‘Scope of Work
Trial Section
Preparing of
‘Subgrade for Canal
Lining
SPECIFICATIONS -
TECHNICAL PROVISIONS
41 —CANAL LINING
44.1 The work te be done by the contractor under this item shall
include preparation of the subgrade and dressing, constructing
concrete lining and all incidental operations necessary to construct
concrete lining in branch canals, distributaries and minors, in
‘accordance with the Drawings and these Specifications and subject to
approval of the Engineer.
41.2 Before starting full scale canal lining operations, the
Contractor shall carry aut a trial section of the complete prism of the
canal for a length of not less than 50 feet, This trial section should be
carried out in the same area on which trial section for earthwork has
already been accepted and approved by the Engineer. The
Contractor shall submit his proposals for this trial section to the
Engineer for approval at least 14 days before he proposes to start the
trial.
The trial section shall demonstrate the sequencing of lining
operations, the effectiveness and the quality control of the
Contractor's methods including, but not limited to the following
matters:
~ Preparation of sub-grade and dressing
= Conerete batching arrangements,
- Arrangement for construction of concrete lining, forms,
transporting, placing, vibrating, screeding and finishing
conerete, placement of joints and associated fillers,
sealants, curing etc.
‘The trial section will be incorporated into the Works provided it
complies in all respects with these Specifications. Should it not so
comply, the Engineer may either instruct remedial measures, or
complete removal of the trial section, reinstatement of the
foundations, and a repeat tral, all at the Contractor's expense.
44.3. (1) Ensuring proper_compaction of subgrade: Prior to
canal lining, the contractor shall prepare the subgrade including
dressing of bed and side slopes filled or excavated sections of canal
and any other backfill over which canal lining is to be placed. Before
proceeding with canal lining, the contractor shall ensure and prove to
the satisfaction of the Engineer by means of compeetion tecte that the
subgrade of the whole canal prism (slopes and bed) is in a state of
compaction equal to 95% Standard Proctor or 70% relative density
depending upon the type of material, to a minimum depth of one (1)
foot below the final grade, measured perpendicular to the surfaces of
the canal prism. No separate payment shall be made for compaction
tests and their cost shall be deemed to have been included in the unit
ates quoted for the other relevant items given in. the BOQ. The
Contractor shall rework the areas which fall to most the compaction
Tequirements es described above and shall perform compaction by
‘employing appropriate equipment and methods in order to ensure
that the reworked portions meet the compaction requirements
described above,
Tsitt-1Crush stone & sand
filter
Concrete Lining
SPECIFICATIONS ~
TECHNICAL PROVISIONS
(2) Refilina of Over-excavated Areas: If ul any point
material has been excavated beyond the neat lines required to
Teceive the canal lining, the excess excavation shall be refilled with
‘compacted fill material and according to Section 3 — Earthwork. It at
any point the foundation material is disturbed or loosened during the
excavation process or otherwise, it shall be moistened if required and
thoroughly compacted by tamping, roling or other approved methods
in accordance with Section 3 — Earthwork to form firm foundations to
place the concrete lining.
@ & ) Lines_end Grades: In addition to the
‘above, the work under Subgrade preparation shall include but not be
limited to cutting, filing, compacting, reworking, dressing and finishing
the canal prism to true and even surfaces to the lines and grades
shown on the Drawings in accordance with these Specifications and
as directed by the Engineer.
144 6" inch thick compacted, filter, crush stone and sand material
with maximum size % inch not more than 35% passing sieve No. 8 &
Hot more than 5% finer than sieve No. 30 meeting the requirement of
ASTM G — 33 under the canal lining will be placed, as per drawings
and approved by the Engineer
418 (1) General: Concrete for canal lining shall be of Class B
nveinforced, and shall be constructed in the canal priem as shown an
the Drawings, and its strength shall be as specified herein.
Plain cement concrete for canal lining shall be plastic enough
to consolidate well and stiff enough to stay in place on specified
slopes over 6° thick compacted, filter as shown on the drawings.
‘Slump shall be in the range of 1 to 3 inches. The water-cement ratio
Shall be adjusted to achieve the specified slump and strength but
Shall not exceed 0.45 In any casc. The compressive cylinder
Strength of the concrete (28 days) shall be 3,000 psi and the concrete
will be cured by application of a curing compound subject to approval
of the Engineer following the submission of a request including
supporting procedural methods and documentation by the Contractor.
Nominal maximum size of aggregate for concrete in Canal Lining
shall be 3/4 inches. The subgrade shall be well moistened but not
muddy at the time of placing concrete.
(2) Materials and Procedures: All the materials used in
concrete canal lining including Sulphate Resisting Cement, slag,
Sand, aggregate, water, curing compound and admixtures etc., mixing
and batching, sampling and testing shall be in accordance with the
Standards and specifications given in other sections of these
specifications relevant to these items.
Tant2[SPECIFICATIONS -
TECHNICAL PROVISIONS
(3) Formwork: Forms for the concrete canal lining shall be
in accordance with Section 4 - "Concrete, General’ and as approved
by the Engineer.
(4) Construction Joints: The place where contraction joint
is not required but the concrete lining operations are interrupted
because of breakdown or delayed by other causes, the edge of the
fiesh concrete lining chall bo bullheaded to a perpendicular surface to
the lining along transverse or longitudinal lines. When placing
operations are resumed, the surface of the hardened concrete shall
be prepared as a construction joint as specified lnerein. The fresh
concrete shall then be placed against the existing concrete to form a
permanent bond with the existing concrete, No payment shall be
made to the contractor for making construction joints.
(5) | Concrete Temperature: For concrete temperatures,
refer to sub-section ‘Temperature’ of the Section ‘Concrete —
General’ of the Specifications.
(6) Method of Conerete Lining: The contractor shall carry
‘out concrete lining with the lining machine(s)..
a)’ Contractor must deploy the concrete lining machine(s)
comprising Trimmer and Trimmer discharae conveyor,
concrete iine1s, bullom feed conveyer, conorete curing
, jumbo, finishing jumbo and working bridae jumbo till
the completion of canal ining. The concrete liner
*. component for lining machine set should be capable of
concrete lining at least 165 yd° (125m°) per hour for 4
inch (100 mm) thick lining layer.
b) The concrete batching plants, transit mixers, concrete
pump, water chiller plants, crushing plants and other
related equipment should manufacture and maintain
the supply of concrete in such a capacity that the
conerete liner can yield at least 165 yd (729m*) per
hour.
(7) Replacement of Damaged/Rejected Concrete Panels:
Where a damaged/rejected panel of concrete canal lining is to be
roplaced, the old concrete shall he removed to the edges of the
adjacent panels. The surfaces of the existing concrete shall be
prepared as a contraction joint. Fresh concrete shall then be placed
against the existing conte with the full groove contraction joint
formed adjacent to the existing concrete. The groove shall be sealed
with elastomeric sealant in accordance with para 11.6(7) of this
section
(8) Joints: Contraction and dummy joints in lining shall be
constructed as shown on the Drawings, according to the specification
provided in this section. The joint formed at the end of the day's work
in case uf continuous lining, shell be made oo contraction joint.
Expansion joints would be provided where the lining abuts against the
structures (where shown on the drawings) according to the
TSHt3[SPEQIFICATIONS -
TECHNICAL PROVISIONS
specifications given for Expansion Joints in Section-17 "Miscellaneous
Works’.
(9) Curing: The Contractor shall cure lined surfaces of the
Canal as follows:
18) The exposed surfaces of the concrete shall be membrane
cured with an approved, white pigmented curing
compound which forms a water-retaining membrane on
the surfaces of the concrete. Curing compound shall
contorm t0 ASTM Designation. C-309. The compound
shall be of uniform consistency and quality within each
container and from shipment to shipment. No water curing
will be permitted for concrete placed for lining
b) Curing compound shall be applied to the concrete surfaces
by spraying in one coat to provide a continuous, uniform
membrane over all areas. Coverage shall not exceed 150
‘square feet per gallon and on rough surfaces coverage
shall be decreased as necessary to obtain the required
continuous membrane. Mortar encrustation and fines on
surfaces shall be removed prior to application of the curing
‘compound. The repair of all other surface imperfections
shall not be made until after application of curing
compound.
4) when curing compound is used on concrete surfaces
where forms are not used, application of the compound
shall commence immediately after finishing operations are
Completed. When curing compound is to be used on
concrete suriaces where forms are used, the surfaces
shall be moistened with a light spray of water immediately
after the forms are removed and shall be Kept wet unti the
surfaces will not absorb more moisture. As soon as the
Surface film of moiatura disappears but while the surface
still has a damp appearance, the sealing compound shall
be applied. Special care shall be taken fo ensure ample
coverage with the compound at edges, comers and rough
spots of formed surfaces. When application of the sealing
compound has been completed and the coating is dry to
touch, any required repair ot concrete surfaces shall be
performed. Each repair, after being finished ‘shall be
moistened and costed with sealing compound in
accordance with the foregoing requirements.
4) Equipment for applying sealing compound and the method
of application shall be in accordance with the provisions of
Chapter VI of the 8 Edition of the Bureau of Reclamation
Concrete Manual, Any sealing membrane that is damaged
or that peels from concrete surfaces, prior to 28 days after
application, shall be repaired without delay in an approved
manner.
TSNt-4Joints in Gana
Lining
SPECIFICATIONS -
TECHNICAL PROVISIONS
) Sealing compound will be accepted on Manufacturer's
certification of compliance with specifications, but the
acceptance on cettification shall in no way relleve the
Contractor of the responsibility for furnishing the
compound meeting specification requirements. Sealing
compounds shall be subject to sampling and testing. The
Contractor shall provide without charge to the Employer
such facilities and occistances as may be necassary fo
obtain test samples. Sampling will be in accordance with
Designation 38 of the 8” Edition of the Bureau of
Reclamation Concrete Manual.
#) The costs of furnishing and applying all materials for
curing concrete shall be included in the unit rate tendered
in the Bill of Quantities for the applicable concrete item on
‘whieh tho curing materials are used
(10) Tolerances for Concrete Construction: The canal lining
shall be built to the lines, grades and dimensions shown on the
Drawings. The dimensions shown on the Drawings will be subject to
such modifications as may be found necessary by the Engineer to
adapt to the conditions exposed by the excavation or to meet other
site conditions. Where the thickness of any portion of concrete is
Variable, it chall vary uniformly between the dimensions shown.
Tolerances for Canel Lining
T Description init J
Ty | Departure tom established | 2in. on tangents
ligament +24 in.on curves
Ti | Departure from estabished prof | 21 in |
grade.
| | Beparures set tins above shat
be uniform and no correction shall
bbe made i less than 100 feet
Ti} Reduction in thickness oftining | (29. tach of Sprciied Ticicness|
provided that average thick-ness
ver any 20 feet length is not less
than the specifed thickness. |
TW) | Variation fom specified width at | #1 inch of specified with
any height.
(| Wariation trom spaced heiaht of | +t inch of established height.
lining.
116 (1) ‘ypes of joints as shown on the Drawings are
generally contraction end dummy joints which shall be constructed or
placed in concrete canal lining,
The joints shall be made along straight lines and the required shape
and dimensions shall be maintained during any subsequent finishing
operations until the concrete has hardened.
‘The Contractor shall drill 6 inch diameter cores for inspection of joints:
at locations designated by the Engineer to determine the
effectiveness of the Contractors joint installation procedures
Additional cores shall be drilled by the Contractor for any other
TSi18SPECIFICATIONS -
TECHNICAL PROVISIONS
purpose so designated by the Engineer. All core holes shail be
repaired by and at the cost of the Contractor immediately following
‘completion of the inspection of the noies by the Engineer unless
otherwise directed. The method and manner of repair shall be
approved by the Engineer.
If inspection reveals that the joint does not meet these Specifications,
the Contractor shall promptly modify equipment and installation
procedures to ensure compliance with these Specifications and in
addition shall, at his own expense, correct the defective work as
required,
(2) Construction joints: Construction joints are purposely
placed in concrete at spacings that vary from the spacing shown on
the Drawings and in order to facilitate special conditions at structures,
interruption because of breakdown, or delayed by ather causes. The
spacings shall not be less than one-half of the spacing shown on the
Drawings. These joints are provided to reduce initial shrinkage
stresses and cracks) to allow time of the installation of embedded
metal work; or to allow for the subsequent placing of other concrete.
Bond shall be ensured at construction joints.
The location of all construction joints in concrete work shall be subject
to approval of the Engineer, and the joints shall be constructed in
accordance with the Specifications Na payment shall he made to the
Contractor for making construction joints.
3) Contraction Joints: Contraction joints shall be the joints
placed in concrete to provide for volumetric shrinkage of a monolithic
unit or movement between monolithic units. The concrete lining
placing operations should be scheduled such that stoppage of day's
‘work is at specified location of the contraction joint as for as possible.
The joints shall be so constructed that there will ba na hand between
the concrete surfaces forming the joint.
Contraction joints shall be constructed at location shown on the
Drawings. The joints shall be made by forming the concrete on one
side of the joint and allowing it to set before concrete is placed on the
other side of the joint. The surface of the concrete first placed at the
contraction joint shall be coated with curing compound and two coats
of bitumen before the concrete is placed on the other side of the joint.
Special care shall be taken to ensure proper compaction of concrete
ear the joint faces.
A groove will be formed at the top of lining on one side of the joint as
shown on the Drawings and filed with elastomeric sealant in
accordance with paragraph (7) below.
(4) Dummy Joints: Dummy joints shall be the joints
provided in the lining in the slopes and bed of the canal lining as
shown on the Drawings. They are to be grooved into fresh concrete
and filled with elaetomeric cealant in accordance with tho paragraph
(7) below.
1stMeasurement and
Payment
‘SPECIFICATIONS -
‘TECHNICAL PROVISIONS
(5) Approval of Joints: One copy and one reproducible of
the drawings and data showing the joints, joint intersections, and the
melliud uf construction shall bo cubmitted by the Contractor to the
Engineer for approval
(6) Edges: The Contractor shall tool or chamfer edges of
concrete where shown on the Drawings and elsewhere as directed by
the Engineer.
(7) ‘Sealant: The elastomeric sealant to be used in joints
shall’be of the type suitable for immersion in water and conforming to
‘ASTM C920-98 type S or M or equivalent subject to approval by the
Engineer.
The sealant shall be filled in the groove as soon as the concrete has
gained its 14 days strength in order to avoid deposition and
consolidation of any undesirable material in the groove which may
impair the function of the joint.
The concrete groove shall be sand blasted to produce a rough
surface and to remove all debris, scale, dirt, oil, taitance, curing
‘compound, and other foreign materials just before the application of
the elastomeric sealant. The concrete shall be at least 14 days old
before it is sand blasted. The joint groove that has been sandblasted
shall be blown out under high pressure compressed air to remove all
residue. Elastomeric sealant shall not be placed in dusty weather or
while rain is falling At the time of placing the joint sealant, the joint
groove shall be clean and dry.
The storage and application of the sealant and any necessary primer
shall be strictly in accordance with the manufacturers
recommendations. The method of mixing the sealant shall result in
homogeneous material.
The sealant shall he extruded at the bottom of the joint groove and.
shall be tooled as necessary to work the sealant into intimate contact
with the concrete without entrapping air. The top surface of the
sealant shall be tooled to the shape shown on the Drawings.
Elastomeric sealant which does not cure to a homogenous, rubber
like compound, of which does not bond to the Joint-groove faces or to
this Specification shall be removed and replaced by the Contractor at
no additional cost to the Employer.
14.7 (1) Sub-arade Preparation including dressing: Measure-
ment for payment of sub-grade preparation including dressing shall
be made for the surface area of sub-grade prepared under the canal
lining in bed and side slopes and shall be measured in hundred
square feet.
Payment shall be made at the unit rate tendered per hundred square-
feet in the BOG for preparation of sub-grade and dressing and shail
constitute full compensation for the work performed for sub-grade
preparation and dressing including all labour, equipment, operations
Ten7SPECIFICATIONS -
TECHNICAL PROVISIONS
‘and compaation testing etc., complete in all respects.
(2) Concrete Lining: Measurement for payment of
conerete placed in lining shall be made of the volume of the concrete
placed for canal lining according to the design lines in hundred cubic
feet.
Payment shall be made at the unit rate tendered per hundred cubic.
feet in the BOQ for concrete for canal lining and shall constitute full
‘compensation for the work performed for moictening of subgrade
prior to concrete placement and concrete placement including
material, labour, equipment and its operation, curing compound,
‘admixtures and testing etc., complete in all respects.
(3) 62inch thick filter. crush stone and sand materiat
Measurement of 6” inch thick, fiter, crush stone and sand material
under canal lining shall be made ‘ett of the volume of material
Payment shall be made at the unit price quoted per hundred eft in the
Bill of Quantities for completion of work
‘The amount tendered shall be full payment for completion of the work
including but not limited to procurement, transportation, placing and
compaction according to the specifications and as directed by ine
Engineer.
(4) Contraction Joints: Measurement of contraction joints
in canal lining shall be made of the length of the joints prepared
‘according to design lines for canal linings in running feet.
Payment shall be made at the unit rate tendered per running-foot in
the BOQ for joints in canal lining and shall consutute full
‘compensation for the work of providing joints in canal lining complete
jn all respects including two coats of bitumen on vertical face of
contraction joint and providing sealant in the groove.
(6) Dummy Joints: Measurement of dummy joints in canal
lining shall be made of the length of the joints prepared according to
desian lines for canal linings in running feet.
Payment shall be made at the unit rate tendered per running-foot in
the BOQ for joints in canal lining and shall constitute full
‘compensation for the work of providing joints in canal lining complete
in all respects including providing sealant in the groove.
(6) Rainwater_Drain_Inlet Structures: Measurement for
rainwater drain inlet structures shall be made in number of complete
inlet structures constructed in canal banks a» per drawings.
Payment shall be made in number of inlet structures for specified pipe
diameter measured as above and shall constitute full payment for
provision of MS grating, stone pitching, RCC pipes, concrete and
other materials and operations required to complete the specified
TSN18[SPECIFICATIONS -
‘TECHNICAL PROVISIONS
works in all respects.
™ it Drain le Structures with Chu
Measurement for rainwater drain manhole structures with chutes shall
be made in number of completed manhole structures along with
chutes constructed in deep cut areas in specified reaches as per
drawings.
Payment for rainwater drain manhole structures for the specified
chute elze ae measured above shall be mad at the unit rate tendered
per number of each size and shall constitute full payment for manhole
structure and chute constructed of plain cement concrete and brick
masonry, lean concrete, etc. including all material, labour, operations
(curing), and equipment to complete the specified works in all
respects.
(8) Bathing Steps: Measurement for installing reinforced
concrete class B bathing steps using slag and SRC, shall be made in
hundred cubic feet of reinforced concrete placed in bathing steps as
per drawings.
Payment for installing reinforced conorete bathing steps shall be
made at the unit rate tendered per hundred cubic feet and shall
constitute full payment tor materials including curing compound,
admixtures, etc. complete in all respects excluding reinforcement.
rans