Professional Documents
Culture Documents
Potter Spread Sheet
Potter Spread Sheet
Recycle
5 cups
Throwing Kiln
45 cups/batch Wheel Drying Loading
Kiln Kiln
Glaze Loading Firing
Mass Flow
Throwing: takes 1 hour to throw 20 cups 20 cups/hr
Drying: 200 cup capacity, takes 24 hours 8.33 cups/hr
Kiln loading: 50 cup capacity, takes .5 hours
Kiln Firing: 8 hours (kiln capacity is 50 cups)
Cooling: 8 hours
Kiln unloading: .5 hours
Total kiln time 17 hours 3.03 cups/hr
Glaze: 2 hours for 50 cups (kiln load) 25 cups/hr
Kiln loading: 50 cup capacity, takes .5 hours cups/hr
Kiln Firing: 8 hours cups/hr
Cooling: 8 hours cups/hr
Kiln unloading: .5 hours cups/hr
Total kiln time 17 hours 3.03 cups/hr
Packing: 1 cup per minute 60 cups/hr
Quick solution: We can see right away by reviewing the mass flows above that the kiln operation is the bottlen
capacity of the system.
If the potter were able to always load the kiln before the workday ends, and then fire them ove
2000/(24/17 * 50)/.95=29.8 days for one of the kiln operations. If we were to consider the oth
It would be very difficult to get more precise than this using a spreadsheet with no simulation a
Kiln Kiln
Firing Cooling Unloading
Kiln
Cooling Unloading Packing 2000 cups
Scrap
3-5 cups
bottleneck
kiln operation is the bottleneck. We can use that as an initial estimate as to the
nds, and then fire them overnight, the production rate would be greater than 1 kiln-load per day.
we were to consider the other (second) kiln operation, the time required would be 60 days.
Production volume per year: 11000 Since the production rate is estimated (on the mass flow page) at 60 days for 2000 cups
Fixed costs
Buildings maintenance $/year $3,000.00
Equipment maintenance $/year $2,000.00
Taxes and utilities $/yr $3,500.00
Total $8,500.00
Per cup $0.77
Buildings $130,000
Net Profits
Total cost per cup (with no depreciation) $1.92
Price per cup $4.00
Net Profit $22,850
Taxes (at 20%) $4,570
NOPAT $18,280
EVA Calculation
WACC 16%
Working Capital $3,667
Capital Charge $22,667
EVA -$4,387