Professional Documents
Culture Documents
Microgridsoperationinislandedmode FINAL R1
Microgridsoperationinislandedmode FINAL R1
Abstract
The smart grid concept is intended to improve power system operation and control. A
feasible path to make the system smarter is through microgrids deployment. A microgrid is a
small-scale power system with its power generation units and deferrable loads, and it may work
islanded or connected to the main power grid. The main objective of microgrids in islanded
mode is to allow the system to operate even in adverse scenarios, such as faults in main grid,
high prices of main grid’s power, and supplying remote areas. In the case of an islanding, high
priority loads, such as hospitals, transportation, and telecommunication facilities must have their
supply assured. This is possible due to the penetration of Distributed Energy Resources
(DERs), including renewable, fossil, combined heat and power, and energy storage units.
However, the operation of microgrids in islanded mode requires more attention due to the
higher outage risk since the power generation capacity is limited. Consequently, microgrids may
be provided by an Energy Management System (EMS) responsible for managing the scarce
power resources to maintain the supply for the highest priority customers connected to the grid.
Such management strategy is a complicated and ambitious task and demands a robust and
reliable communication system .
This chapter investigates some control and management issues in microgrids islanded
operation mode. Firstly, the main features and requirements of islanded mode in comparison
with connected mode are described. Some discussions about control requirements on different
control levels are presented. Communications networks are also discussed. These
communications networks enable the expected smart features in the microgrids through the
bidirectional data flow. The steps for designing a mobile telecommunication network for a
microgrid are described, and a study case considering a small microgrid is investigated to show
the communication network design steps and the operation of an islanded microgrid during one
day.
1. INTRODUCTION
Microgrids are a feasible way to deploy the smart grids, since connecting
small and smart microsystems in different sites is more realistic and less
expensive than building a completely new infrastructure [1]-[2]. These
distributed Microsystems should have their own Distributed Energy Resources
(DERs), e.g., wind turbines, photovoltaic arrays, energy storage systems
(ESSs), and fossil-fuel microturbines. They also have a communication network,
which enables some data exchange between the local controller and Microgrid’s
Central Controller (MGCC), or between distributed agents. Metering and
sensing are also expected features that enable grid smartness.
The microgrid’s capacity to operate in islanded mode, the proper
operation of the protection schemes and the application of different
methodologies of grid reconfiguration enables the self-healing capacity. The
continuity of power supply in islanded mode depends on the existence of
enough DER installed capacity, proper energy management and other issues
related to grid dynamic behavior, e. g. power balancing, low grid inertia, and
higher frequency variations.
The islanded operation has some tighter requirements than connected
operation. Larger frequency variations, nodal voltage limits, lack of high inertia
power sources, and the randomness of the renewable power generation are
some issues that should be faced.
This chapter aims to discuss the architecture of an MGCC and the
communication infrastructure necessary for its proper operation in islanded
mode. The designing process of a mobile telecommunication network for a
microgrid is also detailed. Finally, a study case of an islanded microgrid is also
presented, where the ideas and concepts previously presented are further
investigated.
Decentralized
Control Droop Response
Voltage Restore
Frrequency Restore
Reconnection Strategy
Centralized
Control
Economic Issues
Losses Reduction
Otimizated Operation
Utility Grid
MGCC
Primary AC DC
DC AC
Control
Secondary and
Tertiary Control Primary AC DC
DC AC MICROGRID
Control
DC
AC
AC DC
DC AC
DC
AC
Droop range
Operation Points
fref Connected Mode
QC
Frequency[Hz]
Voltage [pu]
Connected Mode
Vref
f Islanded Mode
QL
Islanded
V Mode
Frequency[Hz]
Voltage [pu]
fref
Vref*
Vref
3. COMMUNICATIONS IN MICROGRIDS
As mentioned in the previous section, secondary and tertiary control
communications play a key role in microgrid operation. A reliable, efficient and
robust communication network must be implemented since the MGCC
operation is essential for the system reliability.
The major purpose of an intelligent network is to modernize the electrical
system, allowing a two-way flow of energy and information between the
consumer and the utility [9].
Systems will interact with the environment and take decisions
autonomously. To accomplish it, extensive technologies must be put into
operation, and several devices have to interact, such as sensors, meters, and
advanced control systems.
Smart grids should offer communication systems that are secure, reliable
and adaptive to their environment. The amount of information that will flow
across the network is high, and an analysis of each application is required [10].
The communication network architecture is divided into layers, and there
is an interaction between each layer. This interaction makes possible the
inclusion of a new infrastructure model called Advanced Metering Infrastructure
(AMI) [11], which will allow the bidirectional flow of information, increasing
control on demand power distribution and other functionalities.
𝑃𝑡𝑥
𝜂=
𝑃𝑎𝑚𝑝
, (3)
where 𝑃𝑡𝑥 is the amplifier output power, and 𝑃𝑎𝑚𝑝 is the input power for each
antenna.
According to Equation (3), the power consumed by the power amplifier
can be determined using Equation (4):
𝑃𝑇𝑋
𝑃𝑎𝑚𝑝 = (4)
𝜂
where 𝑃𝑎/𝑐 and 𝑃𝑟𝑒𝑐𝑡 are the power consumption of the air conditioning and the
rectifier, and 𝑃𝑎𝑚𝑝 , 𝑃𝑡𝑟𝑎𝑛𝑠𝑐𝑒𝑖𝑣𝑒𝑟 , and 𝑃𝑑𝑠𝑝 are the power consumption of the
amplifier, transceiver and digital signal processing, respectively. Notice that a
microcell scheme does not support more than one sector and air conditioning is
not always implemented, but as the complete power consumption model is
considered, it will be included in it. Table 1 illustrates the power consumption of
components of a Long-Term Evolution (LTE) RBS.
In the case of the study presented in the next section, LTE is the adopted
technology [19]. LTE is a wireless broadband technology, also known as the
fourth generation mobile (4G). Developed by 3GPP (Third Generation
Partnership Project), this is one of the recent standardization of mobile
telephony. The main features of LTE technology are the transmission of data at
a high transmission rate and low latency.
3.1.2 Planning a Mobile Network for a Microgrid
The network planning process is carried out to extract the highest
performance coverage with the least amount of equipment possible. Several
steps have to be fulfilled to achieve these goals. The first planning stage is to
obtain information such as the desired coverage area, the distribution of RBSs
in the coverage area, and the required Quality of Service (QoS).
Some of users who will access the communication networks using RBS
should be assessed. This represents 60% to 80%of energy consumption in a
radio access network [20]. The result will give a minimum density of RBS to be
installed to meet the desired coverage area. The following topics will describe
step by step the cell planning of a micro network for a microgrid considering the
LTE as a candidate technology.
The first stage is to calculate the Link Budget, where the maximum
propagation loss allowed for users who may receive the signal at the edge of
this system is calculated.
After designing the Link Budget, the next step is to determine the
radius of the cell, allowing an estimation of the number of base stations required
to cover the desired area to be connected. Finally, it is possible to assess the
total power consumption of communications network.
A detailed analysis of the site where the LTE wireless communication
system will be implemented is necessary, taking into account characteristics of
the environment, the place where the RBSs will be installed, topography, and
population density.
During the designing of cellular networks, it is necessary to calculate
both the downlink and the uplink link budget [18]. The uplink is important
because it measures the power and sensitivity of the user, while the downlink
considers coverage constraints. As the main objective here is to provide
communications for the maximum area available, the worst value of sensitivity
is considered.
After determining the coverage area, the next step is assessing the link
budget for both the downlink and the uplink. Then, it is possible to determine the
maximum loss per way, which is an important variable to calculate the radius of
the cell [18]. Equation (8) assesses the link budget in decibels [dB]:
𝐿 = 𝑃𝑡𝑥 + 𝐺𝑡𝑥 − 𝐿𝑡𝑥 − 𝑆𝑁𝑅𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 − 𝑆𝑟𝑥 + 𝐺𝑟𝑥 − 𝐿𝑟𝑥 + 𝐺𝑑𝑣 (8)
where, L is the path loss for downlink, 𝑃𝑡𝑥 is the transmission power [dBm], 𝐺𝑡𝑥
is the transmit antenna gain [dBi], 𝐿𝑡𝑥 are the loss of transmission [dB],
𝑆𝑁𝑅𝑟𝑒𝑞𝑢𝑖𝑟𝑒𝑑 is the Required Signal Noise Ratio [dB], 𝑆𝑟𝑥 is the required receiver
sensitivity [dB], 𝐺𝑟𝑥 is the receiver antenna gain [dBi], 𝐿𝑟𝑥 are the losses in
reception [dB], 𝐺𝑑𝑣 is the diversity gain [dBi].
Therefore, the calculation of the maximum propagation loss for the link
propagation is described in Equation (9):
where 𝐿𝑝𝑒𝑛𝑒𝑡𝑟𝑎𝑡𝑖𝑜𝑛 indicates the loss of radio signal due to obstruction, BL is the
losses due to obstruction to by a body and F is the fade margin, it means the
minimum acceptable receiver level. For calculating the maximum path loss, the
following values from Table 2 are used [23].
Table 2 - Parameters for Path Loss Calculation
where R is the maximum range in meter, ℎ𝑢𝑠𝑒𝑟 and ℎ𝐵𝑆 are the antenna and
RBS height in meters. After this stage, it is possible to determine the number of
RBS for a predetermined circular area applying Equation (11) [23]:
So, the maximum power consumption from all RBSs (Pmax) is assessed
according to Equation (12):
𝑁𝑢𝑚𝑏𝑒𝑟𝐵𝑆
632
1.5 km
611 684 671 692 675
652 680
0.4 km
Figure 5 – Modified IEEE 13 bus system coverage area.
From the Figure 5 and Equation (11), it is determined the number of base
stations for the desired area as in Equation (22),
0.6
𝑁𝑢𝑚𝑏𝑒𝑟𝑅𝐵𝑆 = =3 (22)
𝜋 ∗ (0.25)2
And finally, the total power consumption for an LTE system network
implemented for communications in a microgrid is assessed in Equation (23), as
described earlier in Equation (12),
𝑃𝑚𝑎𝑥 = 3 ∗ 376.62 = 3 ∗ 376.62 = 1130 𝑊 (23)
After discussing the communications network design for this specific
study case, the modifications to the power grid need to be described further.
Three dispatchable units are considered, one ESS, three renewable units, and
three base stations. The topology of the proposed microgrid is illustrated in
Figure 6.
Substation
~
_
_ 650
~
646 645 633 634
632
~ ~
~
_
_ _
~
_
~
_
652 680
Figure 6 – The Microgrid test system
The RBSs were dimensioned considering the power demand and the
size of the system. According to the approach described in the previous section
and to cover the whole area, three base stations should be installed. Each one
consumes 1.13 kW, and they are located as depicted in Figure 6.
During the islanded operation, the power supply to all loads must be
kept. However, a large piece of the power generation from the microgrid is
based on small-scale renewables. Their intermittent feature may cause a large
variation in the power generation, which is regulated by the presence of ESSs.
Connected to the microgrid, there are high priority customers which must
be supplied at any time. Therefore, an operation framework must be developed
to ensure the supply of the highest priority loads by applying some actions, e.g.
load shedding schemes.
Some important pieces of information about loads values and generation
schedule, both dispatchable and non-dispatchable, are presented in Tables 3
and 4, respectively. In Table 4, the droop coefficients and the maximum power
of the dispatchable units are also presented.
Equivalent Demand
Bus Power Factor Priority
[kW]
Droop Droop
Bus Maximum Power [pu]
coefficient 𝒎 Coefficient 𝒏
650 Variable Variable 0.6
632 0.025 0.00001 0.6
633 0.025 0.00001 0.6
Photovoltaic arrays and wind turbines are considered as non-
dispatchable units. In this case, they operate in PQ mode. The models used for
photovoltaic arrays and wind turbines are presented in [26]-[27]. The ESSs
have PQ inverters that control the injected power based on the system’s
demand. The data regarding renewable sources and ESS are summarized in
Table 5.
Table 5 – Renewable and ESS configuration.
Solar
Bus 𝒏𝒔 𝒏𝒑 𝑷 [𝒑𝒖]
680 20 20 0,35
Wind Turbine
Bus 𝝎𝒄𝒊 [𝒎/𝒔] 𝝎𝒄𝒐 [𝒎/𝒔] 𝝎𝒓 [𝒎/𝒔] 𝑷 [𝒑𝒖]
645 4 12 8 0,1
692 4 12 8 0,1
Batteries
Bus 𝑪𝒂𝒑𝒎á𝒙 [𝒑𝒖. 𝒉𝒓] 𝑪𝒂𝒑𝒎𝒊𝒏 [𝒑𝒖. 𝒉𝒓] 𝑷[𝒑𝒖]
633 0.03 0.002 0,01
10 1000
[kW/m 2]
[m/s]
5 500
0 0
01 :00
03 :59
05 58
07 57
09 :56
11 55
13 :55
15 :54
17 53
19 52
21 :51
23 50
0
01 :00
03 :59
05 58
07 57
09 :56
11 55
13 :55
15 :54
17 53
19 52
21 :51
23 50
0
:5
:5
:
:
:
:
:
:
:
:
:
00
00
Photovoltaic cell temperature Loads´ Factor
40 2
30 1.5
[ºC]
20 1
10 0.5
01 :00
03 :59
05 58
07 57
09 :56
11 55
13 :55
15 :54
17 53
19 52
21 :51
23 50
0
01 :00
03 :59
05 58
07 57
09 :56
11 55
13 :55
15 :54
17 53
19 52
21 :51
23 50
0
:5
:5
:
:
:
:
:
:
:
:
:
00
00
2
Dispatchable Units
1.8
Renewable Units
1.6 Total Generation
Load System
1.4
Active Power [pu]
1.2
0.8
0.6
0.4
0.2
0
0
0
:0
:5
:5
:5
:5
:5
:5
:5
:5
:5
:5
:5
:5
00
01
03
05
07
09
11
13
15
17
19
21
23
59.7
59.6
59.5
[Hz]
59.4
59.3
59.2
59.1
59
0
0
:0
:5
:5
:5
:5
:5
:5
:5
:5
:5
:5
:5
:5
00
01
03
05
07
09
11
13
15
17
19
21
23
Figure 9 – Frequency profile of the microgrid
Capacity of Batteries |
0.03
0.02
[pu.hr]
0.01
0
0
0
:0
:5
:5
:5
:5
:5
:5
:5
:5
:5
:5
:5
:5
00
01
03
05
07
09
11
13
15
17
19
21
23
Power of Batteries
0.01
0.005
[pu]
-0.005
-0.01
0
0
:0
:5
:5
:5
:5
:5
:5
:5
:5
:5
:5
:5
:5
00
01
03
05
07
09
11
13
15
17
19
21
23
0.8
1
0.8
1
0.8
1
0.8
1
:0 :0 :0 :0
03 0 03 0 03 0 03 0
:5 :5 :5 :5
8 8 8 8
07 07 07 07
:5 :5 :5 :5
6 6 6 6
11 11 11 11
:5 :5 :5 :5
15 5 15 5 15 5 15 5
:5 :5 :5 :5
3 3 3 3
19 19 19 19
:5 :5 :5 :5
1 1 1 1
23 23 23 23
:5 :5 :5 :5
0 0 0 0
0.8
0.8
0.8
1
1
1
:0 :0 :0
03 0 03 0 03 0
:5 :5 :5
8 8 8
07 07 07
:5 :5 :5
11 6 11 6 11 6
:5 :5 :5
15 5 15 5 15 5
:5 :5 :5
3 3 3
19 19 19
:5 :5 :5
1 1 1
23 23 23
:5 :5 :5
0 0 0
:0 :0 :0
03 0 03 0 03 0
:5 :5 :5
8 8 8
07 07 07
:5 :5 :5
6 6 6
11 11 11
:5 :5 :5
Figure 5 – Voltage profiles for all buses.
15 5 15 5 15 5
:5 :5 :5
3 3 3
19 19 19
:5 :5 :5
1 1 1
23 23 23
:5 :5 :5
0 0 0
1
1
1
:0 :0 :0
03 0 03 0 03 0
:5 :5 :5
8 8 8
07 07 07
:5 :5 :5
6 6 6
11 11 11
:5 :5 :5
15 5 15 5 15 5
:5 :5 :5
3 3 3
19 19 19
:5 :5 :5
1 1 1
23 23 23
:5 :5 :5
0 0 0
REFERENCES
[1] H. Farhangi, “The Path of the Smart Grid,” IEEE Power & Energy Magazine, vol. 8, no.
1, pp.18-28, 2010.
[2] A. Khodaei “Resiliency-Oriented Microgrid Optimal Scheduling,” IEEE Transactions on
Smart Grid, vol. 5, no. 4, pp. 1584-1591, 2014.
[3] B. Starfield, H. Lotfi, A. Khodaei, and S. Bahramirad, “State of the Art in Research on
Microgrids: A Review,” IEEE Access, vol. 3, no. 1, pp. 890–925, 2015.
[4] J. A. P. Lopes, C. L. Moreira, and A. G. Madureira, “Defining Control Strategies for
MicroGrids Islanded Operation,” IEEE Transactions Power Systems., vol. 21, no. 2, pp.
916–924, 2006.
[5] J. M. Guerrero, J. C. Vasquez, J. Matas;, L. G. de Vicuña, and M. Castilla, “Hierarchical
Control of Droop-Controlled AC and DC Microgrids — A General Approach Toward
Standardization,” IEEE Transactions. Industrial Electronics, vol. 58, no. 1, pp. 158–172,
2011.
[6] A. C. Zambroni de Souza, M. Santos, M. Castilla, J. Miret, L. G. De Vicuña, and D.
Marujo, “Voltage security in AC microgrids : a power flow-based approach considering
droop- controlled inverters,” IET Renewable Power Generation, pp. 1–7, 2015.
[7] Y. Jia, D. Liu, and J. Liu, “A Novel Seamless Transfer Method for a Microgrid Based on
Droop Characteristic Adjustment,” in IEEE Internacional Power Electronics and Motion
Control Conference, 2012, pp. 362–367.
[8] C. Jin, M. Gao, X. Lv, and M. Chen, “A Seamless Transfer Strategy of Islanded and
Grid-connected Mode Switching for Microgrid based on Droop Control,” in IEEE Energy
Conversion Congress and Exposition, 2012, pp. 969–973.
[9] V. C. Gungor, D. Sahin, T. Kocak, S. Ergut, C. Buccella, C. Cecati, and G. P. Hancke,
“A Survey on smart grid potential applications and communication requirements,” IEEE
Transactions Industrial Informatics, vol. 9, no. 1, pp. 28–42, 2013.
[10] K. Tomsovic, D. E. Bakken, V. Venkatasubramanian, and A. Bose, “Designing the Next
Generation of Real-Time Control, Communication, and Computations for Large Power
Systems,” Proceedings of IEEE, vol. 93, no. 5, pp. 965–979, 2005.
[11] R. R. Mohassel, A. Fung, F. Mohammadi, and K. Raahemifar, “A survey on Advanced
Metering Infrastructure,” International Journal of Electrical Power Energy Systems, vol.
63, pp. 473–484, 2014.
[12] V. Aravinthan, B. Karimi, V. Namboodiri, and W. Jewell, “Wireless communication for
smart grid applications at distribution level—Feasibility and requirements,” IEEE Power
Energy Society General Meeting 2011 IEEE, pp. 1–8, 2011.
[13] Michel Daoud Yacoub. 1993. Foundations of Mobile Radio Engineering (1st ed.). CRC
Press, Inc., Boca Raton, FL, USA.
[14] M. Gruber, O. Blume, D. Ferling, D. Zeller, M. A. Imran, and E. C. Strinati, “EARTH —
Energy Aware Radio and Network Technologies,” 2009 IEEE 20th International
Symposium on Personal Indoor Mobile Radio Communications, January, pp. 1–5, 2009.
[15] S. N. Roy, “Energy Logic : A Road Map to Reducing Energy Consumption in
Telecommunications Networks,” IEEE 30th International Telecommunications Energy
Conference, , pp. 2–10, 2008.
[16] A. Fehske, J. Malmodin, G. Biczók, and G. Fettweis, “The Global Footprint of Mobile
Communications–The Ecological and Economic Perspective,” IEEE Communications
Magazine, August, pp. 55–62, 2011.
[17] M. Deruyck, W. Joseph, and L. Martens, “Power consumption model for macrocell and
microcell base stations,” Transactions on Emerging Telecommunications Technologies,
August 2012, pp. 320–333, 2014.
[18] ETSI, “TR 36.921 - V9.0.0 - LTE; Evolved Universal Terrestrial Radio Access (E-
UTRA); FDD Home eNode B (HeNB) Radio Frequency (RF) requirements analysis
(3GPP TR 36.921 version 9.0.0 Release 9),” Eur. Telecommun., vol. 0, pp. 0–44, 2010.
[19] G. Koutitas and P. Demestichas, “A Review of Energy Efficiency in Telecommunication
Networks,” Telfor Journal, vol. 2, no. 1, pp. 2–7, 2010.
[20] Theodore Rappaport. 2001. Wireless Communications: Principles and Practice (2nd
ed.). Prentice Hall PTR, Upper Saddle River, NJ, USA.
[21] V. Erceg et al., “Channel Models for Fixed Wireless Applications” IEEE802.16.3c-
01/29r4, Broadband Wireless Working Group, IEEE P802.16, 2001.
[22] M. Deruyck, W. Vereecken, E. Tanghe, W. Joseph, M. Pickavet, L. Martens, and P.
Demeester, “Power consumption in wireless access networks,” European Wireless.
Conference, pp. 924–931, 2010.
[23] TSGR. TS 136 104 - V11.4.0 - LTE; Evolved Universal Terrestrial Radio Access (E-
UTRA); Base Station (BS) radio transmission and reception (3GPP TS 36.104 version
11.4.0 Release 11), 2013.
[24] IEEE Distribution Feeders Analysis Subcommittee. Distribution Test Feeders. Available
on: http://ewh.ieee.org/soc/pes/dsacom/testfeeders/index.html.
[25] M. M. A. Abdelaziz, H. E. Z. Farag, E. El-Saadany, Y. A.-R. I. Mohamed. “A Novel and
Generalized Three-Phase Power Flow Algorithm for Islanded Microgrids Using a
Newton Trust Region Method”. IEEE Transactions on Power Systems, V. 1, No. 28, pp.
198-201, 2013.
[26] M. Katsanevakis. “Modelling the photovoltaic module”, 2011 IEEE International
Symposium on Industrial Electronics (ISIE), June de 2011, pp. 1414-1419.
[27] E. Vittal; M. O'Malley; A. Keane; “A Steady-State Voltage Stability Analysis of Power
Systems With High Penetrations of Wind”. IEEE Transactions on Power Systems, vol.
25, pp. 433-442, 2010.