1. The document is an estimate for emergency road work including dismantling existing structures, excavation, laying pipes and concrete work.
2. Items include removing a cement mortar structure, excavating to lay 1000mm diameter hume pipes, providing bedding and backfill, and casting concrete foundations, headwalls and wheel guards.
3. Reinforced concrete will be used to construct pipe culverts and the total estimated cost is Rs. 9,07,631.
1. The document is an estimate for emergency road work including dismantling existing structures, excavation, laying pipes and concrete work.
2. Items include removing a cement mortar structure, excavating to lay 1000mm diameter hume pipes, providing bedding and backfill, and casting concrete foundations, headwalls and wheel guards.
3. Reinforced concrete will be used to construct pipe culverts and the total estimated cost is Rs. 9,07,631.
1. The document is an estimate for emergency road work including dismantling existing structures, excavation, laying pipes and concrete work.
2. Items include removing a cement mortar structure, excavating to lay 1000mm diameter hume pipes, providing bedding and backfill, and casting concrete foundations, headwalls and wheel guards.
3. Reinforced concrete will be used to construct pipe culverts and the total estimated cost is Rs. 9,07,631.
Based on S.S.R. Issued By MPRRDA Madhya Pradesh, Bhopal w.e.f. 15 aug 2013 TYPE :- Hume Pipe Culvert 3 Row 1000 mm dia S.No. Item No. Description of Items No. L (m) B (m) D/H (m) Quantity Unit Rate (Rs.) Amount (Rs.) 1 2.6 (b) ii Dismentling of strucutre ii cement mortar 2 14 0.85 2.2 52.36 cum 174 9110.64 2 2.7 (b) Removing of pipe (b) above 600mm to 900 mm dia hume pipe 4 2.5 10 RM 168 1680
3 9.1 Excavation for Structures
Earthwork in excavation for foundation of structures A. Ordinary soil (i) Upto 1.5 m depth Face wall 2 10.000 1.600 1.500 48.000 Protection wall u/s 1 20.000 1.600 1.500 48.000 Protection wall d/s 1 15.000 1.600 1.500 36.000 Approne d/s 2 2.000 1.100 1.000 4.400 Approne wall 1 7.000 1.100 1.000 7.700 Below pipes 1 5.500 4.500 0.750 18.563 Total 162.663 cum 143.00 23,261 (ii) 1.5 m to 3 m depth Face wall 2 6.300 1.600 0.000 0.000 Total 0.000 cum 0.00 0 4 9.2 Bedding for Pipe (ii) Type B (First Class) Bedding Laying (First Class) bedding with wel I. Sand filling 1 5.410 4.550 0.690 16.985 Deduction of opening of pipe 1 5.410 0.0968113192 -0.524 Total 16.461 cum 557.00 9,169 5 11.2 Fillling in foundation trenches as per drawing and te I. Sand filling Below face wall 2 10.000 1.600 0.300 9.600 9.600 cum 557.00 5,347 6 11.4 Providing concrete for plain/reinforced concrete in I. P.C.C grade M 10 (i) Nominal mix 1:3:6 with 40 Conc. For face wall 2 10.000 1.600 0.150 4.800 Conc. For Protection wall u/s 1 20.000 1.500 0.150 4.500 Conc. For Protection wall d/s 1 15.000 1.500 0.150 3.375 Approne d/s 2 2.000 1.100 0.150 0.660 Approne wall 1 7.000 1.100 0.150 1.155 Deduction of pipe 1 0.786 (1.23)(6.57+5.68)/2 2 0.000 Net Qty. 14.490 cum 3933.00 56,989 7 11.4 Providing concrete for plain/reinforced concrete in II. P.C.C grade M 15 (i) Nominal mix (1:2.5:5) with (0.40+1.45)/2 Conc. For face wall 2 10.000 0.925 3.150 58.275 Conc. For Protection wall u/s 1 20.000 0.900 3.000 54.000 Conc. For Protection wall d/s 1 15.000 0.900 3.000 40.500 Approne d/s 2 2.000 0.700 1.800 5.040 Approne wall 1 7.000 0.700 1.800 8.820 Approne pcc 1 7.000 2.000 0.150 2.100 Deduction of opening of pipe Taper portion 2x3 0.785 (1.23)2 0.805 -5.700 Net Qty. 163.035 cum 3939.00 642,195 8 12.5 Plain/reinforced cement concrete in substructure co IV. R.C.C grade M 20 Conc. for wheel guard 10 0.200 0.200 0.300 0.120 Conc. for name plate 6 0.400 0.400 0.600 0.576 Total 0.696 cum 4648.00 3,235 9 9.3
Providing and Laying Reinforced Cement Concrete P
Providing and laying ISI mark reinforced cement conc (B) 1000 mm dia 3 10.000 - - 30.000 m 5099.00 152,970 10 12.6
Supplying, fixing and placing HYSD bar reinforcemen
Deformed Bar Tor Steel Vertical 12mm dia. 6x4 1 24
Total 48 @ 0.89 Kg/M 42.720 Stirrups 8mm dia. 150 c/c 2x3 1.550 27.900 Stirrups 8mm dia. 150 c/c 0x2 0.750 15.000 Total 42.900 @ 0.395 Kg/M 16.946 Grand Total 0.060 t 61588 3,675 Grand Total 907,631 Say Rs. In L 9.08