Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

296 IEEE TRANSACTIONS ON SMART GRID, VOL. 8, NO.

1, JANUARY 2017

AC Versus DC Microgrid Planning


Hossein Lotfi, Student Member, IEEE, and Amin Khodaei, Senior Member, IEEE

Abstract—This paper presents a microgrid planning model C. Parameters


for determining the optimal size and the generation mix of
distributed energy resources (DERs), as well as the microgrid
c Generation price for dispatchable units.
type, i.e., ac or dc. Considering the growing ratio of dc loads CC Annualized investment cost of generating units.
and DERs, dc microgrids could be potentially more benefi- CE Annualized investment cost of storage—energy.
cial than ac microgrids by avoiding the need to synchronize CI Annualized investment cost of dc-to-ac inverters.
generators, reducing the use of converters, facilitating the con- CP Annualized investment cost of storage—power.
nection of various types of DERs and loads to the microgrid
common bus with simplified interfaces, and reducing losses asso-
CR Annualized investment cost of ac-to-dc rectifiers.
ciated with the ac–dc energy conversion. The microgrid type Ccap Allowable energy storage installation capacity.
is selected based on economic considerations, where the plan- d Discount rate.
ning objective includes the investment and operation costs of D Local demand.
DERs, cost of energy purchase from the main grid, and the reli- M Large positive constant.
ability cost. Numerical simulations exhibit the effectiveness of
the proposed model and investigate in detail the impact of vari-
Pcap Allowable DER installation capacity.
ety of factors on planning results, including the ratio of critical Pmax
M Flow limit between the microgrid and the main grid.
loads, the ratio of dc loads, and the efficiency of inverters and pp Normalized forecast of nondispatchable generation.
converters. u Binary islanding parameter.
Index Terms—AC microgrid, dc microgrid, distributed energy α Ratio of dc loads to total loads.
resource (DER), microgrid planning. β Ratio of critical loads to total loads.
κ Coefficient of present-worth value.
ρ Market price.
N OMENCLATURE v Value of lost load.
η Efficiency (energy storage, inverters, and rectifiers).
A. Indices
b Index for hour.
D. Variables
ch Superscript for energy storage charging mode.
dch Superscript for energy storage discharging mode. Cmax Installed energy storage capacity.
h Index for day. IC Total investment cost.
i Index for distributed energy resources (DERs). LS Load curtailment.
inv Subscript for dc-to-ac inverters. OC Total operation cost.
rec Subscript for ac-to-dc rectifiers. P DER output power.
t Index for year. Pmax Installed DER capacity.
PM Main grid power.
RC Total reliability cost.
B. Sets z Microgrid investment state (0 if ac, 1 if dc).
G Set of all dispatchable units.
Gac Set of ac dispatchable units. I. I NTRODUCTION
Gdc Set of dc dispatchable units. ICROGRIDS have attracted significant attention in
I
R
Set
Set
of
of
dc-to-ac inverters.
ac-to-dc rectifiers.
M recent years due to providing significant advantages
for electricity consumers and power grid operators. Microgrid
S Set of energy storage systems. deployments are trusted to improve power quality, reduce
W Set of all nondispatchable units. emissions, reduce network congestion and power losses,
Wac Set of ac nondispatchable units. increase energy efficiency, and potentially improve system
Wdc Set of dc nondispatchable units. economics. Microgrids can also eliminate investments on addi-
tional generation and transmission facilities to supply remote
Manuscript received January 28, 2015; revised May 15, 2015; accepted loads. Moreover, microgrids islanding capability in the event
July 12, 2015. Date of publication August 26, 2015; date of current version of faults or disturbances in upstream networks would enhance
December 21, 2016. Paper no. TSG-00088-2015.
The authors are with the Department of Electrical and Computer grid and customers’ reliability and resilience [1]–[12].
Engineering, University of Denver, Denver, CO 80210 USA (e-mail: Microgrids can be categorized into different groups based
hossein.lotfi@du.edu; amin.khodaei@du.edu). on the type (such as campus, military, residential, com-
Color versions of one or more of the figures in this paper are available
online at http://ieeexplore.ieee.org. mercial, and industrial), the size (such as small, medium,
Digital Object Identifier 10.1109/TSG.2015.2457910 and large scales), the application (such as premium power,
1949-3053 c 2015 IEEE. Personal use is permitted, but republication/redistribution requires IEEE permission.
See http://www.ieee.org/publications_standards/publications/rights/index.html for more information.
LOTFI AND KHODAEI: AC VERSUS DC MICROGRID PLANNING 297

resilience-oriented, and loss reduction), and the connectivity of storage are taken as objective functions, and the mathe-
(remote and grid-connected). Based on the voltages and cur- matical model is built and solved to obtain the Pareto-optimal
rents adopted in a microgrid, however, three microgrid types solution. Hema and Dhanalakshmi [18] investigated a control
can be identified: 1) ac; 2) dc; and 3) hybrid. In ac microgrids, system for hybrid ac–dc microgrids connected by multilevel
all DERs and loads are connected to a common ac bus. DC inverters. The droop control technique is offered to manage
generating units as well as energy storage will be connected to power flows between ac microgrid, dc microgrid, and the main
the ac bus via dc-to-ac inverters, and further, ac-to-dc rectifiers grid. Eghtedarpour and Farjah [19] discuss the power manage-
are used for supplying dc loads. In dc microgrids, however, ment in a hybrid ac–dc microgrid and propose an interlinking
the common bus is dc, where ac-to-dc rectifiers are used for ac–dc converter accompanied by a suitable control system.
connecting ac generating units, and dc-to-ac inverters are used The power flow between different sources throughout both
for supplying ac loads. In hybrid microgrids, which could be microgrids is controlled. The hybrid ac–dc microgrid allows
considered as a combination of ac and dc microgrids, both different loads and DERs to connect with the minimum need
types of buses exist, where the type of connection to each for electrical conversion, which decreases the cost and energy
bus depends on the proximity of the DER/load to the bus. losses. Shimoda et al. [20] state that the efficiency of dis-
Extensive studies can be found on different aspects of micro- tributed generations and energy storage systems in a microgrid
grids operation and control, where the majority of these studies might reduce because of microgrid operation, hence run-
focus on ac microgrids, perceivably due to the connection to ning some consumers into problem. This paper proposes an
the ac utility grid and the utilization of ac DERs. DC micro- optimized operation planning for distributed generations and
grids could, however, offer several advantages when studied in energy storage systems in microgrids to solve this issue.
detail and compared with ac microgrids: 1) higher efficiency It is assumed in this paper that the microgrid developer
and reduced losses due to the reduction of multiple converters is planning to deploy a microgrid; however, the challenge is
used for dc loads; 2) easier integration of various dc DERs, to determine the type of the microgrid, i.e., either ac or dc,
such as energy storage, solar photovoltaic (PV), and fuel cells, based on the system characteristics and accordingly determine
to the common bus with simplified interfaces; 3) more efficient the optimal DER generation mix. This paper aims at propos-
supply of dc loads, such as electric vehicles and LED lights; ing a microgrid planning model with the overarching goals of:
4) eliminating the need for synchronizing generators, which 1) determining the optimal DER generation mix; 2) determin-
enables rotary generating units to operate at their own opti- ing the optimal type of the microgrid, i.e., either ac or dc, from
mum speed; and 5) enabling bus ties to be operated without the an economic perspective; and 3) identifying threshold ratios
need for synchronizing the buses [13]. These benefits, com- of dc loads which make the dc microgrid a more economically
bined with the significant increase in dc loads such as personal viable alternative than the ac microgrid.
computers, laptop computers, LED lights, data and telecom- Although the proposed planning model can be extended to
munication centers, and other applications where the typical include hybrid microgrids, it is limited in this paper to the
50- and 60-Hz ac systems are not available, could potentially modeling of individual ac and dc microgrids. The proposed
introduce dc microgrids as viable and economic solutions in microgrid planning model minimizes the total planning cost
addressing future energy needs. associated with the investment costs of DERs, ac-to-dc recti-
The prior research on dc microgrid planning is rather limited fiers, and dc-to-ac inverters, as well as the microgrid operation
and available studies on microgrid planning mostly focus on and reliability costs.
ac microgrids. Khodaei et al. [14] proposes a planning model The rest of this paper is organized as follows.
for ac microgrid considering uncertain physical and financial Sections II and III present the model outline and the
information. In this paper, the microgrid planning problem formulation of the proposed microgrid planning problem,
is broken down into an investment problem and an opera- respectively. The numerical simulations for a test microgrid
tion subproblem. The optimality of the solution is examined are performed in Section IV. Section V provides a discussion
by employing the optimal planning decisions obtained from on the proposed model and Section VI concludes this paper.
the master problem in the subproblem under uncertain con-
ditions. Baboli et al. [15] suggests an operation modeling of
hybrid ac–dc microgrids. It explains that the operation model II. M ICROGRID P LANNING P ROBLEM M ODEL O UTLINE
of such hybrid microgrid consists of system and device levels. The investment cost is typically higher for DERs compared
This model includes advantages of both ac and dc microgrids, to conventional energy resources within large-scale power
and performs both optimal scheduling and voltage control. plants due to economies-of-scale of the latter. Nevertheless,
Huang et al. [16] proposes an operation planning model DERs can provide less expensive energy in comparison with
considering load/generation changes for a low-voltage dc the energy purchased from the main grid specifically during
microgrid including dc sources such as battery, fuel cell, and peak hours when the market price is high. The energy storage
PVs. The objective of this paper is to minimize daily operation can be further employed to be charged by the power from the
costs. The model utilizes a multipath dynamic programming main grid during low-price hours and discharged during high-
approach to solve the problem. Lu et al. [17] presents a mul- price hours. One important and salient feature of microgrids
tiobjective optimal scheduling of a dc microgrid consisting that increases the reliability is their islanding capability which
of a PV system and an electric vehicle charging station. allows microgrids to be disconnected from the main grid in the
In this paper, the cost of electricity and energy circulation presence of faults, disturbances, or voltage fluctuations in the
298 IEEE TRANSACTIONS ON SMART GRID, VOL. 8, NO. 1, JANUARY 2017

Fig. 2. General structure of ac microgrids.


Fig. 1. General structure of dc microgrids.
The capacity of lines in a microgrid distribution network is
upstream network. However, if after disconnecting from the typically much higher than the power transferred through the
main grid, the microgrid could not supply all the loads, some lines; therefore, the power flow is not considered in the pro-
loads should be curtailed, but critical loads will still be sup- posed planning problem as the congestion is less likely and
plied. Another economic benefit of the microgrid is selling would not impact the planning results. Moreover, although the
back the excess power to the main grid. The microgrid eco- proposed planning model can be extended to include hybrid
nomic viability is ensured when the total microgrid revenue microgrids, it is limited in this paper to the modeling of indi-
from all available value streams in a specified time horizon vidual ac and dc microgrids. The hybrid microgrid planning
exceeds the microgrid total investment cost. The total plan- problem will be investigated as a follow-on work.
ning cost comprises three parts: 1) the investment cost; 2) the
operation cost; and 3) the reliability cost. The investment cost III. M ICROGRID P LANNING P ROBLEM F ORMULATION
is long-term, and is calculated annually while the operation The objective of the microgrid planning problem is to min-
and reliability costs are short-term, and should be calculated imize the microgrid total planning cost (1), which comprises
hourly for each day of the planning horizon. the investment cost of DERs, rectifiers, and inverters, the
In reality, several components should be considered to microgrid operation cost, and the reliability cost. The invest-
install the microgrid, but only the investment cost of DERs, ment, operation, and reliability costs are determined in (2)–(5).
rectifiers, and inverters are included in this paper. Other costs Associated constraints are defined in (6)–(17). The type of the
associated with distribution network upgrade and installation microgrid, i.e., either ac or dc, would impact the components
of additional transformers, switches, measurement devices, to be installed in the microgrid, and accordingly, alter the
and controllers are ignored in this paper since these costs will investment cost. Constraints (2) and (3), respectively, define
be similar in both types of the microgrid. A general structure of the dc investment cost and the ac investment cost, based on
dc microgrids is shown in Fig. 1. In dc microgrids, three-phase a binary decision variable z. If the microgrid is dc, the binary
ac-to-dc rectifiers and transformers are required to connect ac decision variable is set to one, relaxing (3), and the investment
DERs to the common bus, single- and three-phase dc-to-ac cost would be determined by (2). Similarly, if the microgrid
inverters are needed for supplying ac loads, and a three-phase is ac, the binary decision variable is set to zero, relaxing (2),
dc-to-ac/ac-to-dc converter, a transformer, and a point of com- and the investment cost would be determined by (3)
mon coupling switch are required for connecting the microgrid min IC + OC + RC (1)
to the utility grid. ⎛  ⎞
κt CCit Pi max
A general structure of ac microgrids is shown in Fig. 2. ⎜ t i∈{G,W} ⎟
In ac microgrids, three-phase dc-to-ac inverters are required ⎜ +   κ CP Pmax + CE Cmax  ⎟
⎜ t it i it i ⎟
to connect dc DERs to the common bus, three-phase ac-to- ⎜ t i∈S  ⎟
⎜ ⎟
dc rectifiers are needed for supplying dc loads, and similar to −M(1 − z) ≤ IC − ⎜ + κt CRit Pmax ⎟
⎜ t i∈{Gac ,Wac }
i ⎟
dc microgrids, a transformer and a point of common coupling ⎜   ⎟
⎜ + κt CI it (1 − α). max(Dbht ) ⎟
switch are required to connect the microgrid to the utility grid. ⎜ ⎟
⎝ t 
i∈I ⎠
The direction of arrows in Figs. 1 and 2 shows the direction of + κt CI it Pmax
M
power flow. It should be noted that different dc loads require t i∈I
different dc voltage levels, so some dc-to-ac converters have to ≤ M(1 − z) (2)
be considered as well in order to change the voltage level of the ⎛  ⎞
κt CCit Pi max
dc sources to desired levels. In both microgrids, a common bus ⎜ t
 
i∈{G,W} ⎟
⎜ + κt CPit Pmax + CEit Cimax ⎟
is considered to show all the connections of loads and DERs. ⎜ i ⎟
⎜ t i∈S  ⎟
In reality, however, the common bus can represent one or more −Mz ≤ IC − ⎜ ⎟
⎜ + κt CI it Pi
max

loop/radial distribution networks that connect loads and DERs ⎜ t i∈{Gdc ,Wdc ,S} ⎟
within the microgrid. In dc microgrids, the common bus would ⎝  ⎠
+ κt CRit α. max(Dbht )
handle dc voltages and currents, while in ac microgrids the t i∈R
common bus would be used for ac voltages and currents. ≤ Mz (3)
LOTFI AND KHODAEI: AC VERSUS DC MICROGRID PLANNING 299


OC = κt ci Pibht the islanding ability of the microgrid, it is required to consider
t h b i∈G a condition to make sure that dispatchable generation capacity

+ κt ρbht PM,bht (4) installed in the microgrid is adequate to seamlessly supply
t h b critical loads (6). The parameter β defines the peak ratio of
critical loads to total loads
RC = κt vbht LSbht . (5)
t
β max(Dt ) ≤ Pmax
i . (6)
h b
i∈G
AC and dc microgrids have some similar components in Sum of the power from the main grid and from all DERs,
the investment cost. The first two terms within the invest- including dispatchable and nondispatchable units as well as
ment cost in (2) and (3) indicate the investment cost of DERs energy storage, should be equal to the total load in each schedul-
and energy storage, respectively. The investment cost of DERs ing hour. Equations (7) and (8) consider the power balance
depends on their installed power capacity which will be deter- equation in dc and ac microgrids, respectively. If the microgrid
mined by the optimization problem. The investment cost of is dc, the binary decision variable is set to one, thus (8) would
energy storage further depends on its installed energy capacity. be relaxed, and (7) would be applied. Similarly, if the microgrid
A single-step price curve is considered for DERs, which could is ac, (7) would be relaxed and (8) would be applied
⎛   dch ⎞
be simply extended to a multistep price curve. If the micro- Pibht + Pibht − Pch ibht
grid is dc, the output voltage of ac generating units should be ⎜ i∈{Gdc ,Wdc } i∈S ⎟
⎜ ⎟
converted to dc using rectifiers. Therefore, another term that ⎜    ⎟
−M(1 − z) ≤ ⎜ ⎜ + P ibht + PM,bht .η rec ⎟

should be considered is related to the investment cost of ac-to- ⎜ i∈{Gac ,Wac } ⎟
dc rectifiers. Additionally, there are ac loads in the microgrid ⎝ (1 − α).Dbht ⎠
requiring the use of dc-to-ac inverters. As a result, the invest- + LSbht − α.Dbht −
ηinv
ment cost of these inverters is included in the investment cost. ≤ M(1 − z) ∀b, ∀h, ∀t (7)
The last term of the investment cost considers the dc-to-ac ⎛  ⎞
Pibht
inverter which is used for connecting the dc microgrid to the ⎜ i∈{Gac
,Wac } ⎟
⎜ ⎟
utility grid. For ac microgrids, as proposed in (3), dc-to-ac ⎜   dch  ⎟
inverters have to be used for connecting dc units to the micro- −Mz ≤ ⎜ ⎜ + Pibht + P ibht − P ch
ibht · η inv⎟

grid, and ac-to-dc rectifiers are needed for supplying dc loads. ⎜ i∈{Gdc ,Wdc } i∈S ⎟
⎝ α · Dbht ⎠
These costs are included in the investment cost as well. + PM,bht + LSbht − (1 − α).Dbht −
ηrec
The operation cost (4) includes the generation cost of dis-
≤ Mz ∀b, ∀h, ∀t. (8)
patchable generating units and the cost of energy purchase from
the main grid, which is defined as the amount of purchased In dc microgrids, since power conversion causes power loss,
energy times the market price at the point of common cou- an efficiency coefficient is defined in (7) for ac-to-dc recti-
pling. If the microgrid is exporting its excess power to the main fiers, used for converting the output of ac generating units
grid, the main grid power PM would be negative (assumed to and the power from the main grid, and for dc-to-ac inverters,
be paid at the market price under net metering); hence, there used for supplying ac loads. Similar efficiency coefficients are
would be a benefit from selling the excess power. On the other considered for the ac microgrid (8).
hand, if there is a need for importing power from the main The planning problem is further subject to constraints asso-
grid, PM would be positive, increasing the operation costs. ciated with the main grid power limits (9), dispatchable and
The reliability cost (5), which is the cost of unserved energy, is nondispatchable unit operation and planning (10)–(12), energy
defined as the load curtailment quantity multiplied by the value storage (12)–(16), and load curtailment (17)
of lost load (VOLL). VOLL represents customers’ willingness
−Pmax
M ubht ≤ PM,bht ≤ PM ubht ∀b, ∀h, ∀t
max (9)
to pay for reliable electricity service in order to avoid outage.
VOLL highly depends on sector or customer type, timing of 0 ≤ Pibht ≤ Pimax ∀i ∈ G, ∀b, ∀h, ∀t (10)
outage, duration of outage, and time of advanced notification of Pibht = Pmax
i · pp ibht ∀i ∈ W, ∀b, ∀h, ∀t (11)
outage and preparation. Generally, VOLL for residential cus- cap
Pmax
i ≤ Pi ∀i ∈ {G, W, S} (12)
tomers ranges from approximately $0/MWh to $17 976/MWh,
0 ≤ Pdch
ibht ≤ Pi
max ∀i ∈ S, ∀b, ∀h, ∀t (13)
while for commercial and industrial customers ranges from
$3000/MWh to $53 907/MWh [21]. Higher VOLLs represent 0 ≤ Pch
ibht ≤ Pi
max ∀i ∈ S, ∀b, ∀h, ∀t (14)
cap
more critical loads [22] and [23]. A discount rate d is consid- Ci ≤ Ci
max ∀i ∈ S (15)
ered in order to evaluate the objective in terms of discounted   ch  
0≤ k≤b Pikht − Pikht ηi
dch ≤ Cimax ∀i ∈ S, ∀b, ∀h, ∀t (16)
costs. The present-worth cost component κt is present in all
0 ≤ LSbht ≤ Dbht ∀b, ∀h, ∀t. (17)
parts of the cost function, and is calculated as κt = 1/(1+d)t−1 .
In (1)–(5), investment costs are calculated annually while oper- The amount of exchanged power with the main grid is lim-
ation and reliability costs are calculated hourly and summed ited by the capacity of the line connecting the main grid
over all the years in the planning horizon. to the microgrid (9). In (9), the islanding capability of the
Islanding is the most salient feature of microgrids, which microgrid is considered by defining a binary parameter which
enables the microgrid to be disconnected from the main grid in controls microgrid islanding. The power generated by dis-
the case of upstream network disturbances. In order to include patchable units is limited by their installed capacity (10).
300 IEEE TRANSACTIONS ON SMART GRID, VOL. 8, NO. 1, JANUARY 2017

TABLE I TABLE IV
D ISPATCHABLE U NITS C HARACTERISTICS A NNUALIZED I NVESTMENT C OST OF C ONVERTERS

TABLE V
I NSTALLED DER C APACITY (MW) (β = 0.50 AND η = 0.70)

TABLE II
N ONDISPATCHABLE U NITS C HARACTERISTICS

TABLE III
E NERGY S TORAGE C HARACTERISTICS

data obtained from the Illinois Institute of Technology Campus


Microgrid [24]. Data of wind, solar, fuel cell, and converters
are gathered from [25]–[28]. The efficiency of energy stor-
age and VOLL are considered to be 90% and $10 000/MWh,
respectively. The planning horizon is 20 years. The lifetime
of candidate DERs is considered to be equal to the plan-
For nondispatchable units, a variable and a parameter are used ning horizon, i.e., 20 years. Twelve hours of islanding is
to consider their generation. Similar to dispatchable units, the considered in each planning year. The microgrid planning
variable Pmax
i represents their installed capacity, which will problem was implemented on a high-performance computing
be determined via the optimization problem. The parameter server consisting of four 10-core Intel Xeon E7-4870 2.4 GHz
ppibht represents the normalized generation forecast of nondis- processors. The problem was formulated by mixed-integer
patchable units, and has a value between 0 and 1 (11). Once programming (MIP) and solved by CPLEX 12.6 [29]. The fol-
a forecast is obtained, it is divided by the rated power of the lowing cases are studied. The approximate running time for
candidate DER; hence, the normalized generation forecast is each simulation is 118–155 min:
obtained. In this case, the selected size of the nondispatchable 1) case 0: Base case microgrid planning;
unit will be considered as a scaling factor to scale up/down the 2) case 1: Sensitivity analysis on the ratio of dc loads;
normalized generation forecast and further obtain the actual 3) case 2: Sensitivity analysis on the ratio of critical loads;
generation. All DERs have an allowable installation capacity, 4) case 3: Sensitivity analysis on the efficiency of ac-to-dc
and their installed capacity cannot exceed this limit (12). The rectifiers and dc-to-ac inverters;
allowable installation capacity may be obtained from budget 5) case 4: Sensitivity analysis on the market price.
limitations, choice of technology, or space limitations. The Case 0: Initial values for the ratio of dc loads α, the ratio of
energy storage charging and discharging power in all hours is critical loads β, and the efficiency of inverters and rectifiers η
limited by its installed capacity (13), (14). The installed energy are chosen to be 0.40, 0.50, and 0.70, respectively. The micro-
capacity of the energy storage is limited by its allowable instal- grid planning solution would install dispatchable units 3 and 4
lation energy capacity (15). Additionally, its stored energy is and the solar unit all with the maximum allowable capac-
determined based on the net charged power, efficiency, and the ity. The planning solution would be the ac microgrid. The
stored energy in previous hours (16). It is further ensured that total planning cost in the base case is $25 608 640 with a cost
in case of local curtailments, the hourly curtailed load does breakdown of $6 679 653, $18 614 730, and $314 251 for the
not exceed the hourly total load (17). investment, operation, and reliability costs, respectively.
Case 1: In this case, the effect of changing the ratio of
IV. N UMERICAL S IMULATIONS dc loads α on the type of the microgrid and installation
A microgrid is to be installed for a group of electricity cus- of DERs is studied. The ratio of dc loads is changed by
tomers with a peak annual load demand of 8.5 MW. The set of a step of 0.1 while all other parameters are kept unchanged.
DERs used in this paper includes four ac dispatchable units, Results are represented in Tables V and VI. For values of
one ac nondispatchable unit (wind generator), one dc dispatch- α between 0 and 0.4, the microgrid planning solution would
able unit (fuel cell), one dc nondispatchable unit (solar PV), install dispatchable units 3 and 4 and the solar unit, while by
and one energy storage, as represented in Tables I–III. The changing α between 0.5 and 0.8, dispatchable units 1 and 2
cost of converters is provided in Table IV. The load, renew- are also installed. However, for α = 0.9 and 1, units 1 and 2
able energy, and market price are forecasted based on historical are not installed anymore, and the microgrid planning solution
LOTFI AND KHODAEI: AC VERSUS DC MICROGRID PLANNING 301

TABLE VI TABLE VII


M ICROGRID C OSTS (β = 0.50 AND η = 0.70) I NSTALLED DER C APACITY (MW) (α = 0.40 AND η = 0.70)

TABLE VIII
M ICROGRID C OSTS (α = 0.40 AND η = 0.70)

as the overall exchanged power with the main grid decreases


by changing all loads to dc. Accordingly, the microgrid total
planning cost would decrease by increasing α from 0.9 to 1.
An interesting point is the change in the total planning cost
Fig. 3. Annual average value of load and solar generation (MW), and the
by changing the load mixture. According to Table VI, increas-
market price ($/MWh) for 24 h. ing the ratio of dc loads would cause an increase followed by
a decrease in the total planning cost. Therefore, it would iden-
would install the energy storage since the type of the micro- tify threshold ratios of dc loads which make the dc microgrid
grid is dc. The obtained results advocate that the installation a more economically viable solution than the ac microgrid.
of dispatchable units 3 and 4 with a higher investment cost In other words, for ratios smaller than the threshold ratio, ac
is more economical than that of units 1 and 2. The reason is microgrid would be more economical and for ratios larger than
that units 3 and 4 offer a less expensive power compared to that, dc microgrid would be more economical.
units 1 and 2. Additionally, between the two available nondis- Case 2: In this case, the effect of changing the ratio of
patchable units, the solar unit is installed for all values of α critical loads β on planning results is studied. Results are
although it has a higher investment cost than the wind unit represented in Tables VII and VIII. The microgrid planning
since the generation pattern of the solar unit partially coin- solution would be the ac microgrid for all values of β. It is rea-
cides with market price and load variations. The daily values sonable that by keeping α constant, there is not a shift from the
of load, solar generation, and market price, averaged over one ac microgrid to the dc microgrid. The impact of β, however,
year, are shown in Fig. 3 to demonstrate the partial correla- could be noticed on the installed generation mix. According
tion of the solar generation with the market price and the load. to Table VII, when the value of β is between 0.1 and 0.7,
According to Fig. 3, during the day, especially at peak hours, the microgrid planning solution would install dispatchable
the market price is higher, and the solar unit generates power. units 3 and 4 and the solar unit. By increasing the ratio of
Therefore, part of loads could be supplied by solar genera- critical loads to 0.8 and more, units 1 and 2 are also installed,
tion. On the other hand, the wind energy is available mostly and their installed capacity would increase in order to supply
at early morning hours, when the market price is relatively low. critical loads. It is noticeable that the fuel cell, i.e., unit 5,
As expected, according to results and based on the values of would not be installed for any value of β. The reason is that
β and η, increasing the ratio of dc loads causes the microgrid the capital cost of fuel cell is much higher than that of other
to shift from ac (associated with z = 0) to dc (associated with DERs. It should be noted, however, that if the total critical
z = 1). According to Table VI, by increasing α from 0.4 to 0.8, load exceeds the total allowable DER capacity of available
the microgrid investment cost increases because of increasing dispatchable units, the fuel cell would be installed as a last
the installed capacity of units 1 and 2 and also increasing the resort to ensure that critical loads would be supplied during
investment cost of rectifiers for supplying dc loads. For values islanding events. In other words, the supply feasibility would
of α between 0.4 and 0.8, the operation cost would increase as become a more important factor than the economy.
well since the amount of hourly power generated by dispatch- Similar to case 1, the solar unit is always installed due to the
able units 1 and 2 increases. By increasing α from 0.8 to 0.9, coincidence of its generation pattern with the load and market
again the investment cost rises due to the installation of the price variations. According to Table VIII, the operation and
energy storage, but the operation cost would decrease. The reliability costs would decrease by increasing β. Increasing
investment and operation costs would decrease by increasing the ratio of critical loads would cause an increase in the total
α from 0.9 to 1. The investment cost drops as there are not installed DER capacity, while the total load has not changed.
any ac loads in the microgrid when α = 1, thus the invest- As a result, the excess power would be sold to the main
ment cost of inverters is eliminated. The operation cost drops grid, which would increase the revenue of the microgrid thus
302 IEEE TRANSACTIONS ON SMART GRID, VOL. 8, NO. 1, JANUARY 2017

TABLE IX TABLE XI
M ICROGRID C OSTS (α = 0.40 AND β = 0.50) M ICROGRID C OSTS (α = 0.40, β = 0.50 AND η = 0.70)

TABLE X
I NSTALLED DER C APACITY (MW) (α = 0.40, β = 0.50 AND η = 0.70)

DERs 3, 4, and 7, thus the investment cost would increase.


By increasing the market price by 20% or more, the micro-
grid should generate more power in several hours in order
to supply loads, and on the other hand, it would be desir-
able to sell more electricity to the main grid. Therefore, all
ac dispatchable units, wind generator, and solar PV would
be installed at their maximum capacity, and the exchanged
power with the main grid would be negative in several hours.
As a result, the operation cost would decrease due to the rev-
decreasing the operation cost. On the other hand, by increasing enue from selling more power to the main grid. It is further
the ratio of critical loads, the additional available dispatch- reasonable that all critical loads be supplied by increasing the
able capacity would fully supply loads during islanding events, total DER capacity. Accordingly, there would not be any load
which causes load curtailments to decrease. Specifically, if all curtailment, which causes the reliability cost to reach zero.
loads are considered as critical (associated with β = 1.0), the Since DER generation mix is the same when there is a 20%
microgrid planning solution would install more dispatchable or more increase in the market price, the investment cost would
capacity so as to fully supply all loads which causes load cur- not change. Similar to previous cases, the type of the micro-
tailments to reach zero in expense of a higher investment cost. grid would remain the same, i.e., ac, since the ratio of dc loads
Case 3: In this case, the effect of changing the efficiency is unchanged. It should be finally noted that since the capital
of inverters and rectifiers η, which are considered to be investment cost of the fuel cell is too large, it would not be
equal, on planning results is studied. Results show that installed under any studied market prices.
changing converters efficiencies while other parameters are Although in proposed studies it is assumed that annual
kept unchanged would not affect either the type of the changes in load, renewable generation, and market prices are
microgrid or installed DER mix. According to Table IX, the negligible, the proposed microgrid planning model has the
significant impact of changing η would be on the operation capability to efficiently consider respective annual changes.
and reliability costs. By increasing η, there would be less Considering significantly small changes in the load is a prac-
power loss in inverters and rectifiers. Therefore, the importing tical assumption, perceivably due to the limited geographical
power from the main grid in many operation hours would boundaries of the microgrid which limits significant load
decrease, which causes a reduction in the total operation cost. increase as well as the increased adoption of efficiency
On the other hand, because of the reduced power loss in schemes which helps with load reduction. Also renewable
converters, more critical loads could be supplied by increasing generation would remain the same over the planning horizon
the efficiency. Accordingly, there would be a reduction in as the installed capacity will not change. The market price,
the load curtailment which reduces the reliability cost. Since however, has the highest possibility to increase. To demon-
the installed power of all DERs is unchanged, the investment strate the impact of increase in the market price, the proposed
cost for different values of η would not change. planning problem is solved for a 2% annual increase in mar-
Case 4: In this case, the effect of changing the market ket prices. The total planning cost in this case is reduced to
price ρ on planning results is studied. The installed power $24 635 350 with a cost breakdown of $9 296 503, $15 239 520,
of DERs and costs associated with different market prices and $99 326 for the investment, operation, and reliability costs,
are represented in Tables X and XI, respectively. By 10% respectively. Following the increase in market prices, the
decrease in the market price, the microgrid planning solution microgrid would be willing to sell more power to the main
remains unchanged, except for the installed capacity of dis- grid which causes a drop in the operation cost. On the other
patchable units 3 and 4. Generally, when the market price is hand, in order to be able to sell more electricity the micro-
low, the microgrid would buy more power from the main grid, grid would install additional DER capacity which causes an
hence the exchanged power with the main grid would be pos- increase in the investment cost.
itive in many hours. Therefore, the power generation of DERs Arbitrary values for DERs’ allowable installation capacity
would decrease in several hours, which reduces the operation were used in the proposed studies to show the effectiveness
cost. Increasing the market price by 10% causes the micro- of the microgrid planning model in handling capacity limita-
grid planning solution to install DERs 1 and 2 in addition to tions. If the limits are removed, the planning problem will
LOTFI AND KHODAEI: AC VERSUS DC MICROGRID PLANNING 303

select only the most economical candidate while ignoring thus decreasing the load curtailment, and accordingly,
all other candidates, which is not a very practical assump- the reliability cost.
tion. Some examples of these limitations are the rooftop solar The proposed microgrid planning problem model
panel installations in a community microgrid, which would could be further expanded to enhance practicality and
be restricted by the rooftop area that can be covered by pan- computational viability. Specific areas for the future work are
els, and thermal unit, which cannot be installed in densely identified as listed in the following.
populated areas.
A. Uncertainty Consideration
V. D ISCUSSION In this paper, forecasted data were used for hourly load,
renewable energy, and market prices. Moreover, the islanding
DC microgrids could potentially improve microgrid eco- is considered within some specific hours in a planning year.
nomic benefits when the ratio of dc loads is high, and further The accurate data forecasting in microgrid planning models is
be considered as viable alternatives to ac microgrid installa- a difficult task as there are various uncertainties in the plan-
tions. According to the studied cases, the following could be ning data. In other words, there is an error associated with all
concluded. forecasted values. Uncertainty considerations could potentially
1) Among ac dispatchable generating units, those which alter the microgrid planning results. This issue has been stud-
offer a less expensive power would be installed first ied in [14]. Similar methods can be applied here to expand
although they may be associated with higher capi- the microgrid planning problem and make a more accurate
tal costs. decision between ac and dc microgrid installations.
2) Among nondispatchable units, the solar unit would be
installed in all cases because of the partial coincidence B. Computational Complexity
of its generation pattern with the market price and load
variations. The type of the microgrid and DER generation mix in the
3) The fuel cell would not be installed in any cases since it proposed microgrid planning model are determined in an inte-
is associated with a significantly higher investment cost grated fashion by solving a single optimization problem. This
compared to other DERs. problem, however, is large-scale and nonconvex. A decom-
4) The most decisive factor in determining the type of the position method could be employed in this case to convert
microgrid is the ratio of dc loads. Changing this ratio the problem into a set of smaller and easier to solve, yet
would cause the total cost to change, so it could be coordinated, subproblems. The application of decomposition
used as a tool to find a critical point where dc microgrid methods in solving large-scale planning problems is exten-
would be more economical than the ac microgrid. sively discussed in the literature and can be directly used here.
5) Increasing critical loads, converters efficiency, or the A suggested decomposition for the proposed microgrid plan-
market price would cause a decrease in the operation ning problem would include a long-term investment master
and reliability costs. problem, a short-term operation subproblem, and a reliabil-
6) An increase in critical loads would cause the microgrid ity subproblem. The investment plan obtained in the master
planning solution to install more dispatchable capac- problem will be examined in subproblems to find optimal
ity which increases the investment cost. Since the total DER schedule as well as desired levels of reliability. The final
load is unchanged, there would be an excess generated solution would be obtained in an iterative fashion.
power which would be sold to the main grid, hence the
operation cost would decrease. On the other hand, more VI. C ONCLUSION
critical loads would be supplied which causes a decrease Among different categories of microgrids, i.e., ac, dc, and
in the load curtailment and the reliability cost. hybrid, extensive research has been conducted in the operation
7) Increasing converters efficiency would cause a decrease and control of ac microgrids. DC microgrids could, however,
in the power loss which on one hand decreases the offer several advantages compared to ac microgrids: providing
importing power from the main grid in many hours, a more efficiently supply of dc loads and reducing losses due
thus decreasing the total operation cost, and on the other to the reduction of multiple converters used for dc loads, easier
hand, more critical loads could be supplied; hence, there integration of dc DERs, and eliminating the need for synchro-
would be a reduction in the load curtailment which nizing generators. In this paper, different components of ac
reduces the reliability cost. and dc microgrids were explained, followed by developing
8) The investment cost would change by changing the a microgrid planning model with the objective of determining
installed DER capacity. Therefore, the investment cost the optimal DER generation mix and the type of the micro-
would remain unchanged by increasing η since the DER grid, i.e., either ac or dc. It was shown that this model was
generation mix does not change. able to identify threshold ratios of dc loads which made the
9) By increasing the market price, it would be desirable to dc microgrid a more economically viable solution than the ac
install all dispatchable and nondispatchable units, except microgrid. In other words, for ratios smaller than the thresh-
for the fuel cell, in order to sell as much power as pos- old ratio, ac microgrid would be more economical and for
sible to the main grid which would cause a decrease ratios larger than that, dc microgrid would be more economi-
in the operation cost, and also supply all critical loads, cal. The problem objective was to minimize the total planning
304 IEEE TRANSACTIONS ON SMART GRID, VOL. 8, NO. 1, JANUARY 2017

cost subject to prevailing planning and operation constraints, [17] X. Lu, N. Liu, Q. Chen, and J. Zhang, “Multi-objective optimal schedul-
and was formulated using MIP. Numerical results were pre- ing of a DC micro-grid consisted of PV system and EV charging
station,” in Proc. IEEE Innovat. Smart Grid Technol.—Asia (ISGT Asia),
sented to analyze the impact of the ratio of dc loads, the ratio Kuala Lumpur, Malaysia, May 2014, pp. 487–491.
of critical loads, converters efficiency, and market price on [18] V. K. Hema and R. Dhanalakshmi, “Analysis of power sharing on hybrid
microgrid planning solutions. It was verified that the decisive AC-DC microgrid,” in Proc. Annu. Int. Conf. Emerg. Res. Areas Magn.
Mach. Drives (AICERA/iCMMD), Kottayam, India, Jul. 2014, pp. 1–6.
factor in determining the type of the microgrid would be the [19] N. Eghtedarpour and E. Farjah, “Power control and management in
ratio of dc loads. In other words, if other parameters changed a hybrid AC/DC microgrid,” IEEE Trans. Smart Grid, vol. 5, no. 3,
except for the ratio of dc loads, the type of the microgrid pp. 1494–1505, May 2014.
[20] E. Shimoda, S. Numata, J. Baba, T. Nitta, and E. Masada, “Operation
would not change. It was also shown that increasing the ratio planning and load prediction for microgrid using thermal demand esti-
of critical loads would increase the total installed dispatchable mation,” in Proc. IEEE Power Energy Soc. Gen. Meeting, San Diego,
generation capacity. Finally, it was demonstrated that changing CA, USA, Jul. 2012, pp. 1–7.
[21] Estimating the Value of Lost Load. [Online]. Available:
critical loads, converters efficiency, or the market price would http://www.ercot.com/content/gridinfo/resource/2015/mktanalysis/
significantly affect the operation and reliability costs. ERCOT_ValueofLostLoad_LiteratureReviewandMacroeconomic.pdf,
accessed Jan. 25, 2015.
[22] C. K. Woo and R. L. Pupp, “Cost of service disruptions to electricity
R EFERENCES consumers,” Int. J. Energy, vol. 17, no. 2, pp. 109–126, Feb. 1992.
[23] Y. L. Mok and T. S. Chung, “Prediction of domestic, industrial and
[1] M. Shahidehpour, “Role of smart microgrid in a perfect power system,”
commercial interruption costs by relational approach,” in Proc. 4th Int.
in Proc. IEEE Power Energy Soc. Gen. Meeting, Minneapolis, MN,
Conf. Adv. Power Syst. Control Oper. Manage., vol. 1. Hong Kong,
USA, Jul. 2010, p. 1.
Nov. 1997, pp. 209–215.
[2] M. Shahidehpour and J. Clair, “A functional microgrid for enhancing
[24] Illinois Institute of Technology Campus Data. [Online]. Available:
reliability, sustainability, and energy efficiency,” Elect. J., vol. 25, no. 8,
http://www.iitmicrogrid.net/microgrid.aspx, accessed Jan. 25, 2015.
pp. 21–28, Oct. 2012.
[25] S. Schoenung, “Energy storage systems cost update,” Sandia Nat. Lab.,
[3] S. Bahramirad, W. Reder, and A. Khodaei, “Reliability-constrained opti-
Albuquerque, NM, USA, Tech. Rep. SAND2011-2730, 2011.
mal sizing of energy storage system in a microgrid,” IEEE Trans. Smart
[26] Distributed Generation Renewable Energy Estimate of Costs. [Online].
Grid, vol. 3, no. 4, pp. 2056–2062, Dec. 2012.
Available: http://www.nrel.gov/analysis/tech_lcoe_re_cost_est.html,
[4] N. Hatziargyriou, H. Asano, M. R. Iravani, and C. Marnay, “Microgrids:
accessed Jan. 25, 2015.
An overview of ongoing research, development and demonstration
[27] R. Remick and D. Wheeler. Molten Carbonate and Phosphoric Acid
projects,” IEEE Power Energy Mag., vol. 5, no. 4, pp. 78–94,
Stationary Fuel Cells: Overview and Gap Analysis. [Online]. Available:
Jul./Aug. 2007.
http://www.nrel.gov/docs/fy10osti/49072.pdf, accessed Jan. 25, 2015.
[5] A. G. Tsikalakis and N. D. Hatziargyriou, “Centralized control for opti-
[28] List of Converters Prices. [Online]. Available: http://www.alibaba.com/
mizing microgrids operation,” IEEE Trans. Energy Convers., vol. 23,
product-detail/2wm-3wm-5wm-rectifier-system-and_60148157747.html,
no. 1, pp. 241–248, Mar. 2008.
accessed Jan. 25, 2015.
[6] B. Kroposki et al., “Making microgrids work,” IEEE Power Energy
[29] CPLEX 12. (2013). IBM ILOG CPLEX User’s Manual. [Online].
Mag., vol. 6, no. 3, pp. 40–53, May 2008.
Available: http://gams.com/dd/docs/solvers/cplex.pdf, accessed
[7] S. Parhizi, H. Lotfi, A. Khodaei, and S. Bahramirad, “State of the art in
Jan. 25, 2015.
research on microgrids: A review,” IEEE Access., vol. 3, pp. 890–925,
Jul. 2015.
[8] A. Khodaei, “Microgrid optimal scheduling with multi-period islanding
constraints,” IEEE Trans. Power Syst., vol. 29, no. 3, pp. 1383–1392,
May 2014.
[9] A. Khodaei, “Resiliency-oriented microgrid optimal scheduling,”
IEEE Trans. Smart Grid, vol. 5, no. 4, pp. 1584–1591, Jul. 2014. Hossein Lotfi (S’15) received the B.S. degree in electrical engineering and
[10] A. Khodaei and M. Shahidehpour, “Microgrid-based co-optimization of the Master’s degree in business administration from the Sharif University of
generation and transmission planning in power systems,” IEEE Trans. Technology, Tehran, Iran, in 2008 and 2010, respectively. He is currently
Power Syst., vol. 28, no. 2, pp. 1582–1590, May 2013. pursuing the Ph.D. degree in electrical engineering with the Department
[11] S. Bahramirad, A. Khodaei, J. Svachula, and J. R. Aguero, “Building of Electrical and Computer Engineering, University of Denver, Denver,
resilient integrated grids: One neighborhood at a time,” IEEE Electrific. CO, USA.
Mag., vol. 3, no. 1, pp. 48–55, Mar. 2015. His current research interests include electricity markets, power system
[12] H. Nikkhajoei and R. H. Lasseter, “Distributed generation interface economics, microgrid planning, and smart electricity grids.
to the CERTS microgrid,” IEEE Trans. Power Del., vol. 24, no. 3,
pp. 1598–1608, Jul. 2009.
[13] P. Cairoli and R. A. Dougal, “New horizons in DC shipboard power
systems: New fault protection strategies are essential to the adoption
of dc power systems,” IEEE Electrific. Mag., vol. 1, no. 2, pp. 38–45,
Dec. 2013.
[14] A. Khodaei, S. Bahramirad, and M. Shahidehpour, “Microgrid plan-
ning under uncertainty,” IEEE Trans. Power Syst., vol. 30, no. 5,
pp. 2417–2425, Sep. 2015.
[15] P. T. Baboli, M. Shahparasti, M. P. Moghaddam, M. R. Haghifam, Amin Khodaei (SM’14) received the Ph.D. degree in electrical engineering
and M. Mohamadian, “Energy management and operation modelling from the Illinois Institute of Technology, Chicago, IL, USA, in 2010.
of hybrid AC–DC microgrid,” IET Gen. Trans. Dist., vol. 8, no. 10, He was a Visiting Faculty with the Robert W. Galvin Center for Electricity
pp. 1700–1711, Oct. 2014. Innovation, Chicago, from 2010 to 2012. He joined the University of Denver,
[16] C. Huang, M. Chen, Y. Liao, and C. Lu, “DC microgrid operation Denver, CO, USA, in 2013, as an Assistant Professor. His current research
planning,” in Proc. Int. Conf. Renew. Energy Res. Appl. (ICRERA), interests include power system operation, planning, computational economics,
Nagasaki, Japan, pp. 1–7, Nov. 2012. microgrids, and smart electricity grids.

You might also like