TotalFinaElf E & P Nederland B.V.

Den Haag, november 2002


OPE/#12945/JCS/MH/AVE

FINAL DRILLING REPORT OF WELL K6-GT4

Dear Sirs,

Please find herewith a copy of the final drilling report of K6-GT4 well that TotalFinaElf
E&P Nederland B.V. drilled from October 13, 2001 till December 12, 2001 with the
Noble Ronald Hoope jack-up rig.

DCD Manager

M. Raimond
TotalFinaElf E & P Nederland B.V. DISTRIBUTION LIST

To :
TFE DIG EUROPE Paris M. Daubenfeld
TFE DGEP/TDO/FPL Pau M. Brangetto/N. Seureau
TFE TDO/FPL/METHODES DOCUMENTATION Pau (2 ex.) D. Mathorel
TFE TDO/FPL/OPERATIONS Paris R. Bériot
TFE TDO/FPL/METHODES DOCUMENTATION Paris Ms. M. Leroux / P. costes
(1 paper copy + Adobe file)

TotalFinaElf E & P Nederland B.V.


Geoscience Division (2 ex.) P. Bousquié/E. Ducornaud
Archives
Operations Manager/Petroleum Engineering (1 ex. in circ.) E. Proust / PED
Drilling and Completion Department (original+ 2 copies) A. van ES
Health Safety and Environment Manager J. Klootsema
Field Operations/Production Engineering J. Monsma
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 3
Ref : OPE/#12945/JCS/MH/AVE

TABLE OF CONTENTS

1 K6-GT4 WELL SUMMARY ......................................................................................................................... 4

2 RIG MOVE + RIG PREPARATION / CONDUCTOR PIPE SET AT 138M RKB............................... 4

3 26” PHASE: FROM 138M TO 682M – 20” CASING AT 678M .............................................................. 5


3.1 MUD SYSTEM ................................................................................................................................................ 5
3.2 20” CASING AND CEMENTING ........................................................................................................................ 6
3.3 CEMENT COMPOSITION .................................................................................................................................. 6
4 17”½ PHASE: FROM 682M TO 1698M - 13"3/8 CASING AT 1694M................................................... 7
4.1 MUD SYSTEM ................................................................................................................................................ 7
4.2 13”3/8 CASING AND CEMENTING ................................................................................................................... 8
4.3 CEMENT COMPOSITION .................................................................................................................................. 8
5 12”¼ PHASE: FROM 1698M TO 3850M – 9”5/8 CSG AT 3848M.......................................................... 9
5.1 MUD SYSTEM .............................................................................................................................................. 10
5.2 9”5/8 CASING AND CEMENTING ................................................................................................................... 11
5.3 CEMENT COMPOSITION ................................................................................................................................ 11
6 8”½ PHASE FROM 3850M TO 4798M – 7”LINER AT 4791M............................................................. 12
6.1 MUD SYSTEM ............................................................................................................................................... 13
6.2 7” LINER AND CEMENTING ........................................................................................................................... 13
6.3 CEMENT COMPOSITION ................................................................................................................................ 14
7 5-7/8” PHASE FROM 4791M TO 5206M.................................................................................................. 15
7.1 MUD SYSTEM ............................................................................................................................................... 16
7.2 LOGGING...................................................................................................................................................... 16
8 ABANDONMENT......................................................................................................................................... 17
8.1 CEMENT COMPOSITION ................................................................................................................................ 18
9 ATTACHMENTS AND JULIA FINAL REPORT................................................................................... 19
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 4
Ref : OPE/#12945/JCS/MH/AVE

1 K6-GT4 Well Summary

K6-GT4 was drilled after L/4A operations L4A2 workover and coil tubing interventions).
The rig move between L4/A platform and K-GT4 platform started on October 13, 2001
at 04h00.
The well K6-GT4 was spud in on October 15, 2001 at 10h00.
TD (5206 MD-RT) was reached on December 4, 2001. The well was abandoned after
the final logging. K6-GT4 drilling operations were finished on December 12, 2001 at
16h00. A geological side-track was decided into the G3 mid panel for production
acceleration purpose, based on the poor result of the well.
A separate report is issued for the K6GT4G operations.

Total well duration: 60.5 days including P&A


Total depth reached: 5206m MD/RKB (5224m planned)

2 Rig move + rig preparation / Conductor pipe set at 138m RKB

The rig move started on October 13, 2001 at 04h00 and was completed on October
15, 2001 at 10h00.
Planned = 1 days Realised = 2.24 days

The 30” Conductor Phase was set at 138m.


Planned = 2 days Realised = 1.56 days (including clean out)
30" 309.72 lbs/ft X52 pipes with D60 Dril-Quip connector were run. Conductor pipe
was hammered to 138m with a last blow of 200 blows / 25 cm. The final penetration
was 53m below mud line.
The 30”CP was then cut 5m below rotary table and the diverter installed.
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 5
Ref : OPE/#12945/JCS/MH/AVE

3 26” Phase: from 138m to 682m – 20” casing at 678m

26” drilling planned = 3 days Realised = 1.83 days)

The objective of this section was to set a secondary string with the shoe 20m in the
North Sea Group Claystone in order to isolate the North Sea Group sand and
therefore drill the deviated 17”1/2 section with weighted mud.
A 26” mill tooth bit was run with a BHA incorporating the 11”3/4 DHM and the AKO
set at 1.3° bent. The 30”CP was cleaned out and at 149m; a gyro survey was done to
control the angle and orientated the assembly. From 240m to 250m, it was difficult to
achieve the required dogleg due to erratic formation. After 350m, it was then possible
to achieve 0.85°/10m. At 650m, the well was lined up according to directional plan
with 31° angle and 62°azimuth. At TD, a wiper trip was performed. Back reaming was
necessary in the clay section from 682m to 335m but no overpull was observed
indicating the hole was in good shape. After having run back to bottom, a 50m3 hivis
pill was spot prior to run the 20”casing.

3.1 Mud System

MUD TYPE Bentonite Spud Mud (BBS)


DRILLED DEPTH 138m – 682m
FROM/TO
DENSITY SG 1.04 – 1.17

FUNNEL VIS s/qt 45 – 60


PV cP 9 – 10
YV lbs/100ft2 32 – 35
6 RPM 26 – 30
FLUID LOSS cc 17 – 22
KCl g/l 0

During this section the rheology was kept to the targets, there was no indication of
poor hole cleaning, as cuttings returns over the shakers were observed during the
whole section. The Shale shakers (4 x VSM 100) were dressed with 84’s and 105’s
Baroid screens, and 2 Centrifuges (1-Low speed, and 1-High speed) ran at all time
during this section, helping a lot in keeping the mud weight down. The dilution rate
was slightly higher than planned (1.08m3/m, planned 1 m3/m).
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 6
Ref : OPE/#12945/JCS/MH/AVE

3.2 20” casing and cementing

20” casing planned = 3 days Realised = 2.56 days

20” 129.33# X56 RL4s casings were run to 678m without problem. After having
circulated a casing volume, the 5”1/2 cement stinger was run to 658m.
The casing was cemented with a total cement slurry volume of 166m3 (118m3 Lead
slurry @ 1.44sg and 48m3 Tail slurry @1.67sg). The cement stinger was then pulled
to surface.
After having cut the 20” casing, the 20”3/4 x 3k FMC casing head was installed and
the diverter put in place and tested.

3.3 Cement composition

Cmt/Flush/Spacer Volume Top of cement Event


Recipes
20” Casing at -Got cement returns
on surface after
678 m TMD = 656m Spacer : 10 m3 Lead: up to
pumping 118m3 LS,
TVD surface.
Lead : 118 m3 (represent 7% open
Cementing with stinger Tail : 476m (+/- hole excess),
Tail : 48 m3
system 200m from followed by 48m3 of
Volume: 50% excess shoe) Tail slurry.
Spacer : FW+5-7
on annular for Lead
kgs PAC-R /m3.
and Tail.
Sg:1.15.
Displacement rate:
Lead: Pozmix 8000+
1400 lpm.
Sea Water + 0.5 ltr/ton
NF-6- at 1.44 Sg Displacement
volume: 8.5 m3.
Tail: Pozmix 8000+
Sea Water + 0.5 ltr/ton
NF-6- at 1.67 Sg
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 7
Ref : OPE/#12945/JCS/MH/AVE

4 17”½ Phase: from 682m to 1698m - 13"3/8 casing at 1694m

17”1/2 drilling planned = 6 days Realised = 4.25 days


The objective of this section was to drill into the top of the Ommelanden Chalk and to
cover the North Sea Group claystone. The trajectory was designed to hold the
32°angle until shoe depth.
A 17”1/2 Smith MGSSH mill tooth bit was run with a steerable BHA incorporating the
11”1/4 DHM and the AKO set at 1.2°. The section was drilled from 682m to 1698m
with KCl mud, sweeping hole time to time. At 1227m, a wiper trip was performed
without problem to control the wellbore. The mud weight was increased based on
observation of caving in the cuttings. During drilling, the Rop was controlled to
20m/hour in order to minimise overloading the annulus with cuttings and risking
plugging surface flow lines. At section TD, a wiper trip was performed with difficult
tight spots and pack off tendencies. The assembly was eventually pulled out to
surface after having spot a 25m3 hi-vis pill at bottom while pumping out of hole.

4.1 Mud System

MUD TYPE KCl/Glycol/Polymer


DRILLED DEPTH 682m – 1698m
FROM/TO
DENSITY SG 1.16 – 1.30

FUNNEL VIS s/qt 70 – 83


PV cP 21 – 25
YV lbs/100ft2 28 – 30
6 RPM 10 – 20
FLUID LOSS cc 7–4
KCl g/l 130

The mud system used to drill this section was a KCl/Glycol/Polymer with initial mud
weight 1.16 sg. New mud was mixed at the required KCl level of 130 g/l and Glycol
concentration of 3%. In the interval 1140m to 1225m the Geomechanical log showed
an increase 10 – 25%, the hole was then circulated and at the same time the mud
weight was increased from 1.22sg to 1.30sg. During drilling through the clay section,
heavy dilution were made to control the yield point below 30 and fluid loss around
5cc. To maintain the clay inhibition properties, the KCl content was maintained to
remain around 130g/l and Glycol (GEM GP) content at 3% by volume. The Shale
shakers were dressed with 105 and 120 mesh screens and the Centrifuges were run
all times during this section.
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 8
Ref : OPE/#12945/JCS/MH/AVE

4.2 13”3/8 casing and cementing

13”3/8 casing planned = 4 days Realised = 2.54 days

13”3/8 61# N80 BTC casings were run without problem to 1694m breaking circulation
time to time.
The casing was cemented with 49m3 cement slurry @ 1.67sg. During the
displacement, losses where observed and the flow rate was reduced to 1200L/min.
At bumped the casing was tested to 120 bar.
After having cut the 13”3/8 casing, the 13”5/8 x 5K FMC casing head was installed
and the 13”5/8 Bop put in place and tested.

4.3 Cement composition

Cmt/Flush/Spacer Volume Top of cement Event


Recipes
13”3/8 Casing at - After 1hr pumping
1694 m cement, computer
Spacer : 10 m3 Estimated @
gave problem,
Cementing with 1194m (500m
Slurry : 49 m3 continued on
plugs system above shoe)
manual mode.
Spacer:
Volume slurry : - Problem with
FW+4-6 kgs
- 30% excess water supply, then
PAC-R /m3.
on annular cement venturi
Sg:1.40
plugged off.
Slurry: Pozmix Displacement rate:
2000 - 1500 lpm, - Overall job – ok.
8000+ Fresh
Water + 7.2 ltr then 1200 lpm, due
HR-4L/ton +0.5 ltr to losses.
NF-6/ton at Bumping at 120
1.67sg bar.
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 9
Ref : OPE/#12945/JCS/MH/AVE

5 12”¼ Phase: from 1698m to 3850m – 9”5/8 csg at 3848m

12”1/4 drilling planned = 22 days Realised = 13.08 days (including 6.5


hours NPT for OBM transfer pump
failure)

FIT: 1.50sg EMW at 1522m TVD/RKB (13"3/8 casing shoe)

The objective of this section was to drill to the top of the Zechstein salt in order to get
good shoe strength to drill through the salt section. The trajectory was designed to
build angle to 55° and hold until shoe depth.

The Upper Chert formation was drilled with one 12”1/4 insert bit ReedEHP42H from
1698m to 1982m with an average Rop of 12.3m/hour. A steerable assembly with a
9”1/2 DHM and the AKO set at 1.2° was used to build the angle to 55°. The assembly
was pulled to run a PDC bit when the build section was finished and confirmation of
the chert was passed.
A Hughes Christensen BX547 PDC bit was picked up with the same assembly and
drilled with good directional behaviour from 1982m to 3086m and with an average
Rop of 15m/hour. The bit was preventively pulled at top of the bottom cherts to
preserve it.
The lower Ommelanden cherts formation was drilled from 3086m to 3262m with one
12”1/4 insert bit Smith FGS26OD on the same assembly. The DH motor was
changed for a new one although no specific wear was noticed. The AKO was reset to
1.2° to stop the drop tendency seen at end of previous run. In the middle of the
section and to take advantage of a good weather window, the well was displaced with
OBM in order to pass the Holland / Vlieland formations with the next bit. The average
Rop for the run was 3.49m/hour. The bit was pulled when confirmation of cherts was
passed.
A Hughes Christensen BX536 was made up together with the same assembly. The
assembly behaved perfectly well and very little correction was needed to keep the
well on trajectory. The bit drilled from 3262m to 3850m into the Holland / Vlieland
formation at an average Rop of 8m/hour. Prior to enter the salt section, mud weight
was increased to 1.3sg. At section TD, a wiper trip was performed to 13”3/8 shoe
without any problem indicating the well was in good shape. The 9”5/8 casing was
then run.
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 10
Ref : OPE/#12945/JCS/MH/AVE

5.1 Mud System

MUD TYPE Bento/Poly. LTOBM-Enviromul


DRILLED DEPTH 1,694m – 3,146m 3,146m – 3,850m
FROM/TO
DENSITY SG 1.11 – 1.17 1.25 – 1.30
FUNNEL VIS s/qt 49 – 58 50 – 52
PV cP 15 – 18 17 – 24
YV lbs/100ft2 24 – 29 15 – 17
6 RPM 7 – 11 10 – 11
FLUID LOSS cc 6 – 4.5 6.8 – 4.2
KCl, g/l 30 – 10 85 – 130
NaCl, g/l 0 200
Glycol, % depleted N/a
HP-HT, cc N/a 4.3 – 3.8
O/W ratio N/a 75/25 - 79/21
LGS, % N/a 6.9 – 8.8
WPS, g/l N/a 199 – 243
ES, Volt N/a 910 - 920

The salvaged mud from the last phase was diluted to 1.10sg. This mud was used to
drill down to 3146m, at which depth the flow check showed the well was flowing at
200 ltr/hr. A trip to shoe was performed with no excess drag; at the shoe another flow
check confirmed the well was stable. The well was then displaced to LTOBM when
the bit back to bottom, and drilling was resumed to top of the Zechstein anhydrite at
3767m as indicated by dropping of ROP to 3-4 mtr/hr. Drilling was continued to
3830m the top of Zechstein Salt as indicated by increasing of ROP 10-15m/hr, and
stopped at 3850m as section TD. After a wiper trip, at bottom a 3m3 low visc (base
oil) followed by 5m3 weighted high visc (1.57sg) pills were pumped and circulated
out, then during the final circulation the YP was decreased to +/- 15 by adding OMC-
42 and bleeding premix to the active. The mud weight was kept within the target.
The Shale shakers were dressed with 145’s and 165’s during the WBM phase, then
some was changed with 230’s in OBM phase. The centrifuges ran as required.
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 11
Ref : OPE/#12945/JCS/MH/AVE

5.2 9”5/8 casing and cementing

9”5/8 casing planned = 5 days Realised = 4.23 days (including 1 hours


problem with cement lines pressure test)
9”5/8 53.5# P110 New Vam casings were run to 3848m breaking circulation every
400m. The cement job went as per programme but plugs were not bumped at end of
displacement. 3.6m3 of losses were observed during the cement job.
During waiting on cement a wire line gyro survey was performed inside the casing.
After having cut the 9”5/8 casing, the FMC 13”5/8 x 10K casing head and 13”5/8 x
10K tubing head was installed and the 13”5/8 Bop was tested.

5.3 Cement composition

Cmt/Flush/Spacer Volume Top of cement Event


9-5/8” Casing at 3848m Job sequences: -Top of slurry at - Mud losses
MD = 2776m TVD 3348m. during RIH csg
-Pump 3.2 m3 Flush
=10m3, and
One stage cementing -Internal top at
-Followed by 10m3 during the job=
using plugs system. 3794m.
spacer. 3.6 m3.
Flush : Base oil Is only estimation
- Cmt slurry 22m3 - Cmt head was
+4ltr/m3 HYFLO-IV. by calculating
- Displacement rate : leaking badly
20% excess in
Spacer: FW+29kgs on a lo-torq
1550 –1000 lpm, with annular open-
Spacer- valve
total volume 145m3, hole.
500E/m3+5ltr/m3 PEN- caused1h30’
plug not bumped
5+15ltr/m3 lost time.
Musol+barite Sg=1.40.
Slurry : G neat+Sea
water+12.4 ltr/ton HR-
4L+0.5 ltr/ton NF-6,
Sg=1.92
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 12
Ref : OPE/#12945/JCS/MH/AVE

6 8”½ Phase from 3850m to 4798m – 7”liner at 4791m

Planned = 9 days Realised = 5.25 days (including 20 hours to change


MWD/GR)

FIT: 2.07sg EMW at 2777m TVD/RKB (9”5/8 casing shoe)

The purpose of this section was to cover the Zechstein salt formation with the 7”liner
prior to drill the reservoir section with a lower MW mud. The trajectory was designed
to hold angle to 4400m and then drop angle to 26° at shoe depth.

Because of the directional constraint, it was important to have a PDC bit with good
sliding ability. A Bit Smith M16VPX was chosen with an assembly incorporating a DH
motor with an AKO set a 1.1° and an MWD/GR to established the complex salt
section. Just at start of drilling into the formation, the gamma ray sensor failed to
work. However, In order to establish the steerability of the BHA component, it was
decided to drill few stands. It turn out that the PDC bit was too aggressive and kept
stalling the motor resulting with an unstable tool face. The bit drilled from 3850m to
3937m at an average Rop of 14.5 m/hour. The assembly was therefore pulled out to
change the bit and the MWD/GR.
A Hughes Christensen AG 382 was made up and drilled from 3937m to 4791m in
rotating and sliding mode. The average Rop was 11.8m over the section. At the end
of the section, in the Anhydrite and the Carbonate, it was no longer possible to
orientate the assembly. However, the final angle reached was 27.8°.
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 13
Ref : OPE/#12945/JCS/MH/AVE

6.1 Mud system

MUD TYPE ENVIROMUL


LTOBM.
DRILLED DEPTH 3,850m– 4,791m
FROM/TO
DENSITY SG 1. 65 – 1.66
FUNNEL VIS s/qt 47 – 55
PV cP 23 – 24
YV lbs/100ft2 15 – 17
6 RPM 10 – 11
HPHT LOSS cc 4.0 – 3.6
O/W ratio 79/21 – 81/19
LGS, % 2.3
WPS, gr/lt 286 – 293
ES, Volt 840 – 1070

A 1.65 sg ENVIROMUL LTOBM was used to drill this section. A 200 ltrs mud gain
was observed when drilling at 4056m, but no pressure increase was seen when the
well was shut-in. Another flow checks were done and confirmed the well stability.
Several mud checks were made to monitor any increase in the magnesium level, also
the Lime content was maintained at 7 g/l minimum. Drilling was continued to TD at
4791m without problems. No over pull was observed during wiper trip; however a
slight increase of cuttings was observed when a Low-visc and high visc/high weight
was on surface. During the final circulation the YP was decreased to 13 lbs/100ft2.

6.2 7” liner and cementing

7”liner planned = 5 days Realised = 4.79 days (including 4.5 hours NPT
for TDS repair)
7" - 35 lbs/ft – P110 New vam casings were run with 7-5/8" 59 lbs/ft-P110 Vam FJL
incorporated in the string in front of the complex salt formations (see composition).
The liner was run without problem to 3915m. At that depth, the liner was work until
3919m where it was stuck. The string was eventually freed with 50T overpull. The
rest of the run was done normally breaking circulation every 200m. No losses were
observed while running further and circulating at bottom. The cement job went as per
programme. The liner was tested at 150 bar after the bump and the integral packer
was energised with 32T Weight prior to perform the reverse. No losses were seen
during the cement job.
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 14
Ref : OPE/#12945/JCS/MH/AVE

6.3 Cement composition

Cmt/Spacer/Flush Volume Top of cement Event


Recipes
7”Liner at 4790mTMD Job sequence : -Top of liner Jobs went fine.
= 3385m TVD
-Preflush : 30 bbls -Slurry mixed using
TOL at 3698m 30m3 Batch mixer.
-Spacer : 6.4 m3
LC at 4733.52m - No losses.
- Cmt slurry : 17 m3
Top PBR at 3693m. -Was not able to
- Displaced with:
rotate the string,
OBM 60.1m3 at rate
high torque reading.
850 lpm max.
Cmt formulation :
-Bumping up to 150
HMR cmt +FW+ 127 kg
bars- hold 5 mins,
salt/ton cmt+ 7.8 kg
bled-off 4 bbls
CFR-3 /ton cmt+4.7 kg
return.
HR-4/ton cmt+1 ltr NF-
6/ton cmt Sg=1.90. -Set TSP packer
applied 32t down
Pre flush: Base oil+6.5
weight, pressure up
ltr HYFLO/10 bbls.
string 50bars.
Spacer: FW+18.5 kg
-Reverse circulation
E500/m3+260 kg
660lpm, 55 bars,
salt/m3+ 15 ltr
10.7 m3
Musol/m3+5 ltr Pen-
cmt/spacer/mud
5M/m3+Barite.
contaminated
Sg=1.80.
recovered.
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 15
Ref : OPE/#12945/JCS/MH/AVE

7 5-7/8” Phase from 4791m to 5206m

Planned = 14 days (dry hole) Realised = 10.63 (drilling) days


(Including 35.5 hours for fishing
3 rock bit cones)

The objective of this section was to drill through the Silverpit formation and recognise
the Lower Slochteren and eventual Wesphalian sand reservoirs. The trajectory was
designed to drop as close as possible to the vertical in order to optimise the
fracturation job that was planned to be performed in the reservoir.
A Hughes Christensen STR438G8 PDC bit was run with a Down Hole Motor M1XL-P
(Xtreme motor) from BHI (Ako set at 0.8°) and drilled from 4791m to 4878m. The
motor bit combination was chosen to give the maximum performance in rotary mode
with a dropping tendency. However, the assembly showed a slight build tendency. As
far as the Rop was concerned, the performance was very good but disappointing for
the sliding tendency. As the drop was necessary to follow the trajectory, it was
decided to pull and change the bit for a less aggressive one.
A Diamant Drilling services SPH633 PDC bit was run with the same motor and the
Ako set at 1.2°. The bit drilled from 4878m to 4921m. The first 20m were drilled
without problem and good tool face control. After this, sliding became impossible due
to hanging problem resulting in erratic tool face. With a check survey showing a slight
build, it was decided to pull out and change the assembly in order to maximise the
chance to drop.
A Hughes STR20 insert bit was run with a new Mach1 XL motor with the Ako set at
1.2°and the agitator. The bit drilled from 4921m to 4997m. The combination of the
rock bit motor and agitator made it easy to slide and hence resulted in good doglegs.
After 400Krevs, it was decided to pull the bit out of hole. At surface, the cones
appeared to be left in hole and the shanks were worn up to the body. No sign at
surface was seen that could have indicated the cones were lost during drilling.
A 5”9/16 Reverse Circulating Junk Basket was run and 0.6m was cored. At surface, a
piece of aluminium and few pieces of formation were pulled but no steel junk was
recovered.
From an assumption that the cones had disappeared (Milled with the formation), a
new PDC bit from Varel MKF39 was run. The bit drilled from 4997m to 5206m (TD) at
an average of 3m/hour. At the end of the run, the BHA had again a build tendency
but no correction was performed as the angle was kept within the limit to do the Frac
job (<10°).
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 16
Ref : OPE/#12945/JCS/MH/AVE

7.1 Mud system

MUD TYPE ENVIROMUL


LTOBM-Dolomite
DRILLED DEPTH 4,791 – 5,206m
FROM/TO
DENSITY SG 1.25 – 1.26
FUNNEL VIS s/qt 52 – 58
PV cP 19 – 23
YV lbs/100ft2 14 – 17
6 RPM 9 – 12
HPHT LOSS cc 4.6 – 4.0
O/W ratio 75/25 – 79/21
WPS, g/lt 211 – 238
ES, Volt 605 – 986
HGS, % 6.47 – 4.12
LGS, % 6.74 – 12.1

The reservoir section was drilled with a 1.25 sg high Dolomite weighted ENVIROMUL
LTOBM. The mud properties were kept roughly within the targets except for the HGS
(Barite content). The Centrifuge ran at low speed to reduce the amount of HGS to
around 4%. The major cause of the HGS content being above specification was due
to contamination from the pool supply boat system. The HGS was correctly below 4%
from the LMP at the beginning.

7.2 Logging

Planned = 4 days Realised = 2.73days (including 6.5 hours NPT for


repairing the wireline winch)
Run#1: EMS-AIT-DSI-GR
Log from bottom to 4850m and GR-DSI to surface
Run#2: SRFT-GR-ACTS
Performed 19 pressure tests
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 17
Ref : OPE/#12945/JCS/MH/AVE

8 Abandonment

Abandonment planned = 4 days Realised = 4.79 days


A 2”7/8 cement stinger was run and prior to put the abandonment cement plug in
place a mini Frac was performed to facilitate the Frac job calculation.
• A cement plug#1 was put in place from 5206m to 5000m.
• A cement plug#2 was put in place in the same run from 4856m to 4580m across
the 7”liner shoe.
This second cement plug was tagged and confirmed with 10t WOB at 4580m.
Following operations were performed to complete the well abandonment:
• Cement plug#3: across the 7” liner top from 3773m to 3623m.
• A 9”5/8 bridge plug was put in place at 3050m and tested on Shear blind rams
at 70 bar.
Refer to Well abandonment drawing for additional details.
The 13”5/8 BOP was then lift and the 11” tubing head and intermediate spool were
removed prior to put the BOP back in place and retest.
K6-GT4 drilling operations were finished on December 12, 2001 at 16h00.
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 18
Ref : OPE/#12945/JCS/MH/AVE

8.1 Cement composition

Plug #1 Plug #2 Plug#3


5206 – 5000m 4856- 4580m 3773 – 3623m
Cmt formulation : HMR /ton+ FW+1 ltr HMR /ton+ FW+1 ltr Gneat/ton + FW + 1 ltr
NF-6+3.9 kg Halad- NF-6+3.9 kg Halad- NF-6 + 3.5 kg HR-4
100L + 5.9 kg CFR- 100L + 5.9 kg CFR-3
3 + 5.1 kg HR-4 + + 5.1 kg HR-4 + 56.3
56.3 ltr Microblok. ltr Microblok.
Sg=1.85 Sg=1.85 Sg=1.92
Volume = 5.0m3 Volume = 5.0m3 Volume= 5.0 m3.

Spacer formulation :
Base oil+4 ltr Base oil+4 ltr Base oil+4 ltr
Hyflo/m3 Hyflo/m3 Hyflo/m3
Job sequences :
- Pump 1.75m3 - Pump 1.83m3 - Pump 3.7m3
front spacer front spacer front spacer
- Slurry 5.0 m3 - Slurry 5.0 m3 - Slurry 5.0 m3
- 0.32 m3 tail - 0.33 m3 tail - 0.33 tail spacer
spacer spacer. - Displace with
- close well while - Displace with OBM.
pumping cmt 38.3m3 - Pooh to 3550m
- squeeze 1m3 - Pooh to 4506m - Reverse, got
OBM. 0.5m3 cmt and
- Circulate 190m3
- Displace with OBM, no cmt 1.5m3 front
42.3 m3 OBM returns. spacer on surface.
- Pooh to 4853m - Cmt was tagged at - Theoretical TOC
for cmt plug 4580m. @3615m.
no.2
- Circulate
150m3 no cmt
returns.
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 19
Ref : OPE/#12945/JCS/MH/AVE

9 Attachments and JULIA Final Report

• Well data
• Logistics, Rig & Equipment, Service Companies
• Environment
• Well architecture
• Geology
• Exploration progress curve with lithology
• Electric Logging
• Time distribution
• Incidents report
• Mud Summary by Interval (F3f)
• Drill string composition (BHA’s)
• Final trajectory
• Final status
• Abandonment drawing
• Abandonment. sheet
• Final drilling cost (F3 Jbis)
• Penetration chart
• Casing and cementing reports
• Detailed composition of the casing/tubing string
• Formation integrity LOT
• Bit record
• Enclosures
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 20
Ref : OPE/#12945/JCS/MH/AVE

- Well Data

- Logistics

- Environment

- Well Section
WELL DATA K/06-GT4
E & P Nederland B.V.

Normelfa well operation ident. K/06-GT4 Country Netherland


Normelfa well identification K/06-GT4 Geological basin K6
Well name K/06-GT4 Field K6
Block K6

PURPOSE OF WELL PARTNERS

Oil/gas Name % Name %


Underground storage TFE E&P Nederland B.V. 58,16
Geothermal EBN 40
Mining
Coparex 3,84
Other

OPERATOR REFERENCE WELLS


TotalFinaElf E&P Nederland B.V. K6-6; 10; 11.

INITIAL PURPOSE WELL HEAD LOCATION COORDINATES


1 Exploration Environment Geographical coordinates Rectangular coordinates Ref meridien
2 Development
3 Appraisal Land Latitude 53°45'12.91" X(m) 428546.5
4 Re-entry Longitude 3°54'58.875" Y(m) 5956778.3 Projection reference
Offshore
5 Other Datum Z(m) UTM 5°E

DEPTH REFERENCE Land Offshore Swamp TYPE OF SITUATION PRE-DRILLING


Reference Ground Mud line MSL Mud line
Green Yes
Distance RKB / REF 84.65 43.85
Yellow No
Distance TBG HEAD / REF
Red
Water depth 40.8

DRILLING OBJECTIVES

Formation
Objective Formation Departure Inclination Risk
vertical depth

Permian/rotliegend Lower Slochteren 3635mRKB 3173 5 H2S


Carboniferous Westphalian C 3687 3178 5 Shallow gas

MAXIMUM PRESSURE WAS THE OBJECTIVE REACHED ?


GRADIENT
Yes/No Formation top vertical depth Departure Inclination
E. M. W. 1.2 Objective 1 Yes 3614.31
Vertical depth/RKB 3635 Objective 2 Yes 3662.62
Objective 3
RESULTS TYPE OF HYDROCARBON
Compact formation Water
Shows Other Gas H2S CO2
No reservoir Impregnated
FINAL STATUS FUNCTION OF WELL

Definitively plugged #REF!

DATES DEPTH / TRAJECTORY

Vertical Deviation
dd/mm/yy hh:mm Duration
Beginning of well operation 13-10-2001 4:00
Beginning of drilling 16-10-2001 13:00 3 days Horizontal Multi Drains Other
End of drilling 07-12-2001 21:00 52 days Drain length
End of well operation 12-12-2001 16:00 5 days Number
Starting depth 85.00 Maximum deviation 57.1 Max dev at objective
MD 5206 Tangent angle Open hole diam at TD 5 7/8"
TVD 3770 Number of side track Displacement at TD 3219
RIG & EQUIPMENT K/06-GT4
E & P Nederland B.V.

Rig name Ronald Hoope Contractor NOBLE DRILLING

Rig type Jack up

Platform name K6GT

Positioning

Conventional Heading 83.9°

Dynamic

Drawworks Continental Emsco C-3 type 2, 1600 HP

Top drive TDS-4H Varco

Rig pumps Number 3 Total hydraulic power 4800hp CV

Mud tanks Number 5 Total capacity 248.00 m3

Rig design
Normal design Heli rig Slim hole

Coil tubing Other

Comments
SERVICE COMPANIES K/06-GT4
E & P Nederland B.V.

CONTRACTOR NOBLE DRILLING

TYPE OF CONTRACT Day rate

SERVICE COMPANIES

Integrated Integrated
Services Services
Mud engineering Baroid Drill stem testing
Mud logging Geoservices Slick line service Schlumberger
Electrical logging Schlumberger Casing running services BJ
Cementing / pumping Halliburton Liner hanger services
Production testing Schlumberger Turbodrilling
Directional drilling Baker Hughes Inteq Fishing
Wellbore survey W H / CSG recovery
Well head FMC Sub sea services
Perforation Schlumberger Under water television
Waste disposal Coring
Sand control Supply vessels Supply Link
Stimulation Crew boats
Gauges Tug boats
Downhole equipment Helicopters Schreiner
Environmental control
Inland transportation
Access road maintenance

Comments
WELL ARCHITECTURE K/06-GT4
E & P Nederland B.V.

Casing Casing
Drill Starting Final Shoe LOT/FIT
Period Phase (diameter) Axis Starting date Final date Duration String function String type diameter by length by Component
diam depth depth depth at shoe
section section
(m) (m) (days)
MOV Moving 1 13-10-2001 4:00 15-10-2001 10:00 2.25
MOV 30" CP driving 1 91.00 15-10-2001 10:00 138.00 16-10-2001 23:30 1.56 Surface Complete column 30" 109.00 138.00
DRP Drlling 26" 26" 1 85.00 16-10-2001 23:30 682.00 18-10-2001 19:30 1.83 Surface Complete column
CSP Casing 20" 1 18-10-2001 19:30 21-10-2001 9:00 2.56 Surface Complete column 20" 649.00 678.00
DRP Drilling 17"1/2 17"1/2 1 682.00 21-10-2001 9:00 1698.00 25-10-2001 15:00 4.25 Surface Complete column
CSP Casing 13"3/8 1 25-10-2001 15:00 28-10-2001 4:00 2.54 Technical Complete column 13"3/8 1667.00 1694.00 1.40
DRP Drilling 12"1/4 12"1/4 1 1698.00 28-10-2001 4:00 3850.00 10-11-2001 6:00 13.08
CSP Casing 9"5/8 1 10-11-2001 6:00 14-11-2001 11:30 4.23 Production Complete column 9"5/8 3820.00 3848.00 2.07
DRP Drilling 8½ 8½ 1 3850.00 14-11-2001 11:30 4791.00 19-11-2001 17:30 5.25
CSP Liner 7'' 1 19-11-2001 17:30 24-11-2001 12:30 4.79 Production Liner 7" x 7"5/8 1097.00 4790.00 2.29
DRP Drilling 5"7/8 5"7/8 1 4791.00 24-11-2001 12:30 5206.00 05-12-2001 3:30 10.63
GEP Geology and evaluation 1 05-12-2001 3:30 07-12-2001 21:00 2.73
RAP Plug and Abandon 1 07-12-2001 21:00 5206.00 12-12-2001 16:00 4.79
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 21
Ref : OPE/#12945/JCS/MH/AVE

- Geology progress curve

- Electrical logging summary


TotalFinaElf SURFACE : Slot T
K6-GT4 TYPE : RIG : OBJECTIVES : LONG : 03°54’58.875” E ( Y: 5956778.3 m )
Devel. Noble Hoope LOWER SLOCHTEREN LAT : 53°45'12.910" N ( X: 428546.5 m )
OPERATOR :
TotalFinaElf E&P NEDERLAND B.V: 56.16% GL/WD : 40 m
RT : +45m/MSL
D
WELL : 13/10/2001 / /
PROGNOSIS ACTUAL SPUD : 14/10/2001/ /
DRILLING STRAT DEPTH DEPTH DRILLING WELL PROGRESS CHART
CASING LITHO
m/RT m/MSL
m m/MSL m/RT
LITHO SHOWS AND
10
ESTIMATED :
20 30 40
ACTUAL :
50 60 70 80 90
LOGGING CASING
45
Bento : <1.12 Water
Sea

85 40 85 30"
30"
138m
Upper North Sea GR

135m BGG
QUARTERNARY

0.001% 6.31
- 6.5 293.5 338
Ø 26" 346 300 10.72
BGG
0.04%

BGG
26.08 20”
20
0.07 - 0.1 % 31.30 678 m
676m 682 m
681 757
TERTIARY TO

BGG
0.02 - 0.03 %
923 32.04
821
Brussel

1000 1000
BGG
KCl mud :1.25

0.015 - 0.035 %
31.64
Ø 17"1/2
Ieper Clay

BGG
0.015 - 0.035 %
32.49
BGG 13” 3/8
13 3/8" 1646 1440 +10.1 1450.1 1662 0.025 - 0.045 % 32.17 1694 m
1676m
1698 m
1762 1540 +22.2 1800
1562.2 48.33 FIT
1.50 sg
UPPER CRETACEOUS

BGG
0.009 % 55.39
2000 2000
OMMELANDEN

BGG
0.013-0.028 % 55.54
KCl mud: 1.15 / LTOBM 1.25

BGG
0.013%

Ø 12 1/4" BGG
0.013-0.028 %
55.68
BGG
3000 0.013-0.020 % 53.81 3000
2306.4 3084
3163 2360 -53.6 BGG
0.009-0.023 % 56.78
BGG
2401.8 3255 0.02-0.05 % 56.63
3307 2440 -38.2 BGG
LTOBM
Vliel HOL Texel

0.025 % 56.52
3468 2530 -19 2511 3454
L. Cret

3558 2580 +2.7


2582.7 3582 BGG
0.025-0.04 % 55.80
3702 2660 +8 2668 3732 9”5/8
T B -15.5 2694.5 3779
3792 2710 BGG 56.68 3848 m
2726.5 3830 0.029-0.058 %
BGG 3850 m FIT
9 5/8" 3918 2780 -53.5 0.021-0.026% 57.25 2.07 sg EMW
4000 3948m BGG 4000
0.025-0.030% 54.17
PERMIAN.
ZECHSTEIN

BGG
LTOBM: 1.65-1.70

0.024-0.072% 54.10
Ø 8 1/2"
LTOBM

BGG
0.022-0.032%
34.20
L 7" 4702 3260 +12.2 BGG
3272.2 4712 0.027-0.108% 27.40
4749 3300 +24.8 3324.8 4772
SILVERPIT

4779m BGG 28.19


0.030-0.050% 4790 m
LTOBM: 1.25

BGG FIT
0.030-0.040% 16.78 4791 m 2.44 sg EMW
5000 5000
5053 3588 +12.3 3600.3 FG
LS 5072 0.62-0.060%
Ø 5 7/8" 5105 3640 +7.7 3647.7 5120 8.66
CARBO.

............ BGG 1 2 3
WEST C

L 4 1/2” 5224 3760 3732.4 5206 0.03-0.04% 8.68


5223m TD 5206 m

1 Logging
2 Liner
3 Completion

REPORT DATE DEPTH at 24h PROG PHASE OPERATIONS :Perform cement plug #3 CURRENT ACTIVITY AT 8H00 DEPTH: 5206 m
No: 60 11/12/01 5206 m 0m 5”7/8 (3773-3615m). POOH cement stinger.
Begin BOP test.
Set 9"5/8 BP at 3050m. R/d diverter.
PROGRAM : BOP test. RIH 9”5/8 cutting BHA.
LITHOLOGY : SHOWS :
REMARKS :
No drilling. No drilling.

.
GEOLOGY K/06-GT4
E & P Nederland B.V.

Bottom
Top depth Stage Formation Main lithology Shows Comment
depth

85.00 149.00 Quaterny North sea group Coarse sand


149.00 338.00 Quaterny North sea group Coarse sand
338.00 558.00 Tertiary North sea group Clays BGG:0.15%
558.00 682.00 Tertiary North sea group Clays BGG:0.1%
682.00 936.00 Tertiary North sea group Clays BGG:0.01%
936.00 1247.00 Tertiary North sea group Clays BGG:0.02%
1247.00 1607.00 Tertiary North sea group Clays BGG:0.03%
1607.00 1662.00 Tertiary North sea group Clays BGG:0.02%
1662.00 1698.00 Upper Cretaceous Ommelanden Upper cherts BGG:0.03%
1698.00 1800.00 Upper Cretaceous Ommelanden Upper cherts BGG:0.01%
1800.00 1879.00 Upper Cretaceous Ommelanden Chalk BGG:0.01%
1879.00 2002.00 Upper Cretaceous Ommelanden Chalk BGG:0.01%
2002.00 2420.00 Upper Cretaceous Ommelanden Chalk BGG:0.02%
2420.00 2836.00 Upper Cretaceous Ommelanden Chalk BGG:0.02%
2836.00 3084.00 Upper Cretaceous Ommelanden Chalk BGG:0.02%
3084.00 3117.00 Upper Cretaceous Ommelanden Chalk+0 to 15% cherts BGG:0.01%
3117.00 3146.00 Upper Cretaceous Ommelanden Chalk + 15%to25% cherts. BGG:0.01%
3146.00 3212.00 Upper Cretaceous Ommelanden Chalk + 10% to 15% cherts BGG:0.02%
3212.00 3255.00 Upper Cretaceous Ommelanden Chalk BGG:0.04%
3255.00 3262.00 Upper Cretaceous Texel Chalk Limestone BGG:0.04%
3262.00 3387.00 Upper Cretaceous Texel Chalk Limestone BGG:0.03%
3387.00 3454.00 Upper Cretaceous Texel Chalk Limestone BGG:0.03%
3454.00 3582.00 Lower Cretaceous Holland Marl Red Marl BGG:0.03%
3582.00 3650.00 Lower Cretaceous Vlieland Shale Clays BGG:0.03%
3650.00 3732.00 Lower Cretaceous Vlieland Shale Clays BGG:0.04%
3732.00 3779.00 Triassic Lower bunter Clays + 5% Anhadrite BGG:0.03%
3779.00 3817.00 Permian Zechstein anhydrite Anhydrite BGG:0.06%
3817.00 3830.00 Permian Zechstein anhydrite Anhydrite BGG:0.07%
3830.00 3850.00 Permian Zechstein halite Halite BGG:0.03%
3850.00 3937.00 Permian Zechstein halite Potassic salt - Halite BGG:0.025%
3937.00 4056.00 Permian Zechstein halite Halite BGG:0.03%
4056.00 4294.00 Permian Zechstein halite Anhydrite + Halite + Polyha. BGG:0.03%
4294.00 4668.00 Permian Zechstein halite Anhydrite + Halite + Polyha. BGG:0.03%
4668.00 4772.00 Permian Zechstein Halite-Anhyd.-Polyha.-Lmst. BGG:0.08% Gas peak: 0.1080% at 4772.5 m
4772.00 4791.00 Saxonian Silverpit Claystone Claystone BGG: 0.06%
4791.00 4850.00 Saxonian Silverpit Claystone Claystone BGG: 0.06%
4850.00 4878.00 Saxonian Silverpit Claystone Claystone BGG: 0.04%
4878.00 4921.00 Saxonian Silverpit Claystone Claystone BGG: 0.04%
4921.00 4985.00 Saxonian Silverpit Claystone Claystone BGG: 0.04%
4985.00 4997.00 Saxonian Silverpit Claystone Claystone BGG: 0.08% Gas peak: 0.18% at 4991 mRKB
4997.00 5056.00 Saxonian Silverpit Claystone Claystone + siltstone BGG: 0.04%
5056.00 5072.00 Saxonian Silverpit Claystone Claystone + siltstone BGG: 0.04%
5072.00 5127.00 Saxonian Lower Slochteren Sandstone BGG: 0.04% Gas peak: 0.6% at 5076 mRKB.
5127.00 5142.00 Carboniferous Westphalian Claystone, Sandstone BGG: 0.03%
5142.00 5188.00 Carboniferous Westphalian Claystone, Sandstone BGG: 0.04%
5188.00 5206.00 Carboniferous Westphalian Claystone, Sandstone BGG: 0.04%
ELECTRICAL LOGGING K/06-GT4
E & P Nederland B.V.

Type
Report Depth (metres)
Phase (Running Run n° Type of log
n° From To
mean)
54 5 7/8 EMS-GR-DSI-AIT 4650.00 5196.50
GR sonic 4790.00 surface
56 5 7/8 ACTS-GR-SRFT

COMMENTS

SIDE WALL CORES (SWC)


Number Number
Run DEPTH of Formation Run DEPTH of Formation
n° from to SWC's n° from to SWC's
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 22
Ref : OPE/#12945/JCS/MH/AVE

- -Time distribution

- -Incident report
TIME DISTRIBUTION K/06-GT4
E & P Nederland B.V.

WELL TIME ANALYSIS


non %
productive productive NPT/TOT
MOVING (MOV) 86:00 3:00 0.21%
REENTRY/ABANDON (RAP) 96:00 1:00 0.07%
DRILLING (DRP) 790:00 27:30 1.89%
CASING/CEMENTING (CSP) 359:30 6:00 0.41%
GEOLOGY (GEP) 57:30 7:30 0.52%
RESERVOIR EVALUATION (REP)
WORKOVER/COMPLETION (WCP) 18:00
SIDETRACK OPERATIONS
TOTAL HOURS 1407:00 45:00
TOTAL DAYS 58.63 1.88
TOTAL DURATION IN DAYS 60.50

MOVING
A1A Rig move between locations ( and Mob/Demob if any ) 3:30 AN1 Downtime for Moving/Skidding Operations (Mooring pb….)
A1B Rig Skidding 3:00 AN2 Downtime due to underwater (ROV) Service Company
A2 Positionning,Anchor handling,Tests,Pre- 55:30 AN3 Downtime due to civil works Service Company
loading,Preparation for drilling
A3 Conductor pipe driving operations 24:00 AN4 Downtime due to onshore transportation Services
A4 Other Productive Operations during rig moves AN5 Downtime due to CP driving operations
AN6 Downtime due to Marine Services Company
AN7 Downtime due to Rig Equipment Failure
AN8 Waiting on Weather
AN9A Other Downtime due to Operator
AN9B Other Downtime due to Drilling Contractor 3:00
AN9C Downtime due to Other Services Companies
PRODUCTIVE TIME IN HOURS 86:00 NON PRODUCTIVE TIME IN HOURS 3:00

REENTRY/ABANDON
B1A Opening, installation of special equipment for side track BN2 Downtime due to Kick Control or Losses Curing
B1B Other well related planned operations for re-entry BN3 Downtime due to Rig Drillstring Failure
B1C Mud line reconnection : casings installation including BN4 Downtime due to Cementing Operations Failure
tests (Fixed platform rig/JU...)
B1D Wellhead and BOPs installation and tests (Fixed platform BN5 Unscheduled events while removing equipments
rig/JU...) 18:00
B1E Mud line reconnection : BOP's & Riser installation BN6A Downtime due to Services Companies
including tests (Floating rig)
B2 Well Plugging & Abandon 11:00 BN6B Downtime due to Fishing Services Companies
B2A Circulations to control a well before & during BN6C Downtime due to Directional Drilling Services Companies
abandonment
B2B Equipment removal operations BN6D Downtime due to Wellhead Equipment Failure
B2C Operations for isolating and securing the well 67:00 BN7 Downtime due to Rig Equipment Failure 1:00
B2D Cut/Perforation & retrieving casing BN8 Waiting on Weather
B2E Others operations associated with Well plugging & BN9A Other Downtime due to Operator
Abandon
B3 Well Suspension BN9B Other Downtime due to Drilling Contractor
B4 Removal of Production Equipement BN9C Downtime due to Other Services Companies
PRODUCTIVE TIME IN HOURS 96:00 NON PRODUCTIVE TIME IN HOURS 1:00

DRILLING
F1 Drilling & connections 501:45 FN1 Downtime due to Hole Stability (Tool sticking,not able to 0:30
reach bottom....but excluding downtime due to kick control
F2 Tripping FN1A Well conditionning : Unscheduled operations : wiper
F2A Tripping in open hole 47:15 FN1B Mud conditionning : Unscheduled operations :
F2B Tripping in case hole 101:30 FN1C Stuck pipe : Working pipe & fishing due to hole stability...
F2C Tripping : handling BHA 65:00 FN2 Downtime due to Kick Control or Losses Curing
F3 Well conditionning Scheduled wiper trips ,reaming .. 41:00 FN3 Downtime due to Drill string Failure & related fishing
F4 Mud conditionning : Scheduled mud change , ..... 8:30 FN5 Downtime due to Unscheduled Directional Drilling
F5 Hole Opening or Underreaming FN6A Downtime due to Directional Drilling Service Company 20:00
F6 B.O.P. test during drilling or geology evaluation FN6B Downtime due to Failure of Equipment provided by
operations Operator
F7 Deviation surveys in vertical or deviated wells 8:30 FN6C Downtime due to electrical logging Service Company (back
F9 Formation Integriy Tests L.O.T., Shoe Bond Test ... 11:00 FN6D Downtime due to Wellhead Equipment Failure
F10 Normal maintenance of the rig 5:30 FN6E Downtime due to underwater (ROV...) Service Company
F11 Preparation for Side Track Operations FN7 Downtime due to Rig Equipment Failure 7:00
FN7A Downtime due to Rig BOPs Equipment Failure
FN8 Waiting on Weather during drilling operations
FN9A Other Downtime due to Operator
FN9B Other Downtime due to Drilling Contractor
FN9C Downtime due to Other Services Companies
PRODUCTIVE TIME IN HOURS 790:00 NON PRODUCTIVE TIME IN HOURS 27:30

03-12-2002 1/6
TIME DISTRIBUTION K/06-GT4
E & P Nederland B.V.

CASING/CEMENTING
C1A Preparation,R/U and R/D floor equipment 30:30 CN1 Downtime due to Hole Stability
C1B Running casing / liner 84:00 CN2 Downtime due to Kick Control or Losses
C2 Cementing Operations including circulation & scheduled CN3A Downtime due to Casing string Failure or stuck
W.O.C. 36:00
C3 Wellhead & B.O.P, : N/U , N/D and Test 86:30 CN3B Downtime due to Liner Failure or stuck
C4 Drill out cement & casing tests 52:00 CN4 Downtime due to Cement Operation Failure (including
C5 Control Trip before running casing/liner 70:30 CN5 Unscheduled Waiting on Cement
C6 Cement Job Evaluation : CBL,CET,,,,,,,,, CN6A Downtime due to Cementing Services Company 1:30
CN6B Downtime due to Electrical Logging Company
CN6C Downtime due to Casing Running Company
CN6D Downtime due to Wellhead Equipment Failure
CN7 Downtime due to Rig Equipment Failure 4:30
CN8 Waiting on Weather during casing/cementing operations
CN9A Other Downtime due to Operator
CN9B Other Downtime due to Drilling Contractor
CN9C Downtime due to Others Services Companies
PRODUCTIVE TIME IN HOURS 359:30 NON PRODUCTIVE TIME IN HOURS 6:00

GEOLOGY
G1 Coring & connections GN1A Well conditionning while logging : Unscheduled wiper
G2 All tripping associated with coring operations including GN1C Fishing during logging phase
circulation
G2C Handling BHA,Core barrel and Core recovery GN1D Well conditionning while coring : Unscheduled wiper
G3 Hole Opening / Well Conditionning after coring GN1E Mud conditionning while coring : Unscheduled
G4 Geological Circulation : after drilling break, for cuttings,.... 0:30 GN1F Fishing during coring phase (Stuck pipe / core barrel... )

G5 Formation Testing : RFT, .... ( excluding DST,s ) 14:00 GN2 Downtime due to Kick Control or Losses Curing
G6 Electrical Logging (geology or drilling evaluation ) 19:00 GN3 Downtime due to Rig Coring string Failure
G7 Other measurements for geological evaluation : VSP GN6A Downtime due to Coring Company
G8 Other measurements for geological evaluation : LWD GN6B Downtime due to Electrical Logging Company 6:30
G9 Other Planned Operations during geology evaluation 24:00 GN6C Downtime due to LWD, FEWD or PWD tool failure
phase
GN6D Downtime due to Well Seismic Service Company (VSP)
GN7 Downtime due to Rig Equipment Failure
GN8 Waiting on Weather
GN9A Other Downtime due to Operator
GN9B Other Downtime due to Drilling Contractor
GN9C Downtime due to Other Services Companies 1:00
PRODUCTIVE TIME IN HOURS 57:30 NON PRODUCTIVE TIME IN HOURS 7:30

RESERVOIR EVALUATION
W1 Scheduled Hole Conditionning for Reservoir Evaluation WN1A Well conditionning : Unscheduled operations : wiper
W1A B.O.P, Wellhead, Casing & Associated Operations (NU, WN1B Mud conditionning : Unscheduled operations :
Tests & Trips) circulation,,,,
W2 Electrical Operations or TCP : Perfs,correlation logs ..... WN1C Working pipe (Stuck pipe )
W3A Surface equipment preparation WN2 Downtime due to Kick Control or Losses Curing
W3B Handling Dst Assembly : BHA,SSTT… WN3 Downtime due toTubing string Failure
W3C Tripping of DST Assy WN5 Downtime due to Surface Testing Equipment Company
W4 Wireline Operations for Data Acquisition : PLT , WN6A Downtime due to Downhole Testing Equipment Company
flowmeter,sampling ....
W5 DST Operations : flowing & build-up periods WN6B Downtime due to Electrical Logging Company
W6 Circulation , Desanchoring packer & Squeeze with DST WN6C Downtime due to Tubing Running Company
string
W7 Formation Stimulation for well testing purposes WN7 Downtime due to Rig Equipment Failure
W8 Tested interval isolation (cement plug,bridge plug ...... ) WN8 Waiting on Weather and Daylight
WN8A Waiting on Weather
WN8B Waiting on Daylight
WN9A Other Downtime due to Operator
WN9B Other Downtime due to Drilling Contractor
WN9C Downtime due to Other Services Companies
PRODUCTIVE TIME IN HOURS NON PRODUCTIVE TIME IN HOURS

03-12-2002 2/6
TIME DISTRIBUTION K/06-GT4
E & P Nederland B.V.

WORKOVER/COMPLETION
P1A Hole Conditioning :pulling tubing,drilling out PN1 Downtime due to Unexpected Hole Conditions
equipment,circulation, .....
P1B All extra operations for hole conditioning PN2 Downtime due to Kick Control or Losses Curing
P1C Setting Killing Fluids and/orPlugging Agents PN3 Downtime due to Completion String Failure
P1D N/U or N/D BOP's,N/U or N/D Production Wh Equipment PN5 Downtime due to Slick-line Service Company
and Testing same
P1F Preparation & Running scab liner , casing tie-back, ... PN6A Downtime due to Testing Service Company
P2 Scheduled Cementing Operations : squeeze, ... PN6B Downtime due to Electrical Logging Service Company
P3A Electrical Logging including preparation PN6C Downtime due to Tubing Running Company
P3B Perforations & Openings for well production purposes PN6D Downtime due to Wellhead Equipment Failure (Xmas-
P3C Perforations with TCP PN7 Downtime due to Rig Equipment Failure
P4D Setting Completion Fluid PN8 Waiting on Weather and Daylight
P4F Preparation & Running Completion PN8A Waiting on Weather
P5 Gravel Pack Operations PN8B Waiting on Daylight
P6A Trips for running/retieving temporary completion for PN9A Other Downtime due to Operator
stimulation
P6B Formation stimulation for production purpose 18:00 PN9B Other Downtime due to Drilling Contractor
P7 Wireline Operations ( slick line ) ,including preparation PN9C Downtime due to Other Services Companies
P8 Production Tests : clean up,flowing,build-up, .. PN9D Downtime due to Sand Control Service Company
P9 Coiled Tubing Operations
P10 Snubbing Operations
P11 Normal maintenance of the rig
PRODUCTIVE TIME IN HOURS 18:00 NON PRODUCTIVE TIME IN HOURS

03-12-2002 3/6
INCIDENT K/06-GT4
E & P Nederland B.V.
Date & time Phase Code Depth Comments

03-11-2001 17:30 Drilling 12"1/4 FN7 Downtime due to rig equipment failure: OBM transfer pump failure (shaft between motor
and pump broken). Meanwhile circulate well with 950 l/min, 50-60 bar.
Attempt to pressure test cmt lines without success - Locate leak on Cmt head manifold
11-11-2001 12:30 Casing 9"5/8 CN6A
lower low-torc valve.
14/11/2001 20:30 Casing 9"5/8 FN6A Circulate with 1800l/min 218b.
15/11/2001 00:00 Drilling 8½ FN6A Continue POOH 8½ steeering BHA from 2000m to top of MWD.

Shut in well on 5½ pipe rams due to negative drlg break at 4056m (ROP drop fr 25m/h to
15/11/2001 23:30 Drilling 8½ FN1
10m/h) and Flow returns increase fr 50 to 52%,200l gain in active - Observe for pressure
build up - No increase - Open well - Flow check - Ok.Daily steel recovered:0kg.
Repair TDS rotary function : Change out oil pump - M/up circulating sub and install high
20/11/2001 22:00 Liner 7'' CN7
pressure lines - Circulate at 3950m inside string with 730l/min 52b.
Repair TDS rotary function:Change out oil pump - Circulate at 3950m inside string with
21/11/2001 00:00 Liner 7'' CN7
650l/min 48b.
Attempt to pressure test high pressure lines: Fix leak on 2" elbow on cement line and 2"
21/11/2001 13:00 Liner 7'' CN6A
Standpipe connection.
05-12-2001 14:30 Drilling 5"7/8 GN6B Repair winch. Drive sprocket broken.
BJ hydraulic unit failure, connection hose broken (for 3½ DP power tong) : Change out f
06-12-2001 7:00 ology and evalua GN9C
back up (Weatherford).
BJ hydraulic unit failure ,abnormal vibration and noise (for 3½ DP power tong) : Change
07-12-2001 2:00 eology and evalua GN9C
out for back up ( Weatherford).
12-12-2001 10:00 Plug and Abando BN7 Changed out the annular control hose .
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 23
Ref : OPE/#12945/JCS/MH/AVE

- Mud summary by interval (F3f)


TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 24
Ref : OPE/#12945/JCS/MH/AVE

- Drill string composition

- Final Trajectory
FINAL TRAJECTORY K/06-GT4
E & P Nederland B.V.

Theoretical azimuth 64.20 deg MINIMUM CURVATURE


Section azimuth 64.20 deg
Distance reference / RKB 43.85 SURVEY DATA
Projection reference 63.82

The first point is either (0,0,0) or the tie-on point : give the six parameters.
MD Incl. Grid azi Tool TVD Dep X Dep Y Hor. displ. DLS Section Well azi.
m/RKB deg deg m/RKB m (E-W) m (N-S) m/RKB deg/10m m/RKB deg
1 88.00 0.27 289.66 GMS 0.00 0.00 0.00 0.00 - 0.00 0.00
2 100.03 0.39 300.61 GMS 12.03 -0.06 0.03 0.07 0.112 -0.04 296.13
3 110.04 0.36 297.99 GMS 22.04 -0.12 0.06 0.13 0.035 -0.08 297.70
4 120.01 0.37 303.67 GMS 32.01 -0.17 0.10 0.20 0.038 -0.11 298.72
5 130.04 0.33 301.28 GMS 42.04 -0.23 0.13 0.26 0.042 -0.15 299.62
6 140.08 0.26 329.26 GMS 52.08 -0.26 0.16 0.31 0.157 -0.16 301.87
7 150.01 0.50 60.13 GMS 62.01 -0.24 0.20 0.31 0.571 -0.12 310.85
8 160.02 0.93 73.04 GMS 72.02 -0.12 0.25 0.28 0.456 0.00 334.30
9 170.11 1.14 78.75 GMS 82.11 0.06 0.29 0.30 0.232 0.18 11.02
10 180.10 1.31 80.27 GMS 92.09 0.27 0.33 0.43 0.173 0.38 38.88
11 190.08 1.54 78.92 GMS 102.07 0.51 0.38 0.63 0.233 0.62 53.64
12 200.08 1.89 77.25 GMS 112.07 0.80 0.44 0.92 0.354 0.91 61.39
13 210.13 2.20 73.30 GMS 122.11 1.15 0.53 1.27 0.339 1.27 65.24
14 220.03 2.74 72.79 GMS 132.00 1.56 0.66 1.69 0.546 1.69 67.20
15 230.08 3.63 71.58 GMS 142.04 2.09 0.83 2.25 0.888 2.24 68.42
16 240.02 4.38 73.06 GMS 151.95 2.75 1.04 2.94 0.762 2.93 69.35
17 250.07 4.95 74.04 GMS 161.97 3.54 1.27 3.76 0.573 3.73 70.27
18 260.03 5.45 75.90 GMS 171.89 4.41 1.50 4.66 0.530 4.62 71.19
19 270.12 5.80 76.98 GMS 181.93 5.37 1.73 5.64 0.362 5.59 72.11
20 280.08 6.03 77.34 GMS 191.83 6.37 1.96 6.66 0.234 6.59 72.89
21 290.09 6.13 77.39 GMS 201.79 7.40 2.19 7.72 0.100 7.62 73.50
22 300.05 6.30 77.63 GMS 211.69 8.46 2.43 8.80 0.173 8.67 73.99
23 310.08 6.53 77.92 GMS 221.66 9.55 2.66 9.92 0.232 9.76 74.42
24 320.11 6.80 78.10 GMS 231.62 10.69 2.90 11.08 0.270 10.89 74.80
25 330.03 6.94 78.40 GMS 241.47 11.85 3.15 12.26 0.146 12.04 75.13
26 340.06 7.25 78.94 GMS 251.42 13.07 3.39 13.50 0.316 13.24 75.46
27 350.12 7.67 80.21 GMS 261.40 14.35 3.63 14.80 0.448 14.50 75.82
28 360.05 7.96 81.39 GMS 271.23 15.68 3.84 16.15 0.334 15.79 76.24
29 370.01 8.26 82.19 GMS 281.09 17.08 4.04 17.55 0.322 17.13 76.68
30 380.08 8.48 82.54 GMS 291.06 18.53 4.24 19.01 0.224 18.52 77.12
31 390.03 8.80 83.29 GMS 300.89 20.01 4.42 20.49 0.341 19.94 77.54
32 400.11 9.28 83.74 GMS 310.85 21.58 4.60 22.07 0.481 21.44 77.97
33 410.02 9.87 84.60 GMS 320.62 23.22 4.77 23.71 0.613 22.98 78.40
34 420.10 10.43 85.45 GMS 330.54 24.99 4.92 25.47 0.575 24.64 78.86
35 430.06 11.27 84.95 GMS 340.33 26.86 5.08 27.34 0.849 26.39 79.30
36 440.03 12.10 84.19 GMS 350.09 28.87 5.27 29.35 0.847 28.29 79.66
37 450.01 13.10 83.63 GMS 359.83 31.04 5.50 31.52 1.009 30.34 79.95
38 460.00 13.89 82.91 GMS 369.54 33.35 5.77 33.85 0.808 32.54 80.18
39 470.10 14.61 82.52 GMS 379.33 35.82 6.09 36.33 0.719 34.90 80.35
40 480.10 15.33 81.79 GMS 388.99 38.38 6.44 38.91 0.744 37.36 80.47
41 490.07 15.72 81.64 GMS 398.60 41.02 6.83 41.58 0.393 39.90 80.55
42 500.02 16.31 80.96 GMS 408.16 43.73 7.24 44.33 0.622 42.52 80.60
43 510.06 17.25 79.97 GMS 417.77 46.59 7.72 47.23 0.979 45.31 80.59
44 520.01 18.41 78.59 GMS 427.25 49.58 8.29 50.27 1.241 48.25 80.51
45 530.06 19.59 76.84 GMS 436.75 52.78 8.99 53.54 1.304 51.43 80.34
46 540.06 20.54 74.97 GMS 446.14 56.11 9.83 56.96 1.146 54.79 80.07
47 550.09 21.31 73.63 GMS 455.51 59.55 10.80 60.52 0.904 58.32 79.73
48 560.10 21.95 72.36 GMS 464.82 63.08 11.87 64.19 0.792 61.96 79.34
49 570.09 22.87 70.63 GMS 474.05 66.69 13.08 67.96 1.133 65.74 78.90
50 580.12 24.00 69.20 GMS 483.25 70.44 14.46 71.91 1.261 69.71 78.40
51 590.08 25.23 67.87 GMS 492.31 74.30 15.97 76.00 1.354 73.84 77.87
52 600.03 26.47 67.12 GMS 501.26 78.31 17.64 80.27 1.289 78.18 77.31
53 610.05 27.36 66.72 GMS 510.20 82.48 19.41 84.73 0.906 82.71 76.76
54 620.07 28.13 66.24 GMS 519.06 86.76 21.28 89.33 0.800 87.37 76.22
55 630.10 29.16 65.41 GMS 527.87 91.14 23.24 94.06 1.101 92.17 75.69
56 640.10 30.13 64.46 GMS 536.56 95.62 25.34 98.92 1.078 97.12 75.16
57 650.11 30.66 63.93 GMS 545.19 100.18 27.55 103.90 0.593 102.18 74.63
58 660.03 30.85 63.93 GMS 553.72 104.74 29.77 108.89 0.192 107.26 74.13
59 670.05 30.93 63.87 GMS 562.32 109.36 32.04 113.95 0.086 112.40 73.67
60 680.05 30.37 63.62 GMS 570.92 113.93 34.29 118.98 0.574 117.50 73.25
61 690.11 29.84 63.41 GMS 579.62 118.45 36.54 123.96 0.537 122.54 72.85
62 700.05 29.63 63.50 GMS 588.25 122.86 38.75 128.82 0.216 127.47 72.50
63 710.10 29.50 63.56 GMS 596.99 127.30 40.96 133.72 0.133 132.43 72.16
64 720.04 29.75 63.57 GMS 605.64 131.70 43.14 138.58 0.252 137.35 71.86
65 730.09 30.18 64.13 GMS 614.34 136.20 45.36 143.55 0.510 142.36 71.58
66 740.01 30.46 64.28 GMS 622.90 140.71 47.54 148.52 0.292 147.37 71.33
67 750.07 30.82 64.49 GMS 631.56 145.33 49.75 153.61 0.373 152.50 71.10
68 760.01 31.07 64.40 GMS 640.09 149.94 51.96 158.69 0.256 157.61 70.89
69 770.08 31.53 64.57 GMS 648.69 154.67 54.21 163.89 0.465 162.84 70.68
70 780.01 32.08 64.52 GMS 657.13 159.39 56.46 169.10 0.555 168.08 70.49
71 790.04 32.44 64.36 GMS 665.61 164.22 58.77 174.42 0.369 173.43 70.31
72 800.08 32.66 64.46 GMS 674.07 169.09 61.10 179.79 0.226 178.83 70.13
73 810.01 32.95 64.20 GMS 682.42 173.94 63.43 185.15 0.325 184.21 69.96
74 820.07 32.88 63.60 GMS 690.86 178.85 65.84 190.58 0.331 189.68 69.79
75 830.03 32.81 63.15 GMS 699.23 183.68 68.26 195.95 0.255 195.08 69.61
76 840.11 32.79 62.95 GMS 707.71 188.55 70.73 201.38 0.109 200.54 69.44
77 850.10 32.82 62.82 GMS 716.10 193.36 73.20 206.76 0.077 205.95 69.27
78 860.08 32.74 62.73 GMS 724.49 198.17 75.67 212.13 0.094 211.35 69.10
79 870.03 32.76 62.69 GMS 732.86 202.95 78.14 217.48 0.030 216.73 68.94
80 880.11 32.72 62.88 GMS 741.34 207.80 80.63 222.90 0.109 222.18 68.79
81 890.10 32.55 62.69 GMS 749.75 212.59 83.10 228.26 0.199 227.57 68.65
82 900.09 32.43 62.63 GMS 758.18 217.36 85.56 233.59 0.124 232.93 68.51
83 910.00 32.13 62.90 GMS 766.56 222.06 87.98 238.86 0.336 238.22 68.39
84 920.05 32.09 62.76 GMS 775.07 226.82 90.42 244.18 0.084 243.56 68.26
85 930.09 31.77 62.83 GMS 783.59 231.54 92.85 249.46 0.321 248.87 68.15
86 940.05 31.48 62.93 GMS 792.07 236.19 95.23 254.66 0.296 254.09 68.04
87 950.01 31.31 62.99 GMS 800.57 240.81 97.59 259.83 0.174 259.28 67.94
88 960.02 31.15 63.27 GMS 809.13 245.44 99.94 265.00 0.216 264.47 67.85
89 970.04 31.18 63.03 GMS 817.71 250.07 102.28 270.17 0.128 269.65 67.76
90 980.07 31.05 63.00 GMS 826.29 254.68 104.63 275.34 0.131 274.84 67.67
91 990.10 30.71 63.06 GMS 834.90 259.27 106.96 280.47 0.340 279.98 67.58
92 1000.00 30.66 63.18 GMS 843.42 263.78 109.25 285.51 0.080 285.03 67.50
93 1010.06 30.64 63.03 GMS 852.07 268.35 111.57 290.62 0.079 290.16 67.42
94 1020.04 30.85 63.07 GMS 860.65 272.90 113.88 295.71 0.211 295.26 67.35
95 1030.02 30.96 63.13 GMS 869.21 277.47 116.20 300.82 0.114 300.39 67.28
96 1040.12 30.81 63.38 GMS 877.88 282.10 118.53 305.99 0.195 305.57 67.21
97 1050.08 30.78 63.47 GMS 886.43 286.66 120.81 311.08 0.055 310.67 67.15
98 1060.03 31.00 63.56 GMS 894.97 291.23 123.09 316.18 0.226 315.78 67.09
99 1070.12 31.26 63.73 GMS 903.61 295.91 125.41 321.39 0.272 320.99 67.03
100 1080.07 31.17 63.94 GMS 912.12 300.54 127.68 326.53 0.142 326.15 66.98
101 1090.06 31.15 63.94 GMS 920.67 305.18 129.95 331.70 0.020 331.32 66.93
102 1100.01 31.07 63.86 GMS 929.19 309.80 132.21 336.83 0.090 336.46 66.89
103 1110.02 31.11 63.83 GMS 937.76 314.44 134.49 341.99 0.043 341.63 66.84
104 1120.01 31.08 63.93 GMS 946.31 319.07 136.76 347.14 0.060 346.79 66.80
105 1130.04 30.95 64.01 GMS 954.91 323.71 139.03 352.31 0.136 351.96 66.76
106 1140.09 30.98 64.12 GMS 963.53 328.36 141.29 357.47 0.064 357.13 66.72
107 1150.08 30.91 64.03 GMS 972.10 332.98 143.54 362.60 0.084 362.26 66.68
108 1160.10 30.89 63.87 GMS 980.69 337.61 145.80 367.74 0.084 367.41 66.64
109 1170.00 31.09 63.97 GMS 989.18 342.18 148.04 372.83 0.209 372.51 66.60
110 1180.00 31.32 63.62 GMS 997.73 346.83 150.33 378.01 0.293 377.69 66.57
111 1190.01 31.71 63.92 GMS 1006.27 351.53 152.64 383.24 0.420 382.92 66.53
112 1200.11 31.87 63.79 GMS 1014.85 356.30 154.99 388.55 0.172 388.24 66.49
113 1210.07 31.88 63.63 GMS 1023.31 361.02 157.32 393.80 0.085 393.50 66.45
114 1220.11 31.70 63.76 GMS 1031.84 365.76 159.66 399.09 0.192 398.79 66.42
115 1230.05 31.74 63.88 GMS 1040.30 370.45 161.96 404.31 0.075 404.01 66.38
116 1240.11 31.64 64.08 GMS 1048.86 375.20 164.28 409.59 0.144 409.30 66.35
117 1250.04 31.40 64.04 GMS 1057.32 379.87 166.55 414.78 0.243 414.49 66.32
118 1260.08 31.29 64.12 GMS 1065.90 384.56 168.84 419.99 0.117 419.71 66.30
119 1270.02 31.21 64.26 GMS 1074.40 389.21 171.08 425.15 0.109 424.87 66.27
120 1280.06 31.06 64.34 GMS 1082.99 393.88 173.33 430.34 0.155 430.06 66.25
121 1290.01 31.04 64.43 GMS 1091.52 398.51 175.55 435.47 0.051 435.19 66.23
122 1300.02 30.94 64.33 GMS 1100.10 403.16 177.78 440.62 0.112 440.35 66.20
123 1310.05 31.06 64.15 GMS 1108.69 407.81 180.03 445.78 0.151 445.51 66.18
124 1320.08 31.20 63.65 GMS 1117.28 412.47 182.31 450.96 0.293 450.70 66.15
125 1330.12 31.44 63.40 GMS 1125.86 417.14 184.63 456.17 0.272 455.92 66.12
126 1340.03 31.43 63.23 GMS 1134.31 421.76 186.95 461.34 0.090 461.08 66.09
127 1350.09 31.38 63.27 GMS 1142.90 426.44 189.31 466.57 0.054 466.33 66.06
128 1360.01 31.44 63.23 GMS 1151.36 431.06 191.64 471.74 0.064 471.50 66.03
129 1370.05 31.51 63.34 GMS 1159.93 435.74 194.00 476.97 0.090 476.74 66.00
130 1380.10 31.89 63.29 GMS 1168.48 440.46 196.37 482.25 0.379 482.02 65.97
131 1390.04 32.22 63.36 GMS 1176.90 445.17 198.74 487.52 0.334 487.29 65.94
132 1400.10 32.12 63.51 GMS 1185.42 449.96 201.13 492.87 0.127 492.65 65.92
133 1410.07 32.18 63.55 GMS 1193.86 454.71 203.50 498.17 0.064 497.95 65.89
134 1420.02 32.09 63.59 GMS 1202.28 459.45 205.85 503.46 0.093 503.25 65.87
135 1430.11 32.03 63.46 GMS 1210.84 464.24 208.24 508.81 0.091 508.60 65.84
136 1440.05 31.92 63.36 GMS 1219.27 468.95 210.60 514.07 0.123 513.86 65.82
137 1450.01 31.67 63.45 GMS 1227.73 473.64 212.95 519.31 0.255 519.11 65.79
138 1460.05 31.66 63.30 GMS 1236.28 478.35 215.31 524.58 0.079 524.38 65.77
139 1470.10 31.73 63.37 GMS 1244.83 483.07 217.68 529.85 0.079 529.66 65.74
140 1480.03 31.76 63.40 GMS 1253.27 487.74 220.02 535.07 0.034 534.88 65.72
141 1490.08 32.12 63.56 GMS 1261.80 492.50 222.39 540.39 0.368 540.20 65.70
142 1500.07 32.41 63.81 GMS 1270.25 497.28 224.76 545.72 0.320 545.53 65.68
143 1510.01 32.67 64.03 GMS 1278.63 502.08 227.11 551.06 0.287 550.88 65.66
144 1520.10 32.70 64.02 GMS 1287.12 506.98 229.49 556.51 0.030 556.33 65.65
145 1530.07 32.67 64.11 GMS 1295.51 511.82 231.85 561.89 0.057 561.71 65.63
146 1540.04 32.61 64.04 GMS 1303.91 516.66 234.20 567.26 0.071 567.09 65.62
147 1550.03 32.52 64.03 GMS 1312.33 521.50 236.55 572.64 0.090 572.47 65.60
148 1560.02 32.49 64.04 GMS 1320.75 526.32 238.90 578.01 0.031 577.84 65.59
149 1570.02 32.56 64.18 GMS 1329.18 531.16 241.25 583.38 0.103 583.21 65.57
150 1580.10 32.61 63.97 GMS 1337.68 536.04 243.63 588.81 0.123 588.64 65.56
151 1590.09 32.53 64.13 GMS 1346.10 540.88 245.98 594.18 0.118 594.02 65.55
152 1600.07 32.42 64.30 GMS 1354.52 545.70 248.31 599.54 0.143 599.38 65.53
153 1610.08 32.40 64.38 GMS 1362.97 550.54 250.63 604.90 0.047 604.74 65.52
154 1620.07 32.45 64.28 GMS 1371.40 555.37 252.95 610.26 0.073 610.10 65.51
155 1630.09 32.40 64.47 GMS 1379.86 560.21 255.28 615.63 0.113 615.47 65.50
156 1640.09 32.42 64.48 GMS 1388.30 565.05 257.59 620.99 0.021 620.83 65.49
157 1650.09 32.45 64.55 GMS 1396.74 569.89 259.89 626.35 0.048 626.19 65.48
158 1660.10 32.63 64.52 GMS 1405.18 574.75 262.21 631.74 0.181 631.58 65.48
159 1670.00 32.33 64.55 GMS 1413.53 579.55 264.49 637.05 0.303 636.90 65.47
160 1680.01 32.02 64.70 GMS 1422.00 584.37 266.78 642.38 0.320 642.23 65.46
161 1690.01 31.87 64.77 GMS 1430.49 589.15 269.04 647.67 0.155 647.52 65.46
162 1700.03 32.16 64.91 GMS 1438.98 593.96 271.30 652.98 0.299 652.83 65.45
163 1710.02 32.90 65.28 GMS 1447.41 598.83 273.56 658.36 0.767 658.20 65.45
164 1720.01 33.66 65.67 GMS 1455.76 603.82 275.83 663.84 0.790 663.68 65.45
165 1730.10 34.73 66.10 GMS 1464.10 608.99 278.15 669.51 1.087 669.35 65.45
166 1740.05 35.85 66.68 GMS 1472.23 614.26 280.45 675.26 1.175 675.09 65.46
167 1750.04 36.56 66.84 GMS 1480.29 619.68 282.78 681.15 0.717 680.99 65.47
168 1760.10 37.68 66.56 GMS 1488.31 625.26 285.18 687.22 1.126 687.05 65.48
169 1770.03 38.84 66.36 GMS 1496.10 630.90 287.64 693.37 1.175 693.20 65.49
170 1780.06 39.66 66.11 GMS 1503.87 636.70 290.19 699.72 0.833 699.54 65.50
171 1790.02 40.72 65.27 GMS 1511.48 642.56 292.84 706.14 1.195 705.96 65.50
172 1800.08 41.61 64.66 GMS 1519.05 648.56 295.64 712.77 0.971 712.58 65.49
173 1810.00 42.40 64.31 GMS 1526.42 654.55 298.50 719.40 0.831 719.22 65.48
174 1820.01 43.30 63.64 GMS 1533.76 660.67 301.49 726.21 1.008 726.03 65.47
175 1830.05 44.18 63.33 GMS 1541.02 666.88 304.59 733.15 0.902 732.97 65.45
176 1840.06 44.84 63.84 GMS 1548.16 673.16 307.71 740.16 0.750 739.99 65.43
177 1850.08 45.55 64.68 GMS 1555.22 679.57 310.80 747.27 0.925 747.10 65.42
178 1860.01 46.18 65.26 GMS 1562.13 686.03 313.81 754.39 0.760 754.22 65.42
179 1870.02 47.02 65.30 GMS 1569.01 692.63 316.85 761.67 0.840 761.49 65.42
180 1880.01 48.03 65.15 GMS 1575.75 699.32 319.94 769.03 1.017 768.86 65.42
181 1890.00 48.90 65.10 GMS 1582.38 706.11 323.09 776.51 0.872 776.34 65.41
182 1900.09 49.83 65.12 GMS 1588.95 713.05 326.31 784.17 0.922 783.99 65.41
183 1910.04 50.95 65.40 GMS 1595.29 720.01 329.52 791.83 1.146 791.66 65.41
184 1920.10 51.73 65.31 GMS 1601.58 727.15 332.79 799.69 0.778 799.51 65.41
185 1930.03 52.61 65.04 GMS 1607.67 734.27 336.09 807.53 0.912 807.35 65.41
186 1940.08 53.59 64.48 GMS 1613.70 741.54 339.51 815.57 1.072 815.39 65.40
187 1950.02 54.43 64.21 GMS 1619.54 748.79 343.00 823.61 0.873 823.43 65.39
188 1960.05 55.03 64.11 GMS 1625.34 756.16 346.57 831.80 0.604 831.62 65.38
189 1970.09 55.41 64.16 GMS 1631.06 763.58 350.16 840.04 0.381 839.87 65.36
190 1980.03 55.44 64.18 GMS 1636.70 770.95 353.73 848.22 0.034 848.05 65.35
191 1990.08 55.23 64.14 GMS 1642.42 778.39 357.33 856.49 0.212 856.32 65.34
192 2000.09 55.40 64.18 GMS 1648.12 785.80 360.92 864.72 0.173 864.55 65.33
193 2010.11 55.33 64.17 GMS 1653.81 793.22 364.51 872.96 0.070 872.79 65.32
194 2020.04 55.26 64.24 GMS 1659.46 800.57 368.06 881.12 0.091 880.96 65.31
195 2030.08 55.36 64.28 GMS 1665.18 808.00 371.65 889.38 0.105 889.21 65.30
196 2040.10 55.41 64.24 GMS 1670.87 815.43 375.23 897.62 0.060 897.46 65.29
197 2050.05 55.35 64.29 GMS 1676.52 822.81 378.78 905.81 0.073 905.65 65.28
198 2060.07 55.42 64.28 GMS 1682.21 830.24 382.36 914.05 0.070 913.89 65.27
199 2070.05 55.55 64.36 GMS 1687.87 837.65 385.93 922.28 0.146 922.12 65.26
200 2080.11 55.62 64.31 GMS 1693.56 845.13 389.52 930.57 0.081 930.42 65.25
201 2090.05 55.59 64.32 GMS 1699.17 852.52 393.08 938.77 0.031 938.62 65.25
202 2100.09 55.54 64.27 GMS 1704.85 859.98 396.67 947.05 0.065 946.90 65.24
203 2110.05 55.71 64.27 GMS 1710.47 867.39 400.24 955.27 0.171 955.12 65.23
204 2120.10 55.67 64.12 GMS 1716.14 874.86 403.85 963.57 0.130 963.42 65.22
205 2130.04 55.77 64.16 GMS 1721.73 882.25 407.43 971.79 0.106 971.63 65.21
206 2140.10 55.72 64.11 GMS 1727.40 889.73 411.06 980.10 0.064 979.95 65.20
207 2150.04 55.68 64.19 GMS 1733.00 897.12 414.64 988.31 0.078 988.16 65.19
208 2160.08 55.70 64.07 GMS 1738.66 904.58 418.26 996.60 0.101 996.45 65.19
209 2170.02 55.68 64.12 GMS 1744.26 911.97 421.85 1004.81 0.046 1004.66 65.18
210 2180.06 55.62 64.11 GMS 1749.93 919.43 425.46 1013.10 0.060 1012.95 65.17
211 2190.09 55.61 64.11 GMS 1755.59 926.87 429.08 1021.37 0.010 1021.23 65.16
212 2200.02 55.75 64.17 GMS 1761.19 934.25 432.66 1029.57 0.150 1029.43 65.15
213 2210.10 55.69 64.11 GMS 1766.87 941.75 436.29 1037.90 0.077 1037.76 65.14
214 2220.05 55.66 64.19 GMS 1772.48 949.14 439.87 1046.12 0.073 1045.98 65.14
215 2230.11 55.60 64.20 GMS 1778.16 956.62 443.49 1054.42 0.060 1054.28 65.13
216 2240.08 55.62 64.15 GMS 1783.79 964.03 447.07 1062.65 0.046 1062.51 65.12
217 2250.02 55.72 64.15 GMS 1789.39 971.41 450.65 1070.85 0.101 1070.72 65.11
218 2260.08 55.75 64.18 GMS 1795.06 978.90 454.27 1079.17 0.039 1079.03 65.11
219 2270.03 55.69 64.18 GMS 1800.66 986.30 457.85 1087.39 0.060 1087.25 65.10
220 2280.11 55.72 64.21 GMS 1806.34 993.79 461.48 1095.71 0.039 1095.58 65.09
221 2290.03 55.71 64.06 GMS 1811.93 1001.17 465.05 1103.91 0.125 1103.78 65.08
222 2300.07 55.84 64.10 GMS 1817.58 1008.63 468.68 1112.21 0.134 1112.08 65.08
223 2310.10 55.75 64.10 GMS 1823.21 1016.10 472.31 1120.50 0.090 1120.37 65.07
224 2320.05 55.71 64.03 GMS 1828.82 1023.49 475.90 1128.72 0.071 1128.60 65.06
225 2330.02 55.80 64.09 GMS 1834.43 1030.90 479.51 1136.96 0.103 1136.84 65.06
226 2340.04 55.74 64.02 GMS 1840.06 1038.35 483.13 1145.25 0.083 1145.12 65.05
227 2350.06 55.70 63.96 GMS 1845.71 1045.79 486.76 1153.53 0.064 1153.40 65.04
228 2360.07 55.65 63.96 GMS 1851.35 1053.22 490.39 1161.79 0.050 1161.67 65.03
229 2370.09 55.75 63.96 GMS 1857.00 1060.66 494.03 1170.07 0.100 1169.95 65.03
230 2380.05 55.75 63.89 GMS 1862.60 1068.05 497.64 1178.30 0.058 1178.18 65.02
231 2390.10 55.61 63.93 GMS 1868.27 1075.51 501.29 1186.60 0.143 1186.48 65.01
232 2400.05 55.69 63.96 GMS 1873.89 1082.89 504.90 1194.81 0.084 1194.69 65.00
233 2410.01 55.55 64.01 GMS 1879.51 1090.27 508.51 1203.03 0.147 1202.91 65.00
234 2420.07 55.56 63.91 GMS 1885.20 1097.73 512.15 1211.32 0.083 1211.21 64.99
235 2430.11 55.71 64.06 GMS 1890.87 1105.18 515.79 1219.61 0.194 1219.50 64.98
236 2440.05 55.73 64.06 GMS 1896.47 1112.56 519.38 1227.82 0.020 1227.71 64.98
237 2450.09 55.60 64.03 GMS 1902.13 1120.02 523.01 1236.11 0.132 1236.00 64.97
238 2460.03 55.62 64.08 GMS 1907.74 1127.39 526.60 1244.31 0.046 1244.20 64.96
239 2470.09 55.68 63.92 GMS 1913.42 1134.86 530.24 1252.62 0.144 1252.51 64.96
240 2480.12 55.76 63.99 GMS 1919.07 1142.30 533.88 1260.90 0.098 1260.80 64.95
241 2490.02 55.69 63.97 GMS 1924.64 1149.66 537.46 1269.08 0.073 1268.98 64.94
242 2500.09 55.59 63.98 GMS 1930.33 1157.13 541.11 1277.40 0.100 1277.29 64.94
243 2510.06 55.62 63.93 GMS 1935.96 1164.52 544.72 1285.62 0.051 1285.52 64.93
244 2520.03 55.54 63.89 GMS 1941.59 1171.90 548.34 1293.84 0.087 1293.74 64.92
245 2530.10 55.56 63.98 GMS 1947.29 1179.36 551.99 1302.15 0.076 1302.04 64.92
246 2540.06 55.43 63.90 GMS 1952.93 1186.74 555.59 1310.35 0.146 1310.25 64.91
247 2550.03 55.37 64.03 GMS 1958.59 1194.11 559.20 1318.56 0.123 1318.46 64.91
248 2560.02 55.35 63.91 GMS 1964.27 1201.50 562.80 1326.78 0.101 1326.68 64.90
249 2570.00 55.24 64.05 GMS 1969.96 1208.87 566.40 1334.98 0.160 1334.88 64.90
250 2580.09 55.18 64.06 GMS 1975.71 1216.32 570.03 1343.27 0.060 1343.17 64.89
251 2590.05 55.13 64.13 GMS 1981.40 1223.67 573.60 1351.44 0.076 1351.34 64.89
252 2600.03 55.09 64.09 GMS 1987.11 1231.04 577.17 1359.63 0.052 1359.53 64.88
253 2610.09 55.12 64.11 GMS 1992.87 1238.46 580.78 1367.88 0.034 1367.78 64.88
254 2620.04 55.07 64.08 GMS 1998.56 1245.80 584.34 1376.03 0.056 1375.94 64.87
255 2630.01 54.93 64.13 GMS 2004.28 1253.15 587.91 1384.20 0.146 1384.11 64.87
256 2640.08 54.97 64.12 GMS 2010.06 1260.56 591.51 1392.44 0.041 1392.35 64.86
257 2650.04 55.03 64.18 GMS 2015.77 1267.91 595.06 1400.60 0.078 1400.51 64.86
258 2660.05 54.92 64.21 GMS 2021.52 1275.29 598.63 1408.80 0.113 1408.71 64.85
259 2670.01 54.74 64.25 GMS 2027.26 1282.62 602.17 1416.94 0.184 1416.85 64.85
260 2680.10 54.84 64.27 GMS 2033.07 1290.04 605.75 1425.18 0.100 1425.09 64.85
261 2690.03 55.20 64.57 GMS 2038.77 1297.38 609.27 1433.32 0.439 1433.23 64.84
262 2700.05 55.58 64.61 GMS 2044.46 1304.83 612.80 1441.57 0.381 1441.48 64.84
263 2710.10 55.56 64.64 GMS 2050.14 1312.32 616.36 1449.86 0.032 1449.76 64.84
264 2720.04 55.54 64.68 GMS 2055.76 1319.73 619.87 1458.05 0.039 1457.96 64.84
265 2730.02 55.52 64.71 GMS 2061.41 1327.17 623.38 1466.28 0.032 1466.19 64.84
266 2740.10 55.44 64.68 GMS 2067.12 1334.68 626.93 1474.59 0.083 1474.49 64.84
267 2750.04 55.33 64.68 GMS 2072.77 1342.07 630.43 1482.77 0.111 1482.67 64.84
268 2760.01 55.22 64.74 GMS 2078.45 1349.48 633.93 1490.96 0.121 1490.87 64.84
269 2770.05 55.25 64.68 GMS 2084.17 1356.94 637.45 1499.21 0.057 1499.12 64.84
270 2780.02 55.15 64.71 GMS 2089.86 1364.34 640.95 1507.39 0.103 1507.30 64.84
271 2790.01 54.99 64.83 GMS 2095.58 1371.75 644.45 1515.59 0.188 1515.49 64.84
272 2800.02 54.97 64.73 GMS 2101.33 1379.16 647.94 1523.78 0.084 1523.69 64.84
273 2810.05 54.92 64.89 GMS 2107.09 1386.59 651.43 1531.99 0.140 1531.90 64.84
274 2820.07 54.85 64.92 GMS 2112.85 1394.02 654.91 1540.19 0.074 1540.09 64.84
275 2830.10 55.11 65.03 GMS 2118.61 1401.46 658.38 1548.40 0.274 1548.31 64.84
276 2840.01 55.94 65.63 GMS 2124.22 1408.88 661.79 1556.57 0.975 1556.48 64.84
277 2850.04 56.25 65.89 GMS 2129.81 1416.47 665.21 1564.90 0.377 1564.80 64.84
278 2860.07 56.32 66.07 GMS 2135.38 1424.09 668.61 1573.24 0.165 1573.14 64.85
279 2870.04 56.14 66.11 GMS 2140.92 1431.67 671.97 1581.52 0.184 1581.42 64.86
280 2880.03 55.97 66.14 GMS 2146.50 1439.25 675.32 1589.81 0.172 1589.70 64.86
281 2890.05 55.93 66.07 GMS 2152.11 1446.84 678.68 1598.11 0.070 1598.00 64.87
282 2900.07 55.85 66.16 GMS 2157.73 1454.42 682.04 1606.40 0.109 1606.29 64.88
283 2910.01 55.70 66.16 GMS 2163.32 1461.94 685.36 1614.62 0.151 1614.51 64.88
284 2920.10 55.55 66.35 GMS 2169.02 1469.56 688.72 1622.95 0.215 1622.83 64.89
285 2930.09 55.38 66.25 GMS 2174.68 1477.10 692.03 1631.17 0.189 1631.05 64.90
286 2940.12 55.37 66.41 GMS 2180.38 1484.66 695.34 1639.42 0.132 1639.30 64.90
287 2950.03 55.26 66.46 GMS 2186.02 1492.13 698.60 1647.57 0.118 1647.44 64.91
288 2960.04 55.09 66.44 GMS 2191.74 1499.66 701.88 1655.78 0.171 1655.65 64.92
289 2970.07 55.04 66.48 GMS 2197.48 1507.20 705.16 1664.00 0.060 1663.87 64.93
290 2980.03 54.81 66.59 GMS 2203.20 1514.68 708.41 1672.15 0.248 1672.01 64.93
291 2990.08 54.51 66.81 GMS 2209.02 1522.21 711.65 1680.35 0.348 1680.20 64.94
292 3000.01 54.19 66.90 GMS 2214.80 1529.63 714.82 1688.41 0.331 1688.26 64.95
293 3010.03 54.53 66.89 GMS 2220.64 1537.12 718.02 1696.55 0.339 1696.40 64.96
294 3020.08 54.98 66.99 GMS 2226.44 1544.67 721.23 1704.75 0.455 1704.60 64.97
295 3030.03 54.82 66.98 GMS 2232.16 1552.16 724.42 1712.89 0.161 1712.73 64.98
296 3040.10 54.42 67.09 GMS 2237.99 1559.72 727.62 1721.09 0.407 1720.93 64.99
297 3050.08 54.28 67.17 GMS 2243.81 1567.19 730.77 1729.20 0.155 1729.03 65.00
298 3060.04 53.92 67.22 GMS 2249.65 1574.63 733.90 1737.26 0.364 1737.08 65.01
299 3070.01 53.99 66.91 GMS 2255.52 1582.05 737.04 1745.31 0.261 1745.14 65.02
300 3080.05 54.46 66.85 GMS 2261.39 1589.55 740.24 1753.46 0.471 1753.27 65.03
301 3090.06 55.05 66.83 GMS 2267.16 1597.06 743.45 1761.63 0.590 1761.44 65.04
302 3100.00 55.64 66.33 GMS 2272.82 1604.56 746.70 1769.80 0.724 1769.61 65.04
303 3110.01 55.80 65.35 GMS 2278.45 1612.11 750.09 1778.07 0.825 1777.88 65.05
304 3120.08 56.06 63.96 GMS 2284.10 1619.65 753.66 1786.41 1.172 1786.22 65.05
305 3130.04 56.09 63.48 GMS 2289.65 1627.06 757.32 1794.67 0.401 1794.48 65.04
306 3140.09 56.09 63.43 GMS 2295.26 1634.52 761.05 1803.01 0.041 1802.82 65.03
307 3150.02 56.21 63.30 GMS 2300.79 1641.89 764.74 1811.26 0.163 1811.07 65.03
308 3160.06 56.34 63.27 GMS 2306.37 1649.35 768.50 1819.60 0.132 1819.42 65.02
309 3170.10 56.51 63.21 GMS 2311.92 1656.82 772.26 1827.96 0.176 1827.78 65.01
310 3180.08 56.66 63.13 GMS 2317.42 1664.25 776.02 1836.29 0.165 1836.11 65.00
311 3190.04 56.69 63.12 GMS 2322.89 1671.68 779.79 1844.61 0.031 1844.43 64.99
312 3200.01 56.50 62.84 GMS 2328.38 1679.09 783.57 1852.92 0.302 1852.75 64.98
313 3210.01 56.09 62.53 GMS 2333.93 1686.48 787.39 1861.24 0.484 1861.07 64.97
314 3220.07 56.20 62.51 GMS 2339.53 1693.90 791.24 1869.58 0.111 1869.42 64.96
315 3230.08 56.37 62.53 GMS 2345.09 1701.28 795.08 1877.90 0.171 1877.74 64.95
316 3240.07 56.49 62.64 GMS 2350.61 1708.67 798.91 1886.22 0.151 1886.06 64.94
317 3250.06 56.66 62.63 GMS 2356.11 1716.08 802.75 1894.55 0.170 1894.40 64.93
318 3260.03 56.73 62.70 GMS 2361.59 1723.48 806.57 1902.88 0.092 1902.73 64.92
319 3270.08 56.85 62.78 GMS 2367.09 1730.95 810.42 1911.28 0.137 1911.13 64.91
320 3280.03 56.90 62.80 GMS 2372.53 1738.36 814.24 1919.61 0.053 1919.46 64.90
321 3290.07 57.01 62.86 GMS 2378.00 1745.85 818.08 1928.02 0.120 1927.88 64.89
322 3300.04 56.83 62.90 GMS 2383.45 1753.29 821.89 1936.36 0.184 1936.23 64.88
323 3310.09 56.94 63.00 GMS 2388.94 1760.78 825.71 1944.78 0.138 1944.64 64.88
324 3320.02 56.85 63.07 GMS 2394.36 1768.20 829.49 1953.09 0.108 1952.96 64.87
325 3330.05 56.84 63.09 GMS 2399.85 1775.68 833.29 1961.48 0.019 1961.35 64.86
326 3340.08 56.73 63.19 GMS 2405.34 1783.17 837.08 1969.87 0.138 1969.74 64.85
327 3350.02 56.78 63.29 GMS 2410.79 1790.59 840.82 1978.18 0.098 1978.06 64.85
328 3360.08 56.71 63.36 GMS 2416.31 1798.11 844.60 1986.59 0.091 1986.47 64.84
329 3370.02 56.61 63.51 GMS 2421.77 1805.54 848.31 1994.89 0.161 1994.77 64.83
330 3380.09 56.56 63.52 GMS 2427.31 1813.06 852.06 2003.30 0.050 2003.18 64.83
331 3390.09 56.56 63.73 GMS 2432.82 1820.54 855.77 2011.64 0.175 2011.52 64.82
332 3400.01 56.50 63.77 GMS 2438.30 1827.96 859.43 2019.91 0.069 2019.79 64.82
333 3410.03 56.45 63.91 GMS 2443.83 1835.46 863.11 2028.26 0.127 2028.15 64.82
334 3420.07 56.45 64.04 GMS 2449.38 1842.97 866.78 2036.63 0.108 2036.52 64.81
335 3430.01 56.36 64.09 GMS 2454.88 1850.42 870.40 2044.91 0.100 2044.79 64.81
336 3440.04 56.47 64.13 GMS 2460.43 1857.94 874.05 2053.27 0.115 2053.15 64.81
337 3450.09 56.39 64.29 GMS 2465.98 1865.48 877.69 2061.64 0.155 2061.52 64.80
338 3460.05 56.36 64.37 GMS 2471.50 1872.95 881.29 2069.93 0.073 2069.82 64.80
339 3470.09 56.32 64.47 GMS 2477.06 1880.49 884.90 2078.29 0.092 2078.17 64.80
340 3480.02 56.30 64.51 GMS 2482.57 1887.95 888.45 2086.55 0.039 2086.44 64.80
341 3490.07 56.17 64.59 GMS 2488.16 1895.49 892.04 2094.91 0.145 2094.79 64.80
342 3500.01 56.25 64.57 GMS 2493.69 1902.95 895.59 2103.17 0.082 2103.05 64.80
343 3510.08 56.09 64.72 GMS 2499.29 1910.51 899.17 2111.53 0.201 2111.42 64.80
344 3520.05 56.04 64.88 GMS 2504.86 1918.00 902.69 2119.80 0.142 2119.69 64.80
345 3530.02 55.93 64.84 GMS 2510.44 1925.48 906.21 2128.07 0.115 2127.95 64.80
346 3540.05 55.88 64.98 GMS 2516.06 1933.00 909.73 2136.37 0.126 2136.26 64.80
347 3550.01 55.92 65.02 GMS 2521.64 1940.47 913.21 2144.62 0.052 2144.50 64.80
348 3560.09 55.79 65.17 GMS 2527.30 1948.04 916.73 2152.96 0.178 2152.85 64.80
349 3570.06 55.68 65.27 GMS 2532.91 1955.52 920.18 2161.20 0.138 2161.08 64.80
350 3580.04 55.65 65.32 GMS 2538.54 1963.01 923.62 2169.44 0.051 2169.32 64.80
351 3590.02 55.70 65.47 GMS 2544.17 1970.50 927.06 2177.68 0.134 2177.56 64.80
352 3600.06 55.59 65.51 GMS 2549.84 1978.04 930.49 2185.97 0.114 2185.85 64.81
353 3610.03 55.61 65.57 GMS 2555.47 1985.53 933.90 2194.20 0.054 2194.07 64.81
354 3620.03 55.55 65.62 GMS 2561.12 1993.04 937.31 2202.45 0.073 2202.32 64.81
355 3630.02 55.62 65.64 GMS 2566.77 2000.55 940.71 2210.69 0.072 2210.56 64.82
356 3640.05 55.52 65.70 GMS 2572.44 2008.09 944.12 2218.96 0.111 2218.83 64.82
357 3650.04 55.43 65.77 GMS 2578.10 2015.59 947.50 2227.19 0.107 2227.06 64.82
358 3660.03 55.49 65.79 GMS 2583.76 2023.10 950.88 2235.42 0.062 2235.28 64.83
359 3670.01 55.36 65.79 GMS 2589.43 2030.59 954.25 2243.63 0.130 2243.50 64.83
360 3680.00 55.37 65.73 GMS 2595.11 2038.09 957.62 2251.85 0.050 2251.71 64.83
361 3690.01 55.35 65.69 GMS 2600.80 2045.59 961.01 2260.09 0.038 2259.95 64.84
362 3700.02 55.27 65.67 GMS 2606.49 2053.09 964.40 2268.32 0.082 2268.17 64.84
363 3722.00 55.40 63.88 MWD 2618.99 2069.45 972.10 2286.39 0.672 2286.25 64.84
364 3751.00 55.50 63.58 MWD 2635.44 2090.87 982.67 2310.27 0.092 2310.14 64.83
365 3780.00 55.86 63.72 MWD 2651.79 2112.33 993.30 2334.22 0.130 2334.09 64.82
366 3809.00 56.43 63.91 MWD 2667.95 2133.94 1003.93 2358.30 0.204 2358.17 64.80
367 3834.00 56.68 64.32 MWD 2681.73 2152.71 1013.04 2379.16 0.169 2379.03 64.80
368 3869.00 56.75 65.50 MWD 2700.93 2179.20 1025.44 2408.42 0.283 2408.28 64.80
369 3899.00 57.02 65.22 MWD 2717.32 2202.04 1035.92 2433.54 0.119 2433.41 64.81
370 3920.00 57.25 65.02 MWD 2728.72 2218.04 1043.34 2451.18 0.136 2451.04 64.81
371 3958.00 57.31 63.35 MWD 2749.26 2246.82 1057.26 2483.15 0.370 2483.01 64.80
372 3986.00 57.49 63.13 MWD 2764.35 2267.88 1067.88 2506.73 0.092 2506.60 64.79
373 4016.00 56.29 62.20 MWD 2780.73 2290.21 1079.42 2531.84 0.477 2531.71 64.76
374 4045.00 54.17 61.83 MWD 2797.27 2311.24 1090.60 2555.63 0.739 2555.52 64.74
375 4074.00 54.30 61.21 MWD 2814.22 2331.93 1101.82 2579.12 0.179 2579.02 64.71
376 4103.00 54.57 60.47 MWD 2831.09 2352.53 1113.31 2602.66 0.227 2602.57 64.67
377 4132.00 54.72 60.81 MWD 2847.87 2373.14 1124.91 2626.26 0.109 2626.18 64.64
378 4161.00 55.38 59.92 MWD 2864.48 2393.80 1136.66 2649.96 0.339 2649.89 64.60
379 4191.00 54.73 61.50 MWD 2881.67 2415.25 1148.69 2674.49 0.483 2674.44 64.56
380 4220.00 53.61 63.65 MWD 2898.64 2436.11 1159.53 2697.99 0.714 2697.94 64.55
381 4249.00 53.95 62.97 MWD 2915.78 2457.01 1170.03 2721.38 0.223 2721.33 64.54
382 4278.00 54.10 62.53 MWD 2932.82 2477.88 1180.78 2744.84 0.133 2744.79 64.52
383 4307.00 54.36 62.11 MWD 2949.77 2498.71 1191.71 2768.35 0.148 2768.31 64.50
384 4336.00 54.59 62.19 MWD 2966.62 2519.58 1202.74 2791.93 0.082 2791.90 64.48
385 4365.00 55.10 61.33 MWD 2983.32 2540.47 1213.96 2815.61 0.300 2815.58 64.46
386 4394.00 53.54 62.70 MWD 3000.23 2561.27 1225.01 2839.15 0.661 2839.12 64.44
387 4423.00 52.36 62.27 MWD 3017.70 2581.80 1235.70 2862.28 0.424 2862.26 64.42
388 4452.00 52.58 61.04 MWD 3035.37 2602.04 1246.62 2885.25 0.345 2885.23 64.40
389 4481.00 50.52 61.42 MWD 3053.40 2621.94 1257.55 2907.92 0.718 2907.91 64.38
390 4510.00 48.00 63.71 MWD 3072.33 2641.44 1267.68 2929.88 1.055 2929.87 64.36
391 4539.00 46.36 62.75 MWD 3092.04 2660.43 1277.26 2951.15 0.615 2951.14 64.35
392 4568.00 44.32 62.02 MWD 3112.42 2678.71 1286.82 2971.76 0.726 2971.75 64.34
393 4597.00 41.65 62.60 MWD 3133.63 2696.21 1296.01 2991.52 0.931 2991.51 64.33
394 4626.00 37.98 62.37 MWD 3155.91 2712.68 1304.58 3010.08 1.267 3010.07 64.32
395 4655.00 34.21 61.86 MWD 3179.33 2727.78 1312.57 3027.14 1.304 3027.14 64.30
396 4683.00 30.74 63.24 MWD 3202.95 2741.11 1319.51 3042.17 1.267 3042.16 64.29
397 4713.00 29.71 62.82 MWD 3228.87 2754.57 1326.35 3057.27 0.350 3057.26 64.29
398 4742.00 28.55 63.22 MWD 3254.21 2767.15 1332.76 3071.38 0.406 3071.38 64.28
399 4775.00 27.78 62.94 MWD 3283.30 2781.04 1339.81 3086.95 0.237 3086.95 64.28
400 4801.00 27.84 63.23 MWD 3306.29 2791.86 1345.30 3099.08 0.057 3099.08 64.27
401 4830.00 28.05 63.54 MWD 3331.91 2804.01 1351.39 3112.67 0.088 3112.67 64.27
402 4859.00 28.19 63.89 MWD 3357.49 2816.26 1357.44 3126.34 0.075 3126.33 64.27
403 4887.00 27.12 63.23 MWD 3382.29 2827.90 1363.23 3139.33 0.397 3139.33 64.26
404 4903.00 27.60 63.11 MWD 3396.50 2834.46 1366.55 3146.68 0.302 3146.68 64.26
405 4920.00 27.98 63.07 MWD 3411.54 2841.53 1370.13 3154.61 0.224 3154.61 64.26
406 4949.00 23.95 67.05 MWD 3437.61 2853.02 1375.51 3167.29 1.513 3167.29 64.26
407 4979.00 16.78 75.76 MWD 3465.72 2862.84 1378.96 3177.63 2.589 3177.63 64.28
408 5007.00 13.78 84.10 MWD 3492.73 2870.07 1380.30 3184.74 1.326 3184.73 64.32
409 5037.00 13.84 60.31 MWD 3521.89 2876.75 1382.44 3191.68 1.880 3191.67 64.33
410 5066.00 11.77 59.74 MWD 3550.17 2882.32 1385.65 3198.09 0.715 3198.08 64.32
411 5094.00 8.37 66.54 MWD 3577.73 2886.66 1387.90 3202.98 1.284 3202.97 64.32
412 5123.00 8.66 67.27 MWD 3606.41 2890.61 1389.59 3207.27 0.107 3207.26 64.33
413 5152.00 8.99 65.83 MWD 3635.07 2894.69 1391.36 3211.71 0.137 3211.70 64.33
414 5184.00 8.68 65.06 MWD 3666.69 2899.16 1393.40 3216.63 0.104 3216.62 64.33
415 5206.00 8.70 65.00 ZZZ 3688.44 2902.17 1394.80 3219.95 0.010 3219.94 64.33
Report N° 4
BHA K/06-GT4
E & P Nederland B.V. 16/10/2001
BHA 1 Upper
Component OD ID connection Nbr Length

5"1/2 HWDP 5"1/2 3"3/4 5"1/2HT55 8 75.24

X/O 7" 2"15/16 5"1/2HT55 1 0.92

8'' Jar - s/n 1588 1020 7"13/16 3" 6"5/8Reg 1 9.69

8"1/4 DC 8" 3" 6"5/8Reg 3 27.16

X/O 7"3/4 2"15/16 6"5/8Reg 1 0.92

22" Stabilizer - s/n DIS10176 9"1/2 2"7/8 7"5/8Reg 1 2.42

9"1/2 DC 9"1/8 3"1/8 7"5/8Reg 1 9.45

UBHO sub - s/n 05470 9"1/2 3"1/16 7"5/8Reg 1 0.87

MWD - Baker s/n JHA3858 9"1/2 2"13/16 7"5/8Reg 1 9.92

22" Stabilizer - s/n IS8579 9"1/2 3"1/16 7"5/8Reg 1 2.27

Floatsub - s/n 35370 w/ float valve 9"1/2 3" 7"5/8 Reg 1 0.65

Mud motor-Baker Navidrill M1C - s/n 11222 - Sleeve


11"1/4 7"5/8Reg 1 9.66
25"3/4 - BH:1.3°

Rock bit-Reed EMS11GC - s/n X83407 dressed w/ 3*22 +


26" 7"5/8Reg 1 0.67
1*12

Page 1 de 1
Report N° 8
BHA K/06-GT4
E & P Nederland B.V. 20/10/2001
BHA 2 Upper
Component OD ID connection Nbr Length

5"1/2 HWDP 5"1/2 3"3/4 HT 55 14 131.79

XO 7" 2"15/16 HT 55 1 0.92

8" DC 8" 3" 6"5/8 Reg 2 18.10

8" Jar 7"13/16 3" 6"5/8 Reg 1 9.69

8" DC 8" 3" 6"5/8 Reg 6 54.66

XO 7"3/4 2"15/16 6"5/8 Reg 1 0.92

9"1/2 DC 9"1/2 3"1/8 7"5/8 Reg 3 28.24

MWD Baker 9"1/2 2"13/16 7"5/8 Reg 1 9.92

Stabilizer 16"3/4 3" 7"5/8 Reg 1 2.10

Float sub + Float valve 9"1/2 3" 7''5/8 Reg 1 0.65

Mud motor Navidrill M1C + sleeve 17"1/4 - AKO 1.2° 11"1/4 7"5/8 Reg 1 9.67

Near bit reamer 17"13/32 3"3/16 7"5/8 Reg 1 1.13

Rock bit Smith MGSSH s/n LR 9915 3x20+1x19 17"½ 3"3/8 7"5/8Reg 1 0.43

Page 1 de 1
Report N° 15
BHA K/06-GT4
E & P Nederland B.V. 27/10/2001
BHA 3 Upper
Component OD ID connection Nbr Length

HW 5"1/2 HT 55 14 131.79

XO 7" 2"15/16 HT 55 1 0.92

DC 8"1/8 3" 6"5/8 REG 2 18.10

Jar 7"13/16 3" 6"5/8 REG 1 9.69

DC 7"15/16 2"13/16 6"5/8 REG 6 54.66

XO 7"3/4 2"15/16 6"5/8 REG 1 0.92

DC 9"1/4 3"1/8 7"5/8 REG 3 28.24

MWD 9"1/4 3"3/16 7"5/8 REG 1 9.63

Float sub 9"1/2 3" 7"5/8 REG 1 0.65

Mud motor (Navidrill M1XL) 9"1/2 2" 7"5/8 REG 1 11.51

NB Reamer 9"1/2 3"1/8 6"5/8 REG 1 0.37

12"1/4 Bit (Reed EHP 42H) 12"1/4 6"5/8 REG 1 0.35

Page 1 de 1
Report N° 17
BHA K/06-GT4
E & P Nederland B.V. 29/10/2001
BHA 4 Upper
Component OD ID connection Nbr Length

HW 5"1/2 HT 55 14 131.79

XO 7" 2"15/16 HT 55 1 0.92

DC 8" 3" 6"5/8 REG 2 18.10

Jar 8" 3" 6"5/8 REG 1 9.69

DC 8" 2"13/16 6"5/8 REG 6 54.66

Circul sub 7"3/4 2"1/4 6"5/8 REG 1 0.75

XO 7"3/4 2"15/16 6"5/8 REG 1 0.92

MWD 9"1/2 3"3/16 7"5/8 REG 1 9.63

Float sub 9"1/2 3" 7"5/8 REG 1 0.65

Mud motor (Navidrill M1XL) 9"1/2 2" 7"5/8 REG 1 11.51

12"1/4 PDC Bit (Baker BX547) 12"1/4 7"5/8 REG 1 0.70

Page 1 de 1
Report N° 21
BHA K/06-GT4
E & P Nederland B.V. 02/11/2001
BHA 5 Upper
Component OD ID connection Nbr Length

HW 5"1/2 HT 55 14 131.79

XO 7" 2"15/16 HT 55 1 0.92

DC 8" 3" 6"5/8 REG 5 45.60

Jar 8" 3" 6"5/8 REG 1 9.69

DC 8" 2"13/16 6"5/8 REG 3 27.16

Circul sub 7"3/4 2"1/4 6"5/8 REG 1 0.75

XO 7"3/4 2"15/16 6"5/8 REG 1 0.92

DC 9"1/2 3"1/8 7"5/8 REG 3 28.24

MWD 9"1/2 3"3/16 7"5/8 REG 1 9.63

Float sub 9"1/2 3" 7"5/8 REG 1 0.65

Mud motor (Navidrill M1XL) 9"1/2 2" 7"5/8 REG 1 11.39

NB Reamer 9"1/2 3"1/8 6"5/8 REG 1 0.38 Picture 1

12"1/4 Bit (Smith FG26OD) 12"1/4 6"5/8 REG 1 0.32 Picture 1

Page 1 de 1
Report N° 24
BHA K/06-GT4
E & P Nederland B.V. 05/11/2001
BHA 6 Upper
Component OD ID connection Nbr Length

HW 5"1/2 HT 55 14 131.79

XO 7" 2"15/16 HT 55 1 0.92

DC 8" 3" 6"5/8 REG 2 18.10

Jar 8" 3" 6"5/8 REG 1 9.69

DC 8" 2"13/16 6"5/8 REG 7 63.90

Circul sub 7"3/4 2"1/4 6"5/8 REG 1 0.75

XO 7"3/4 2"15/16 6"5/8 REG 1 0.92

MWD 9"1/2 3"3/16 7"5/8 REG 1 9.63

Float sub 9"1/2 3" 7"5/8 REG 1 0.65

Mud motor (Navidrill M1XL) 9"1/2 2" 7"5/8 REG 1 11.39

12"1/4 PDC Bit (BX536K from Baker) 12"1/4 7"5/8 REG 1 0.68 Picture 1

Page 1 de 1
Report N° 32
BHA K/06-GT4
E & P Nederland B.V. 13/11/2001
BHA 7 Upper
Component OD ID connection Nbr Length

XO 7" 2"3/4 HT55 1 0.78

5" DP 5" 4"1/4 4½ IF 90 860.30

5'' HWDP 5" 3" 4½ IF 12 106.64

Dart sub 5" 3" 4½ IF 1 0.63

5" HWDP 5" 3" 4½ IF 1 8.73

6"1/2 Jar accelerator 6"1/2 2"1/2 4½ IF 1 10.67

5" HWDP 5" 3" 4½ IF 1 8.73

XO 6"1/2 2"15/16 4½ IF 1 1.01

6"1/4 DC 6"1/4 2"3/4 4" IF 2 18.82

6"1/2 Jar 6"1/2 2"1/2 4" IF 1 9.85

6"1/4 DC 6"1/4 2"3/4 4" IF 11 102.66

Circulating sub 6"5/8 2"1/4 4" IF 1 0.77

Float sub (+Float valve) 6"7/8 2"5/8 4" IF 1 0.60

XO Non magnetic 6"1/4 2"5/8 4" IF 1 0.49

6"3/4 MWD DG 6"3/4 2"13/16 4½ IF 1 11.62

Mud motor Navidril Mach 1XL AKO 1.1° 8"3/8 4½ IF 1 10.17

8½ Near bit stab 8"7/16 2"5/8 4½ Reg 1 0.32

8½ PDC bit #7 Smith M16VPX s/n JS5474 nozzles


8½ 4½ Reg 1 0.27
3x13+3x14

Page 1 de 1
Report N° 34
BHA K/06-GT4
E & P Nederland B.V. 15/11/2001
BHA 8 Upper
Component OD ID connection Nbr Length

XO 7" 2"3/4 HT55 1 0.78

5" DP 5" 4"1/4 4½ IF 90 860.30

5'' HWDP 5" 3" 4½ IF 12 106.64

Dart sub 5" 3" 4½ IF 1 0.63

5" HWDP 5" 3" 4½ IF 1 8.73

6"1/2 Jar accelerator 6"1/2 2"1/2 4½ IF 1 10.67

5" HWDP 5" 3" 4½ IF 1 8.73

XO 6"1/2 2"15/16 4½ IF 1 1.01

6"1/4 DC 6"1/4 2"3/4 4" IF 2 18.82

6"1/2 Jar 6"1/2 2"1/2 4" IF 1 9.85

6"1/4 DC 6"1/4 2"3/4 4" IF 11 102.66

Circulating sub 6"5/8 2"1/4 4" IF 1 0.77

Float sub (+Float valve) 6"7/8 2"5/8 4" IF 1 0.60

XO Non magnetic 6"1/4 2"5/8 4" IF 1 0.49

6"3/4 MWD DG 6"3/4 2"13/16 4½ IF 1 11.62

Mud motor Navidril Mach 1XL AKO 1.1° 8"3/8 4½ IF 1 10.17

8½ Near bit stab 8"7/16 2"5/8 4½ Reg 1 0.32 Picture 1

8½ PDC bit #8 Baker G382 8½ 4½ Reg 1 0.27

Page 1 de 1
Report N° 34
BHA K/06-GT4
E & P Nederland B.V. 15/11/2001
BHA 9 Upper
Component OD ID connection Nbr Length

XO 7" 2"3/4 HT55 1 0.78

5" DP 5" 4"1/4 4½ IF 90 860.30

5'' HWDP 5" 3" 4½ IF 12 106.64

Dart sub 5" 3" 4½ IF 1 0.63

5" HWDP 5" 3" 4½ IF 1 8.73

6"1/2 Jar accelerator 6"1/2 2"1/2 4½ IF 1 10.67

5" HWDP 5" 3" 4½ IF 1 8.73

XO 6"1/2 2"15/16 4½ IF 1 1.01

6"1/4 DC 6"1/4 2"3/4 4" IF 2 18.82

6"1/2 Jar 6"1/2 2"1/2 4" IF 1 9.85

6"1/4 DC 6"1/4 2"3/4 4" IF 11 102.66

Circulating sub 6"5/8 2"1/4 4" IF 1 0.77

Float sub (+Float valve) 6"7/8 2"5/8 4" IF 1 0.60

XO Non magnetic 6"1/4 2"5/8 4" IF 1 0.49

6"3/4 MWD DG 6"3/4 2"13/16 4½ IF 1 11.81

Mud motor Navidril Mach 1XL AKO 1.1° 8"3/8 4½ IF 1 10.17

8½ Near bit stab 8"7/16 2"5/8 4½ Reg 1 0.32 Picture 3

8½ PDC bit #8 Hughes Christensen G382D62KU1X s/n


8½ 4½ Reg 1 0.29
1214202 nozzles 3x18+1x15

Page 1 de 1
Report N° 42
BHA K/06-GT4
E & P Nederland B.V. 23/11/2001
BHA 10 Upper
Component OD ID connection Nbr Length

XO 7" 2"3/4 HT 55 1 0.78

XO 6"9/16 2"1/4 4"1/2 IF 1 0.92

DP 3"1/2 WT 38 144 1375.97

HW 5" WT 38 12 112.74

Jar acceler 4"3/4 WT 38 1 9.93

HW 5" WT 38 6 56.26

Jar 4"3/4 WT 38 1 9.00

Dart Sub 4"11/16 2"1/4 WT 38 1 0.68

XO 4"3/4 2"1/4 WT 38 1 1.01

DC 5" 3"1/2 IF 5 45.66

XO 5" 2"9/16 3"1/2 IF 1 0.94

Circul sub 4"11/16 2" WT 38 1 0.97

XO 4"3/4 2"1/4 WT 38 1 1.01

Stab 4"3/4 2"3/8 3"1/2 IF 1 1.24

DC 4"3/4 3"1/2 IF 1 9.15

MWD 4"3/4 3"1/2 IF 1 0.76

NMCSDP 4"5/8 2"13/16 3"1/2 IF 1 9.10

Pin-Pin Sub 4"11/16 2"3/8 3"1/2 IF 1 0.33

Float Sub 4"3/4 2"1/4 3"1/2 IF 1 0.60

Stab 4"3/4 2"3/8 3"1/2 IF 1 1.47

Mud motor Xtrem 4"13/16 3"1/2 IF 1 10.01

PDC Baker G438 SN1212766 5"7/8 3"1/2 REG 1 0.34

Page 1 de 1
Report N° 44
BHA K/06-GT4
E & P Nederland B.V. 25/11/2001
BHA 11 Upper
Component OD ID connection Nbr Length

XO 7" 2"3/4 HT 55 1 0.78

XO 6"9/16 2"1/4 4"1/2 IF 1 0.92

DP 3"1/2 WT 38 156 1491.02

HW 5" WT 38 12 112.74

Jar acceler 4"3/4 WT 38 1 9.93

HW 5" WT 38 6 56.26

Jar 4"3/4 WT 38 1 9.00

Dart Sub 4"11/16 2"1/4 WT 38 1 0.68

XO 4"3/4 2"1/4 WT 38 1 1.01

DC 5" 3"1/2 IF 5 45.66

XO 5" 2"9/16 3"1/2 IF 1 0.94

Circul sub 4"11/16 2" WT 38 1 0.97

XO 4"3/4 2"1/4 WT 38 1 1.01

Stab 4"3/4 2"3/8 3"1/2 IF 1 1.24 Picture 2

DC 4"3/4 3"1/2 IF 1 9.15

MWD 4"3/4 3"1/2 IF 1 0.76

NMCSDP 4"5/8 2"13/16 3"1/2 IF 1 9.10

Pin-Pin Sub 4"11/16 2"3/8 3"1/2 IF 1 0.33

Float Sub 4"3/4 2"1/4 3"1/2 IF 1 0.60

Stab 4"3/4 2"3/8 3"1/2 IF 1 1.47 Picture 1

Mud motor Xtrem 4"13/16 3"1/2 IF 1 10.01

PDC DDS SPH 633 SN S1G0347 5"7/8 3"1/2 Reg 1 0.22

Page 1 de 1
Report N° 46
BHA K/06-GT4
E & P Nederland B.V. 27/11/2001
BHA 12 Upper
Component OD ID connection Nbr Length

XO 7" 2"3/4 HT55 1 0.78

XO 6"9/16 2"1/4 4"1/2 IF 1 0.92

DP 3"1/2 WT 38 156 1491.02

HW 4"3/4 WT 38 12 112.74

Jar acceler 4"3/4 WT 38 1 9.93

HW 4"3/4 WT 38 6 56.26

Jar 4"3/4 WT 38 1 9.00

Dart Sub 4"11/16 2"1/4 WT 38 1 0.68

XO 4"3/4 2"1/4 WT 38 1 1.01

DC 4"3/4 2"9/16 3"1/2 IF 6 54.81

XO 5" 2"9/16 3"1/2 IF 1 0.94

Circul sub 4"11/16 2" WT 38 1 0.97

XO 4"3/4 2"1/4 WT 38 1 1.01

Shocktool 4"3/4 1"1/2 3"1/2 IF 1 2.11

Agitator 4"3/4 2"1/8 3"1/2 IF 1 2.67

5"1/2 Stab 4"3/4 2"3/8 3"1/2 IF 1 1.24

MWD 4"3/4 3"1/2 IF 1 0.76

KM 4"5/8 2"13/16 3"1/2 IF 1 9.10

PIN/PIN Sub 4"11/16 2"3/8 3"1/2 IF 1 0.33

Float Sub 4"3/4 2"1/4 3"1/2 IF 1 0.60

Navidrill M1XL (1.2 AKO) 4"7/8 3"1/2 IF 1 9.54

Rock bit 5"7/8 3"1/2 REG 1 0.18

Page 1 de 1
Report N° 49
BHA K/06-GT4
E & P Nederland B.V. 30/11/2001
BHA 13 Upper
Component OD ID connection Nbr Length

XO 7" 2"3/4 HT 55 1 0.78

XO 6"9/16 2"1/4 4"1/2 IF 1 0.92

DP 3"1/2 WT 38 156 1491.02

HW 4"3/4 WT 38 12 112.74

Jar acceler 4"3/4 WT 38 1 9.93

HW 4"3/4 WT 38 6 56.26

Jar 4"3/4 WT 38 1 9.00

Dart Sub 4"11/16 2"1/4 WT 38 1 0.68

XO 4"3/4 2"1/4 WT 38 1 1.01

DC 4"3/4 2"9/16 3"1/2 IF 4 36.19

Junk catcher 5"9/16 4" 3"1/2 IF 1 0.98

Page 1 de 1
Report N° 49
BHA K/06-GT4
E & P Nederland B.V. 30/11/2001
BHA 14 Upper
Component OD ID connection Nbr Length

XO 7" 2"3/4 HT55 1 0.78

XO 6"9/16 2"1/4 4"1/2 IF 1 0.92

DP 3"1/2 WT 38 156 1491.02

HW 4"3/4 WT 38 12 112.74

Jar acceler 4"3/4 WT 38 1 9.93

HW 4"3/4 WT 38 6 56.26

Jar 4"3/4 WT 38 1 9.00

Dart Sub 4"11/16 2"1/4 WT 38 1 0.68

XO 4"3/4 2"1/4 WT 38 1 1.01

DC 4"3/4 2"9/16 3"1/2 IF 6 54.81

XO 5" 2"9/16 3"1/2 IF 1 0.94

Circul sub 4"11/16 2" WT 38 1 0.97

XO 4"3/4 2"1/4 WT 38 1 1.01

Shocktool 4"3/4 1"1/2 3"1/2 IF 1 2.11

Agitator 4"3/4 2"1/8 3"1/2 IF 1 2.67

5"1/2 Stab 4"3/4 2"3/8 3"1/2 IF 1 1.24 Picture 4

MWD 4"3/4 3"1/2 IF 1 0.71

KM 4"5/8 2"13/16 3"1/2 IF 1 9.10

PIN/PIN Sub 4"11/16 2"3/8 3"1/2 IF 1 0.33

Float Sub 4"3/4 2"1/4 3"1/2 IF 1 0.60

Navidrill M1XL (1.2 AKO) 4"7/8 3"1/2 IF 1 9.54

5"7/8 PDC Bit 5"7/8 3"1/2 REG 1 0.20

Page 1 de 1
Report N° 55
BHA K/06-GT4
E & P Nederland B.V. 06/12/2001
BHA 15 Upper
Component OD ID connection Nbr Length

X/O 7" 2"3/4 HT55 1 0.78

X/O 6"9/16 2"1/4 4½ IF 1 0.92

3½ DP 3½ 2"9/16 WT38 156 1491.02

3½ HWDP 3½ 2"1/16 WT38 12 112.74

4"3/4 Daily Jar accelerator 4"3/4 2"¾ WT38 1 9.93

3½ HWDP 3½ 2"1/16 WT38 6 56.26

4"3/4 Daily Jar 4"3/4 2"7/8 WT38 1 9.00

Dart sub 4"11/16 2"1/4 WT38 1 0.68

X/O 4"3/4 2"1/4 WT38 1 1.01

4"3/4 DC 4"5/8 2"9/16 3½ IF 5 45.66

5"½ stabiliser 4"3/4 2"3/8 3½ IF 1 1.24

4"3/4 DC 4"11/16 2"5/8 3½ IF 1 9.15

Bit sub 4"11/16 2"1/4 3½ Reg 1 0.76

5"7/8 PDC Varel MKF 39 s/n CP5870C 5"7/8 3½ Reg 1 0.20

Page 1 de 1
Report N° 58
BHA K/06-GT4
E & P Nederland B.V. 09/12/2001
BHA 16 Upper
Component OD ID connection Nbr Length

X/O 7" 2"3/4 HT55 1 0.78

X/O 6"9/16 2"1/4 4½ IF 1 0.92

3½ DP 3½ 2"9/16 WT38 156 1491.02

3½ HWDP 3½ 2"1/16 WT38 12 112.74

4"3/4 Jar accelerator 4"3/4 2"3/4 WT38 1 9.93

3½ HWDP 3½ 2"1/16 WT38 6 56.26

4"3/4 Daily Jar 4"3/4 2"7/8 WT38 1 9.00

X/O 4"3/4 2"1/4 WT38 1 1.01

4"3/4 DC 4"5/8 2"9/16 3½ IF 5 45.66

5½ stabiliser 4"3/4 2"3/8 3½ IF 1 1.24

4"3/4 DC 4"11/16 2"5/8 3½ IF 1 9.15

Circulating sub 4"3/4 1"3/4 3½ IF 1 0.71

Bit sub 4"11/16 2"1/4 3½ IF 1 0.76

5"7/8 PDC Varel MKF 39 s/n CP5870C 5"7/8 3½ Reg 1 0.20

Page 1 de 1
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 25
Ref : OPE/#12945/JCS/MH/AVE

- Final status

- Abandonment drawing

- Costs (F3Jbis)
ABANDONMENT K/06-GT4
E & P Nederland B.V.

CASING Fluid

in annulus
Top
Phase Depth Type Diameter Shoe Hanger cement in Cut Type SG
depth depth annulus depth
CP 30" X X 138.00 driven
26 682.00 Techn 20" X X 678.00 surface
17 1/2 1698.00 Techn 13 3/8 X X 1694.00 1203.00 WBM 1.30
12 1/4 3850.00 Prod 9 5/8" X X 3848.00 3420.00 2972.00 OBM 1.30
8 1/2" 4791.00 Prod 7 X 7 5/8 X 4790.00 3698.00 3698.00 OBM 1.27
X X
X X
X X
X X
X X
X X
X X
X X
X X
X X
X X
X X
X X
X X

Perforation interval Bridge plug/Cement plug


Tested
N° Top depth Bottom depth CP / BP Top depth Bottom depth Y/N
CP 4917.00 5203.00 N
CP 4580.00 4853.00 10T
CP 3615.00 3773.00 N
BP 3050.00 70bar

Comments Abandoned lower part of the well. Retrieved 9 5/8" casing as of 2972m. Started a geological side track. See well K/06-GT04G
ABANDONMENT DRAWING K/06-GT4
E & P Nederland B.V.

Ref: RKB
RKB / MSL = 44m
RKB / Seabed = 85m

30" CP 309.7 # X52


driven to 138 m

26" Drilling to 682m

20" 129.33 # X56 RL4S


shoe @ 678m

1.30sg WBM

17"1/2 Drilling to 1698m

Top cement Theo. at 1203m

13"3/8 BTC 61# N80


Shoe at 1694m
FIT 1.50sg at 1703m
Cut and retrieved casing
at 2972m

1.30sg OBM
Bridge plug at 3050m
12"1/4 Drilling to 3850m
tested 70 bar

Top cement 3420m


Cement plug #3
f/t 3773/3615m
Top 7" liner hanger: 3698 m Theoretical top
PBR at 3693m

9"5/8 New vam 53.5# P110


Shoe at 3848m OBM SG=1.27
FIT 2.07 sg at 3853m

8"1/2 Drilling to 4791m

7" Liner New vam 35# P110 Cement plug #2


( 7 5/8" 59# P110 from f/t 4853/4580m
3924 to 3827m) Tested 10T
Shoe at 4790m
LOT 2.29 sg at 4790m

Cement plug #1
f/t 5203/4917m
5"7/8 TD at 5206m Theoretical top
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 26
Ref : OPE/#12945/JCS/MH/AVE

- Penetration chart
PENETRATION CHART K/06-GT4
E & P Nederland B.V.

DAYS SINCE SPUD 59

00001

00001

00001
COSTS (kusd)

00001 Series1

00000

00000

00000
0 10 20 30 40 50 60 70

0 10 20 30 40 50 60 70
00000

01000
MEASURED DEPTH (m)

02000

Estimated
03000
Actual

04000

05000

06000

ESTIMATED

Period MOV CSP DRP CSP DRP CSP DRP DRP DRP DRP DRP DRP DRP CSP DRP
Phase 26" Drilling 17.5" Drilling 12"25 Drilling - top - Ommelanng - bottom ch
Drilling - Texng - Hollandng - Vlieland ling - Zechstein 8"5 Drilling - Zech
Days 1 2.00 3.00 3.00 6.00 4.00 1.00 8.00 4.00 2.00 2.00 3.00 2.00 5.00 8.00
Depth 677.00 1681.00 1762.00 3162.00 3306.00 3468.00 3557.00 3791.00 3953.00 4748.00

Period DRP CSP DRP DRP DRP CSP REP WCP


Phase illing - Silverpit 5"7/8 Drilling - SilDrilling - LSing - Westphalian
Days 1.00 5.00 6.00 1.00 7.00 5.00 4.00 13.00
Depth 4784.00 5051.00 5103.00 5224.00

ACTUAL

Period MOV DRP CSP DRP CSP DRP CSP DRP CSP DRP GEP RAP
Phase Drlling 26" Drilling 17"1/2 Drilling 12"1/4 Drilling 8½ Drilling 5"7/8
Days 1.56 1.83 2.56 4.25 2.54 13.08 4.23 5.25 4.79 10.63 2.73 4.79
Depth 682.00 1698.00 3850.00 4791.00 5206.00

Beginning of Well operation 13-10-2001 End of Well operation 12-12-2001


Beginning of DRP 16-10-2001 End of DRP 07-12-2001
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 27
Ref : OPE/#12945/JCS/MH/AVE

- Casing and Cement reports

- Detailed composition of the casing/tubing

string
Report N° 3
CASING RUN K/06-GT4
E & P Nederland B.V. 15/10/2001

Function Type Operation date OD Length Weight Grade Connection


in m lbs/ft
Surface / CP Casing
From 15/10/01 18:00 30 138.00 309.7 X52 D60
Technical Liner To
Production Tie Back

Start run.csg at 15-10-2001 18:00 Start circ.on bottom End of displacement

Shoe F. Collar L.Collar DV collar Top Hanger


mMD 138 mMD

mTVD mTVD

Drift diam (min.) in Weight of casing T in air T in mud

inch mMD mTVD N° Axis Deviation

Previous casing KOP at m


WELL CONDITION

Drilling Phase Incl. MD


D1= ° at
D2= ° at
D3= ° at

Wiper trips Caliper log


Open hole conditions (volume, washed out zone, tight spot, losses, gains...)

Thread compound used Clean oil


Average torque to make up joints 20000 ft.lbs LINER EQUIPMENT
Test connection Type / size Length
Filling frequency
Running speed Running string
Centralizers Manufacturer Drift
RUNNING CASING

Nb and type Running tool


Liner Packer
CIRCULATIONS AND DRAG FORCES PBR
Depth Time Flow rate P M.D M.D Liner hanger
m h l/mn bars T T Hydraulic Mechanical
Plug type
Pack off bushing type
Comments

TD

Observations or trouble while running Pipe movement Reciprocating Rotating


WELLHEAD

M.D. indications at the end of displacement T after setting of the cement T

Setting tension on spool T h after the end of displacement


Suspension and spool type
Additionnal seal (Type, dimensions)
Dist. between the upper part of the spool and RKB m Cut casing above spool cm

Cementing Log type after h setting Annular pressure bars


Results Top Cement annulus m
EVALUATION

Pressure test casing to bars Test packer depth m


Test top liner Over pressure Drawdown to bars
Comments / Results
Report N° 3
CASING / TUBING STRING K/06-GT4
E & P Nederland B.V. 15/10/2001
Casing Ø : 30 inch Mud weight : 0.00 SG
Shoe at : 137.75 m Hook weight : 70000 Lbs
Casing / Tubing Centralizer / Others Ordered
Type Grade Weight OD ID Ext Vol Steel Vol Type Supplier Model Length
(Lbs/Ft) (inch) (inch) (l/m) (l/m) (m)
1 X52 310.00 30 28 456.03 58.777 1 134.15
2 2 Stick-Up
3 3 (m)
4 4 -3.60
Joint n° Type Order Joint Cumul. Distance to Cementing
Hook load Mud gain Component type Drift diam Threads Remarks
/ n° n° length length RKB Equipment
Name (m) (m) (m) (Lbs) (m3)
shoe 1 1 13.28 13.28 124.47 83503 0.8 shoe reinforced first 1.20m D60 20 kft.lbs
2 1 2 12.14 25.42 112.33 95847 1.5 26.25 D60
3 1 3 11.94 37.36 100.39 107988 2.2 D60
4 1 4 12.16 49.52 88.23 120352 2.9 D60
5 1 5 12.16 61.68 76.07 132716 3.6 D60
6 1 6 11.91 73.59 64.16 144826 4.3 D60
7 1 7 12.17 85.76 51.99 157201 5.0 D60
8 1 8 12.17 97.93 39.82 169575 5.8 D60
9 1 9 12.15 110.08 27.67 181929 6.5 D60
10 1 12 11.92 122.00 15.75 194050 7.2 D60
11 1 13 12.15 134.15 3.60 206404 7.9 D60
Report N° 6
CASING RUN K/06-GT4
E & P Nederland B.V. 18/10/2001

Function Type Operation date OD Length Weight Grade Connection


in m lbs/ft
Surface / CP Casing
From 18/10/2001 19:30 20 678.00 129.33 X56 RL4S
Technical Liner To
Production Tie Back

Start run.csg at 18-10-2001 21:30 Start circ.on bottom 19-10-2001 12:00 End of displacement 19-10-2001 21:00

Shoe F. Collar L.Collar DV collar Top Hanger


mMD 678 664 mMD

mTVD 656 645 mTVD

Drift diam (min.) 18.56 in Weight of casing 130.5 T in air 111.5 T in mud

inch mMD mTVD N° Axis Deviation

Previous casing 30 138.00 138.00 1 KOP at 187.00 m


WELL CONDITION

Drilling Phase 26" 682.00 Incl. MD


D1= 7.29 ° at 332
D2= 20.63 ° at 536
D3= 31.3 ° at 682

Wiper trips Yes Caliper log


Open hole conditions (volume, washed out zone, tight spot, losses, gains...)
Hole in good shape.

Thread compound used Oil


Average torque to make up joints 25000 ft.lbs LINER EQUIPMENT
Test connection Type / size Length
Filling frequency Each joint
Running speed 2min/jt Running string
Centralizers Manufacturer Weatherford Drift
RUNNING CASING

Nb and type 27 - STA 4 Running tool


Liner Packer
CIRCULATIONS AND DRAG FORCES PBR
Depth Time Flow rate P M.D M.D Liner hanger
m h l/mn bars T T Hydraulic Mechanical
138.00 01:30 475 14 56 55 Plug type
Pack off bushing type
296.00 02:00 1000 38 83 73 Comments

678.00 TD 12:00 2500 20 154 123

Observations or trouble while running Pipe movement Reciprocating Rotating


None
WELLHEAD

M.D. indications at the end of displacement T after setting of the cement T

Setting tension on spool N/A T N/A h after the end of displacement


Suspension and spool type Casing head C-29 type,20"3/4 3000 Top flange X 20'' sliplock bottom
Additionnal seal (Type, dimensions) FS seals
Dist. between the upper part of the spool and RKB 27.83 m Cut casing above spool -0.34 cm

Cementing Log type None after h setting Annular pressure bars


Results Top Cement annulus Surface m
EVALUATION

Pressure test casing to N/A bars Test packer depth m


Test top liner Over pressure Drawdown to bars
Comments / Results
Report N° 7
CEMENTING K/06-GT4
E & P Nederland B.V. 19/10/2001
Casing to Cement 20 inch Cement Job type Primary single stage
Casing shoe 678.00 mMD 656.00 mVD Mud type WBM SG 1.17 BHST 28 °C
Drilling Size 26 inch LOT / FIT N/A EMW at mVD BHCT 25 °C
TD 682.00 mMD 660.00 mVD Pore press. 1.07 EMW at 660.00 mVD API schedule
Prev casing 30 inch 309.7 lbs/ft Format. frac EMW at mVD -Pressure bars
Prev csg shoe 138.00 mMD 138.00 mVD -Temperature °C

Laboratory fluids design


Products and additives Unit SPACERS SLURRIES Characteristics SLURRIES
n°1 n°2 n°1 n°2 n°1 n°2
Fresh water m3 10 Specific gravity ppg 1.44SG 1.67SG
Barite t 1.8 Thickening Time : 40BC 10:35 3:22
Drispac R+ kg 45 Thickening Time: 70BC 11:30 4:38
Pozmix 8000 m3 1000 1000 Thickening Time: 100BC 11:46 4:55
Sea water t 573 1030 Free Water % : vertical 0.9 0
NF-6 ltr 0.5 0.5 Free Water % : 45° N/A N/A
Fluid loss ml N/A N/A
Yield 1.41m3/t 0.95m3/t

Compress Strength 12h 3.5b N/A


24h 27b 131b

Final volume or Yield


Rheologies (laboratory / on site)
FLUIDS T° SG F300 F200 F100 F60 F30 F6 F3 G0 G10 PV YV n K
Mud
Spacer1 N/a
Spacer2
Slurry 1 23 1.44 9 7 5 4 3 3 2 N/A N/A 6 3 0.49 0.44
Slurry 2 23 1.67 70 60 49 37 34 19 12 N/A N/A 33 38 0.29 11.34

Mud
Spacer1 20 1.15 52 44 31 22 15 7 6 4 N/A 39 18 0.50 2.23
Spacer2
Slurry 1 20 1.44 14 10 7 6 4 3 3 6 N/A 9 4 0.51 0.57
Slurry 2 20 1.67 111 92 66 54 43 25 19 22 N/A 78 40 0.48 5.61

Products used and cost Operation summary


Products Unit SPACERS SLURRIES Unit Cost Operation Volume Flow Press Time
n°1 n°2 n°1 n°2 price break down m3 L/mn bars mn
Barite t 1.8 122.5 220.5 Circulation 140 2500 20 60
Drispac R+ kg 45 4.4 200.0 Batch mixing
NF 6 ltr 42 18 25.9 1554.0 Pump spacer 10 1000 20 20
Pozmix 8000 t 73.7 36.3 137.0 15074.5 Pump lead cmt 118 900 13 120
Sea water m3 Pump tail cmt 48 1000 15 50
Displacement 8.5 1400 50 10

Total displac.
Pressure test
Slurries volumes excess (%)
Caliper OR Theoretical
Total cost 420.5 11187.7 5440.8 17049.0 slurry 1 50
Fabrication Halliburton slurry 2
Silos Noble Ronald Hoope
Material used Displacement Halliburton Results Plan. Actual
on site Pits Noble Ronald Hoope Top slurry 1 Surface Surface mMD
Top slurry 2 476.00 354.00 mMD
internal top mMD

Comments CMT Specific gravity checked all along cmt operation : Ok,despite the discrepancy between the theoritical cmt quantity to used and quantity actually used...
Got cement return at surface after 118m3 of lead cement pumped ==> 7% open hole excess.

Rig Noble Ronald Hoo


Cement Contract Halliburton
Report N° 5
CASING / TUBING STRING K/06-GT4
E & P Nederland B.V. 17/10/2001
Casing Ø : 20 inch Mud weight : 1.15 SG
Shoe at : 678.00 m Hook weight : 70000 Lbs
Casing / Tubing Centralizer / Others Ordered
Type Grade Weight OD ID Ext Vol Steel Vol Type Supplier Model Length
(Lbs/Ft) (inch) (inch) (l/m) (l/m) (m)
1 X56 129.33 20 18.75 202.68 24.543 1 Weatherford sta 4 678.76
2 2 Stick-Up
3 3 (m)
4 4 0.76
Joint n° Type Order Joint Cumul. Distance to Cementing
Hook load Mud gain Component type Drift diam Threads Remarks
/ n° n° length length RKB Equipment
Name (m) (m) (m) (Lbs) (m3)
shoe A 1 1 0.50 0.50 677.50 70181 0.0
jnt sh A 1 2 12.00 12.50 665.50 74526 0.3 2 central
float A 1 3 1.82 14.32 663.68 75185 0.4
joint fl A 1 4 11.02 25.34 652.66 79175 0.6 2 central
59 1 5 12.40 37.74 640.26 83664 0.9 2 central
58 1 6 12.40 50.14 627.86 88154 1.2 1 central
57 1 7 12.40 62.54 615.46 92643 1.5
56 1 8 12.40 74.94 603.06 97133 1.8 1 central
55 1 9 12.41 87.35 590.65 101626 2.1
54 1 10 12.41 99.76 578.24 106119 2.4 1 central
53 1 11 12.42 112.18 565.82 110616 2.8
52 1 12 12.41 124.59 553.41 115109 3.1 1 centr
51 1 13 12.41 137.00 541.00 119602 3.4
50 1 14 12.41 149.41 528.59 124095 3.7 1 centr
49 1 15 12.40 161.81 516.19 128585 4.0
48 1 16 12.41 174.22 503.78 133078 4.3 1 centr
47 1 17 12.41 186.63 491.37 137571 4.6
46 1 18 12.40 199.03 478.97 142060 4.9 1 centr
45 1 19 12.08 211.11 466.89 146434 5.2
44 1 20 12.40 223.51 454.49 150924 5.5 1 centr
43 1 21 12.42 235.93 442.07 155420 5.8
42 1 22 12.41 248.34 429.66 159914 6.1 1 centr
41 1 23 12.40 260.74 417.26 164403 6.4
40 1 24 12.41 273.15 404.85 168896 6.7 1 centr
39 1 25 12.41 285.56 392.44 173389 7.0
38 1 26 12.42 297.98 380.02 177886 7.3 1 centr
37 1 27 12.41 310.39 367.61 182379 7.6
36 1 28 12.40 322.79 355.21 186869 7.9 1 centr
35 1 29 12.41 335.20 342.80 191362 8.2
34 1 30 12.09 347.29 330.71 195739 8.5 1 centr
33 1 31 12.42 359.71 318.29 200236 8.8
32 1 32 12.41 372.12 305.88 204729 9.1 1 centr
31 1 33 12.40 384.52 293.48 209219 9.4
30 1 34 12.41 396.93 281.07 213712 9.7 1 centr
29 1 35 12.09 409.02 268.98 218089 10.0
28 1 36 12.10 421.12 256.88 222470 10.3 1 centr
27 1 37 12.09 433.21 244.79 226847 10.6
26 1 38 12.36 445.57 232.43 231322 10.9 1 centr
25 1 39 12.07 457.64 220.36 235692 11.2
24 1 40 12.41 470.05 207.95 240185 11.5 1 centr
23 1 41 12.09 482.14 195.86 244563 11.8
22 1 42 12.42 494.56 183.44 249059 12.1 1 centr
21 1 43 12.41 506.97 171.03 253553 12.4
20 1 44 12.09 519.06 158.94 257930 12.7 1 centr
19 1 45 11.92 530.98 147.02 262246 13.0
18 1 46 12.09 543.07 134.93 266623 13.3 1 centr
17 1 47 12.43 555.50 122.50 271123 13.6
16 1 48 12.10 567.60 110.40 275504 13.9
15 1 49 12.11 579.71 98.29 279889 14.2
14 1 50 12.11 591.82 86.18 284273 14.5
13 1 51 12.42 604.24 73.76 288770 14.8
12 1 52 12.43 616.67 61.33 293270 15.1
11 1 53 12.42 629.09 48.91 297767 15.4
10 1 54 12.42 641.51 36.49 302264 15.7
special 1 55 12.40 653.91 24.09 306753 16.0 w.rigid centralizer 25.5 inch
9 1 56 12.43 666.34 11.66 311254 16.4
Report N° 5
CASING / TUBING STRING K/06-GT4
E & P Nederland B.V. 17/10/2001
Casing Ø : 20 inch Mud weight : 1.15 SG
Shoe at : 678.00 m Hook weight : 70000 Lbs
Casing / Tubing Centralizer / Others Ordered
Type Grade Weight OD ID Ext Vol Steel Vol Type Supplier Model Length
(Lbs/Ft) (inch) (inch) (l/m) (l/m) (m)
1 X56 129.33 20 18.75 202.68 24.543 1 Weatherford sta 4 678.76
2 2 Stick-Up
3 3 (m)
4 4 0.76
Joint n° Type Order Joint Cumul. Distance to Cementing
Hook load Mud gain Component type Drift diam Threads Remarks
/ n° n° length length RKB Equipment
Name (m) (m) (m) (Lbs) (m3)
8 1 57 12.42 678.76 -0.76 315751 16.7
Report N° 13
CASING RUN K/06-GT4
E & P Nederland B.V. 25/10/2001

Function Type Operation date OD Length Weight Grade Connection


in m lbs/ft
Surface / CP Casing
From 25/10/01 07:00 13"3/8 61 N80 BTC
Technical Liner To
Production Tie Back

Start run.csg at 25-10-2001 17:30 Start circ.on bottom 26-10-2001 6:00 End of displacement

Shoe F. Collar L.Collar DV collar Top Hanger


mMD 1694 1655 mMD

mTVD 1520.90 mTVD

Drift diam (min.) in Weight of casing 153 T in air 128 T in mud

inch mMD mTVD N° Axis Deviation

Previous casing 20" 678.00 1 KOP at m


WELL CONDITION

Drilling Phase 17"1/2 1698.00 Incl. MD


D1= 20 ° at 540
D2= 31 ° at 1000
D3= 32 ° at 1681

Wiper trips 1 Caliper log


Open hole conditions (volume, washed out zone, tight spot, losses, gains...)

Thread compound used


Average torque to make up joints LINER EQUIPMENT
Test connection Type / size Length
Filling frequency each joint
Running speed 11 jnts/hr Running string
Centralizers Manufacturer Weatherford Drift
RUNNING CASING

Nb and type 28 STA4 Running tool


Liner Packer
CIRCULATIONS AND DRAG FORCES PBR
Depth Time Flow rate P M.D M.D Liner hanger
m h l/mn bars T T Hydraulic Mechanical
678.00 00:15 950 24 82 80 Plug type
1100.00 00:15 950 27 120 90 Pack off bushing type
1600.00 00:15 950 33 170 105 Comments

1694.00 TD 950

Observations or trouble while running Pipe movement Reciprocating Rotating


WELLHEAD

M.D. indications at the end of displacement T after setting of the cement T

Setting tension on spool T h after the end of displacement


Suspension and spool type
Additionnal seal (Type, dimensions)
Dist. between the upper part of the spool and RKB m Cut casing above spool cm

Cementing Log type after h setting Annular pressure bars


Results Top Cement annulus 1203.00 m
EVALUATION

Pressure test casing to 120 bars Test packer depth m


Test top liner Over pressure Drawdown to bars
Comments / Results
Report N° 14
CEMENTING K/06-GT4
E & P Nederland B.V. 26/10/2001
Casing to Cement 13"3/8 inch Cement Job type Primary single stage
Casing shoe 1694.00 mMD mVD Mud type WBM SG 1.30 BHST 62 °C
Drilling Size 17"1/2 inch LOT / FIT EMW at mVD BHCT 47 °C
TD 1698.00 mMD mVD Pore press. EMW at mVD API schedule
Prev casing 20" inch 129.33 lbs/ft Format. frac EMW at mVD -Pressure bars
Prev csg shoe 678.00 mMD mVD -Temperature °C

Laboratory fluids design


Products and additives Unit SPACERS SLURRIES Characteristics SLURRIES
n°1 n°2 n°1 n°2 n°1 n°2
Pozmix 8000 kg 1000 Specific gravity ppg 13.9
Fresh water ltr 543 Thickening Time : 40BC 5:58
Defoamer NF-6 ltr 0.5 Thickening Time: 70BC 5:54
HR-4L ltr 7.2 Thickening Time: 100BC 5:48
Free Water % : vertical 0.4
Barite kg sg=1.15 Free Water % : 45°
Drispac kg 7 Fluid loss ml
Yield 0.92 m3/t

Compress Strength 12h


24h 4000

Final volume or Yield


Rheologies (laboratory / on site)
FLUIDS T° SG F300 F200 F100 F60 F30 F6 F3 G0 G10 PV YV n K
Mud
Spacer1
Spacer2
Slurry 1 15°C 1.67 30 21 12 9 7 4 3.5 27 3 0.81 0.20
Slurry 2

Mud
Spacer1 15°C 1.4 47 38 26 18 12 7 6 8 36 14 0.55 1.55
Spacer2
Slurry 1 15°C 1.67 42 31 17 12 9 5 3 7 42 3 0.87 0.19
Slurry 2

Products used and cost Operation summary


Products Unit SPACERS SLURRIES Unit Cost Operation Volume Flow Press Time
n°1 n°2 n°1 n°2 price break down m3 L/mn bars mn
Pozmix t 48 137.0 6578.0 Circulation
HR4L ltr 400 5.1 2040.0 Batch mixing
NF6 ltr 40 25.9 1036.0

Barite t 7.9 122.5 967.8


Drispac R+ kg 45 4.4 199.8

Total displac.
Pressure test
Slurries volumes excess (%)
Caliper OR Theoretical
Total cost 1167.6 9654.0 10821.5 slurry 1 50
Fabrication Halliburton slurry 2
Silos Noble Ronald Hoope
Material used Displacement Halliburton Results Plan. Actual
on site Pits Noble Ronald Hoope Top slurry 1 1194.00 mMD
Top slurry 2 mMD
internal top mMD

Comments

Rig
Cement Contract
Report N° 10
CASING / TUBING STRING K/06-GT4
E & P Nederland B.V. 22/10/2001
Casing Ø : 13 3/8 inch Mud weight : 1.30 SG
Shoe at : 1694.00 m Hook weight : 70000 Lbs
Casing / Tubing Centralizer / Others Ordered
Type Grade Weight OD ID Ext Vol Steel Vol Type Supplier Model Length
(Lbs/Ft) (inch) (inch) (l/m) (l/m) (m)
1 N80 61.00 13 3/8 12.515 90.64 11.282 1 Weatherford STA 4 1,695.78
2 2 Stick-Up
3 3 (m)
4 4 1.78
Joint n° Type Order Joint Cumul. Distance to Cementing
Hook load Mud gain Component type Drift diam Threads Remarks
/ n° n° length length RKB Equipment
Name (m) (m) (m) (Lbs) (m3)
Shoe A 1 1 13.64 13.64 1680.36 72277 0.2
BL 5 1 2 12.78 26.42 1667.58 74411 0.3
BL 4 1 3 12.84 39.26 1654.74 76554 0.4
BL 3 1 4 13.01 52.27 1641.73 78726 0.6
Float A 1 5 13.84 66.11 1627.89 81037 0.7
138 1 6 13.06 79.17 1614.83 83217 0.9
137 1 7 12.79 91.96 1602.04 85352 1.0
136 1 8 13.08 105.04 1588.96 87536 1.2
135 1 9 12.87 117.91 1576.09 89685 1.3
134 1 10 12.90 130.81 1563.19 91838 1.5
133 1 11 13.00 143.81 1550.19 94008 1.6
132 1 12 13.16 156.97 1537.03 96205 1.8
131 1 13 12.97 169.94 1524.06 98371 1.9
130 1 14 13.07 183.01 1510.99 100553 2.1
129 1 15 13.10 196.11 1497.89 102740 2.2
128 1 16 13.26 209.37 1484.63 104953 2.4
127 1 17 12.33 221.70 1472.30 107012 2.5
126 1 18 12.73 234.43 1459.57 109137 2.6
125 1 19 13.34 247.77 1446.23 111364 2.8
124 1 20 13.11 260.88 1433.12 113553 2.9
123 1 21 13.13 274.01 1419.99 115745 3.1
122 1 22 13.04 287.05 1406.95 117922 3.2
121 1 23 13.01 300.06 1393.94 120094 3.4
120 1 24 12.75 312.81 1381.19 122222 3.5
119 1 25 13.23 326.04 1367.96 124431 3.7
118 1 26 12.91 338.95 1355.05 126586 3.8
117 1 27 13.21 352.16 1341.84 128792 4.0
116 1 28 13.37 365.53 1328.47 131024 4.1
115 1 29 13.22 378.75 1315.25 133231 4.3
114 1 30 13.20 391.95 1302.05 135434 4.4
113 1 31 13.09 405.04 1288.96 137620 4.6
112 1 32 11.89 416.93 1277.07 139605 4.7
111 1 33 13.10 430.03 1263.97 141792 4.9
110 1 34 12.22 442.25 1251.75 143832 5.0
109 1 35 13.12 455.37 1238.63 146022 5.1
108 1 36 13.30 468.67 1225.33 148242 5.3
107 1 37 12.72 481.39 1212.61 150366 5.4
106 1 38 13.37 494.76 1199.24 152598 5.6
105 1 39 12.97 507.73 1186.27 154763 5.7
104 1 40 13.07 520.80 1173.20 156945 5.9
103 1 41 12.78 533.58 1160.42 159079 6.0
102 1 42 11.96 545.54 1148.46 161076 6.2
101 1 43 12.81 558.35 1135.65 163214 6.3
100 1 44 13.09 571.44 1122.56 165399 6.4
99 1 45 13.12 584.56 1109.44 167590 6.6
98 1 46 13.09 597.65 1096.35 169775 6.7
97 1 47 12.78 610.43 1083.57 171909 6.9
96 1 48 10.50 620.93 1073.07 173662 7.0
95 1 49 12.77 633.70 1060.30 175794 7.1
94 1 50 12.86 646.56 1047.44 177940 7.3
93 1 51 13.20 659.76 1034.24 180144 7.4
92 1 52 12.94 672.70 1021.30 182304 7.6
91 1 53 12.74 685.44 1008.56 184431 7.7
90 1 54 12.97 698.41 995.59 186597 7.9
89 1 55 13.20 711.61 982.39 188800 8.0
88 1 56 13.12 724.73 969.27 190991 8.2
Report N° 10
CASING / TUBING STRING K/06-GT4
E & P Nederland B.V. 22/10/2001
Casing Ø : 13 3/8 inch Mud weight : 1.30 SG
Shoe at : 1694.00 m Hook weight : 70000 Lbs
Casing / Tubing Centralizer / Others Ordered
Type Grade Weight OD ID Ext Vol Steel Vol Type Supplier Model Length
(Lbs/Ft) (inch) (inch) (l/m) (l/m) (m)
1 N80 61.00 13 3/8 12.515 90.64 11.282 1 Weatherford STA 4 1,695.78
2 2 Stick-Up
3 3 (m)
4 4 1.78
Joint n° Type Order Joint Cumul. Distance to Cementing
Hook load Mud gain Component type Drift diam Threads Remarks
/ n° n° length length RKB Equipment
Name (m) (m) (m) (Lbs) (m3)
87 1 57 12.02 736.75 957.25 192997 8.3
86 1 58 11.86 748.61 945.39 194977 8.4
85 1 59 13.11 761.72 932.28 197166 8.6
84 1 60 13.12 774.84 919.16 199356 8.7
83 1 61 11.84 786.68 907.32 201333 8.9
82 1 62 12.78 799.46 894.54 203466 9.0
81 1 63 13.12 812.58 881.42 205657 9.2
80 1 64 13.39 825.97 868.03 207892 9.3
79 1 65 12.91 838.88 855.12 210047 9.5
78 1 66 12.84 851.72 842.28 212191 9.6
77 1 67 13.07 864.79 829.21 214373 9.8
76 1 68 12.79 877.58 816.42 216508 9.9
75 1 69 12.77 890.35 803.65 218640 10.0
74 1 70 12.71 903.06 790.94 220762 10.2
73 1 71 13.12 916.18 777.82 222952 10.3
72 1 72 12.93 929.11 764.89 225111 10.5
71 1 73 12.87 941.98 752.02 227260 10.6
70 1 74 13.25 955.23 738.77 229472 10.8
69 1 75 12.92 968.15 725.85 231629 10.9
68 1 76 11.91 980.06 713.94 233617 11.1
67 1 77 12.66 992.72 701.28 235730 11.2
66 1 78 13.11 1005.83 688.17 237919 11.3
65 1 79 12.58 1018.41 675.59 240019 11.5
64 1 80 13.26 1031.67 662.33 242233 11.6
63 1 81 13.03 1044.70 649.30 244408 11.8
62 1 82 13.09 1057.79 636.21 246594 11.9
61 1 83 13.12 1070.91 623.09 248784 12.1
60 1 84 12.63 1083.54 610.46 250892 12.2
59 1 85 12.50 1096.04 597.96 252979 12.4
58 1 86 13.07 1109.11 584.89 255161 12.5
57 1 87 12.88 1121.99 572.01 257311 12.7
56 1 88 13.27 1135.26 558.74 259527 12.8
55 1 89 13.08 1148.34 545.66 261710 13.0
54 1 90 12.97 1161.31 532.69 263876 13.1
53 1 91 13.18 1174.49 519.51 266076 13.3
52 1 92 13.08 1187.57 506.43 268260 13.4
51 1 93 13.38 1200.95 493.05 270493 13.5
50 1 94 13.09 1214.04 479.96 272679 13.7
49 1 95 13.10 1227.14 466.86 274866 13.8
48 1 96 13.27 1240.41 453.59 277081 14.0
47 1 97 13.19 1253.60 440.40 279283 14.1
46 1 98 13.30 1266.90 427.10 281504 14.3
45 1 99 13.04 1279.94 414.06 283681 14.4
44 1 100 13.18 1293.12 400.88 285881 14.6
43 1 101 13.08 1306.20 387.80 288065 14.7
42 1 102 12.87 1319.07 374.93 290213 14.9
41 1 103 12.90 1331.97 362.03 292367 15.0
40 1 104 13.24 1345.21 348.79 294577 15.2
39 1 105 13.25 1358.46 335.54 296789 15.3
38 1 106 13.12 1371.58 322.42 298979 15.5
37 1 107 12.79 1384.37 309.63 301115 15.6
36 1 108 13.11 1397.48 296.52 303303 15.8
35 1 109 12.90 1410.38 283.62 305457 15.9
34 1 110 13.09 1423.47 270.53 307642 16.1
33 1 111 13.04 1436.51 257.49 309819 16.2
32 1 112 12.00 1448.51 245.49 311823 16.3
Report N° 10
CASING / TUBING STRING K/06-GT4
E & P Nederland B.V. 22/10/2001
Casing Ø : 13 3/8 inch Mud weight : 1.30 SG
Shoe at : 1694.00 m Hook weight : 70000 Lbs
Casing / Tubing Centralizer / Others Ordered
Type Grade Weight OD ID Ext Vol Steel Vol Type Supplier Model Length
(Lbs/Ft) (inch) (inch) (l/m) (l/m) (m)
1 N80 61.00 13 3/8 12.515 90.64 11.282 1 Weatherford STA 4 1,695.78
2 2 Stick-Up
3 3 (m)
4 4 1.78
Joint n° Type Order Joint Cumul. Distance to Cementing
Hook load Mud gain Component type Drift diam Threads Remarks
/ n° n° length length RKB Equipment
Name (m) (m) (m) (Lbs) (m3)
31 1 113 12.73 1461.24 232.76 313948 16.5
30 1 114 13.04 1474.28 219.72 316125 16.6
29 1 115 13.11 1487.39 206.61 318313 16.8
28 1 116 12.34 1499.73 194.27 320374 16.9
27 1 117 13.22 1512.95 181.05 322581 17.1
26 1 118 13.26 1526.21 167.79 324794 17.2
25 1 119 13.09 1539.30 154.70 326980 17.4
24 1 120 13.00 1552.30 141.70 329150 17.5
23 1 121 13.11 1565.41 128.59 331339 17.7
22 1 122 12.58 1577.99 116.01 333439 17.8
21 1 123 13.02 1591.01 102.99 335612 17.9
20 1 124 13.11 1604.12 89.88 337801 18.1
19 1 125 13.03 1617.15 76.85 339976 18.2
18 1 126 13.21 1630.36 63.64 342182 18.4
17 1 127 13.06 1643.42 50.58 344362 18.5
16 1 128 13.10 1656.52 37.48 346549 18.7
15 1 129 13.09 1669.61 24.39 348734 18.8
14 1 130 13.19 1682.80 11.20 350936 19.0
13 1 131 12.98 1695.78 -1.78 353103 19.1
Report N° 30
CASING RUN K/06-GT4
E & P Nederland B.V. 11/11/2001

Function Type Operation date OD Length Weight Grade Connection


in m lbs/ft
Surface / CP Casing
From 10/11/01 8:00 9 5/8 3850.00 53.5 P110 New Vam
Technical Liner To 11/11/01 11:00
Production Tie Back

Start run.csg at 10-11-2001 9:00 Start circ.on bottom 11-11-2001 11:00 End of displacement 11-11-2001 18:00

Shoe F. Collar L.Collar DV collar Top Hanger


mMD 3848 3794 mMD

mTVD 2776.5 2746.6 mTVD

Drift diam (min.) 8.583 in Weight of casing 300 T in air 252 T in mud

inch mMD mTVD N° Axis Deviation

Previous casing 13 3/8 1694.00 1520.90 1 KOP at 187.00 m


WELL CONDITION

Drilling Phase 12.25 3850.00 Incl. MD


D1= 20 ° at 540m
D2= 33 ° at 800
D3= 55 ° at 1966

Wiper trips 1 Caliper log


Open hole conditions (volume, washed out zone, tight spot, losses, gains...)
Only one tight spots at 3477m during wiper trip. No problem to run casing to bottom , bottom was tagged. Total losses while running casing = 10m3.

Thread compound used Shell Malleus


Average torque to make up joints 15900 ft*lbs LINER EQUIPMENT
Test connection Type / size Length
Filling frequency every joint
Running speed 1min/joint in casing , 2mins/joint in open hole Running string
Centralizers Manufacturer Weatherford Drift
RUNNING CASING

Nb and type 53 STA3 Running tool


Liner Packer
CIRCULATIONS AND DRAG FORCES PBR
Depth Time Flow rate P M.D M.D Liner hanger
m h l/mn bars T T Hydraulic Mechanical
1694.00 00:40 1500 35 160 109 Plug type
2500.00 00:10 1500 38 214 127 Pack off bushing type
2900.00 00:10 1500 40 245 141 Comments
3300.00 00:10 1500 45 304 150
3848.00 TD 02:00 1500 50 340 160

Observations or trouble while running Pipe movement Reciprocating Rotating


Total losses while running = 10m3
WELLHEAD

M.D. indications at the end of displacement 164 T after setting of the cement 191 T

Setting tension on spool 268 T 11:00 h after the end of displacement


Suspension and spool type FMC , C29 slips, Casing spool C29 20 3/4 3K bot * 13 5/8 5K speedloc clamp top .
Additionnal seal (Type, dimensions) FS seal 9 5/8
Dist. between the upper part of the spool and RKB 27.21 m Cut casing above spool 21 cm

Cementing Log type after h setting Annular pressure bars


Results Top Cement annulus 3420.00 m
EVALUATION

Pressure test casing to 395 bars Test packer depth m


Test top liner Over pressure Drawdown to bars
Comments / Results the 14th nov 2001 , 20 mins , ok
Report N° 14
CEMENTING K/06-GT4
E & P Nederland B.V. 26/10/2001
Casing to Cement 13"3/8 inch Cement Job type Primary single stage
Casing shoe 1694.00 mMD mVD Mud type WBM SG 1.30 BHST 62 °C
Drilling Size 17"1/2 inch LOT / FIT EMW at mVD BHCT 47 °C
TD 1698.00 mMD mVD Pore press. EMW at mVD API schedule
Prev casing 20" inch 129.33 lbs/ft Format. frac EMW at mVD -Pressure bars
Prev csg shoe 678.00 mMD mVD -Temperature °C

Laboratory fluids design


Products and additives Unit SPACERS SLURRIES Characteristics SLURRIES
n°1 n°2 n°1 n°2 n°1 n°2
Pozmix 8000 kg 1000 Specific gravity ppg 13.9
Fresh water ltr 543 Thickening Time : 40BC 5:58
Defoamer NF-6 ltr 0.5 Thickening Time: 70BC 5:54
HR-4L ltr 7.2 Thickening Time: 100BC 5:48
Free Water % : vertical 0.4
Barite kg sg=1.15 Free Water % : 45°
Drispac kg 7 Fluid loss ml
Yield 0.92 m3/t

Compress Strength 12h


24h 4000

Final volume or Yield


Rheologies (laboratory / on site)
FLUIDS T° SG F300 F200 F100 F60 F30 F6 F3 G0 G10 PV YV n K
Mud
Spacer1
Spacer2
Slurry 1 15°C 1.67 30 21 12 9 7 4 3.5 27 3 0.81 0.20
Slurry 2

Mud
Spacer1 15°C 1.4 47 38 26 18 12 7 6 8 36 14 0.55 1.55
Spacer2
Slurry 1 15°C 1.67 42 31 17 12 9 5 3 7 42 3 0.87 0.19
Slurry 2

Products used and cost Operation summary


Products Unit SPACERS SLURRIES Unit Cost Operation Volume Flow Press Time
n°1 n°2 n°1 n°2 price break down m3 L/mn bars mn
Pozmix t 48 137.0 6578.0 Circulation
HR4L ltr 400 5.1 2040.0 Batch mixing
NF6 ltr 40 25.9 1036.0

Barite t 7.9 122.5 967.8


Drispac R+ kg 45 4.4 199.8

Total displac.
Pressure test
Slurries volumes excess (%)
Caliper OR Theoretical
Total cost 1167.6 9654.0 10821.5 slurry 1 50
Fabrication Halliburton slurry 2
Silos Noble Ronald Hoope
Material used Displacement Halliburton Results Plan. Actual
on site Pits Noble Ronald Hoope Top slurry 1 1194.00 mMD
Top slurry 2 mMD
internal top mMD

Comments

Rig
Cement Contract
Report N° 30
CASING / TUBING STRING K/06-GT4
E & P Nederland B.V. 11/11/2001
Casing Ø : 9"5/8 inch Mud weight : 1.30 SG
Shoe at : 3848.00 m Hook weight : 60000 Lbs
Casing / Tubing Centralizer / Others Ordered
Type Grade Weight OD ID Ext Vol Steel Vol Type Supplier Model Length
(Lbs/Ft) (inch) (inch) (l/m) (l/m) (m)
1 P110 53.50 9.625 8.535 46.94 10.030 1 Weatherford STA 3 3,821.00
2 2 Stick-Up
3 3 (m)
4 4 -27.00
Joint n° Type Order Joint Cumul. Distance to Cementing
Hook load Mud gain Component type Drift diam Threads Remarks
/ n° n° length length RKB Equipment
Name (m) (m) (m) (Lbs) (m3)
Float shoe 1 1 0.55 0.55 3847.45 60081 0.0
Shoe joint 1 2 13.00 13.55 3834.45 61984 0.1 Backerlock 8.535 2 Centr + 2SC New Vam
BL1 1 3 13.35 26.90 3821.10 63939 0.3 Backerlock 8.535 2 Centr + 2SC New Vam
BL2 1 4 13.40 40.30 3807.70 65901 0.4 Backerlock 8.535 2 Centr + 2SC New Vam
BL3 1 5 13.11 53.41 3794.59 67820 0.5 Backerlock 8.535 2 Centr + 2SC New Vam
Float collar 1 6 0.56 53.97 3794.03 67902 0.5 Backerlock
Float joint 1 7 13.35 67.32 3780.68 69857 0.7 Backerlock 8.535 2 Centr + 2SC New Vam
BL4 1 8 13.25 80.57 3767.43 71797 0.8 Backerlock 8.535 2 Centr + 2SC New Vam
178 1 9 12.69 93.26 3754.74 73655 0.9 8.535 1 Centr + 1SC New Vam
177 1 10 13.15 106.41 3741.59 75581 1.1 8.535 1 Centr + 1SC New Vam
176 1 11 11.40 117.81 3730.19 77250 1.2 8.535 1 Centr + 1SC New Vam
175 1 12 11.03 128.84 3719.16 78865 1.3 8.535 1 Centr + 1SC New Vam
174 1 13 12.38 141.22 3706.78 80677 1.4 8.535 1 Centr + 1SC New Vam
173 1 14 13.34 154.56 3693.44 82631 1.6 8.535 1 Centr + 1SC New Vam
172 1 15 13.11 167.67 3680.33 84550 1.7 8.535 1 Centr + 1SC New Vam
171 1 16 11.95 179.62 3668.38 86300 1.8 8.535 1 Centr + 1SC New Vam
170 1 17 13.35 192.97 3655.03 88255 1.9 8.535 1 Centr + 1SC New Vam
169 1 18 13.32 206.29 3641.71 90205 2.1 8.535 1 Centr + 1SC New Vam
168 1 19 11.03 217.32 3630.68 91820 2.2 8.535 1 Centr + 1SC New Vam
167 1 20 11.84 229.16 3618.84 93554 2.3 8.535 1 Centr + 1SC New Vam
166 1 21 11.23 240.39 3607.61 95198 2.4 8.535 1 Centr + 1SC New Vam
165 1 22 13.37 253.76 3594.24 97155 2.5 8.535 1 Centr + 1SC New Vam
164 1 23 12.84 266.60 3581.40 99035 2.7 8.535 1 Centr + 1SC New Vam
163 1 24 13.35 279.95 3568.05 100990 2.8 8.535 1 Centr + 1SC New Vam
162 1 25 13.52 293.47 3554.53 102970 2.9 8.535 1 Centr + 1SC New Vam
161 1 26 11.14 304.61 3543.39 104601 3.1 8.535 1 Centr + 1SC New Vam
160 1 27 13.15 317.76 3530.24 106526 3.2 8.535 1 Centr + 1SC New Vam
159 1 28 12.80 330.56 3517.44 108400 3.3 8.535 1 Centr + 1SC New Vam
158 1 29 12.40 342.96 3505.04 110216 3.4 8.535 1 Centr + 1SC New Vam
157 1 30 11.98 354.94 3493.06 111970 3.6 8.535 1 Centr + 1SC New Vam
156 1 31 12.44 367.38 3480.62 113792 3.7 8.535 1 Centr + 1SC New Vam
155 1 32 11.98 379.36 3468.64 115546 3.8 8.535 1 Centr + 1SC New Vam
154 1 33 13.48 392.84 3455.16 117519 3.9 8.535 1 Centr + 1SC New Vam
153 1 34 13.49 406.33 3441.67 119495 4.1 8.535 1 Centr + 1SC New Vam
152 1 35 11.17 417.50 3430.50 121130 4.2 8.535 1 Centr + 1SC New Vam
151 1 36 13.56 431.06 3416.94 123116 4.3 8.535 1 Centr + 1SC New Vam
150 1 37 13.39 444.45 3403.55 125076 4.5 8.535 1 Centr + 1SC New Vam
149 1 38 11.84 456.29 3391.71 126810 4.6 8.535 1 Centr + 1SC New Vam
148 1 39 11.97 468.26 3379.74 128562 4.7 8.535 1 Centr + 1SC New Vam
147 1 40 13.73 481.99 3366.01 130573 4.8 8.535 1 Centr + 1SC New Vam
146 1 41 13.40 495.39 3352.61 132535 5.0 8.535 1 Centr + 1SC New Vam
145 1 42 13.17 508.56 3339.44 134463 5.1 8.535 1 Centr + 1SC New Vam
144 1 43 13.49 522.05 3325.95 136438 5.2 8.535 1 Centr + 1SC New Vam
143 1 44 13.37 535.42 3312.58 138396 5.4 8.535 1 Centr + 1SC New Vam
142 1 45 13.32 548.74 3299.26 140346 5.5 8.535 1 Centr + 1SC New Vam
141 1 46 13.48 562.22 3285.78 142320 5.6 8.535 1 Centr + 1SC New Vam
140 1 47 13.45 575.67 3272.33 144289 5.8 8.535 1 Centr + 1SC New Vam
139 1 48 13.36 589.03 3258.97 146246 5.9 8.535 1 Centr + 1SC New Vam
138 1 49 12.19 601.22 3246.78 148030 6.0 8.535 1 Centr + 1SC New Vam
137 1 50 13.30 614.52 3233.48 149978 6.2 8.535 1 Centr + 1SC New Vam
136 1 51 12.82 627.34 3220.66 151855 6.3 8.535 1 Centr + 1SC New Vam
135 1 52 13.09 640.43 3207.57 153772 6.4 8.535 1 Centr + 1SC New Vam
134 1 53 13.36 653.79 3194.21 155728 6.6 8.535 1 Centr + 1SC New Vam
133 1 54 13.30 667.09 3180.91 157675 6.7 8.535 New Vam
132 1 55 11.14 678.23 3169.77 159306 6.8 8.535 New Vam
131 1 56 13.58 691.81 3156.19 161295 6.9 8.535 New Vam
Report N° 30
CASING / TUBING STRING K/06-GT4
E & P Nederland B.V. 11/11/2001
Casing Ø : 9"5/8 inch Mud weight : 1.30 SG
Shoe at : 3848.00 m Hook weight : 60000 Lbs
Casing / Tubing Centralizer / Others Ordered
Type Grade Weight OD ID Ext Vol Steel Vol Type Supplier Model Length
(Lbs/Ft) (inch) (inch) (l/m) (l/m) (m)
1 P110 53.50 9.625 8.535 46.94 10.030 1 Weatherford STA 3 3,821.00
2 2 Stick-Up
3 3 (m)
4 4 -27.00
Joint n° Type Order Joint Cumul. Distance to Cementing
Hook load Mud gain Component type Drift diam Threads Remarks
/ n° n° length length RKB Equipment
Name (m) (m) (m) (Lbs) (m3)
130 1 57 13.28 705.09 3142.91 163239 7.1 8.535 New Vam
129 1 58 12.87 717.96 3130.04 165123 7.2 8.535 New Vam
128 1 59 11.70 729.66 3118.34 166837 7.3 8.535 New Vam
127 1 60 11.13 740.79 3107.21 168466 7.4 8.535 New Vam
126 1 61 12.25 753.04 3094.96 170260 7.6 8.535 New Vam
125 1 62 12.13 765.17 3082.83 172036 7.7 8.535 New Vam
124 1 63 13.28 778.45 3069.55 173980 7.8 8.535 New Vam
123 1 64 13.33 791.78 3056.22 175932 7.9 8.535 New Vam
122 1 65 10.84 802.62 3045.38 177519 8.1 8.535 New Vam
121 1 66 13.28 815.90 3032.10 179464 8.2 8.535 New Vam
120 1 67 13.30 829.20 3018.80 181411 8.3 8.535 New Vam
119 1 68 12.97 842.17 3005.83 183310 8.4 8.535 New Vam
118 1 69 13.29 855.46 2992.54 185256 8.6 8.535 New Vam
117 1 70 13.39 868.85 2979.15 187217 8.7 8.535 New Vam
116 1 71 13.59 882.44 2965.56 189207 8.9 8.535 New Vam
115 1 72 13.37 895.81 2952.19 191164 9.0 8.535 New Vam
114 1 73 13.40 909.21 2938.79 193126 9.1 8.535 New Vam
113 1 74 13.30 922.51 2925.49 195074 9.3 8.535 New Vam
112 1 75 12.62 935.13 2912.87 196921 9.4 8.535 New Vam
111 1 76 13.04 948.17 2899.83 198831 9.5 8.535 New Vam
110 1 77 13.16 961.33 2886.67 200758 9.6 8.535 New Vam
109 1 78 13.22 974.55 2873.45 202693 9.8 8.535 New Vam
108 1 79 13.32 987.87 2860.13 204644 9.9 8.535 New Vam
107 1 80 13.28 1001.15 2846.85 206588 10.0 8.535 New Vam
106 1 81 13.08 1014.23 2833.77 208503 10.2 8.535 New Vam
105 1 82 12.71 1026.94 2821.06 210364 10.3 8.535 New Vam
104 1 83 12.78 1039.72 2808.28 212235 10.4 8.535 New Vam
103 1 84 13.27 1052.99 2795.01 214178 10.6 8.535 New Vam
102 1 85 13.37 1066.36 2781.64 216136 10.7 8.535 New Vam
101 1 86 13.37 1079.73 2768.27 218094 10.8 8.535 New Vam
100 1 87 13.25 1092.98 2755.02 220034 11.0 8.535 New Vam
99 1 88 13.43 1106.41 2741.59 222000 11.1 8.535 New Vam
98 1 89 13.37 1119.78 2728.22 223958 11.2 8.535 New Vam
97 1 90 13.36 1133.14 2714.86 225914 11.4 8.535 New Vam
96 1 91 13.36 1146.50 2701.50 227870 11.5 8.535 New Vam
95 1 92 13.25 1159.75 2688.25 229810 11.6 8.535 New Vam
94 1 93 13.27 1173.02 2674.98 231753 11.8 8.535 New Vam
93 1 94 13.08 1186.10 2661.90 233668 11.9 8.535 New Vam
92 1 95 13.37 1199.47 2648.53 235626 12.0 8.535 New Vam
91 1 96 13.37 1212.84 2635.16 237584 12.2 8.535 New Vam
90 1 97 13.41 1226.25 2621.75 239547 12.3 8.535 New Vam
89 1 98 12.99 1239.24 2608.76 241449 12.4 8.535 New Vam
88 1 99 13.21 1252.45 2595.55 243383 12.6 8.535 New Vam
87 1 100 13.40 1265.85 2582.15 245345 12.7 8.535 New Vam
86 1 101 12.72 1278.57 2569.43 247208 12.8 8.535 New Vam
85 1 102 13.38 1291.95 2556.05 249167 13.0 8.535 New Vam
84 1 103 13.32 1305.27 2542.73 251117 13.1 8.535 New Vam
83 1 104 13.27 1318.54 2529.46 253060 13.2 8.535 New Vam
82 1 105 12.75 1331.29 2516.71 254927 13.4 8.535 New Vam
81 1 106 11.63 1342.92 2505.08 256630 13.5 8.535 New Vam
80 1 107 12.74 1355.66 2492.34 258495 13.6 8.535 New Vam
79 1 108 13.63 1369.29 2478.71 260491 13.7 8.535 New Vam
78 1 109 12.03 1381.32 2466.68 262252 13.9 8.535 New Vam
77 1 110 12.76 1394.08 2453.92 264121 14.0 8.535 New Vam
76 1 111 12.84 1406.92 2441.08 266001 14.1 8.535 New Vam
75 1 112 13.18 1420.10 2427.90 267930 14.2 8.535 New Vam
Report N° 30
CASING / TUBING STRING K/06-GT4
E & P Nederland B.V. 11/11/2001
Casing Ø : 9"5/8 inch Mud weight : 1.30 SG
Shoe at : 3848.00 m Hook weight : 60000 Lbs
Casing / Tubing Centralizer / Others Ordered
Type Grade Weight OD ID Ext Vol Steel Vol Type Supplier Model Length
(Lbs/Ft) (inch) (inch) (l/m) (l/m) (m)
1 P110 53.50 9.625 8.535 46.94 10.030 1 Weatherford STA 3 3,821.00
2 2 Stick-Up
3 3 (m)
4 4 -27.00
Joint n° Type Order Joint Cumul. Distance to Cementing
Hook load Mud gain Component type Drift diam Threads Remarks
/ n° n° length length RKB Equipment
Name (m) (m) (m) (Lbs) (m3)
74 1 113 13.16 1433.26 2414.74 269857 14.4 8.535 New Vam
73 1 114 13.33 1446.59 2401.41 271809 14.5 8.535 New Vam
72 1 115 13.34 1459.93 2388.07 273762 14.6 8.535 New Vam
71 1 116 10.71 1470.64 2377.36 275331 14.8 8.535 New Vam
70 1 117 13.41 1484.05 2363.95 277294 14.9 8.535 New Vam
69 1 118 11.15 1495.20 2352.80 278927 15.0 8.535 New Vam
68 1 119 12.26 1507.46 2340.54 280722 15.1 8.535 New Vam
67 1 120 13.33 1520.79 2327.21 282673 15.3 8.535 New Vam
66 1 121 13.20 1533.99 2314.01 284606 15.4 8.535 New Vam
65 1 122 13.30 1547.29 2300.71 286554 15.5 8.535 New Vam
64 1 123 13.34 1560.63 2287.37 288507 15.7 8.535 New Vam
63 1 124 13.23 1573.86 2274.14 290444 15.8 8.535 New Vam
62 1 125 13.35 1587.21 2260.79 292399 15.9 8.535 New Vam
61 1 126 13.30 1600.51 2247.49 294346 16.1 8.535 New Vam
60 1 127 12.91 1613.42 2234.58 296236 16.2 8.535 New Vam
59 1 128 11.16 1624.58 2223.42 297870 16.3 8.535 New Vam
58 1 129 12.31 1636.89 2211.11 299673 16.4 8.535 New Vam
57 1 130 13.38 1650.27 2197.73 301632 16.6 8.535 New Vam
56 1 131 13.29 1663.56 2184.44 303578 16.7 8.535 New Vam
55 1 132 12.91 1676.47 2171.53 305468 16.8 8.535 New Vam
54 1 133 13.11 1689.58 2158.42 307388 16.9 8.535 New Vam
53 1 134 13.44 1703.02 2144.98 309356 17.1 8.535 New Vam
52 1 135 13.36 1716.38 2131.62 311312 17.2 8.535 New Vam
51 1 136 13.53 1729.91 2118.09 313293 17.4 8.535 New Vam
50 1 137 10.61 1740.52 2107.48 314846 17.5 8.535 New Vam
49 1 138 13.24 1753.76 2094.24 316785 17.6 8.535 New Vam
48 1 139 13.43 1767.19 2080.81 318751 17.7 8.535 New Vam
47 1 140 13.18 1780.37 2067.63 320681 17.9 8.535 New Vam
46 1 141 12.84 1793.21 2054.79 322561 18.0 8.535 New Vam
45 1 142 13.57 1806.78 2041.22 324548 18.1 8.535 New Vam
44 1 143 13.19 1819.97 2028.03 326479 18.3 8.535 New Vam
43 1 144 13.28 1833.25 2014.75 328424 18.4 8.535 New Vam
42 1 145 13.34 1846.59 2001.41 330377 18.5 8.535 New Vam
41 1 146 13.33 1859.92 1988.08 332329 18.7 8.535 New Vam
40 1 147 12.79 1872.71 1975.29 334201 18.8 8.535 New Vam
39 1 148 13.17 1885.88 1962.12 336130 18.9 8.535 New Vam
38 1 149 13.12 1899.00 1949.00 338051 19.0 8.535 New Vam
37 1 150 11.62 1910.62 1937.38 339752 19.2 8.535 New Vam
36 1 151 12.19 1922.81 1925.19 341537 19.3 8.535 New Vam
35 1 152 13.61 1936.42 1911.58 343530 19.4 8.535 New Vam
34 1 153 12.35 1948.77 1899.23 345338 19.5 8.535 New Vam
33 1 154 12.65 1961.42 1886.58 347190 19.7 8.535 New Vam
32 1 155 12.39 1973.81 1874.19 349005 19.8 8.535 New Vam
31 1 156 13.47 1987.28 1860.72 350977 19.9 8.535 New Vam
30 1 157 13.42 2000.70 1847.30 352942 20.1 8.535 New Vam
29 1 158 13.50 2014.20 1833.80 354918 20.2 8.535 New Vam
28 1 159 13.30 2027.50 1820.50 356866 20.3 8.535 New Vam
27 1 160 13.17 2040.67 1807.33 358794 20.5 8.535 New Vam
26 1 161 11.87 2052.54 1795.46 360532 20.6 8.535 New Vam
25 1 162 11.03 2063.57 1784.43 362147 20.7 8.535 New Vam
24 1 163 11.83 2075.40 1772.60 363879 20.8 8.535 New Vam
23 1 164 13.32 2088.72 1759.28 365830 20.9 8.535 New Vam
22 1 165 13.44 2102.16 1745.84 367797 21.1 8.535 New Vam
21 1 166 13.27 2115.43 1732.57 369740 21.2 8.535 New Vam
20 1 167 12.23 2127.66 1720.34 371531 21.3 8.535 New Vam
19 1 168 13.03 2140.69 1707.31 373439 21.5 8.535 New Vam
Report N° 30
CASING / TUBING STRING K/06-GT4
E & P Nederland B.V. 11/11/2001
Casing Ø : 9"5/8 inch Mud weight : 1.30 SG
Shoe at : 3848.00 m Hook weight : 60000 Lbs
Casing / Tubing Centralizer / Others Ordered
Type Grade Weight OD ID Ext Vol Steel Vol Type Supplier Model Length
(Lbs/Ft) (inch) (inch) (l/m) (l/m) (m)
1 P110 53.50 9.625 8.535 46.94 10.030 1 Weatherford STA 3 3,821.00
2 2 Stick-Up
3 3 (m)
4 4 -27.00
Joint n° Type Order Joint Cumul. Distance to Cementing
Hook load Mud gain Component type Drift diam Threads Remarks
/ n° n° length length RKB Equipment
Name (m) (m) (m) (Lbs) (m3)
18 1 169 11.87 2152.56 1695.44 375177 21.6 8.535 New Vam
17 1 170 12.25 2164.81 1683.19 376971 21.7 8.535 New Vam
16 1 171 13.33 2178.14 1669.86 378922 21.8 8.535 New Vam
15 1 172 11.95 2190.09 1657.91 380672 22.0 8.535 New Vam
14 1 173 11.73 2201.82 1646.18 382390 22.1 8.535 New Vam
13 1 174 11.62 2213.44 1634.56 384091 22.2 8.535 New Vam
12 1 175 13.44 2226.88 1621.12 386059 22.3 8.535 New Vam
11 1 176 13.30 2240.18 1607.82 388006 22.5 8.535 New Vam
10 1 177 13.14 2253.32 1594.68 389930 22.6 8.535 New Vam
9 1 178 13.30 2266.62 1581.38 391878 22.7 8.535 New Vam
8 1 179 13.47 2280.09 1567.91 393850 22.9 8.535 New Vam
7 1 180 12.98 2293.07 1554.93 395750 23.0 8.535 New Vam
6 1 181 12.93 2306.00 1542.00 397644 23.1 8.535 New Vam
5 1 182 12.89 2318.89 1529.11 399531 23.3 8.535 New Vam
4 1 183 13.26 2332.15 1515.85 401473 23.4 8.535 New Vam
3 1 184 13.18 2345.33 1502.67 403402 23.5 8.535 New Vam
2 1 185 13.15 2358.48 1489.52 405328 23.7 8.535 New Vam
1 1 186 13.38 2371.86 1476.14 407287 23.8 8.535 New Vam
327 1 187 13.04 2384.90 1463.10 409196 23.9 8.535 New Vam
326 1 188 13.37 2398.27 1449.73 411154 24.1 8.535 New Vam
325 1 189 13.37 2411.64 1436.36 413111 24.2 8.535 New Vam
324 1 190 13.15 2424.79 1423.21 415037 24.3 8.535 New Vam
323 1 191 13.44 2438.23 1409.77 417005 24.5 8.535 New Vam
322 1 192 13.32 2451.55 1396.45 418955 24.6 8.535 New Vam
321 1 193 13.21 2464.76 1383.24 420889 24.7 8.535 New Vam
320 1 194 12.85 2477.61 1370.39 422771 24.8 8.535 New Vam
319 1 195 13.34 2490.95 1357.05 424724 25.0 8.535 New Vam
318 1 196 13.19 2504.14 1343.86 426655 25.1 8.535 New Vam
317 1 197 13.26 2517.40 1330.60 428597 25.2 8.535 New Vam
316 1 198 13.30 2530.70 1317.30 430544 25.4 8.535 New Vam
315 1 199 13.33 2544.03 1303.97 432496 25.5 8.535 New Vam
314 1 200 13.41 2557.44 1290.56 434459 25.7 8.535 New Vam
313 1 201 13.48 2570.92 1277.08 436433 25.8 8.535 New Vam
312 1 202 13.37 2584.29 1263.71 438391 25.9 8.535 New Vam
311 1 203 13.27 2597.56 1250.44 440334 26.1 8.535 New Vam
310 1 204 13.31 2610.87 1237.13 442283 26.2 8.535 New Vam
309 1 205 13.22 2624.09 1223.91 444218 26.3 8.535 New Vam
308 1 206 13.35 2637.44 1210.56 446173 26.5 8.535 New Vam
307 1 207 11.14 2648.58 1199.42 447804 26.6 8.535 New Vam
306 1 208 10.52 2659.10 1188.90 449344 26.7 8.535 New Vam
305 1 209 13.24 2672.34 1175.66 451283 26.8 8.535 New Vam
304 1 210 12.75 2685.09 1162.91 453150 26.9 8.535 New Vam
303 1 211 12.94 2698.03 1149.97 455045 27.1 8.535 New Vam
302 1 212 10.41 2708.44 1139.56 456569 27.2 8.535 New Vam
301 1 213 13.16 2721.60 1126.40 458496 27.3 8.535 New Vam
300 1 214 13.18 2734.78 1113.22 460425 27.4 8.535 New Vam
299 1 215 13.35 2748.13 1099.87 462380 27.6 8.535 New Vam
298 1 216 10.73 2758.86 1089.14 463951 27.7 8.535 New Vam
297 1 217 13.14 2772.00 1076.00 465875 27.8 8.535 New Vam
296 1 218 13.07 2785.07 1062.93 467789 27.9 8.535 New Vam
295 1 219 13.22 2798.29 1049.71 469725 28.1 8.535 New Vam
294 1 220 13.22 2811.51 1036.49 471660 28.2 8.535 New Vam
293 1 221 12.55 2824.06 1023.94 473498 28.3 8.535 New Vam
292 1 222 12.74 2836.80 1011.20 475363 28.5 8.535 New Vam
291 1 223 13.15 2849.95 998.05 477289 28.6 8.535 New Vam
290 1 224 13.34 2863.29 984.71 479242 28.7 8.535 New Vam
Report N° 30
CASING / TUBING STRING K/06-GT4
E & P Nederland B.V. 11/11/2001
Casing Ø : 9"5/8 inch Mud weight : 1.30 SG
Shoe at : 3848.00 m Hook weight : 60000 Lbs
Casing / Tubing Centralizer / Others Ordered
Type Grade Weight OD ID Ext Vol Steel Vol Type Supplier Model Length
(Lbs/Ft) (inch) (inch) (l/m) (l/m) (m)
1 P110 53.50 9.625 8.535 46.94 10.030 1 Weatherford STA 3 3,821.00
2 2 Stick-Up
3 3 (m)
4 4 -27.00
Joint n° Type Order Joint Cumul. Distance to Cementing
Hook load Mud gain Component type Drift diam Threads Remarks
/ n° n° length length RKB Equipment
Name (m) (m) (m) (Lbs) (m3)
289 1 225 13.29 2876.58 971.42 481188 28.9 8.535 New Vam
288 1 226 13.18 2889.76 958.24 483118 29.0 8.535 New Vam
287 1 227 13.27 2903.03 944.97 485061 29.1 8.535 New Vam
286 1 228 13.16 2916.19 931.81 486987 29.2 8.535 New Vam
285 1 229 13.33 2929.52 918.48 488939 29.4 8.535 New Vam
284 1 230 13.28 2942.80 905.20 490884 29.5 8.535 New Vam
283 1 231 13.32 2956.12 891.88 492834 29.6 8.535 New Vam
282 1 232 13.51 2969.63 878.37 494812 29.8 8.535 New Vam
281 1 233 13.31 2982.94 865.06 496761 29.9 8.535 New Vam
280 1 234 13.19 2996.13 851.87 498692 30.1 8.535 New Vam
279 1 235 13.19 3009.32 838.68 500623 30.2 8.535 New Vam
278 1 236 12.77 3022.09 825.91 502493 30.3 8.535 New Vam
277 1 237 13.28 3035.37 812.63 504438 30.4 8.535 New Vam
276 1 238 13.32 3048.69 799.31 506388 30.6 8.535 New Vam
275 1 239 13.25 3061.94 786.06 508328 30.7 8.535 New Vam
274 1 240 12.58 3074.52 773.48 510170 30.8 8.535 New Vam
273 1 241 13.26 3087.78 760.22 512112 31.0 8.535 New Vam
272 1 242 13.28 3101.06 746.94 514056 31.1 8.535 New Vam
271 1 243 13.38 3114.44 733.56 516015 31.2 8.535 New Vam
270 1 244 13.12 3127.56 720.44 517936 31.4 8.535 New Vam
269 1 245 13.29 3140.85 707.15 519882 31.5 8.535 New Vam
268 1 246 13.39 3154.24 693.76 521843 31.6 8.535 New Vam
267 1 247 13.25 3167.49 680.51 523783 31.8 8.535 New Vam
266 1 248 13.27 3180.76 667.24 525726 31.9 8.535 New Vam
265 1 249 13.44 3194.20 653.80 527694 32.0 8.535 New Vam
264 1 250 11.25 3205.45 642.55 529341 32.2 8.535 New Vam
263 1 251 13.35 3218.80 629.20 531295 32.3 8.535 New Vam
262 1 252 13.11 3231.91 616.09 533215 32.4 8.535 New Vam
261 1 253 12.99 3244.90 603.10 535117 32.5 8.535 New Vam
260 1 254 13.28 3258.18 589.82 537061 32.7 8.535 New Vam
259 1 255 13.00 3271.18 576.82 538965 32.8 8.535 New Vam
258 1 256 13.25 3284.43 563.57 540905 32.9 8.535 New Vam
257 1 257 13.59 3298.02 549.98 542895 33.1 8.535 New Vam
256 1 258 12.95 3310.97 537.03 544791 33.2 8.535 New Vam
255 1 259 12.26 3323.23 524.77 546586 33.3 8.535 New Vam
254 1 260 12.34 3335.57 512.43 548393 33.5 8.535 New Vam
253 1 261 12.65 3348.22 499.78 550245 33.6 8.535 New Vam
252 1 262 13.26 3361.48 486.52 552187 33.7 8.535 New Vam
251 1 263 12.21 3373.69 474.31 553974 33.8 8.535 New Vam
250 1 264 13.11 3386.80 461.20 555894 34.0 8.535 New Vam
249 1 265 13.48 3400.28 447.72 557868 34.1 8.535 New Vam
248 1 266 13.27 3413.55 434.45 559811 34.2 8.535 New Vam
247 1 267 13.23 3426.78 421.22 561748 34.4 8.535 New Vam
246 1 268 13.28 3440.06 407.94 563692 34.5 8.535 New Vam
245 1 269 13.21 3453.27 394.73 565626 34.6 8.535 New Vam
244 1 270 13.18 3466.45 381.55 567556 34.8 8.535 New Vam
243 1 271 13.21 3479.66 368.34 569490 34.9 8.535 New Vam
242 1 272 13.45 3493.11 354.89 571460 35.0 8.535 New Vam
241 1 273 13.39 3506.50 341.50 573420 35.2 8.535 New Vam
240 1 274 12.15 3518.65 329.35 575199 35.3 8.535 New Vam
239 1 275 12.76 3531.41 316.59 577068 35.4 8.535 New Vam
238 1 276 13.40 3544.81 303.19 579030 35.6 8.535 New Vam
237 1 277 13.55 3558.36 289.64 581014 35.7 8.535 New Vam
236 1 278 13.46 3571.82 276.18 582985 35.8 8.535 New Vam
235 1 279 13.27 3585.09 262.91 584928 36.0 8.535 New Vam
234 1 280 13.42 3598.51 249.49 586892 36.1 8.535 New Vam
Report N° 30
CASING / TUBING STRING K/06-GT4
E & P Nederland B.V. 11/11/2001
Casing Ø : 9"5/8 inch Mud weight : 1.30 SG
Shoe at : 3848.00 m Hook weight : 60000 Lbs
Casing / Tubing Centralizer / Others Ordered
Type Grade Weight OD ID Ext Vol Steel Vol Type Supplier Model Length
(Lbs/Ft) (inch) (inch) (l/m) (l/m) (m)
1 P110 53.50 9.625 8.535 46.94 10.030 1 Weatherford STA 3 3,821.00
2 2 Stick-Up
3 3 (m)
4 4 -27.00
Joint n° Type Order Joint Cumul. Distance to Cementing
Hook load Mud gain Component type Drift diam Threads Remarks
/ n° n° length length RKB Equipment
Name (m) (m) (m) (Lbs) (m3)
233 1 281 13.32 3611.83 236.17 588843 36.2 8.535 New Vam
232 1 282 13.10 3624.93 223.07 590761 36.4 8.535 New Vam
231 1 283 13.21 3638.14 209.86 592695 36.5 8.535 New Vam
230 1 284 13.11 3651.25 196.75 594615 36.6 8.535 New Vam
229 1 285 13.17 3664.42 183.58 596543 36.8 8.535 New Vam
228 1 286 13.44 3677.86 170.14 598511 36.9 8.535 New Vam
227 1 287 13.47 3691.33 156.67 600483 37.0 8.535 New Vam
226 1 288 13.40 3704.73 143.27 602445 37.2 8.535 New Vam
225 1 289 13.27 3718.00 130.00 604388 37.3 8.535 New Vam
224 1 290 13.26 3731.26 116.74 606330 37.4 8.535 New Vam
223 1 291 13.08 3744.34 103.66 608245 37.6 8.535 New Vam
222 1 292 12.82 3757.16 90.84 610122 37.7 8.535 New Vam
221 1 293 13.47 3770.63 77.37 612094 37.8 8.535 New Vam
220 1 294 13.31 3783.94 64.06 614043 38.0 8.535 New Vam
219 1 295 12.78 3796.72 51.28 615914 38.1 8.535 New Vam
218 1 296 13.52 3810.24 37.76 617894 38.2 8.535 New Vam
217 1 297 10.76 3821.00 27.00 619469 38.3 Cut 8.535 New Vam cut
Report N° 38
CASING RUN K/06-GT4
E & P Nederland B.V. 19/11/2001

Function Type Operation date OD Length Weight Grade Connection


in m lbs/ft
Surface / CP Casing
From 19/11/2001 17:30 7" 949.07 35 P110 New Vam
Technical Liner To 7"5/8 147.93 59.2 P110 Vam FJL
Production Tie Back

Start run.csg at 19-11-2001 19:00 Start circ.on bottom 0-1-1900 8:30 End of displacement 0-1-1900 17:00

Shoe F. Collar L.Collar DV collar Top Hanger


mMD 4790 4748 4734 3698.00 mMD

mTVD 3385 3347 3335 2693.00 mTVD

Drift diam (min.) 5.878 in Weight of casing 61.8 T in air 48.8 T in mud

inch mMD mTVD N° Axis Deviation

Previous casing 9"5/8 3848.00 2776.50 1 KOP at 187.00 m


WELL CONDITION

Drilling Phase 8½ 4791.00 Incl. MD


D1= 55.27 ° at 3700
D2= 53.54 ° at 4394
D3= 27.4 ° at 4791

Wiper trips 1 Caliper log


Open hole conditions (volume, washed out zone, tight spot, losses, gains...)
Back reaming during wiper trip - No significant overpull observed - Tight spots during POOH (after wiper trip) fr/to 4678/4575m ,4398/4402m
4198/4186m : 40t overpull.

Thread compound used Malleus STC 1


Average torque to make up joints 7''=1620m.kg-7"5/8=3140m.kg LINER EQUIPMENT
Test connection Type / size Length
Filling frequency Every joint 5½ DP 3691.00
Running speed 2min/jt in open hole Running string
Centralizers Manufacturer Weatherford Drift 2"3/4
RUNNING CASING

Nb and type 56 x STT-ISC 7" Running tool 7"type R 2.45


Liner Packer TSP 1.35
CIRCULATIONS AND DRAG FORCES PBR 7", 15# 4.56
Depth Time Flow rate P M.D M.D Liner hanger 7''x9''5/8 rotating 1.33
m h l/mn bars T T Hydraulic Mechanical
3862.00 15:30 800 55 130 95 Plug type Single Wiper plug MK2 + DP dart
4035.00 03:00 400 48 139 93 Pack off bushing type 7" RMS
4241.00 04:00 400 51 155 107 Comments
4444.00 06:00 485 52 159 100
4791.00 TD 08:00 500 55 168 110

Observations or trouble while running Pipe movement Reciprocating Rotating


Found obstruction at 3915m : Hole restriction? - Ream tight spot to 3919m with 520l/min 53b ,60rpm 1500/2400m.kg ,WOB 14t - String struck after
connection at 3919m - Free string with 50t overpull - Ream down 7'' liner to 3979m with WOB 14t ,450l/min 52b ,60rpm ,1850m.kg - Wash down 7" liner
to 4035m with 400l/min 48b - RIH 7" liner to bottom 4791m without any problem.
WELLHEAD

M.D. indications at the end of displacement T after setting of the cement T

Setting tension on spool T h after the end of displacement


Suspension and spool type
Additionnal seal (Type, dimensions)
Dist. between the upper part of the spool and RKB m Cut casing above spool cm

Cementing Log type after h setting Annular pressure bars


Results Top Cement annulus m
EVALUATION

Pressure test casing to bars Test packer depth m


Test top liner Over pressure Drawdown to bars
Comments / Results
Report N° 38
CEMENTING K/06-GT4
E & P Nederland B.V. 19/11/2001
Casing to Cement 7" inch Cement Job type Primary single stage
Casing shoe 4790.00 mMD 3385.00 mVD Mud type OBM SG 1.65 BHST 113 °C
Drilling Size 8½ inch LOT / FIT 2.07 EMW at 2776.00 mVD BHCT 90 °C
TD 4791.00 mMD 3385.85 mVD Pore press. EMW at mVD API schedule
Prev casing 9"5/8 inch 53.5 lbs/ft Format. frac EMW at mVD -Pressure bars
Prev csg shoe 3848.00 mMD 2776.00 mVD -Temperature °C

Laboratory fluids design


Products and additives Unit SPACERS SLURRIES Characteristics SLURRIES
n°1 n°2 n°1 n°2 n°1 n°2
Base oil liters 1000 Specific gravity ppg 15.8
Hyflo-4 liters 4 Thickening Time : 40BC 6:03
Freshwater liters 747 Thickening Time: 70BC 6:08
Spacer 500E+ powder kg 18.5 Thickening Time: 100BC 6:15
Barite kg 1033 Free Water % : vertical
Musol liters 15 Free Water % : 45° 0.1
Pen-5M liters 5 Fluid loss ml N/A
HMR Cement kg 1000 Yield 0.812m3/t
Fresh water liters 422
Defoamer NF-6 liters 1 Compress Strength 12h
Salt 30% BWOW kg 127 24h
CFR-3 kg 7.8
HR-4 kg 4.7

Final volume or Yield 1.004 1000 0.812m3/t


Rheologies (laboratory / on site)
FLUIDS T° SG F300 F200 F100 F60 F30 F6 F3 G0 G10 PV YV n K
Mud
Spacer1
Spacer2
Slurry 1 20°C 1.9 62 45 26 16 10 4 3 57 7 0.79 0.45
Slurry 2

Mud 50°C 1.66 38 28 19 16 13 9 8 13 19 27 10 0.56 1.16


Spacer1 20°C 1.8 63 51 31 22 16 8 7 9 60 11 0.72 0.72
Spacer2 50°c 1.8 51 41 29 24 19 13 11 13 36 17 0.50 2.27
Slurry 1 20°c 1.87 165 113 58 36 19 6 4 6 165 3 0.96 0.41
Slurry 2

Products used and cost Operation summary


Products Unit SPACERS SLURRIES Unit Cost Operation Volume Flow Press Time
n°1 n°2 n°1 n°2 price break down m3 L/mn bars mn
Base oil m3 5 577.0 2885.0 Circulation 74 550 52 150
Hyflo-4 liters 20 11.6 232.0 Batch mixing
Spacer 500 kg 182 17.5 3185.0 Pre-flush: base oil 4.77 800 81 10
Barite t 6 122.5 735.0 Spacer: 500E 6.4 700 100 10
Musol liters 135 4.1 553.5 Slurry 17 750 107 25
Pen-5 liters 45 7.7 346.5 Displacement OBM 16 850 101 20
HMR Cmt t 21 226.9 4764.9 Displacement OBM 32 810 87 20
NF-6 liters 20 25.9 518.0 Displacement OBM 40 450 26 20
NaCl t 2.5 132.0 330.0 Displacement OBM 59.5 400 73 50
CFR-3 kg 159 19.3 3068.7
HR-4 kg 114 6.4 729.6 Total displac. 60.1
Pressure test 150
Slurries volumes excess (%)
Caliper OR Theoretical
Total cost 3117.0 4820.0 9411.2 17348.2 slurry 1 20%
Fabrication Halliburton slurry 2
Silos Noble Hoope
Material used Displacement Halliburton Results Plan. Actual
on site Pits Noble Hoope (Mud0 + Halliburton (Batch mixer) Top slurry 1 3697.00 3697.00 mMD
Top slurry 2 mMD
internal top 4733.00 4733.00 mMD

Comments Leakage on Halliburton high pressure lines - Lost time : 01:00 - No losses while cementing.

Rig Noble Hoope


Cement Contract Halliburton
Report N° 36
CASING / TUBING STRING K/06-GT4
E & P Nederland B.V. 17/11/2001
Casing Ø : 7 inch Mud weight : 1.65 SG
Shoe at : 4790.00 m Hook weight : 60000 Lbs
Casing / Tubing Centralizer / Others Ordered
Type Grade Weight OD ID Ext Vol Steel Vol Type Supplier Model Length
(Lbs/Ft) (inch) (inch) (l/m) (l/m) (m)
1 P110 35.00 7 6.004 24.83 6.563 1 Weatherford STT 1 SL 1,096.99
2 P110 59.50 7 5/8 6.004 29.46 11.194 2 Stick-Up
3 3 (m)
4 4 -3,693.02
Joint n° Type Order Joint Cumul. Distance to Cementing
Hook load Mud gain Component type Drift diam Threads Remarks
/ n° n° length length RKB Equipment
Name (m) (m) (m) (Lbs) (m3)
Shoe A 1 1 0.91 0.91 4789.09 60083 0.0 Reamer shoe New Vam Bakerlocked
Shoe jt 1 2 13.89 14.80 4775.20 61342 0.1 5.88 2 Cent + 2 stop New Vam Bakerlocked
BL6 1 3 13.82 28.62 4761.38 62595 0.2 5.88 2 Cent + 2 stop New Vam Bakerlocked
BL5 1 4 13.51 42.13 4747.87 63820 0.3 5.88 2 Cent + 2 stop New Vam Bakerlocked
Float A 1 5 0.54 42.67 4747.33 63869 0.3 Float collar 5.88 New Vam Bakerlocked
Float jt 1 6 13.56 56.23 4733.77 65098 0.4 5.88 2 Cent + 2 stop New Vam Bakerlocked
Land coll 1 7 0.25 56.48 4733.52 65121 0.4 Landing collar New Vam Bakerlocked
BL4 1 8 13.75 70.23 4719.77 66368 0.5 5.88 2 Cent + 2 stop New Vam Bakerlocked
73 1 9 13.75 83.98 4706.02 67614 0.6 5.88 1 Cent + 1 stop New Vam
72 1 10 12.73 96.71 4693.29 68769 0.6 5.88 1 Cent + 1 stop New Vam
71 1 11 13.77 110.48 4679.52 70017 0.7 5.88 1 Cent + 1 stop New Vam
70 1 12 13.88 124.36 4665.64 71276 0.8 5.88 1 Cent + 1 stop New Vam
69 1 13 13.32 137.68 4652.32 72483 0.9 5.88 1 Cent + 1 stop New Vam
68 1 14 13.73 151.41 4638.59 73728 1.0 5.88 1 Cent + 1 stop New Vam
67 1 15 13.50 164.91 4625.09 74952 1.1 5.88 1 Cent + 1 stop New Vam
66 1 16 13.82 178.73 4611.27 76205 1.2 5.88 1 Cent + 1 stop New Vam
65 1 17 13.18 191.91 4598.09 77400 1.3 5.88 1 Cent + 1 stop New Vam
64 1 18 13.57 205.48 4584.52 78631 1.3 5.88 1 Cent + 1 stop New Vam
63 1 19 13.80 219.28 4570.72 79882 1.4 5.88 1 Cent + 1 stop New Vam
62 1 20 12.50 231.78 4558.22 81016 1.5 5.88 1 Cent + 1 stop New Vam
61 1 21 13.67 245.45 4544.55 82255 1.6 5.88 1 Cent + 1 stop New Vam
60 1 22 13.62 259.07 4530.93 83490 1.7 5.88 1 Cent + 1 stop New Vam
59 1 23 13.66 272.73 4517.27 84728 1.8 5.88 1 Cent + 1 stop New Vam
58 1 24 13.44 286.17 4503.83 85947 1.9 5.88 1 Cent + 1 stop New Vam
57 1 25 12.65 298.82 4491.18 87094 2.0 5.88 1 Cent + 1 stop New Vam
56 1 26 13.24 312.06 4477.94 88295 2.0 5.88 1 Cent + 1 stop New Vam
55 1 27 13.48 325.54 4464.46 89517 2.1 5.88 1 Cent + 1 stop New Vam
54 1 28 13.74 339.28 4450.72 90763 2.2 5.88 1 Cent + 1 stop New Vam
53 1 29 13.56 352.84 4437.16 91992 2.3 5.88 1 Cent + 1 stop New Vam
52 1 30 12.43 365.27 4424.73 93119 2.4 5.88 1 Cent + 1 stop New Vam
51 1 31 13.30 378.57 4411.43 94325 2.5 5.88 1 Cent + 1 stop New Vam
50 1 32 12.87 391.44 4398.56 95492 2.6 5.88 1 Cent + 1 stop New Vam
49 1 33 13.43 404.87 4385.13 96710 2.7 5.88 1 Cent + 1 stop New Vam
48 1 34 12.91 417.78 4372.22 97880 2.7 5.88 1 Cent + 1 stop New Vam
47 1 35 13.74 431.52 4358.48 99126 2.8 5.88 1 Cent + 1 stop New Vam
46 1 36 13.74 445.26 4344.74 100372 2.9 5.88 1 Cent + 1 stop New Vam
45 1 37 13.03 458.29 4331.71 101553 3.0 5.88 New Vam
44 1 38 13.23 471.52 4318.48 102753 3.1 5.88 1 Cent + 1 stop New Vam
43 1 39 13.92 485.44 4304.56 104015 3.2 5.88 New Vam
42 1 40 13.82 499.26 4290.74 105268 3.3 5.88 1 Cent + 1 stop New Vam
41 1 41 13.48 512.74 4277.26 106490 3.4 5.88 New Vam
40 1 42 12.90 525.64 4264.36 107660 3.4 5.88 1 Cent + 1 stop New Vam
39 1 43 13.70 539.34 4250.66 108902 3.5 5.88 New Vam
38 1 44 13.62 552.96 4237.04 110137 3.6 5.88 1 Cent + 1 stop New Vam
37 1 45 13.42 566.38 4223.62 111354 3.7 5.88 New Vam
36 1 46 13.38 579.76 4210.24 112567 3.8 5.88 1 Cent + 1 stop New Vam
35 1 47 13.13 592.89 4197.11 113757 3.9 5.88 New Vam
34 1 48 13.29 606.18 4183.82 114962 4.0 5.88 1 Cent + 1 stop New Vam
33 1 49 13.44 619.62 4170.38 116181 4.1 5.88 New Vam
32 1 50 13.62 633.24 4156.76 117416 4.2 5.88 1 Cent + 1 stop New Vam
31 1 51 13.71 646.95 4143.05 118659 4.2 5.88 New Vam
30 1 52 13.68 660.63 4129.37 119899 4.3 5.88 1 Cent + 1 stop New Vam
29 1 53 13.80 674.43 4115.57 121151 4.4 5.88 New Vam
28 1 54 13.11 687.54 4102.46 122339 4.5 5.88 1 Cent + 1 stop New Vam
27 1 55 13.56 701.10 4088.90 123569 4.6 5.88 New Vam
XO B 1 56 4.16 705.26 4084.74 123946 4.6 7 5/8 box x 7 pin 5.88 Vam FJL
Report N° 36
CASING / TUBING STRING K/06-GT4
E & P Nederland B.V. 17/11/2001
Casing Ø : 7 inch Mud weight : 1.65 SG
Shoe at : 4790.00 m Hook weight : 60000 Lbs
Casing / Tubing Centralizer / Others Ordered
Type Grade Weight OD ID Ext Vol Steel Vol Type Supplier Model Length
(Lbs/Ft) (inch) (inch) (l/m) (l/m) (m)
1 P110 35.00 7 6.004 24.83 6.563 1 Weatherford STT 1 SL 1,096.99
2 P110 59.50 7 5/8 6.004 29.46 11.194 2 Stick-Up
3 3 (m)
4 4 -3,693.02
Joint n° Type Order Joint Cumul. Distance to Cementing
Hook load Mud gain Component type Drift diam Threads Remarks
/ n° n° length length RKB Equipment
Name (m) (m) (m) (Lbs) (m3)
509 2 57 13.99 719.25 4070.75 126102 4.8 5.88 Vam FJL
508 2 58 14.08 733.33 4056.67 128273 4.9 5.88 Vam FJL
XO A 1 59 4.57 737.90 4052.10 128687 5.0 7 box x 7 5/8 pin 5.88 New Vam
26 1 60 13.76 751.66 4038.34 129935 5.1 5.88 1 Cent + 1 stop New Vam
25 1 61 13.67 765.33 4024.67 131174 5.2 5.88 New Vam
24 1 62 13.69 779.02 4010.98 132415 5.2 5.88 1 Cent + 1 stop New Vam
23 1 63 13.59 792.61 3997.39 133648 5.3 5.88 New Vam
22 1 64 13.43 806.04 3983.96 134865 5.4 5.88 1 Cent + 1 stop New Vam
21 1 65 12.95 818.99 3971.01 136039 5.5 5.88 New Vam
20 1 66 13.63 832.62 3957.38 137275 5.6 5.88 1 Cent + 1 stop New Vam
19 1 67 12.96 845.58 3944.42 138450 5.7 5.88 New Vam
18 1 68 13.48 859.06 3930.94 139673 5.8 5.88 1 Cent + 1 stop New Vam
XO D 1 69 6.83 865.89 3924.11 140292 5.8 7 5/8 box x 7 pin 5.88 New Vam
507 2 70 13.94 879.83 3910.17 142441 6.0 5.88 Vam FJL
506 2 71 14.00 893.83 3896.17 144599 6.1 5.88 Vam FJL
505 2 72 13.80 907.63 3882.37 146726 6.3 5.88 Vam FJL
504 2 73 14.01 921.64 3868.36 148885 6.4 5.88 Vam FJL
503 2 74 14.03 935.67 3854.33 151048 6.6 5.88 Vam FJL
502 2 75 13.32 948.99 3841.01 153101 6.7 5.88 Vam FJL
501 2 76 13.96 962.95 3827.05 155253 6.9 5.88 Vam FJL
XO C 1 77 7.24 970.19 3819.81 155909 6.9 7 box x 7 5/8 pin 5.88 New Vam
17 1 78 12.68 982.87 3807.13 157059 7.0 5.88 1 Cent + 1 stop New Vam
16 1 79 13.61 996.48 3793.52 158293 7.1 5.88 New Vam
15 1 80 12.88 1009.36 3780.64 159461 7.2 5.88 1 Cent + 1 stop New Vam
14 1 81 13.78 1023.14 3766.86 160710 7.3 5.88 New Vam
13 1 82 12.10 1035.24 3754.76 161807 7.4 5.88 1 Cent + 1 stop New Vam
12 1 83 13.78 1049.02 3740.98 163057 7.5 5.88 New Vam
11 1 84 13.52 1062.54 3727.46 164282 7.6 5.88 1 Cent + 1 stop New Vam
10 1 85 12.94 1075.48 3714.52 165456 7.6 5.88 New Vam
9 1 86 13.74 1089.22 3700.78 166702 7.7 5.88 New Vam
XO 1 87 0.32 1089.54 3700.46 166731 7.7 149.3 mm New Vam
Liner hang 1 88 1.33 1090.87 3699.13 166851 7.7 LH PHR 149.5 mm
PKR 1 89 1.24 1092.11 3697.89 166964 7.7 TSP4 Pkr 7" 154.1 mm
PBR 1 90 4.88 1096.99 3693.02 167406 7.8 PBR = 15ft 190.56 mm
Report N° 58
CEMENTING K/06-GT4
E & P Nederland B.V. 09/12/2001
Casing to Cement plug inch Cement Job type Abandonment plug
Casing shoe mMD mVD Mud type LTOBM SG 1.25 BHST 126 °C
Drilling Size 5 7/8 inch LOT / FIT 2.03 EMW at mVD BHCT 110 °C
TD 5206.00 mMD 3776.00 mVD Pore press. EMW at mVD API schedule
Prev casing 7 inch 35 lbs/ft Format. frac EMW at mVD -Pressure bars
Prev csg shoe 4790.00 mMD 3384.00 mVD -Temperature °C

Laboratory fluids design


Products and additives Unit SPACERS SLURRIES Characteristics SLURRIES
n°1 n°2 n°1 n°2 n°1 n°2
Base oil litre 1000 Specific gravity ppg SG=1.85
Hyflo 4 litre 4 Thickening Time : 40BC 4h10
Water litre 391 Thickening Time: 70BC 4h18
HMR cement kg 1000 Thickening Time: 100BC 4h22
Defoamer NF6 litre 1 Free Water % : vertical 0.10%
Halad 100 Kg 3.9 Free Water % : 45°
CFR3 Kg 5.9 Fluid loss ml 86
HR4 Kg 5.1 Yield 0.796m3/t
Microblock litre 56.3
Compress Strength 12h
24h 2500psi

Final volume or Yield


Rheologies (laboratory / on site)
FLUIDS T° SG F300 F200 F100 F60 F30 F6 F3 G0 G10 PV YV n K
Mud
Spacer1
Spacer2
Slurry 1 Ambient 1.85 142 98 54 34 19 7 4 132 10 0.86 0.67
Slurry 2

Mud 50°C 1.27 42 33 24 19 16 12 11 21 37 27 15 0.46 2.40


Spacer1
Spacer2
Slurry 1 15ºC 1.85 >320 273 145 95 53 17 13 19 384 17 0.91 ######
Slurry 2

Products used and cost Operation summary


Products Unit SPACERS SLURRIES Unit Cost Operation Volume Flow Press Time
n°1 n°2 n°1 n°2 price break down m3 L/mn bars mn
Base oil M3 2.5 577.0 1442.5 Circulation 75 1200 214 60
Hyflo 4 ltr 10 11.6 116.0 Batch mixing 5.3 15
HMR cement t 8.5 235.0 1997.5 Front spacer 1.75 300 200 6
HALAD 100A kg 25 49.3 1232.5 Slurry 1.43 300 285 5
HR4 kg 45.5 6.4 291.2 Slurry 3.57 650 100 6
CFR3 kg 45.5 19.3 878.2 Displacement 42 750 100 60
Microblock ltr 385 4.6 1771.0 End of displacement 0.3 300 30 1
NF6 ltr 10 25.9 259.0

Total displac. 42.3


Pressure test n/a
Slurries volumes excess (%)
Caliper OR Theoretical
Total cost 1558.5 6429.4 7987.9 slurry 1 +20%
Fabrication Halliburton slurry 2
Silos Noble Ronald Hoope
Material used Displacement Halliburton Results Plan. Actual
on site Pits Halliburton Batch mixer 30m3 Top slurry 1 4917.00 mMD
Top slurry 2 mMD
internal top mMD

Comments Costs in Euro.


Injected 1m3 1.25sg OBM in formation while pumping cement : Close Well and Pressure up well to 285b with 300l/min (2200l) to open frac then inject
1.25sg OBM - Stop pumping - Open well and continue cement job. ( injected OBM in frac to displace CaCl2 brine in this frac )
No cement in return during circulation after cement job.
Rig NRH
Cement Contract Halliburton
Report N° 59
CEMENTING K/06-GT4
E & P Nederland B.V. 10/12/2001
Casing to Cement plug inch Cement Job type Abandonment plug
Casing shoe mMD mVD Mud type LTOBM SG 1.25 BHST 115 °C
Drilling Size 5.875 inch LOT / FIT 2.45 EMW at 4791.00 mVD BHCT 100 °C
TD 5206.00 mMD 3776.00 mVD Pore press. EMW at mVD API schedule
Prev casing 7 inch 35 lbs/ft Format. frac EMW at mVD -Pressure bars
Prev csg shoe 4790.00 mMD 3384.00 mVD -Temperature °C

Laboratory fluids design


Products and additives Unit SPACERS SLURRIES Characteristics SLURRIES
n°1 n°2 n°1 n°2 n°1 n°2
Base oil litre 1000 Specific gravity ppg SG=1.85
Hyflo 4 litre 4 Thickening Time : 40BC 4h10
Water litre 391 Thickening Time: 70BC 4h18
HMR cement kg 1000 Thickening Time: 100BC 4h22
Defoamer NF6 litre 1 Free Water % : vertical 0.001
Halad 100 Kg 3.9 Free Water % : 45°
CFR3 Kg 5.9 Fluid loss ml 86
HR4 Kg 5.1 Yield 0.796m3/t
Microblock litre 56.3
Compress Strength 12h
24h 2500psi

Final volume or Yield


Rheologies (laboratory / on site)
FLUIDS T° SG F300 F200 F100 F60 F30 F6 F3 G0 G10 PV YV n K
Mud
Spacer1
Spacer2
Slurry 1 Ambient 1.85 142 98 54 34 19 7 4 132 10 0.86 0.67
Slurry 2

Mud 50°C 1.27 42 33 24 19 16 12 11 21 37 27 15 0.46 2.40


Spacer1
Spacer2
Slurry 1 15ºC 1.85 >320 270 146 96 53 12 11 21 372 22 0.89 ######
Slurry 2

Products used and cost Operation summary


Products Unit SPACERS SLURRIES Unit Cost Operation Volume Flow Press Time
n°1 n°2 n°1 n°2 price break down m3 L/mn bars mn
Base oil M3 2.2 577.0 1269.4 Circulation 150 1350 252 60
Hyflo 4 ltr 10 11.6 116.0 Batch mixing 5 15
HMR cement t 8.5 226.9 1928.7 Front spacer=base oil 1.83 630 78 3
HALAD 100A kg 25 49.3 1232.5 Slurry 5 630 95/80 8
HR4 kg 45.5 6.4 291.2 Tail spacer=base oil 0.33 650 80 2
CFR3 kg 45.5 19.3 878.2 Displacement OBM 38.3 780 85/107 50
Microblock ltr 385 4.6 1771.0
NF6 ltr 10 25.9 259.0

Total displac. 38.63


Pressure test n/a
Slurries volumes excess (%)
Caliper OR Theoretical
Total cost 1385.4 6360.5 7745.9 slurry 1 +5%
Fabrication Halliburton slurry 2
Silos Noble Ronald Hoope
Material used Displacement Halliburton Results Plan. Actual
on site Pits Halliburton Batch mixer 30m3 , Mud pit of rig Top slurry 1 4576.00 4580.00 mMD
Top slurry 2 mMD
internal top mMD

Comments Costs in Euro.


no losses , no gain during cement plug job . No cement in return at the circulation after cement job .
Cement plug #2 theoritical top/bottom 4576m/4853m - Actual top:4580m.

Rig NRH
Cement Contract Halliburton
Report N° 60
CEMENTING K/06-GT4
E & P Nederland B.V. 11/12/2001
Casing to Cement plug inch Cement Job type Abandonment plug
Casing shoe mMD mVD Mud type LTOBM SG 1.27 BHST 91 °C
Drilling Size 5.875 inch LOT / FIT 2.03 EMW at 4791.00 mVD BHCT 78 °C
TD 5206.00 mMD 3776.00 mVD Pore press. EMW at mVD API schedule
Prev casing 7 inch 35 lbs/ft Format. frac EMW at mVD -Pressure bars
Prev csg shoe 4790.00 mMD 3384.00 mVD -Temperature °C

Laboratory fluids design


Products and additives Unit SPACERS SLURRIES Characteristics SLURRIES
n°1 n°2 n°1 n°2 n°1 n°2
Base oil ltr 1000 Specific gravity ppg 1.92
Hyflo 4 ltr 4 Thickening Time : 40BC 4:00
Drill water ltr 440 Thickening Time: 70BC 4:05
G cement kg 1000 Thickening Time: 100BC 4:10
Defoamer NF6 ltr 1 Free Water % : vertical 0
HR4 kg 3.5 Free Water % : 45°
Fluid loss ml n/a
Yield 0.75m3/t

Compress Strength 12h


24h 3200psi

Final volume or Yield


Rheologies (laboratory / on site)
FLUIDS T° SG F300 F200 F100 F60 F30 F6 F3 G0 G10 PV YV n K
Mud
Spacer1
Spacer2
Slurry 1 Ambient 1.92 34 22 12 8 4 1 1 30 2 0.87 0.15
Slurry 2

Mud 50°C 1.27 43 34 25 20 17 13 12 20 38 27 16 0.44 2.71


Spacer1
Spacer2
Slurry 1 20°C 1.92 52 38 20 13 8 4 3 5 54 2 0.93 0.16
Slurry 2

Products used and cost Operation summary


Products Unit SPACERS SLURRIES Unit Cost Operation Volume Flow Press Time
n°1 n°2 n°1 n°2 price break down m3 L/mn bars mn
Base oil m3 4 577.0 2308.0 Circulation 42 1750 251 30
Hyflo 4 ltr 16 11.6 185.6 Batch mixing 5 30
G cement t 6 138.4 830.4 Front spacer=base oil 3.7 700 66 5
Defoamer NF6 ltr 10 25.9 259.0 Slurry 5 730 89/72 10
HR4 kg 23 6.4 147.2 Tail spacer=base oil 0.33 400 20 1
Displacement 34.6 830 70/60 45

Total displac. 34.6


Pressure test n/a
Slurries volumes excess (%)
Caliper OR Theoretical
Total cost 2493.6 1236.6 3730.2 slurry 1
Fabrication Halliburton slurry 2
Silos Noble Ronald Hoope
Material used Displacement Halliburton Results Plan. Actual
on site Pits Halliburton batch mixer 30m3 + rig pit. Top slurry 1 3615.00 mMD
Top slurry 2 mMD
internal top mMD

Comments Costs in Euro.


No losses,no gain during cement plug job - After displacement , POOH cmt stinger wet - +/-500 litres of cement in return at the reverse circulation after job.

Cement plug #3 theoritical top/bottom 3615m/3773m.


BHST and BHCT at 3773m MD. Rig NRH
Cement Contract Halliburton
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 28
Ref : OPE/#12945/JCS/MH/AVE

- Pressure test report+diagram (LOT)


FORMATION INTEGRITY LEAK Report N° 16
K/06-GT4
E & P Nederland B.V. OFF TEST 28/10/2001

Measured Depth Vertical Depth


Phase 12"1/4 Hole depth 1703.00 m

Shoe 1694.00 m Zs = 1520.90 m


Axis 1
On bottom 0

Tool 1692 m
Ground or M.L. 84.65
R.K.B. Elevation Assumed
MSL 43.85 Weak Point 1694.00 m Zi = 1520.90 m

Mud characteristics Type = POM MV = 57 YP = 16 Gel 0 / Gel 10


during test PV = 18 W.L. = 11 / 14 Mud weight 1.10

Casing Cement Formation


Planned

Max. allowable pressure Estimated EMW inj. FIT LOT


Test
bars Desired EMW 1.50 Desired EMW 1.50

Type Planned testing pressure Test Pressure Test or Injection Pressure

bars 60.20 bars 60.20 bars

Pump Halliburton Planned flow rate 40 l/min

Injection line Cement line Planned mud volume 400

Pumped (or released) Pressure Total volume pumped 520


Time volume (Unit) Results
by step cumulated bar Total volume released 440
7:12 0.00 0.00 0.00
7:13 40.00 40.00 9.00
7:14 40.00 80.00 15.00 Casing Stabilised Pressure Positive
7:15 40.00 120.00 22.50 test Result
7:16 40.00 160.00 27.00 Stabilised Time Negative
7:17 40.00 200.00 31.75
7:18 40.00 240.00 35.60
7:19 40.00 280.00 39.10 Cement Test Pres. = 60.2 Csg shoe E.M.W. test = 1.50
7:20 40.00 320.00 43.20
7:21 40.00 360.00 46.80 or Injection Pres. = Weak point E.M.W. inj. =
7:22 40.00 400.00 49.80
7:23 40.00 440.00 53.00 formation Formation Pres. = E.M.W. frac. =
7:24 40.00 480.00 56.40 at 1520.90 m
7:25 40.00 520.00 60.20 test bars

Stabilisation
Time Pressure Comments lost suction on pump #1, switch to
pump #2 after 159 ltrs and continue leak off test.
7:25 60.20
7:27 56.60
7:29 54.40
7:31 52.60
7:33 51.15
7:35 49.85
7:37 48.40
7:39 47.55
7:41 46.70
7:43 46.00
FORMATION INTEGRITY / LEAK OFF TEST - K/06-GT4 - 28/10/2001

70.00

60.00

50.00
Pressure (bar)

40.00

80.00
60.00
30.00
40.00
20.00
20.00
0.00
7:19 7:26 7:33 7:40 7:48

10.00

0.00
0.00 100.00 200.00 300.00 400.00 500.00 600.00 700.00
Pumped volume ()
FORMATION INTEGRITY LEAK Report N° 33
K/06-GT4
E & P Nederland B.V. OFF TEST 14/11/2001

Measured Depth Vertical Depth


Phase 8 1/2 Hole depth 3853.00 m

Shoe 3848.00 m Zs = 2776.50 m


Axis 1
On bottom 0

Tool 3838 m
Ground or M.L. 84.65
R.K.B. Elevation Assumed
MSL 43.85 Weak Point 3848.00 m Zi = 2776.50 m

Mud characteristics Type = LTM MV = 51 YP = 13 Gel 0 / Gel 10


during test PV = 20 W.L. = 11 / 20 Mud weight 1.63

Casing Cement Formation


Planned

Max. allowable pressure Estimated EMW inj. FIT LOT


Test
bars Desired EMW Desired EMW 2.05

Type Planned testing pressure Test Pressure Test or Injection Pressure

bars bars 118.00 bars

Pump Halliburton Planned flow rate 70 l/mn

Injection line Cement line connected to drill pipe + choke line. Planned mud volume 1000 liter

Pumped (or released) Pressure Total volume pumped 895 ltres


Time volume 895 liter (Unit) Results
by step cumulated bar Total volume released 895 litres
14:43 100.00 100.00 17.00
100.00 200.00 39.50
100.00 300.00 51.00 Casing Stabilised Pressure Positive
100.00 400.00 63.50 test Result
100.00 500.00 75.50 Stabilised Time Negative
100.00 600.00 88.00
100.00 700.00 100.00
100.00 800.00 112.50 Cement Test Pres. = 120.5 Csg shoe E.M.W. test = 2.07
14:56 95.00 895.00 123.00
or Injection Pres. = Weak point E.M.W. inj. =

formation Formation Pres. = E.M.W. frac. =


at 2776.50 m
test bars

Stabilisation
Time Pressure Comments

14:56 122.40
14:57 122.10
14:58 122.00
14:59 121.70
15:00 121.40
15:01 121.30
15:02 121.10
15:03 120.90
15:04 120.80
15:05 120.70
15:06 120.60
15:07 120.50
FORMATION INTEGRITY / LEAK OFF TEST - K/06-GT4 - 14/11/2001

137.00

117.00

97.00
Pressure (bar)

122.50
77.00 122.00
121.50
121.00
57.00 120.50
120.00
14:52 15:00 15:07 15:14

37.00

17.00
100.00 300.00 500.00 700.00 900.00 1100.00 1300.00
Pumped volume (895 liter)
FORMATION INTEGRITY LEAK Report N° 43
K/06-GT4
E & P Nederland B.V. OFF TEST 24/11/2001

Measured Depth Vertical Depth


Phase 5"7/8 Hole depth 4791.00 m

Shoe 4790.00 m Zs = 3385.00 m


Axis 1
On bottom 0

Tool 4790 m
Ground or M.L. 84.65
R.K.B. Elevation Assumed
MSL 43.85 Weak Point 4790.00 m Zi = 3885.00 m

Mud characteristics Type = OBM MV = 52 YP = 15 Gel 0 / Gel 10


during test PV = 19 W.L. = 17 / 24 Mud weight 1.25

Casing Cement Formation


Planned

Max. allowable pressure Estimated EMW inj. FIT LOT


Test
bars Desired EMW Desired EMW

Type Planned testing pressure Test Pressure Test or Injection Pressure

bars bars 321.00 bars

Pump Halliburton Planned flow rate 80 l/min

Injection line Cement line connected to drill pipe + choke line. Planned mud volume 2625 l

Pumped (or released) Pressure Total volume pumped 3420 l


Time volume (Unit) Results
by step cumulated bar Total volume released 2990 l
16:42 0.00 0.00 0.00
160.00 160.00 24.62
160.00 320.00 40.46 Casing Stabilised Pressure Positive
160.00 480.00 57.70 test Result
160.00 640.00 75.00 Stabilised Time Negative
160.00 800.00 91.00
160.00 960.00 108.10
160.00 1120.00 125.40 Cement Test Pres. = 395 Csg shoe E.M.W. test = 2.44
160.00 1280.00 143.50
160.00 1440.00 160.70 or Injection Pres. = Weak point E.M.W. inj. =
160.00 1600.00 175.50
160.00 1760.00 197.20 formation Formation Pres. = E.M.W. frac. =
160.00 1920.00 216.20 at 3385.00 m
160.00 2080.00 234.80 test bars
160.00 2240.00 252.00
160.00 2400.00 272.00 Stabilisation
160.00 2560.00 290.00 Time Pressure Comments
160.00 2720.00 309.00 Increase pressure up to 395 bar (max allowable casing
160.00 2880.00 328.00 17:46 395.00 pressure) : no injection observed.
160.00 3040.00 347.00 17:47 393.30
160.00 3200.00 367.00 17:48 392.90
160.00 3360.00 384.90 17:49 392.60
17:46 80.00 3440.00 395.00 17:50 392.40
17:51 392.10
17:52 391.90
17:53 391.70
17:54 391.60
17:55 391.40
17:56 391.20
FORMATION INTEGRITY / LEAK OFF TEST - K/06-GT4 - 24/11/2001

450.00

400.00

350.00

300.00
Pressure (bar)

250.00
396.00
395.00
200.00 394.00
393.00
392.00
150.00
391.00
17:4 17:4 17:4 17:5 17:5 17:5
100.00 2 5 8 1 4 7

50.00

0.00
0.00 1000.00 2000.00 3000.00 4000.00 5000.00
Pumped volume ()
FORMATION INTEGRITY LEAK Report N° 47
K/06-GT4
E & P Nederland B.V. OFF TEST 28/11/2001

Measured Depth Vertical Depth


Phase 5"7/8 Hole depth 4921.00 m

Shoe 4790.00 m Zs = 3385.00 m


Axis 1
On bottom 0

Tool 4790 m
Ground or M.L. 84.65
R.K.B. Elevation Assumed
MSL 43.85 Weak Point 4790.00 m Zi = 3385.00 m

Mud characteristics Type = OBM MV = 58 YP = 15 Gel 0 / Gel 10


during test PV = 18 W.L. = 14 / 25 Mud weight 1.27

Casing Cement Formation


Planned

Max. allowable pressure Estimated EMW inj. FIT LOT


Test
bars Desired EMW Desired EMW

Type Planned testing pressure Test Pressure Test or Injection Pressure

bars bars 321.00 bars

Pump Halliburton Planned flow rate 80 l/min

Injection line Cement line connected to drill pipe + choke line. Planned mud volume 2625 l

Pumped (or released) Pressure Total volume pumped 3200 l


Time volume (Unit) Results
by step cumulated bar Total volume released 3200 l
3:47 0.00 0.00 0.00
160.00 160.00 42.20
160.00 320.00 58.40 Casing Stabilised Pressure Positive
160.00 480.00 75.50 test Result
160.00 640.00 93.00 Stabilised Time Negative
160.00 800.00 110.40
160.00 960.00 128.10
160.00 1120.00 146.10 Cement Test Pres. = 390 Csg shoe E.M.W. test = 2.45
160.00 1280.00 165.00
160.00 1440.00 183.80 or Injection Pres. = Weak point E.M.W. inj. =
160.00 1600.00 201.00
160.00 1760.00 219.40 formation Formation Pres. = E.M.W. frac. =
160.00 1920.00 237.80 at 3385.00 m
160.00 2080.00 256.20 test bars
160.00 2240.00 275.00
160.00 2400.00 294.30 Stabilisation
160.00 2560.00 313.20 Time Pressure Comments
160.00 2720.00 332.30 Increase pressure up to 390 bar (max allowable casing
160.00 2880.00 353.20 4:23 390.00 pressure) : no injection observed.
160.00 3040.00 373.00 4:24 382.20
4:23 160.00 3200.00 390.00 4:25 381.90
4:26 381.80
4:27 381.70
4:28 381.60
4:29 381.50
4:30 381.40
4:31 381.40
4:32 381.30
4:33 381.20
FORMATION INTEGRITY / LEAK OFF TEST - K/06-GT4 -

450.00

400.00

350.00

300.00
Pressure (bar)

250.00
392.00
390.00
200.00 388.00
386.00
384.00
150.00
382.00
380.00
100.00 4:22 4:24 4:27 4:30 4:33

50.00

0.00
0.00 500.00 1000.00 1500.00 2000.00 2500.00 3000.00 3500.00 4000.00 4500.00
Pumped volume ()
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 29
Ref : OPE/#12945/JCS/MH/AVE

- Bit record
BIT RECORD K/06-GT4
E & P Nederland B.V.
DESCRIPTION PERFORMANCE

T
Depth Parameters Mud
Rep Bit y Designation Total Total Average
N° N° p Diam Sup (or IADC) Serial No Jets TFA Oper Length Time penet time ROP Dull grading
Start Final WOB RPM Flow Pres Torque Type S.G.
e
4 1 T 26" Reed EMS11GC X83407 3 x 22 + 1x20 1.42 F1 85 149 64 2:30 64 02:30 25.60 3/5 40 2500 51 405 BMS 1.04
5 1 T 26" Reed EMS11GC X83407 3 x 22 + 1x20 1.42 F1 149 318 169 8:30 233 11:00 21.18 2 40 2500 52 405 BMS 1.13
5 1 T 26' Reed EMS11GC X83407 3 x 22 + 1x20 1.42 F1 318 558 240 12:30 473 23:30 20.13 5/15 40 3000 96 814 BMS 1.13
6 1 T 26" Reed EMS11GC X83407 3 x 22 + 1x20 1.42 F1 558 682 124 6:00 597 29:30 20.24 5/10 50 3100 103 1017 BMS 1.17 1-1-WT-A-E-I-NO-TD
8 2 T 17"½ Smith MGSSH LR9915 3 x 20 + 1x19 1.197 F2C BMS 1.17
9 2 T 17½ Smith MGSSH LR9915 3 x 20 + 1x19 1.197 C4 663 682 4:00 5/10 20 2500 73 920 BMS 1.17 Drlg Cmt
9 2 T 17½ Smith MGSSH LR9915 3 x 20 + 1x19 1.197 F1 682 821 139 9:00 139 09:00 15.44 10 0 2700 88 0 KCL 1.16 Sliding mode parameters
9 2 T 17½ Smith MGSSH LR9915 3 x 20 + 1x19 1.197 F1 821 936 115 6:00 254 15:00 16.93 6/7 75 3500 135 1200 KCL 1.20 Rotary mode parameters
10 2 T 17½ Smith MGSSH LR9915 3 x 20 + 1x19 1.197 F1 936 1225 289 17:00 543 32:00 16.97 9/11 80 3500 150 1300 KCL 1.21 Rotary mode parameters
10 2 T 17½ Smith MGSSH LR9915 3 x 20 + 1x19 1.197 F1 1225 1247 22 1:00 565 33:00 17.12 6/8 85 3500 170 1430 KCL 1.30 Rotary mode parameters
11 2 T 17½ Smith MGSSH LR9915 3 x 20 + 1x19 1.197 F1 1247 1610 363 23:59 928 56:59 16.29 15/20 80 3500 190 1800 KCL 1.31 Rotary mode parameters
12 2 T 17½ Smith MGSSH LR9915 3 x 20 + 1x19 1.197 F1 1610 1698 88 6:30 1016 63:29 16.00 15/20 80 3500 205 2000 KCL 1.31 1-2-WT-A-E-2-WO-TD
13 2 T 17½ Smith MGSSH LR9915 3 x 20 + 1x19 1.197 C5 KCL 1.31 1-2-WT-A-E-2-WO-TD
15 3 T 12¼ Reed EHP42H QR6727 3 x 22 + 1x20 1.114 C4
16 3 T 12¼ Reed EHP42H QR6727 3 x 22 + 1x20 1.114 F1 1698 1703 5 0:30 5 00:30 10.00 10 180 3000 160 2200 POM 1.10 Rotary mode parameters
16 3 T 12¼ Reed EHP42H QR6727 3 x 22 + 1x20 1.114 F1 1703 1879 176 15:30 181 16:00 11.31 15/20 200 3250 130 2100 POM 1.10 Rotary mode parameters
17 3 T 12¼ Reed EHP42H QR6727 3 x 22 + 1x20 1.114 F1 1879 1982 103 7:00 284 23:00 12.35 15/20 200 3300 140 2200 POM 1.12 1-1-BT-H-1-I-RR-FM
17 4 X 12¼ Baker BX547 1903210 2x16 + 2x14 + 4x13 1.212 F1 1982 2002 20 1:00 20 01:00 20.00 6 200 3250 145 2450 POM 1.12 Rotary mode parameters
18 4 X 12¼ Baker BX547 1903210 2x16 + 2x14 + 4x13 1.212 F1 2002 2194 192 12:00 212 13:00 16.31 8 200 3300 155 2700 POM 1.14 Rotary mode parameters
18 4 X 12¼ Baker BX547 1903210 2x16 + 2x14 + 4x13 1.212 F1 2194 2420 226 12:00 438 25:00 17.52 8 210 3300 160 2700 POM 1.14 Rotary mode parameters
19 4 X 12¼ Baker BX547 1903210 2x16 + 2x14 + 4x13 1.212 F1 2420 2644 224 12:00 662 37:00 17.89 10 203 3350 175 3400 POM 1.14 Rotary mode parameters
19 4 X 12¼ Baker BX547 1903210 2x16 + 2x14 + 4x13 1.212 F1 2644 2836 192 12:00 854 49:00 17.43 10 225 3650 180 3600 POM 1.14 Rotary mode parameters
20 4 X 12¼ Baker BX547 1903210 2x16 + 2x14 + 4x13 1.212 F1 2836 3016 180 12:00 1034 61:00 16.95 14 225 3650 185 3200 POM 1.15 Rotary mode parameters
20 4 X 12¼ Baker BX547 1903210 2x16 + 2x14 + 4x13 1.212 F1 3016 3086 70 10:30 1104 71:30 15.44 10 220 3600 175 3050 POM 1.15 Rotary mode parameters
21 4 X 12¼ Baker BX547 1903210 2x16 + 2x14 + 4x13 1.212 F2 POM 1.15 1-1-WT-A-X-I-NO-PR
21 5 T 12¼ Smith FG26OD MJ0813 1 x 18 + 3 x 20 1.169 F1 3086 3117 31 6:30 31 06:30 4.77 20 215 3500 170 3000 POM 1.15 Rotary mode parameters
22 5 T 12¼ Smith FG26OD MJ0813 1 x 18 + 3 x 20 1.169 F1 3117 3147 30 7:30 61 14:00 4.36 20 217 3500 170 3050 POM 1.15 Rotary mode parameters
23 5 T 12¼ Smith FG26OD MJ0813 1 x 18 + 3 x 20 1.169 F1 3147 3212 65 20:30 126 34:30 3.65 22 217 3500 230 2300 OBM 1.26 Rotary mode parameters
24 5 T 12¼ Smith FG26OD MJ0813 1 x 18 + 3 x 20 1.169 F1 3212 3262 50 16:00 176 50:30 3.49 26 216 3500 235 2350 OBM 1.25 1-2-BT-H-E-I-NO-FM
25 6 X 12¼ Baker BX536 1905137 6 x 16 1.178 F1 3262 3387 125 18:30 125 18:30 6.76 9 210 3200 230 2550 OBM 1.25
26 6 X 12¼ Baker BX536 1905137 6 x 16 1.178 F1 3387 3455 68 10:30 193 29:00 6.66 9 213 3280 228 2600 OBM 1.25
26 6 X 12¼ Baker BX536 1905137 6 x 16 1.178 F1 3455 3650 195 13:30 388 42:30 9.13 11 213 3280 230 2900 OBM 1.25
27 6 X 12¼ Baker BX536 1905137 6 x 16 1.178 F1 3650 3789 139 15:15 527 57:45 9.13 10/11 220 3400 230 2800 OBM 1.25
27 6 X 12¼ Baker BX536 1905137 6 x 16 1.178 F1 3789 3817 28 8:00 555 65:45 8.44 11/13 220 3400 230 2800 OBM 1.25
28 6 X 12¼ Baker BX536 1905137 6 x 16 1.178 F1 3817 3850 33 5:00 588 70:45 8.31 11/13 220 3400 230 2800 OBM 1.30 1.1.WT.A.X.I.NO.TD
29 6 X 12¼ Baker BX536 1905137 6 x 16 1.178 OBM 1.30 1.1.WT.A.X.I.NO.TD
32 7 X 8½ Smith M16VPX JS5474 3x13+3x14 0.84 F2C OBM 1.30
33 7 X 8½ Smith M16VPX JS5474 3x13+3x14 0.84 C4 3793 3850 6:00 2 165 1540 205 2350 OBM 1.65
33 7 X 8½ Smith M16VPX JS5474 3x13+3x14 0.84 F1 3850 3937 87 6:00 87 06:00 14.50 2 165 1540 210 2350 OBM 1.65 1.1.No.A.X.I.No.DTF
BIT RECORD K/06-GT4
E & P Nederland B.V.
DESCRIPTION PERFORMANCE

T
Depth Parameters Mud
Rep Bit y Designation Total Total Average
N° N° p Diam Sup (or IADC) Serial No Jets TFA Oper Length Time penet time ROP Dull grading
Start Final WOB RPM Flow Pres Torque Type S.G.
e
34 8 X 8½ H/C G382 1214202 3x18+1x15 0.897 F1 3937 4056 119 7:00 119 07:00 17.00 8/10 230 1850 250 2200 OBM 1.65
35 8 X 8½ H/C G382 1214202 3x18+1x15 0.897 F1 4056 4083 27 1:30 146 08:30 17.18 10 230 1850 260 2000 OBM 1.65
35 8 X 8½ H/C G382 1214202 3x18+1x15 0.897 F1 4083 4185 102 16:30 248 25:00 9.92 14 230 1850 245 1950 OBM 1.65
35 8 X 8½ H/C G382 1214202 3x18+1x15 0.897 F1 4185 4198 13 1:00 261 26:00 10.04 13 160 1850 261 Sliding OBM 1.65
35 8 X 8½ H/C G382 1214202 3x18+1x15 0.897 F1 4198 4294 96 5:00 357 31:00 11.52 10 230 1850 260 1750 OBM 1.65
36 8 X 8½ H/C G382 1214202 3x18+1x15 0.897 F1 4294 4497 203 12:00 560 43:00 13.02 11 230 1850 270 1900 OBM 1.65
36 8 X 8½ H/C G382 1214202 3x18+1x15 0.897 F1 4497 4668 171 12:00 731 55:00 13.29 13 230 1850 280 1900 OBM 1.65
37 8 X 8½ H/C G382 1214202 3x18+1x15 0.897 F1 4668 4791 123 17:30 854 72:30 11.78 14 230 1850 290 1900 OBM 1.65 1-1-WT-A-X-I-NO-TD
38 8 X 8½ H/C G382 1214202 3x18+1x15 0.897 F3 4791 4791 2:00 250 2000 265 1900 OBM 1.65 1-1-WT-A-X-I-NO-TD
43 9 X 5"7/8 Baker 438 1212766 0.75 C4 4791 4796 2:30 OBM 1.25
43 9 X 5"7/8 Baker 438 1212766 0.75 F1 4796 4850 54 4:30 54 04:30 12.00 2 1000 260 2550 OBM 1.25
44 9 X 5"7/8 Baker 438 1212766 0.75 F1 4850 4878 28 6:00 82 10:30 7.81 0.50 350 1000 220 2800 OBM 1.25 1-1-NO-A-X-I-PN-BHA
44 10 X 5"7/8 Diam SPH633 S1G0347 3 x 18 0.75 F2 OBM 1.25
45 10 X 5"7/8 Diam SPH633 S1G0347 3 x 18 0.75 F1 4878 4921 43 10:00 43 10:00 4.30 0.5 300 1000 250 2650 OBM 1.25
46 10 X 5"7/8 Diam SPH633 S1G0347 3 x 18 0.75 F2 OBM 1.25 1-1-WO-A-X-I-WO-BHA
47 11 T 5"7/8 Baker STR-20 T62ZY 3 x 20 0.92 F1 4921 4985 64 17:30 64 17:30 3.66 4 280 1000 320 OBM 1.26
48 11 T 5"7/8 Baker STR-20 T62ZY 3 x 20 0.92 F1 4985 4997 12 6:00 76 23:30 3.23 4 280 1000 320 OBM 1.25 8-8-LC-A-F-3-NO-HR
49 12 X 5"7/8 Varel MKF-39 CP5870C 3x12 + 3x16 0.92 F2 OBM 1.26
50 12 X 5"7/8 Varel MKF-39 CP5870C 3x12 + 3x16 0.92 F1 4997 5056 59 12:30 59 12:30 4.72 4 336 1000 290 3250 OBM 1.25
51 12 X 5"7/8 Varel MKF-39 CP5870C 3x12 + 3x16 0.92 F1 5056 5083 27 12:00 86 24:30 3.51 2.5 280 1000 290 OBM 1.24
51 12 X 5"7/8 Varel MKF-39 CP5870C 3x12 + 3x16 0.92 F1 5083 5142 59 12:00 145 36:30 3.97 4.5 335 1000 295 3400 OBM 1.24
52 12 X 5"7/8 Varel MKF-39 CP5870C 3x12 + 3x16 0.92 F1 5142 5160 18 12:00 163 48:30 3.36 5 345 1010 280 3250 OBM 1.24
52 12 X 5"7/8 Varel MKF-39 CP5870C 3x12 + 3x16 0.92 F1 5160 5188 28 12:00 191 60:30 3.16 4.5 345 1010 280 3100 OBM 1.24
53 12 X 5"7/8 Varel MKF-39 CP5870C 3x12 + 3x16 0.92 F1 5188 5206 18 7:00 209 67:30 3.10 5.5 360 1050 295 3100 OBM 1.25 2.4.WT.AX.I.LT.TD
54 12 X 5"7/8 Varel MKF-39 CP5870C 3x12 + 3x16 0.92 F2 OBM 1.25 2-4-WT-A-X-I-LT-TD
55 12 X 5"7/8 Varel MKF-39 CP5870C 3x12 + 3x16 0.92 F2 70 1350 276 3400 OBM 1.25 2-4-WT-A-X-I-LT-TD
56 12 X 5"7/8 Varel MKF-39 CP5870C 3x12 + 3x16 0.92 F2 OBM 1.25 3-5-WT-S-X-I-LT-TD
58 12 X 5"7/8 Varel MKF-39 CP5870C 3x12 0.331 B2C OBM 1.27 3-5-WT-S-X-I-LT-TD
59 12 X 5"7/8 Varel MKF-39 CP5870C 3x12 0.331 B2C 4540 4580 800 55 OBM 1.27 3-5-WT-S-X-I-LT-TD
BIT RECORD K/06-GT4
E & P Nederland B.V.
DESCRIPTION PERFORMANCE

T
Depth Parameters Mud
y Designation Total Total Average
p Diam Sup (or IADC) Serial No Jets TFA Oper penet time ROP Dull grading
Start Final WOB RPM Flow Pres Torque Type S.G.
e
T 26" Reed EMS11GC X83407 3 x 22 + 1x20 1.42 F1 85 682 597 29:30 20.24 5/10 50 3100 103 1017 BMS 1.17 1-1-WT-A-E-I-NO-TD
T 17½ Smith MGSSH LR9915 3 x 20 + 1x19 1.197 F1 682 1698 1016 63:29 16.00 15/20 80 3500 205 2000 KCL 1.31 1-2-WT-A-E-2-WO-TD
T 12¼ Reed EHP42H QR6727 3 x 22 + 1x20 1.114 F1 1698 1982 284 23:00 12.35 15/20 200 3300 140 2200 POM 1.12 1-1-BT-H-1-I-RR-FM
X 12¼ Baker BX547 1903210 2x16 + 2x14 + 4x13 1.212 F1 1982 3086 1104 71:30 15.44 10 220 3600 175 3050 POM 1.15 Rotary mode parameters
T 12¼ Smith FG26OD MJ0813 1 x 18 + 3 x 20 1.169 F1 3086 3262 176 50:30 3.49 26 216 3500 235 2350 OBM 1.25 1-2-BT-H-E-I-NO-FM
X 12¼ Baker BX536 1905137 6 x 16 1.178 F1 3262 3850 588 70:45 8.31 11/13 220 3400 230 2800 OBM 1.30 1.1.WT.A.X.I.NO.TD
X 8½ Smith M16VPX JS5474 3x13+3x14 0.84 F1 3850 3937 87 06:00 14.50 2 165 1540 210 2350 OBM 1.65 1.1.No.A.X.I.No.DTF
X 8½ H/C G382 1214202 3x18+1x15 0.897 F1 3937 4791 854 72:30 11.78 14 230 1850 290 1900 OBM 1.65 1-1-WT-A-X-I-NO-TD
X 5"7/8 Baker 438 1212766 0.75 F1 4796 4878 82 10:30 7.81 0.50 350 1000 220 2800 OBM 1.25 1-1-NO-A-X-I-PN-BHA
X 5"7/8 Diam SPH633 S1G0347 3 x 18 0.75 F1 4878 4921 43 10:00 4.30 0.5 300 1000 250 2650 OBM 1.25
T 5"7/8 Baker STR-20 T62ZY 3 x 20 0.92 F1 4921 4997 76 23:30 3.23 4 280 1000 320 OBM 1.25 8-8-LC-A-F-3-NO-HR
X 5"7/8 Varel MKF-39 CP5870C 3x12 + 3x16 0.92 F1 4997 5206 209 67:30 3.10 5.5 360 1050 295 3100 OBM 1.25 2.4.WT.AX.I.LT.TD
TotalFinaElf E & P Nederland b.v. Drilling and Completion department
Date : November 2002 Rev : 0
Final drilling report of K6-GT4 Authors : J-C Sinet - M.Helmana - S. van Es
Page 30
Ref : OPE/#12945/JCS/MH/AVE

- Enclosures