Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 1

Secant pile walls are formed by constructing intersecting reinforced concrete piles.

The secant
piles are reinforced with either steel rebar or with steel beams and are constructed by either
drilling under mud or augering. Primary piles are installed first with secondary (male) piles
constructed in between primary (female) piles once the latter gain sufficient strength. Pile
overlap is typically in the order of 3 inches (8 cm). In a tangent pile wall, there is no pile overlap
as the piles are constructed flush to each other.

The main advantages of Secant Pile Walls are:


a. Increased construction alignment flexibility.
b. Increased wall stiffness compared to sheet piles.
c. Can be installed in difficult ground (cobbles/boulders).
d. Less noisy construction.

The main disadvantages of secant pile walls are:


a. Verticality tolerances may be hard to achieve for deep piles.
b. Total waterproofing is very difficult to obtain in joints.
c. Increased cost compared to sheet pile walls.

Secant pile wall design when steel beams are used involves the use of weaker than normal
concrete. The pile that is lagging the wall between two main beams has to be examined for
shear and compression arching.

http://www.railsystem.net/wp-content/uploads/2016/09/secant1.png

You might also like