1 2 3 4 5 6 7 8 9 10 11 12

PROTECTIVE EARTHING BAR DETAILS KEY PLAN


88EP006-PE-10 88EP011-PE-20
88EP007-PE-10 88EP012-PE-20
15200 88EP008-PE-10 88EP013-PE-10
88EP009-PE-10 88EP014-PE-10
2000 5000 5000 3200 88EP010-PE-20 88EP015-PE-20
M19
A A
PLATFORM-4 M19
EL. (+)110.532 T.O.G 4040 NOTES: E-HOUSE

EL.+110.508 1. ALL DIMENSIONS ARE IN MM UNLESS OTHERWISE SPECIFIED.


A60 FIRE RATED
(T.O.GRATING) 2. ALL EARTH CABLE SHALL RUN VIA NEAREST RESPECTIVE CABLE LADDER/TRAY.
WALL 354
3. EXACT LOCATION OF EARTH BAR SHALL BE ADJUSTED AS PER MCT LOCATION & WALL SUPPORT.
309

1393
4. FALSE FLOORING SUPPORTS AND ALL INSTRUMENT CABINET SUPPORTS SHALL BE CONNECTED TO PE

328
SYSTEM. SPARE TERMINALS SHALL BE CONSIDERED IN PE, IE, ISE SYSTEM FOR EARTHING SPARE
CABINETS.
JZ3-6,3x25-E16 61E-52x3,6-3ZJ

5. FOR DETAIL INSTALLATION, REFER TO TYPICAL INSTALLATION DETAIL DRAWING.


88EP007-PE-10 6. HVAC DUCT, LIGHTING FIXTURES & SOCKETS SHALL BE BONDED AND EARTHED WITH PE SYSTEM.
88EP006-PE-10 88EP008-PE-10 88EP009-PE-10 7. THE EARTH BAR WHICH INSTALLED IN INSTRUMENT ROOM SHALL BE KEPT UNDER THE RAISED FLOOR
AND THE EARTHING CABLES SHALL BE ROUTED UNDER THE RAISED FLOOR.
88EP015-PE-20 8. ALL JUNCTION BOXES, PAGA LOUD SPEAKERS AND F&G DETECTORS SHALL BE CONNECTED TO THE PE

283
B 2100 B

400mm²
SYSTEM.

88EP010-PE-20
DOWN TO EL.+104.500 9. PE, IE, ISE EARTH BAR (BELOW E-HOUSE) LOCATE BELOW FLOOR PE, IE, ISE EARTH BAR AND MCT.
10. EARTH CABLE SIZE MAY FOR ELECTRICAL SUB DISTRIBUTION BOARDS WILL CHANGE UPON THE CABLE
88EP002-PE-20 UP TO EL.+115.000 SIZE CONFORMATION FROM EQUIPMENT SUPPLIER.
(400mm²)

4040
UP TO EL.+115.000 88EP020-PE-20 11. E-HOUSE LIGHTNING PROTECTION IS NOT REQUIRED BASED ON THE ATEX REPORT

400mm² 88EP024-PE-10 (70mm²) 076328C-TP-00-S-RA-00011_A.


A60 FIRE RATED A60 FIRE RATED 12. PENDING LOCATIONS FOR EARTHING CONNECTION POINTS BELOW E-HOUSE TO FPSO EARTHING POINTS.
WALL
(70mm²) WALL 13. IE, ISE CABLE TO BE CONFIRMED AFTER RECEIVING ALL EQUIPMENT REFERENCE DRAWINGS.

LEGENDS: - EARTHING BUS BAR


BELOW SUBSTATION
- EARTHING CABLE COPPER WITH
PVC COVER-70mm² - EARTHING BUS BAR
8080

C - EARTHING CABLE COPPER WITH - UP INDICATION C


PVC COVER-400mm²

- EARTHING CABLE COPPER WITH - DOWN INDICATION


PVC COVER-25mm²
- EARTHING TERMINAL
- EARTHING BOSS SS316 30 x 40L
- BONDING CONNECTION
4040

TAG NUMBER IDENTIFICATION


88EP XXX - XX - YY
10-EARTHING BAR WITH 10 HOLES
20-EARTHING BAR WITH 20 HOLES

PE-PROTECTION EARTHING
IE-INSTRUMENT EARTHING
ISE-INTRINSICALLY SAFETY EARTHING

D SEQUENTIAL NUMBER D
EP-EARTH BAR
EARTHING & LIGHTNING

REFERENCE DRAWINGS:
076328C-SI-00-E-XE-0001_2 E&I Equipment layout
400mm² 171W007-EHM-XX-BD-TS-00001_Rev_0 E-House Module Technical Specification
171W007-KA-00-E-FD-00002_C1 Electrical Operational and Design Philosophy
3700

076328C-TP-89-E-FB-0011_1 Powering and Earthing Philosophy


20580

076328C-TP-00-I-FD-0002_A Instrument & Telecommunication Installation Specification


076328C-0000-STD-1580-0002_A INTERNAL - Typical Instruments Installation Details For Packages

Information x Review x Certified final √


E As-built x Cancelled E

PLATFORM-3
EL. (+)110.532 T.O.G

88EP011-PE-20
1_V2 IFC 30/09/19 ISSUED FOR CONSTRUCTION MS LC VS
1 IFC xx/10/19 ISSUED FOR CONSTRUCTION MS LC VS
0 IFC 18/07/19 ISSUED FOR CONSTRUCTION MS LC VS
A IFR 25/10/18 ISSUED FOR REVIEW MS LC VS
REV STATUS DATE DESCRIPTION BY CHK. APP.
5800

F F

DOWN TO EL.+104.500
88EP001-PE-20
(400mm²)
2900

7900
88EP012-PE-20
MV/LV-SWITCHGEAR
ROOM
This document and all the information contained herein are the confidential and exclusive property of TechnipFMC,

JZ3-6,3x25-E16
JZ3-6,3x25-E16 JZ3-6,3x25-E16

and may not be reproduced, disclosed, or made public in any manner prior to express written authorization by TechnipFMC.
G G

1000
COMPANY:
ENERGEAN ISRAEL LIMITED
3000

PROJECT: EPCIC Contract in respect of the Karish

61E-52x3,6-3ZJ
Gas Development Offshore of the State of Israel
283

AIRLOCK ROOM
REQUISITION N°: 076328C-SDB-CWP5-CS-SR-3600-0001
REQUISITION TITLE : E-HOUSE
88EP014-PE-10 88EP013-PE-10
DOCUMENT TITLE : E AND I - LIGHTNING PROTECTION AND EARTHING LAYOUT
309
328

354
EQUIP/ TAG NUMERB(s): -
H A60 FIRE RATED VENDOR DOCUMENT REFERENCE: AREA / UNIT: H
WALL
E-01023-EN-EL-025 TS19
COMPANY DOCUMENT REFERENCE: REVISION:
PLAN VIEW @ EL.+110.500 (TOS) - 2nd FLOOR
076328C-SI-89-E-XE-0005 1_V2
1
MAIN CONNECTION-PROTECTIVE EARTHING (PE) ORIG. SIZE: A1 SCALE: 1:50 PRE-FID REV: - SHEET: 4 OF 18