) at the roof top (final full plan floor) and 100 ton loads are placed in each direction. The
corresponding reactions are then checked and a frame participation can be deduced.
If the frames resist at least 25% of the total base shear in a given direction then the system in that
direction is classified as dual, if not then it is classified as a shear wall system. Certain conditions can be
The figure below shows the applied load in the X direction and the areas enclosed in red boxes are the
- 25 -
Figure 9 – X – Direction Reactions
Shear Wall = 96.9 Ton MRFs = 3.10 Ton Controlling System(s) = Shear Walls
The figure below shows the applied load in the Y direction and the areas enclosed in red boxes are the
- 26 -
Figure 11 – Y – Direction Reactions
Shear Wall = 79.82 Ton MRFs = 20.18 Ton Controlling System(s) = Dual (Imposed)
Since the MRF resists approximately 20% of the base shear in the Y direction. It will be assumed
that this system is a dual system and the shear in this direction resisted by the frame will be increased by a
ratio of 1.25 or 25 / 20. This increase will only be done for the purpose of MRF design in the Y direction.
d. Summary of Results
Therefore, the following systems will be used in each direction for the purpose of designing:
- 27 -
ETABS Model Modifications
The following modifications where noted after preliminary analysis of the original ETABS model.
These modifications were applied before shear wall and MRF designs.
2. Ec = 2526.71 Kg/mm2
This section will cover the design and detailing of the shear wall along grid line D using various
methods and techniques. The shear wall will be designed from the ground floor till the 4th floor, and
3 unique designs will be done using hand calculations for efficient results. The table below
summarizes the wall loads and the controlling loads to be used for each design.
- 28 -
b. Modifications to ETABS Model
that direction.
Figure 12 – Plan View of Frame Moment Releases
- 29 -
c. Uniform Reinforcement Design (Hand Calculations)
- 30 -
- 31 -
- 32 -
/m
- 33 -
- 34 -
- 35 -
- 36 -
- 37 -
- 38 -
- 39 -
- 40 -
d. Uniform Reinforcement Design (ETABS)
The shear wall along grid line D will now be designed level by level using the uniform
reinforcement design concept in ETABS. The bar spacing will be fixed to 300 mm and a concrete
cover of 40 mm will be used. The bar diameter will be varied at each level as the loadings decrease to
NOTE: Detailing’s for the above ETABS results will be shown at the end of the shear wall design section.
Only one longitudinal section will be drawn since for each level the only thing that changed is the
- 41 -
e. Simplified T/C Design (ETABS)
The shear wall along grid line D will now be designed using the tensions / compression concept in
ETABS. The two side columns are included in the shear wall design by assigning them the same pier ID
The design showed that the compression boundary elements required no steel, but the steel in the
tension boundary elements will be used on both sides. This design does not account for minimum
reinforcement used in-between boundary elements but this will be shown in the section detailing.
NOTE: Detailing’s for the above ETABS results will be shown at the end of the shear wall design section.
Only one longitudinal section will be drawn since for each level the only thing that changed is the
- 42 -
f. Design Detailing and Comparisons
20
Figure 14 – Shear Wall Section (Uniform Reinforcement Hand Calculations) (4th Floor)
20
NOTE: Typical cross-section views of the wall showing transversal steel can be seen in the “Shear Wall
Hand Calculations” found in the previous section. Boundary element (BE) tie spacing will be
selected as the lesser value between shear wall requirements and SMRF requirements.
- 43 -
Beam and Column Verifications
The only beam failure present in the ETABS model is due to shear. Beam widths will be increased to
overcome the shear failure as a first measure of solving the issue, since shear resistance is more sensitive
B3 – C3 (4th Floor)
The column failures present in the ETABS model are BCC (Beam Column Capacity) and JS (Joint
Shear). These failures are particular to a SMRF frame and need to be satisfied to achieve an adequate
design. All columns on the last floor will be released on their upper ends since it is hard to achieve a
The table below summarizes all the beams and columns that were modified to overcome the various
failures:
- 45 -
18 A4 C 3rd to 4th BCC & JS C40x40 C60x60
19 C4 C Basement to 2rd BCC & JS C40x40 C50x50
20 C4 C 3rd BCC & JS C40x40 C60x60
21 C4 C 4th BCC & JS C40x40 C70x70
22 D4 C 1st to 2rd BCC & JS C40x40 C50x50
23 D4 C 3rd to 4th BCC & JS C40x40 C60x60
24 D5 C 3rd BCC & JS C40x40 C50x50
This will be the final design section of this report and covers the design and detailing of the moment
resists frame along grid line 5 on the first floor with application of all SMRF seismic provisions found in
ACI 318M – 14. The elements to be designed in the frame include: beams, columns, and joints.
Element Key:
Beams –
Columns –
Joints –
- 46 -
The reinforcing steel area will be determined from ETABS by designing the frame as an SMRF
with earthquake and gravity loads properly applied. Also, all earthquake forces in the combinations listed
on page 4 will be multiplied by 1.25 as explained on page 27. The gravity loads will be unaffected and
Using the listed load combinations, the following ultimate bending moment, shear, and axial force
diagrams are obtained from ETABS. All SMRF moment and shear requirements are accounted for by
ETABS even though they are not seen the diagrams below. No pattern live load factor (PLLF) and live
load reduction factor (LLRF) will be considered for this design. Additional hand calculations will be used
- 47 -
Figure 20 – Ultimate Shear Diagram
- 48 -
b. MRF Design (ETABS)
The following figures all show the required flexural and shear steel areas in mm2 as obtained from
- 49 -
- 50 -
Figure 26 – Beam Elevation Detailing
Figure 27 – Beam Section Detailing
- 51 -
- 52 -
Figure 28 – Column Elevation Detailing
Figure 29 – Column Section Detailing
The following figures on the next page show rendered 3D views of the steel rebar layouts to be
used in the beams and columns of the MRF gotten from ETABS.
- 53 -
Figure 30 – Beam Rebar Rendered View
Figure 31 – C40x40 Rebar Rendered View Figure 32 – C30x70 Rebar Rendered View
- 54 -
Figure 33 – SMRF and IMRF Joint Ties
The figure above is obtained from ETABS by designing and detailing the frame joints as SMRF
and IMRF. The results show a significant difference in the spacing and number of ties used in the joints to
The next section of this report will cover hand calculation to verify tie spacing in the beams,
columns, and joints. These results will be compared to the ETABS results for SMRF frames to check for
consistencies in calculations.
- 55 -
c. MRF Design Verification (Hand Calculations)
- 56 -
- 57 -
- 58 -
- 59 -
Conclusion
a. Final Results
The final design results for both shear walls and moment resisting frames show how much reinforcing
steel is required to satisfy seismic provisions. The required steel proved to be much larger than that of
typical gravity resisting elements. Also, several conditions needed to be verified before final results can
be obtained and this show how critical precise calculations are in this case. Overall, seismic elements need
to be properly and carefully designed to ensure that in the case of an earthquake all element can
b. Conclusion
This project proved to be a cumbersome task that required all information presented in the course to
be utilized in addition to basic concrete design techniques from previous undergraduate courses. Being
able to apply all the analysis and design methods into one practical seismic project was truly beneficial in
understanding all topics. Working around certain problems and using different design method to achieve
- 60 -