CSU SHUTDOWN 2019

Team
No Item Start Finish Duration
CTR

1 8478627 INS-VES F-6410B/IN-MAJ ( Filter) 26-Nov 28-Nov 3 MEINDO-1


Spading 26-Nov 26-Nov 1 Supervisor : 1
Open Closure and Internal cleaning 26-Nov 26-Nov 1 Fitter : 1
Assist for inspection 27-Nov 27-Nov 1 Safety : 1
Close Closure and De-spading 28-Nov 28-Nov 1 Helper : 4
Scaffolder : 2
2 8477828 INS-VES A-6360/IN-MAJ ( Gas Cooler) 24-Nov 1-Dec 8
Spading 24-Nov 25-Nov 2
Open Plug and Internal cleaning 25-Nov 26-Nov 2
Assist for inspection 26-Nov 28-Nov 3
Close Plug 29-Nov 30-Nov 2
De-spading 30-Nov 1-Dec 2

3 8477829 INS-VES A-6380/IN-MAJ ( Condensate Cooler) 24-Nov 1-Dec 8


Spading 24-Nov 25-Nov 2
Open Plug and Internal cleaning 25-Nov 26-Nov 2
Assist for inspection 26-Nov 28-Nov 3
Close Plug 29-Nov 30-Nov 2
De-spading 30-Nov 1-Dec 2

4 8477741 INS-VES D-6430/IN-MAJ ( Oily Water system Close Drain 24-Nov 1-Dec 8 MEINDO-2
Spading and open manhole 24-Nov 25-Nov 2 Supervisor : 1
Internal cleaning 26-Nov 28-Nov 3 Fitter : 1 Confined space
Assist for inspection 28-Nov 29-Nov 2 Safety : 1 requirement
Repair (if any) 29-Nov 30-Nov 2 Helper : 4
Closed manhole & de-spading 30-Nov 1-Dec 2 Scaffolder : 1

5 8477742 INS-VES E-6160/IN-MAJ ( Feed Preheater) 24-Nov 30-Nov 7 Arung-1


Spading and open manhole 24-Nov 25-Nov 2 Supervisor : 1
Internal cleaning 25-Nov 26-Nov 2 Fitter : 1
Assist for inspection 26-Nov 28-Nov 3 Safety : 1
CSU SHUTDOWN 2019

Team
No Item Start Finish Duration
CTR
Repair (if any) 28-Nov 30-Nov 3 Helper : 4
Closed manhole & de-spading 29-Nov 30-Nov 2 Scaffolder : 1

6 8441580 INS-VES D-6440/IN-MAJ ( Flare Ko Drum) 24-Nov 1-Dec 8 MENDO-3


Open insulation at spading point and manhole area. 24-Nov 24-Nov 1 Supervisor : 1
Spading and open manhole 24-Nov 25-Nov 2 Fitter : 1 Confined space
Internal cleaning 25-Nov 26-Nov 2 Safety : 1 requirement
Assist for inspection 26-Nov 27-Nov 2 Helper : 3
Repair (if any) 27-Nov 28-Nov 2
Closed manhole & de-spading 28-Nov 29-Nov 2

7 8477830 INS-VES D-6200/IN-MAJ ( Water Condensate Separator) 24-Nov 2-Dec 9 Arung-2 Arung-3
Spading and open Manhole 24-Nov 25-Nov 2 Supervisor : 1 Supervisor : 1
Turbexing and Internal cleaning 25-Nov 29-Nov 5 Fitter : 1 Fitter : 1
Install scafolding 29-Nov 29-Nov 1 Safety : 1 Safety : 1
Assist for inspection 29-Nov 30-Nov 2 Helper : 4 Helper : 4
Repair (if any) 30-Nov 2-Dec 3 Scaffolder : 1 Scaffolder : 1

Assist for inspection after repair 30-Nov 1-Dec 2


Confined space Confined space
Remove scafolding 1-Dec 1-Dec 1 requirement requirement
Closed manhole & de-spading 1-Dec 2-Dec 2
CSU SHUTDOWN 2019

Team
No Item Start Finish Duration
CTR
8 8443232 INS-FLARE FL-6450A/IN-MAJ ( Flare Package) 24-Nov 29-Nov 6 Arung-4
Spading 24-Nov 25-Nov 2 Foreman : 1
Assist for inspection 26-Nov 27-Nov 2 Fitter : 1
Repair (if any) 27-Nov 28-Nov 2 Safety : 1
Closed manhole & de-spading 28-Nov 29-Nov 2 Helper : 3

9 8441581 INS-VES D-6455/IN-MAJ ( Water Seal Drum) 24-Nov 1-Dec 8 Arung-5


Spading and open manhole 24-Nov 25-Nov 2 Supervisor : 1
Internal cleaning 25-Nov 28-Nov 4 Fitter : 1 Confined space
Assist for inspection 28-Nov 29-Nov 2 Safety : 1 requirement
Repair (if any) 29-Nov 30-Nov 2 Helper : 4
Closed manhole & de-spading 30-Nov 1-Dec 2

10 7243187 INS-PIP-REP_2" Drain of 20-DR-B03-6326 24-Nov 2-Dec 9 Arung-6


Spading activity 24-Nov 25-Nov 2 Supervisor : 1
Cold cutting 26-Nov 27-Nov 1 Fitter : 1
Cleaning and install rubber plug 27-Nov 28-Nov 2 Safety : 1
Install new spool and NDT 28-Nov 30-Nov 3 Welder : 2
Depasading 1-Dec 2-Dec 2 Helper : 5

11 8478280 INS-VES V-870/IN-MAJ ( 2nd stage Separator) 24-Nov 2-Dec 9 Arung-11 Arung-12
Spading and open Manhole 24-Nov 25-Nov 2 Supervisor : 1 Supervisor : 1
Turbexing and Internal cleaning 25-Nov 29-Nov 5 Fitter : 1 Fitter : 1
Install scafolding 29-Nov 29-Nov 1 Safety : 1 Safety : 1
Assist for inspection 29-Nov 1-Dec 3 Helper : 5 Helper : 5
Repair (if any) 1-Dec 3-Dec 3
Assist for inspection after repair 3-Dec 4-Dec 2
Remove scafolding 1-Dec 1-Dec 1
Closed manhole & de-spading 1-Dec 2-Dec 2
U SHUTDOWN 2019

Team Date
CST 11/23 11/24 11/25 11/26 11/27 11/28 11/29 11/30 12/1 12/2 12/3

0 0 0 110 110 110 0 0 0 0 0


0 0 0 110 0 0 0 0 0 0 0
0 0 0 110 0 0 0 0 0 0 0
0 0 0 0 110 0 0 0 0 0 0
0 0 0 0 0 110 0 0 0 0 0
0 0 0 0 0 0 0 0 0 0 0
0 110 110 110 110 110 110 110 110 0 0
0 110 110 0 0 0 0 0 0 0 0
0 0 110 110 0 0 0 0 0 0 0
Anto
0 0 0 110 110 110 0 0 0 0 0
Sriwijayanto
0 0 0 0 0 0 110 110 0 0 0
0 0 0 0 0 0 0 110 110 0 0
0 0 0 0 0 0 0 0 0 0 0
0 110 110 110 110 110 110 110 110 0 0
0 110 110 0 0 0 0 0 0 0 0
0 0 110 110 0 0 0 0 0 0 0
0 0 0 110 110 110 0 0 0 0 0
0 0 0 0 0 0 110 110 0 0 0
0 0 0 0 0 0 0 110 110 0 0
0 0 0 0 0 0 0 0 0 0 0
0 110 110 110 110 110 110 110 110 0 0
0 110 110 0 0 0 0 0 0 0 0
0 0 0 110 110 110 0 0 0 0 0
Akbar
0 0 0 0 0 110 110 0 0 0 0
0 0 0 0 0 0 110 110 0 0 0
0 0 0 0 0 0 0 110 110 0 0

0 110 110 110 110 110 110 110 0 0 0


0 110 110 0 0 0 0 0 0 0 0
0 0 110 110 0 0 0 0 0 0 0
Chirul Anam
0 0 0 110 110 110 0 0 0 0 0
U SHUTDOWN 2019

Team Date
Chirul Anam
CST 11/23 11/24 11/25 11/26 11/27 11/28 11/29 11/30 12/1 12/2 12/3

0 0 0 0 0 110 110 110 0 0 0


0 0 0 0 0 0 110 110 0 0 0

0 110 110 110 110 110 110 110 110 0 0


110 0 0 0 0 0 0 0 0 0
0 110 110 0 0 0 0 0 0 0 0
Heriwanto 0 0 110 110 0 0 0 0 0 0 0
0 0 0 110 110 0 0 0 0 0 0
0 0 0 0 110 110 0 0 0 0 0
0 0 0 0 0 110 110 0 0 0 0

0 110 110 110 110 110 110 110 110 110 0


0 110 110 0 0 0 0 0 0 0 0
0 0 110 110 110 110 110 0 0 0 0
0 0 0 0 0 0 110 0 0 0 0

Rinaldi / Ari 0 0 0 0 0 0 110 110 0 0 0


Gunawan 0 0 0 0 0 0 0 110 110 110 0

0 0 0 0 0 0 0 110 110 0 0

0 0 0 0 0 0 0 0 110 0 0
0 0 0 0 0 0 0 0 110 110 0
0 0 0 0 0 0 0 0 0 0 0
U SHUTDOWN 2019

Team Date
CST 11/23 11/24 11/25 11/26 11/27 11/28 11/29 11/30 12/1 12/2 12/3

0 110 110 110 110 110 110 0 0 0 0


0 110 110 0 0 0 0 0 0 0 0
Haeromi 0 0 0 110 110 0 0 0 0 0 0
0 0 0 0 110 110 0 0 0 0 0
0 0 0 0 0 110 110 0 0 0 0

0 110 110 110 110 110 110 110 110 0 0


0 110 110 0 0 0 0 0 0 0 0
0 0 110 110 110 110 0 0 0 0 0
Supadiono
0 0 0 0 0 110 110 0 0 0 0
0 0 0 0 0 0 110 110 0 0 0
0 0 0 0 0 0 0 110 110 0 0
0 0 0 0 0 0 0 0 0 0 0
0 110 110 110 110 110 110 110 110 110 0
0 110 110 0 0 0 0 0 0 0 0
0 0 0 110 110 0 0 0 0 0 0
Gede Andi D
0 0 0 0 110 110 0 0 0 0 0
0 0 0 0 0 110 110 110 0 0 0
0 0 0 0 0 0 0 0 110 110 0
0 0 0 0 0 0 0 0 0 0 0
0 110 110 110 110 110 110 110 110 110 0
0 110 110 0 0 0 0 0 0 0 0
0 0 110 110 110 110 110 0 0 0 0
0 0 0 0 0 0 110 0 0 0 0
CST Mech-09 / CST
0 0 0 0 0 0 110 110 110 0 0
Mech-10
0 0 0 0 0 0 0 0 110 110 110
0 0 0 0 0 0 0 0 0 0 110
0 0 0 0 0 0 0 0 110 0 0
0 0 0 0 0 0 0 0 110 110 0
0 0 0 0 0 0 0 0 0 0 0
CSU SHUTDOWN 2019

Team Da
No Item Start Finish Duration
CTR 11/23 11/24 11/25 11/26

1 8478627 INS-VES F-6410B/IN-MAJ ( Filter) 26-Nov 28-Nov 3 0 0 0 110


Spading 26-Nov 26-Nov 1 0 0 0 110
Open Closure and Internal cleaning 26-Nov 26-Nov 1 0 0 0 110
Assist for inspection 27-Nov 27-Nov 1 0 0 0 0
Close Closure and De-spading 28-Nov 28-Nov 1 0 0 0 0
0 0 0 0
2 8477828 INS-VES A-6360/IN-MAJ ( Gas Cooler) 24-Nov 1-Dec 8 0 110 110 110
Spading 24-Nov 25-Nov 2 0 110 110 0
Open Plug and Internal cleaning 25-Nov 26-Nov 2 0 0 110 110
Assist for inspection 26-Nov 28-Nov 3 MEINDO-1 0 0 0 110
Close Plug 29-Nov 30-Nov 2 0 0 0 0
De-spading 30-Nov 1-Dec 2 0 0 0 0
0 0 0 0
3 8477829 INS-VES A-6380/IN-MAJ ( Condensate Cooler) 24-Nov 1-Dec 8 0 110 110 110
Spading 24-Nov 25-Nov 2 0 110 110 0
Open Plug and Internal cleaning 25-Nov 26-Nov 2 0 0 110 110
Assist for inspection 26-Nov 28-Nov 3 0 0 0 110
Close Plug 29-Nov 30-Nov 2 0 0 0 0
De-spading 30-Nov 1-Dec 2 0 0 0 0
0 0 0 0
4 8477741 INS-VES D-6430/IN-MAJ ( Oily Water system Close Drain 24-Nov 1-Dec 8 0 110 110 110
Spading and open manhole 24-Nov 25-Nov 2 0 110 110 0
Internal cleaning 26-Nov 28-Nov 3 0 0 0 110
MEINDO-2
Assist for inspection 28-Nov 29-Nov 2 0 0 0 0
Repair (if any) 29-Nov 30-Nov 2 0 0 0 0
Closed manhole & de-spading 30-Nov 1-Dec 2 0 0 0 0

5 8441580 INS-VES D-6440/IN-MAJ ( Flare Ko Drum) 24-Nov 1-Dec 8 0 110 110 110
Open insulation at spading point and manhole area. 24-Nov 24-Nov 1 110 0 0
Spading and open manhole 24-Nov 25-Nov 2 0 110 110 0
MENDO-3
CSU SHUTDOWN 2019

Team Da
No Item Start Finish Duration
CTR 11/23 11/24 11/25 11/26

Internal cleaning 25-Nov 26-Nov 2 MENDO-3 0 0 110 110


Assist for inspection 26-Nov 27-Nov 2 0 0 0 110
Repair (if any) 27-Nov 28-Nov 2 0 0 0 0
Closed manhole & de-spading 28-Nov 29-Nov 2 0 0 0 0
HUTDOWN 2019

Date
11/27 11/28 11/29 11/30 12/1 12/7

110 110 0 0 0 0
0 0 0 0 0 0
0 0 0 0 0 0
110 0 0 0 0 0
0 110 0 0 0 0
0 0 0 0 0 0
110 110 110 110 110 0
0 0 0 0 0 0
0 0 0 0 0 0
110 110 0 0 0 0
0 0 110 110 0 0
0 0 0 110 110 0
0 0 0 0 0 0
110 110 110 110 110 0
0 0 0 0 0 0
0 0 0 0 0 0
110 110 0 0 0 0
0 0 110 110 0 0
0 0 0 110 110 0
0 0 0 0 0 0
110 110 110 110 110 0
0 0 0 0 0 0
110 110 0 0 0 0
0 110 110 0 0 0
0 0 110 110 0 0
0 0 0 110 110 0

110 110 110 110 110 0


0 0 0 0 0 0
0 0 0 0 0 0
HUTDOWN 2019

Date
11/27 11/28 11/29 11/30 12/1 12/7

0 0 0 0 0 0
110 0 0 0 0 0
110 110 0 0 0 0
0 110 110 0 0 0
CSU SHUTDOWN 2019

No Item Start Finish

1 8478627 INS-VES F-6410B/IN-MAJ ( Filter) 26-Nov 28-Nov


Spading 26-Nov 26-Nov
Open Closure and Internal cleaning 26-Nov 26-Nov
Assist for inspection 27-Nov 27-Nov
Close Closure and De-spading 28-Nov 28-Nov

1 8478627 INS-VES F-6410B/IN-MAJ ( Filter) 2-Dec 4-Dec


Spading 2-Dec 2-Dec
Open Closure and Internal cleaning 2-Dec 2-Dec
Assist for inspection 3-Dec 3-Dec
Close Closure and De-spading 4-Dec 4-Dec

2 8477828 INS-VES A-6360/IN-MAJ ( Gas Cooler) 24-Nov 1-Dec


Spading 24-Nov 25-Nov
Open Plug and Internal cleaning 25-Nov 26-Nov
Assist for inspection 26-Nov 28-Nov
Close Plug 29-Nov 30-Nov
De-spading 30-Nov 1-Dec

2 8477828 INS-VES A-6360/IN-MAJ ( Gas Cooler) 24-Nov 1-Dec


Spading 24-Nov 25-Nov
Open Plug and Internal cleaning 25-Nov 26-Nov
Assist for inspection 26-Nov 28-Nov
Close Plug 29-Nov 30-Nov
De-spading 30-Nov 1-Dec

3 8477829 INS-VES A-6380/IN-MAJ ( Condensate Cooler) 24-Nov 1-Dec


Spading 24-Nov 25-Nov
Open Plug and Internal cleaning 25-Nov 26-Nov
Assist for inspection 26-Nov 28-Nov
Close Plug 29-Nov 30-Nov
De-spading 30-Nov 1-Dec

3 8477829 INS-VES A-6380/IN-MAJ ( Condensate Cooler) 24-Nov 1-Dec


Spading 24-Nov 25-Nov
Open Plug and Internal cleaning 25-Nov 26-Nov
Assist for inspection 26-Nov 28-Nov
Close Plug 29-Nov 30-Nov
De-spading 30-Nov 1-Dec

4 8477741 INS-VES D-6430/IN-MAJ ( Oily Water system Close Drain 24-Nov 1-Dec
Spading and open manhole 24-Nov 25-Nov
Internal cleaning 26-Nov 28-Nov
Assist for inspection 28-Nov 29-Nov
Repair (if any) 29-Nov 30-Nov
Closed manhole & de-spading 30-Nov 1-Dec
CSU SHUTDOWN 2019

No Item Start Finish


4 8477741 INS-VES D-6430/IN-MAJ ( Oily Water system Close Drain 24-Nov 1-Dec
Spading and open manhole 24-Nov 25-Nov
Internal cleaning 26-Nov 28-Nov
Assist for inspection 28-Nov 29-Nov
Repair (if any) 29-Nov 30-Nov
Closed manhole & de-spading 30-Nov 1-Dec

4A xxxxxxx INTERNAL COATING AT D-6430 ( if Any) 1-Dec 5-Dec


Blasting and primer 1-Dec 2-Dec
Paintiing Top Coat 3-Dec 4-Dec
Curing Time 5-Dec 5-Dec

4A 7154893 INTERNAL COATING AT D-6430 18-Nov 20-Nov


Blasting and primer 18-Nov 18-Nov
Paintiing Top Coat 19-Nov 19-Nov
Curing Time 20-Nov 20-Nov

5 8477742 INS-VES E-6160/IN-MAJ ( Feed Preheater) 24-Nov 30-Nov


Spading and open manhole 24-Nov 25-Nov
Internal cleaning 25-Nov 26-Nov
Assist for inspection 26-Nov 28-Nov
Repair (if any) 28-Nov 30-Nov
Closed manhole & de-spading 29-Nov 30-Nov

5 8477742 INS-VES E-6160/IN-MAJ ( Feed Preheater) 24-Nov 30-Nov


Spading and open manhole 24-Nov 25-Nov
Internal cleaning 25-Nov 26-Nov
Assist for inspection 26-Nov 28-Nov
Repair (if any) 28-Nov 30-Nov
Closed manhole & de-spading 29-Nov 30-Nov

6 8441580 INS-VES D-6440/IN-MAJ ( Flare Ko Drum) 24-Nov 1-Dec


Open insulation at spading point and manhole area. 24-Nov 24-Nov
Spading and open manhole 24-Nov 25-Nov
Internal cleaning 25-Nov 26-Nov
Assist for inspection 26-Nov 27-Nov
Repair (if any) 27-Nov 28-Nov
Closed manhole & de-spading 28-Nov 29-Nov
CSU SHUTDOWN 2019

No Item Start Finish


6 8441580 INS-VES D-6440/IN-MAJ ( Flare Ko Drum) 24-Nov 1-Dec
Open insulation at spading point and manhole area. 24-Nov 24-Nov
Spading and open manhole 24-Nov 25-Nov
Internal cleaning 25-Nov 26-Nov
Assist for inspection 26-Nov 27-Nov
Repair (if any) 27-Nov 28-Nov
Closed manhole & de-spading 28-Nov 29-Nov

7 8477830 INS-VES D-6200/IN-MAJ ( Water Condensate Separator) 24-Nov 2-Dec


Spading and open Manhole 24-Nov 25-Nov
Turbexing and Internal cleaning 25-Nov 29-Nov
Install scafolding 29-Nov 29-Nov
Assist for inspection 29-Nov 30-Nov
Repair (if any) 30-Nov 2-Dec
Assist for inspection after repair 30-Nov 1-Dec
Remove scafolding 1-Dec 1-Dec
Closed manhole & de-spading 1-Dec 2-Dec

7 8477830 INS-VES D-6200/IN-MAJ ( Water Condensate Separator) 24-Nov 2-Dec


Spading and open Manhole 24-Nov 25-Nov
Turbexing and Internal cleaning 25-Nov 29-Nov
Install scafolding 29-Nov 29-Nov
Assist for inspection 29-Nov 30-Nov
Repair (if any) 30-Nov 2-Dec
Assist for inspection after repair 30-Nov 1-Dec
Remove scafolding 1-Dec 1-Dec
Closed manhole & de-spading 1-Dec 2-Dec

8 8443232 INS-FLARE FL-6450A/IN-MAJ ( Flare Package) 24-Nov 29-Nov


Spading 24-Nov 25-Nov
Assist for inspection 26-Nov 27-Nov
Repair (if any) 27-Nov 28-Nov
Closed manhole & de-spading 28-Nov 29-Nov

8 8443232 INS-FLARE FL-6450A/IN-MAJ ( Flare Package) 24-Nov 29-Nov


Spading 24-Nov 25-Nov
Assist for inspection 26-Nov 27-Nov
Repair (if any) 27-Nov 28-Nov
Closed manhole & de-spading 28-Nov 29-Nov

9 8441581 INS-VES D-6455/IN-MAJ ( Water Seal Drum) 24-Nov 1-Dec


Spading and open manhole 24-Nov 25-Nov
Internal cleaning 25-Nov 28-Nov
Assist for inspection 28-Nov 29-Nov
Repair (if any) 29-Nov 30-Nov
Closed manhole & de-spading 30-Nov 1-Dec

9 8441581 INS-VES D-6455/IN-MAJ ( Water Seal Drum) 24-Nov 1-Dec


CSU SHUTDOWN 2019

No Item Start Finish


Spading and open manhole 24-Nov 25-Nov
Internal cleaning 25-Nov 28-Nov
Assist for inspection 28-Nov 29-Nov
Repair (if any) 29-Nov 30-Nov
Closed manhole & de-spading 30-Nov 1-Dec

10 7243187 INS-PIP-REP_2" Drain of 20-DR-B03-6326 24-Nov 2-Dec


Spading activity 24-Nov 25-Nov
Cold cutting 26-Nov 27-Nov
Cleaning and install rubber plug 27-Nov 28-Nov
Install new spool and NDT 28-Nov 30-Nov
Depasading 1-Dec 2-Dec

10 7243187 INS-PIP-REP_2" Drain of 20-DR-B03-6326 24-Nov 2-Dec


Spading activity 24-Nov 25-Nov
Cold cutting 26-Nov 27-Nov
Cleaning and install rubber plug 27-Nov 28-Nov
Install new spool and NDT 28-Nov 30-Nov
Depasading 1-Dec 2-Dec

11 8478280 INS-VES V-870/IN-MAJ ( 2nd stage Separator) 24-Nov 2-Dec


Spading and open Manhole 24-Nov 25-Nov
Turbexing and Internal cleaning 25-Nov 29-Nov
Install scafolding 29-Nov 29-Nov
Assist for inspection 29-Nov 1-Dec
Repair (if any) 1-Dec 3-Dec
Assist for inspection after repair 3-Dec 4-Dec
Remove scafolding 1-Dec 1-Dec
Closed manhole & de-spading 1-Dec 2-Dec

11 8478280 INS-VES V-870/IN-MAJ ( 2nd stage Separator) 24-Nov 2-Dec


Spading and open Manhole 24-Nov 25-Nov
Turbexing and Internal cleaning 25-Nov 29-Nov
Install scafolding 29-Nov 29-Nov
Assist for inspection 29-Nov 1-Dec
Repair (if any) 1-Dec 3-Dec
Assist for inspection after repair 3-Dec 4-Dec
Remove scafolding 1-Dec 1-Dec
Closed manhole & de-spading 1-Dec 2-Dec
Team Date
Duration
CTR CST 11/23 11/24 11/25 11/26 11/27 11/28 11/29

3 Arung-1 0 0 0 110 110 110 0


1 Fitter : 1 0 0 0 110 0 0 0
1 Safety : 1 0 0 0 110 0 0 0
1 Helper : 3 0 0 0 0 110 0 0
1 0 0 0 0 0 110 0
0 0 0 0 0 0 0
1 0 0 0 0 0 0 0
1 0 0 0 0 0 0 0
1 0 0 0 0 0 0 0
1 0 0 0 0 0
( No Repair)
1 0 0 0 0 0

8 0 110 110 110 110 110 110


2 0 110 110 0 0 0 0
2 0 0 110 110 0 0 0
3 0 0 0 110 110 110 0
CST Mech 1
2 0 0 0 0 0 0 110
2 0 0 0 0 0 0 0
0 0 0 0 0 0 0
8 0 100 100 100 100 100 100
2 0 100 100 0 0 0 0
2 0 0 100 100 0 0 0
3 0 0 0 100 100
( No Repair)
2 0 0 0 0 0
2 0 0 0 0 0 0 0
0 0 0 0 0 0 0
8 0 110 110 110 110 110 110
2 0 110 110 0 0 0 0
2 0 0 110 110 0 0 0
3 0 0 0 110 110 110 0
2 0 0 0 0 0 0 110
2 0 0 0 0 0 0 0
0 0 0 0 0 0 0
8 0 100 100 100 100 100 100
2 0 100 100 0 0 0 0
2 0 0 100 100 0 0 0
3 0 0 0 100 100
( No Repair)
2 0 0 0 0 0
2 0 0 0 0 0 0 0
0 0 0 0 0 0 0
8 Arung 2 0 110 110 110 110 110 110
2 Supervisor : 1 0 110 110 0 0 0 0
3 Fitter : 1 0 0 0 110 110 110 0
2 Safety : 1 0 0 0 0 0 110 110
2 Helper : 4 0 0 0 0 0 0 110
2 Scaffolder : 1 0 0 0 0 0 0 0
Team Date
Duration
CTR CST 11/23 11/24 11/25 11/26 11/27 11/28 11/29

8 0 100 100 100 100 100 100


2 0 100 100 0 0 0 0
CST Mech-2
3 0 0 0 100 100 100 0
2 0 0 0 0 0 100 100
2 0 0 ( No Repair) 0 100
2 0 0 0 0 0 0 0
0 0 0 0 0 0 0
5 0
1 0 0 0 0 0 0 0
2 0 0 0 0 0 0 0
1

3 DMG PAINTING-3 0 0 0 0 0 0 0
1 0 0 0 0 0 0 0
2 0 0 0 0 0 0 0
1 0 0 0 0 0 0 0
0 0 0 0 0 0 0
7 Arung-3 0 110 110 110 110 110 110
2 Supervisor : 1 0 110 110 0 0 0 0
2 Fitter : 1 0 0 110 110 0 0 0
CST Mech-3
3 Safety : 1 0 0 0 110 110 110 0
3 Helper : 4 0 0 0 0 0 110 110
2 Scaffolder : 1 0 0 0 0 0 0 110

7 0 110 110 110 110 110 110


2 0 110 110 0 0 0 0
2 0 0 110 110 0 0 0
CST Mech-3
3 0 0 0 110 110 110 0
3 0 0 0 0 0 110 110
2 0 0 0 0 0 0 110

8 Arung-4 0 110 110 110 110 110 110


1 Supervisor : 1 110 0 0 0 0 0
2 Fitter : 1 0 110 110 0 0 0 0
2 Safety : 1 CST E/I - 1 0 0 110 110 0 0 0
2 Helper : 3 0 0 0 110 110 0 0
2 0 0 0 0 110 110 0
2 0 0 0 0 0 110 110
Team Date
Duration
CTR CST 11/23 11/24 11/25 11/26 11/27 11/28 11/29

8 0 100 100 100 100 100 100


1 0 100 0 0 0 0 0
2 0 100 100 0 0 0 0
2 0 0 100 100 0 0 0
2 0 0 0 100 ( No Repair)
2 0 0 0 0 100 100 0
2 0 0 0 0 0 100 100

9 Arung-5 Arung-6 0 110 110 110 110 110 110


2 Supervisor : 1 Supervisor : 1 0 110 110 0 0 0 0
5 Fitter : 1 Fitter : 1 0 0 110 110 110 110 110
1 Safety : 1 Safety : 1 0 0 0 0 0 0 110
2 Helper : 4 Helper : 4 CST Mech-4/5 0 0 0 0 0 0 110
3 Scaffolder : 1 Scaffolder : 1 0 0 0 0 0 0 0
2 0 0 0 0 0 0 0
1 0 0 0 0 0 0 0
2 0 0 0 0 0 0 0
DNG-5 Anji /Jarot
0 0 0 0 0 0 0
(day) (day shift)
9 0 100 100 100 100 100 100
DMG-6 Ari G
2 (night shift) 0 100 100 0 0 0 0
(night)
5 0 0 100 100 100 100 100
1 0 0 0 0 0 0 100
2 0 0 0 0 0 0 100
3 0 0 0 0
( No Repair)
2 0 0 0 0
1 0 0 0 0 0 0 0
2 0 0 0 0 0 0 0
0 0 0 0 0 0 0
6 Arung-7 0 110 110 110 110 110 110
2 Foreman : 1 0 110 110 0 0 0 0
2 Fitter : 1 CST E/I -2 0 0 0 110 110 0 0
2 Safety : 1 0 0 0 0 110 110 0
2 Helper : 3 0 0 0 0 0 110 110

6 0 100 100 100 100 100 100


2 0 100 100 0 0 0 0
2 0 0 0 100 100 0 0
2 0 0 0 0 100 100 0
2 0 0 0 0 0 100 100
0 0 0 0 0 0 0
8 Arung-8 0 110 110 110 110 110 110
2 Supervisor : 1 0 110 110 0 0 0 0
4 Fitter : 1 0 0 110 110 110 110 0
CST Mech-6
2 Safety : 1 0 0 0 0 0 110 110
2 Helper : 4 0 0 0 0 0 0 110
2 0 0 0 0 0 0 0
0 0 0 0 0 0 0
8 0 100 100 100 100 100 100
Team Date
Duration
CTR CST 11/23 11/24 11/25 11/26 11/27 11/28 11/29

2 0 100 100 0 0 0 0
4 0 0 100 100 100 100 0
2 0 0 0 0 0 100 100
2 0 0 0 ( No Repair) 100
2 0 0 0 0 0 0 0
0 0 0 0 0 0 0
9 Arung-9 Arung-10 0 110 110 110 110 110 110
2 Supervisor : 1 Supervisor : 1 0 110 110 0 0 0 0
1 Fitter : 1 Fitter : 1 CST Mech-7 / CST 0 0 0 110 110 0 0
2 Safety : 1 Safety : 1 Mech-8 0 0 0 0 110 110 0
3 Welder : 2 Welder : 2 0 0 0 0 0 110 110
2 Helper : 5 Helper : 5 0 0 0 0 0 0 0
0 0 0 0 0 0 0
9 0 100 100 100 100 100 100
2 0 100 100 0 0 0 0
1 0 0 0 100 100 0 0
2 0 0 0 0 100 100 0
3 0 0 0 ( No Repair) 100
2 0 0 0 0 0 0 0
0 0 0 0 0 0 0
9 Arung-11 Arung-12 0 110 110 110 110 110 110
2 Supervisor : 1 Supervisor : 1 0 110 110 0 0 0 0
5 Fitter : 1 Fitter : 1 0 0 110 110 110 110 110
1 Safety : 1 Safety : 1 0 0 0 0 0 0 110
CST Mech-09 / CST
3 Helper : 5 Helper : 5 Mech-10 0 0 0 0 0 0 110
3 0 0 0 0 0 0 0
2 0 0 0 0 0 0 0
1 0 0 0 0 0 0 0
2 0 0 0 0 0 0 0
0 0 0 0 0 0 0
9 0 110 110 110 110 110 110
2 0 110 110 0 0 0 0
5 0 0 110 110 110 110 110
1 0 0 0 0 0 0 110
3 0 0 0 0 0 0 110
3 0 0 0 0 0 0 0
2 0 0 0 0 0 0 0
1 0 0 0 0 0 0 0
2 0 0 0 0 0 0 0
0 0 0 0 0 0 0
Date
11/30 12/1 12/2 12/3 12/4 12/5 12/6 12/7

0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 110 110 110 0 0 0
0 0 110 0 0 0 0 0
0 0 110 0 0 0 0 0
0 0 110 0 0 0 0
( No Repair)
0 0 0 110 0 0 0

110 110 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
110 0 0 0 0 0 0 0
110 110 0 0 0 0 0 0
0 0 0 0 0 0 0 0
100 110 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0
( No Repair)
0 0 0 0 0 0 0
100 110 0 0 0 0 0 0
0 0 0 0 0 0 0 0
110 110 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
110 0 0 0 0 0 0 0
110 110 0 0 0 0 0 0
0 0 0 0 0 0 0 0
100 100 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0
( No Repair)
0 0 0 0 0 0 0
100 100 0 0 0 0 0 0
0 0 0 0 0 0 0 0
110 110 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
110 0 0 0 0 0 0 0
110 110 0 0 0 0 0 0
Date
11/30 12/1 12/2 12/3 12/4 12/5 12/6 12/7

100 100 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
100 0 0 0 0 0 0 0
100 100 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 110 110 110 110
0 110 110 0 0 0 0 0
0 0 0 110 110 0 0 0
0 0 0 0

0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
110 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
110 0 0 0 0 0 0 0
110 0 0 0 0 0 0 0

110 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
110 0 0 0 0 0 0 0
110 0 0 0 0 0 0 0

110 110 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
Date
11/30 12/1 12/2 12/3 12/4 12/5 12/6 12/7

100 100 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0

110 110 110 0 0 0 0 0


0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
110 0 0 0 0 0 0 0
110 110 110 0 0 0 0 0
110 110 0 0 0 0 0 0
0 110 0 0 0 0 0 0
0 110 110 0 0 0 0 0
0 0 0 0 0 0 0 0
100 100 100 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
100 0 0 0 0 0 0 0
100 100 100 0 0 0 0 0
100 100 0 0 0 0 0 0
0 100 0 0 0 0 0 0
0 100 100 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
110 110 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
110 0 0 0 0 0 0 0
110 110 0 0 0 0 0 0
0 0 0 0 0 0 0 0
100 100 0 0 0 0 0 0
Date
11/30 12/1 12/2 12/3 12/4 12/5 12/6 12/7

0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
100 0 0 0 0 0 0 0
100 100 0 0 0 0 0 0
0 0 0 0 0 0 0 0
110 110 110 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
110 0 0 0 0 0 0 0
0 110 110 0 0 0 0 0
0 0 0 0 0 0 0 0
100 100 100 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
100 0 0 0 0 0 0 0
0 100 100 0 0 0 0 0
0 0 0 0 0 0 0 0
110 110 110 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
110 110 0 0 0 0 0 0
0 110 110 110 0 0 0 0
0 0 0 110 110 0 0 0
0 110 0 0 0 0 0 0
0 110 110 0 0 0 0 0
0 0 0 0 0 0 0 0
110 110 110 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
0 0 0 0 0 0 0 0
110 110 0 0 0 0 0 0
0 110 110 110 0 0 0 0
0 0 0 110 110 0 0 0
0 110 0 0 0 0 0 0
0 110 110 0 0 0 0 0
0 0 0 0 0 0 0 0
WORK PERMIT CSU SHUTDOWN 2019

No Work Permit List : Permit

1 8478627 INS-VES F-6410B/IN-MAJ


1 Mobilisasi material and equipment to H-6320 HWP
2 Install and modification scaffolding for internal claning H-6320. CWP
3 Spading at H-6320 CWP
4 Open manhole at H-6320. CWP
5 Closed manhole and de-spading at H-6320. CWP
6 De-spading at H-6320 CWP
7 Dismantle scaffolding after internal cleaning H-6320. CWP
8 Assist leak test after internal inspection H-6320 CWP
9 De-mobilisasi material and equipment to H-6320 HWP

2/3 8477828 INS-VES A-6360/IN-MAJ & 8477829 INS-VES A-6380/IN-MAJ


1 Mobilisasi material and equipment to A-6360 & A-6380 HWP
2 Install and modification scaffolding for internal claning at A-6360 & A-6380 CWP
3 Spading work at A-6360 & A-6380 CWP
4 De-spading at A-6360 & A-6380 CWP
5 Dismantle scaffolding after internal cleaning at A-6360 & A-6380 CWP
6 Assist leak test after internal inspection A-6360 & A-6380 CWP
7 De-mobilisasi material and equipment to A-6360 & A-6380 HWP

4 8477741 INS-VES D-6430/IN-MAJ


1 Install and modification scaffolding for internal claning at D-6430.
2 Spading at D-6430. CWP
3 Open end closure at at D-6430. CWP
4 External and Internal cleaning at at D-6430. CWP
5 Closed end closure & de-spading at D-6430. CWP
6 De-spading at D-6430. CWP
6 Dismantle scaffolding after internal claning at D-6430. CWP

5 8477742 INS-VES E-6160/IN-MAJ


1 Mobilisasi/De-mobilisasi material and equipment at E-6160. HWP
2 Install and modification scaffolding for internal claning at E-6160. CWP
3 Spading at E-6160. CWP
4 Open Manhole at E-6160. CWP
5 External and Internal cleaning at E-6160. CWP
6 Closed manhole and de-spading at E-6160. CWP
7 Dismantle scaffolding after internal claning at E-6160. CWP
8 De-mobilisasi material and equipment to E-6160 HWP

6 8477830 INS-VES D-6200/IN-MAJ


1 Mobilisasi/De-mobilisasi material and equipment to D-6200 HWP
2 Install and modification scaffolding for internal claning at D-6200. CWP
3 Spading at D-6200 CWP
4 Open Manhole and Turbexing at D-6200. CWP
5 External and Internal cleaning at D-6200. CWP
6 Install and modification scafolding inside Vessel at D-6200. CWP
WORK PERMIT CSU SHUTDOWN 2019

No Work Permit List : Permit


7 Dismantle scaffolding inside Vessel after inspection at D-6200. CWP
8 Closed manhole and de-spading at D-6200. CWP
9 Dismantle scaffolding after internal claning at D-6200. CWP
7 Assist leak test after internal inspection D-6200. CWP
8 De-mobilisasi material and equipment to D-6200. HWP

7 8443232 INS-FLARE FL-6450A/IN-MAJ


1 Install and modification scaffolding for internal claning at D-6450A CWP
2 Hotbolting for internal inspection at D-6450A CWP
3 Spading at D-6450A CWP
4 open manhole at D-6450A CWP
5 External and Internal cleaning at D-6450A CWP
6 Closed manhole & de-spading at D-6450A CWP
7 De-spading at D-6450A CWP
8 Remove scaffolding for internal claning at D-6450A CWP
9 Repair Flare after inspection at FL-6450A. HWP

8 8441580 INS-VES D-6440/IN-MAJ


1 Mobilisasi/De-mobilisasi material and equipment to D-6440. HWP
2 Install and modification scaffolding for internal claning at D-6440. CWP
3 Hot bolting before spading at D-6440. CWP
4 Spading at D-6440. CWP
5 Open end closure at at D-6440. CWP
6 External and Internal cleaning at at D-6440. CWP
7 Closed end closure & de-spading at D-6440. CWP
8 De-spading at D-6440. CWP
8 Dismantle scaffolding after internal claning at D-6440. CWP
10 De-mobilisasi material and equipment to D-6440 HWP

9 8441581 INS-VES D-6455/IN-MAJ


1 Mobilisasi/De-mobilisasi material and equipment to D-6445 HWP
2 Install and modification scaffolding for internal claning at D-6445. CWP
3 Hotbolting for internal inspection at D-6445. CWP
4 Spading at D-6445. CWP
5 open manhole at D-6445 CWP
6 External and Internal cleaning at D-6445 CWP
7 Closed manhole & de-spading at D-6445 CWP
8 De-spading at D-6445 CWP
9 Dismantle scaffolding after internal claning at D-6445 CWP
10 De-mobilisasi material and equipment to D-6445 HWP
TDOWN 2019
updated :
Date
Days Remarks
Execution Closed

7
7
7
7
7
7
7
7
7

5
5
7
7
7
3
4

7
7
7
7
7
7

7
7
5
7
5
7
7
5

5
5
3.5
3.5
3.5
2.5
TDOWN 2019
updated :
Date
Days Remarks
Execution Closed

2.5
7
7
7
7

7
7
7
7
7
7
7
7
2

7
7
7
7
7
7
7
7
7
7

7
7
7
7
7
7
7
7
7
7
WORK ORDER STATUS CSU SHUTDOWN 2019

No Discription

1 8478627 INS-VES F-6410B/IN-MAJ

2 8477828 INS-VES A-6360/IN-MAJ

3 8477829 INS-VES A-6380/IN-MAJ

4 8477741 INS-VES D-6430/IN-MAJ

5 8477742 INS-VES E-6160/IN-MAJ

6 8477830 INS-VES D-6200/IN-MAJ

7 8443232 INS-FLARE FL-6450A/IN-MAJ

8 8441580 INS-VES D-6440/IN-MAJ

9 8441581 INS-VES D-6455/IN-MAJ

10 7243187 INS-PIP-REP_2" Drain of 20-DR-B03-6326