Professional Documents
Culture Documents
Socorro SWA
Socorro SWA
Socorro SWA
Location : 15th Avenue Socorro Quezon City
Subject : Statement of Work Accomplishment
Item Works : Civil and Electrical
Date : As of September 8, 2017
A Preliminaries
1 Mobilization 1.00 lot 5,000.00 5,000.00 80% 4,000.00
Overhead /Management fee 1.00 lot 10,000.00 10,000.00 80% 8,000.00
A.Subtotal 15,000.00
B Scope of Works
1 Installation of welded wiremesh with frame at Parking area left side 5.00 sets 6,000.00 30,000.00 100% 30,000.00
2 CHB Wall making good at parking 15.00 meters 466.67 7,000.00 0% ‐
Painting of covered court walls, columns, parking columns, walls, slabs ceiling & beams, brgy
3 hall interior walls, ceiling at ground 1,526.50 m2 39.31 60,000.00 100% 60,000.00
4 Painting of steel truss and frames, purlins 7.00 sets /truss 6,428.57 45,000.00 100% 45,000.00
Polycarbonate roof canopy with steel frame fabrication, installation and painting at covered
5 court perimeter 135.00 m2 861.33 116,279.41 100% 116,279.41
6 Casement window glass only at brgy hall ground floor 2.00 sets 2,640.00 5,280.00 100% 5,280.00
7 New steel casement window at CR 2.00 sets 1,980.00 3,960.00 100% 3,960.00
8 Repair of metal louver, additional louver installation welding works at 2nd floor 120.00 pcs 250.57 30,067.87 100% 30,067.87
9 Additional floor slab at prking entrance 1.00 set 9,782.76 9,782.76 0% ‐
10 Painting of steel stair 1.00 set 3,629.96 3,629.96 100% 3,629.96
11 Electrical works labor cost (2nd floor court lightings and ground) 1.00 lot 45,000.00 45,000.00 78% 35,100.00
12 Application of skimcoat and sanding to covered court 390.00 m2 64.10 25,000.00 100% 25,000.00
13 Installation of door and jamb at CR 4.00 sets 1,000.00 4,000.00 0% ‐
B.Subtotal 385,000.00
Grand Total 400,000.00 Total Accomplished Value 366,317.24
Less Payments Made
12‐Aug 38,000.00
Submitted by 19‐Aug 40,000.00
26‐Aug 30,000.00
JERRY MIRAFLORES 10‐Sep 5,000.00
TOTAL AMOUNT to BILL 253,317.24