Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 20

1 2 3 4 5 6 7 8 9

Work
SL Job No./ PACKAGE Work Work Section Unit System Equipment
Number completion Equipment Tag#
NO. DCSM No. NUMBER Request # Order No. No. Description
priority

Piping

3-HBFW-110-3001-
DCSM0042 4 4 5 110
D1AS-HS

33
Joint: 007

B43A-DMW-112-
300 DCSM10005 4 4 5 112 3002-07

Joint: 002

B43A-DMW-112-
DCSM10007 4 4 5 112
3002-01

302
Joint: 001

B41R-MPS-110-
306 DCSM10012 4 4 5 110 3002-02

110-TT-007A
flange
leakage

18”-HHBFW-110-
DCSM2357 4 4 5 110 3007-P2AS-HS

548
DEMI WATER
SUPPLY
Valve 3/4 at 6-HPS- PUMPS
DCSM2358 4 4 5 102 102-0101-D1AS-HS TURBINE

549
Damper for
Raw Gas
Bypass
Outlet

550 DCSM2359 4 4 5 111 111-UV-6004


Sea Water
DCSM2360 4 4 5 104 104-Y-002C Screens and
Trash Racks

551
Piping

18-HHPS-113-3013-
562 DCSM2560 4 4 5 113
P0MS-HS

Piping

3’’-HHBFW-110-
1323 DCSM9934 4 4 5 110 4109-P2AS-HS

Piping

24-HHPS-113-3011-
DCSM9935 4 4 5 113 P0MS-HS

1324
Joint: 008

B43A-DMW-112-
1362 DCSM9981 4 4 5 112 3002-06

Joint: 006

B43A-DMW-112-
DCSM9982 4 4 5 112
3002-07

1363
DCSMA0224 4 M19165 6 155 155-A-001-V01A B C Jacketed
spray header

1454
Process

1462 DCSMA0244 4 M24455 6 152 C300-P-152-4206-01

24"-HHPS-110-
1621 DCSMA0572 4 M24494 5 110 3023-P0MS-HS (65 HHPS Header
joints-SCH 100)

Block valve
upstream of
pressure
transmitter

1624 DCSMA0577 4 M24616 5 102 102-PT-0026

welding joint

Welding point of
downstream of let
DCSMA0646 4 M24498 1E+09 5 110 down valve 110-PV-
0034

1655
DCSMA0694 4 M27100 5 112 112-UZV-0001
Inlet
1694 Vaporizer

Minor
Defect-Po:
B41A-CBH-110- 1.6mmØ
1695 DCSMA0695 4 M27101 5 110 3029-01. Joint 001 /
Thick5.54m
m

C100-MPS-141-
DCSMA0697 4 M27104 5 141 5108-69
1696

AG1R-SCW-141-
DCSMA0698 4 M27106 5 141 3013-08
1697

1836 DCSMA904 4 5 110

DCSMA905 4 5 123

1837

122-TT-8077ABC, - 122-E-108,
122-TT-8067ABC, 122-E-109,
122-TT-8087ABC,
20"-LPN-122-4129- 122-E-110)
- Outlet
DCSM10039 4 5 122 A2AA-NI, piping of
8"-HPN-122-4149- 122-E-108,
D1AA-NI,
6"-CCRN-122-4146- 122-E-109,
122-E-110
A2AA-NI

1876

DCSMA1103 4 M32767 5 102 102-P-001B

2124
DCSMA1109 4 M32518 5 110 110-A-003

2130
10 11 12 13 14 15 16

Equipmen Discipline
Job Description Work Category Initial Scope Priority Remark
t Type

110-DS-001 Coolant flange leakage - Remove the clamp.


- Cleaning the surface of flange.
SO-008 - Repair the damaged collant
Defect flange by rewelding and refacing.
MECHANIC Rectification Require Cutting and
Piping by - Reinstall. 1
AL Welding
NSRP

Repair welding defect during DCSM - Erect Scaffolding.


( Outstanding during WTFT). - Rremove Insulation (Protect
insulation from damage).
Defect - Cuting & Rewelding.
INSPECTIO Require Cutting and
Piping rectification by - NDE. 1
N - Reinstall insulation. Welding
NSRP
- Dismantle Scaffolding.

Repair welding defect during DCSM - Erect Scaffolding.


( Outstanding during WTFT). - Rremove Insulation (Protect
insulation from damage).
Defect - Cuting & Rewelding.
INSPECTIO Require Cutting and
Piping rectification by - NDE. 1
N NSRP - Reinstall insulation. Welding
- Dismantle Scaffolding.

Repair welding defect during DCSM - Erect Scaffolding.


( Outstanding during WTFT). - Rremove Insulation (Protect
insulation from damage).
Defect - Cuting & Rewelding.
INSPECTIO Require Cutting and
Piping rectification by - NDE. 1
N - Reinstall insulation. Welding
NSRP
- Dismantle Scaffolding.

110-TT-0007A flange leakage. - Remove the clamp


Temporary solution by online clamp. - Cleaning the surface of flange
Permanent solution need apply - Repair the damaged flange by
during SD: remove clamp, re facing rewelding and refacing.
flange, replace gasket. Defect - Reinstall.
MECHANIC Require Cutting and
Piping Rectification by 1
AL Welding
SO-019 NSRP

Drain valve HPS and MPS passing at - Replace with the new valve.
102-PST-001-A/B need to cut and
replace. Defect
Manual MECHANIC Rectification by Maybe require Cutting
1
Valve AL and Welding
NSRP

FGD 111-UV-6004 By pass damper - Open investigate root cause and


out let FGD abnormal sound and not repair
full open. Inside inspection need to
be carry out for verify whether
damaged or not. Repair method
need prepare in advance Defect
Damper MECHANIC Rectification by Require Cutting and
1
AL NSRP Welding
During normal operation we found
the rope of 104-Y-002C Track rack
o Inspection by diver to find out
broken down. At that time track rack the root cause of blocking
can not moving more. We TRASH MECHANIC Maybe require Cutting
Maintenance o Fix the broplem 1
suspect that stuck up far from RACKS AL and Welding
o Clean and repair the frame if
bottom to the top around 1.5 required
meter. Request to check inside by
diver.

STG No 01 Flange leakage. The - Open the Clamp.


Flange located at 113-FT-7115 - Bolt dismantle.
- Cutting to remove Flange.
SO-001 - Do the PT check the defect of
flange.
- Refacing Flange.
- Re-welding flange on the pipe.
- Replace new gaket and bolt
Defect tightening.
MECHANIC Rectification by - Install new insulation. Require Cutting and
Piping 1
AL - QCR record for Flange (including Welding
NSRP
flange reapair and blolt
tightening).

110-FE-6002 Leakage - Remove the clamp


- Cleaning the surface of flange
SO-008 - Repair the damaged collant
Defect flange by rewelding and refacing.
MECHANIC Rectification by - Reinstall. Require Cutting and
Piping 1
AL Welding
NSRP

STG No 04 Flange leakage. The - Open the Clamp.


Flange located at 113-FT-7415 - Bolt dismantle.
- Cutting to remove Flange.
SO-001 - Do the PT check the defect of
flange.
- Refacing Flange.
- Re-welding flange on the pipe.
- Replace new gaket and bolt
Defect tightening.
MECHANIC Rectification by - Install new insulation. Require Cutting and
Piping 1
AL - QCR record for Flange (including Welding
NSRP
flange reapair and blolt
tightening).

Repair welding defect during DCSM - Erect Scaffolding.


( Outstanding during WTFT). - Rremove Insulation (Protect
insulation from damage).
Defect - Cuting & Rewelding.
INSPECTIO Require Cutting and
Piping rectification by - NDE. 1
N - Reinstall insulation. Welding
NSRP
- Dismantle Scaffolding.

Repair welding defect during DCSM - Erect Scaffolding.


( Outstanding during WTFT). - Rremove Insulation (Protect
insulation from damage).
Defect - Cuting & Rewelding.
INSPECTIO Require Cutting and
Piping rectification by - NDE. 1
N - Reinstall insulation. Welding
NSRP
- Dismantle Scaffolding.
1) Remove Insulation around the
area
'2) remove 4"x2" jacket pipe
2) Cutting and remove the Drum
Sulphur Spray Header
Leak from nozzle connection of 3) Grind and Edge preparation as
'Jacketed spray header @ 155-A- MECHANIC Maintenance required Require Cutting and
Piping 1
001-V01A B C result in liquid sulfur AL 4) Weld as per WPS. visual check Welding
spread out to the open area and dimension check
4) NDE.
5) Reinstall jacket pipe and install
sulphur spray
6) reinstall Drum Sulphur Sray
Header insulation.

Repair welding seam for C300-P- 1) Bling as per Blind List


152-4206-01, joint 007 Defect 2) Cutting , Edge Preparation and
MECHANIC Rectification by Re-Weld. Require Cutting and
Piping 1
AL 3) NDE. Welding
NSRP

1) Erect scaffolding as required


2) Remove insulation at all the 65
joints are shown by Inspection
Team
3) Clean the joints with Wire brush
or buffing
4) Carry out PT for all the weld
joints(inspect weld cap)
Dec 2018 3 joint between spool 5) Carry out UT for all the
crack due to welding joint damaged. MECHANIC Defect welds( inspect the Fill, Root pass Maybe require Cutting
Request Inspection all other Piping Rectification by and Hot Pass) 1
AL and Welding
remaining welding joints. Repair in NSRP 6) Cut , Edge preparation and Re-
case fail inspection. Weld for joints confirmed by
Inspection as defects
7) Carry out UT for weld joints
8) Carry out PWHT for the weld
joints
9) Carry out UT again
10) Insulate all the joints
11) And Remove scaffolding

Block valve upstream of pressure


transmitter damage cannot operate. 1. Provide scaffolding
It need to cut and replace 2. Isolate the repair point
3. Cutting the damaged valve
Defect 4. Beveling
Manual MECHANIC Require Cutting and
Rectification by 5. Rewelding new valve 1
valve AL Welding
NSRP 6. NDE check after rewelding
7. De isolate the repair point

5S- HPS header HPS leak at 1. Isolate the repair point


downstream let down valve 110-PV- 2. Remove the online sealing
0034 clamp
3. cut the crack welding joint
4. Remove the spool by crane
5. Bevelling the flange and spool
6. Rewelding
Defect
Piping MECHANIC Rectification by 7. NDE confirm the welding joint 1 Require Cutting and
AL 8. Reinstall by crane Welding
NSRP 9. De isolate the repair point
Defect
Control MECHANIC Rectification Require Cutting and
by
valve AL Welding
NSRP
UZV plug welding

Defect
MECHANIC Rectification by Require Cutting and
Piping AL Welding
NSRP
Cut/WELD .

Defect
MECHANIC Require Cutting and
Piping Rectification by
AL Welding
NSRP
Cut/WELD .

Defect
MECHANIC Require Cutting and
Piping AL Rectification by Welding
NSRP
Cut/WELD .

1) Scaffolding work, remove


MECHANIC insulation Require Cutting and
Piping 1
AL 2) Blind as per Blind List Welding
3) Cutting , Edge Preparation and
Re-Weld.
Cut & Reweld weld joint at ISO No. Defect 4) NDE.
B41R-DKW-110-3001-04, Joint No. Rectification by 5) Deblind/Resintate
004 NSRP insulation/Dismantle scaffolding

1) Scaffolding work, remove


MECHANIC insulation Require Cutting and
Piping 1
AL 2) Blind as per Blind List Welding
3) Cutting , Edge Preparation and
Re-Weld.
Cut & Reweld weld joint at ISO No. Defect 4) NDE.
B32A-RFO-123-0002-02, Joint No. Rectification by 5) Deblind/Resintate
002 NSRP insulation/Dismantle scaffolding

- Replace 09 TW/TE sets of 122-TT-


8077ABC, 122-TT-8067ABC, 122-TT-
8087ABC by TW/TE sets with extend
length of 500mm 1. Isolate nitrogen vaporizers and
- Install 09 new TT sets at vaporizer outlet pipes
outlet line. Use 2oo3 voting 2. Depressure
connecting to PUCS to close PV Heat 3. Install additional TTs at
control valves @ vaporizers inlet Require Cutting and
when low temp. @ outlet also stop exchanger MECH Project vaporizer outline lines Welding
/Piping 4. Replace existing TW/TE by
HPN pumps. extended length TW/TE
-Use soft Hand Switch at DCS graphic 5. Modify control system (PUCS,
and Local HMI for operator to select
any signal from existing TT and 03 DCS)
new installed TTs @ vaporizer outlet
for control

welding joint cracked, 3/4", in MPS MECHANIC Require Cutting and


Piping Maintenance
bypass line AL Welding
HHPS drain pot line at boiler #3 is MECHANIC
Piping Maintenance
leaking, remove clamp and repair AL

Require Cutting and


Welding
17 17 18 19

Met Comment Class Base metal Thckness Weld type NDE GW Execution by Originator Initiated Date

1.PT
Flange overlay D1AS A106-B t7.62 OVL Not required
2.MT

1.PT
Pipe cut and 2.PT
A0JW A312-304 t3.05 BW GW
weld 3.PT
4.RT

1.PT
Pipe cut and 2.PT
A0LW A312-304 t3.05 BW GW
weld 3.PT
4.RT

1.PT
Files not 2.MT
B1AS A106-B t7.8 BW GW
opened 3.MT
4.RT

Flange weld 1.PT


P2AS A216-WCB OVL Not required
and reface 2.MT

1.PT
Valve cut and 2.MT
D1AS A106-B t3.91 BW GW
repair 3.MT
4.RT

Alloy 6XN(UNS
08367)- Alloy Alloy
6XN(UNS 6XN(UNS 1. PT
08367) FW Not required
Alloy 6XN(UNS 08367)- 2. PMI
ALLOY 926
08367)- ALLOY
926
Material of 1.PT
trash racks 1.4404 OVL Not required
2.PT
frame 316L

1.PT
2.PT
Which flange? 3.RT
A358-347-
on 24" or FT P0MS t29.36 OVL 4.PT GW
1
flange? 5.FN
6PMI
7.RT/UT

Flange weld 1.PT


P2AS A105 t31.75 OVL Not required
and reface 2.MT

1.PT
2.PT
Which flange? 3.RT
A358-347- t38
on 24" or FT P0MS OVL 4.PT GW
1
flange? 5.FN
6PMI
7.RT/UT

1.PT
Cut and weld 2.PT
A0JW A312-304 t3.05 BW GW
pipe 3.PT
4.RT

1.PT
Isometric 2.PT
A0JW A312-304 t3.05 BW GW
missing? 3.PT
4.RT
How many 1.PT
locations? 2.PT
A106-B t7 BW GW Le Minh Cuong 2-Jan-19
Cals based on 3.PT
1 joint 4.RT

1.PT
Cut and repair 2.MT
A1AP A106-B t5.49 OVL GW 7-Jan-19
pipe 3.MT
4.RT
Tran Quang Khai

1.PT
2.PT
3.RT
No PWHT A358-347- t38
P0MS BW 4.PT GW Le The Manh 30-Jan-19
required 1 5.FN
6PMI
7.RT/UT

1.PT
2.MT
B1AS A106-B t5.54 BW GW 30-Jan-19
3.MT
4.RT

Le The Manh

1.PT
Cut and repair B1AS A106-B t7.92 BW 2.MT GW 20-Mar-19
pipe 3.MT
4.RT

Chu Sy Thanh
LTCS,-50deg D1GP A352 LCC FW 1.PT Not required 30-May-2019
Le The Manh

1.PT
2.MT
A2AP A106-B t5.54 BW GW 30-May-2019
3.MT
4.RT
Tran Quang Kha
1.PT
2.MT
B1AS A106-B t12.7 BW GW 30-May-2019
3.MT
4.RT
Tran Quang Kha
1.PT
2.MT
A2AS A106-B t7.8 BW 3.MT GW 30-May-2019
4.RT
Tran Quang Kha

1.PT
2.PT
A0LW A312-316 t3.05 BW 3.PT GW 43615
4.PMI
5.RT

Tran Quang Kha

1.PT
2.MT
A1AD A106-B t7.11 BW GW 43615
3.MT
4.RT

Tran Quang Kha

- MOC will be
prepared 1.PT
'- Urgent 2.MT DCSM
procurement A2AA A106-B BW GW
3.MT CONTRACTOR
for TT and
surplus is on-
going

1. PT
2. MT
B1AS A106 Gr.B t3.91 BW GW
3. MT
4. RT
1. PT
2. MT
3. MT
4. RT
5. PWHT
Pre heat min 200 M5IPNC A335 P91 t5 BW GW
6.MT
7. RT
8. Hardness T
20 21 22 23 24 25 26 27 28 29

Blinding Schedule(P6)
DN NUMBER P& ID number Required Line Numbers Inlet Size Inlet rating Outlet Size Outlet rating Job Scope status
YES/NO

D-110-1225- 3"-HBFW-110-
0006S S2
3001-D1AS-HS

DN-03307-S

D-112-1225-
3 A0JW S2
0006S

D-112-1225- 3 A0JW S2
0006S

110-3003S 18 B1AS S2

18”-HHBFW-
D-110-1225-
110-3007- S2
0001S P2AS-HS

D-102-1225-
6"-HPS-102-
0003S 0.75 0 S2
0101-D1AS-HS

#N/A #N/A S2
#N/A S2

VS2158-412-A- 18"-HHPS-113-
247 S2
3013-P0MS-HS

3’’-HHBFW-
VS215B-001- 110-4109- S2
A-063 P2AS-HS

VS2158-412-A-
247 24"-HHPS-113- S2
3011-P0MS-HS

D-112-1225- 3" A0JW A0JW S2


0006S

D-112-1225- 3" A0JW A0JW S2


0006S
VG215A-101-A-007 3"X2"-P-155-1104-CSJ-SJ CORRECTIVE M #N/A

3"-P-152-4206-
D-152-1225-0042G
A1AP-NI
CORRECTIVE M S1

24''-HHPS-
D-110-1225- 110-3023- PREVENTIVE M S1
3002S P0MS-HS

3/4"#300

D-102-1225-1001S 12"-MPS-102-0 REPLACEMENT S1

D-110-1225- 16"-HPS-110-
0006S 0453-D1AS-HS

S1
D-112-1225- 6''
0001S 6"-P-112-
3019-D1GP-NI #N/A

D-110-1225- 2''
3009S
2"-CBH-110-
3029-A2AP-NI #N/A

D-141-1225-
3503G
30"-MPS-141-
5108-B1AS-HS #N/A

141-3005S,
~3008S
8"-SCW-141-
3013-A2AS-NI #N/A

3" #N/A

6" #N/A

#N/A

You might also like