No Process Risk
1 HR Employee absenteeism
2 HR/ HSE Fire Mock Drills at HO by HR and SAFETY at Site
3 Maintenance Unavailability of spares
4 Maintenance Unavailability of proper tools
5 QA/QC Method error
6 QA/QC Testing/NDT of welding not proper
7 QA/QC Instruments error
8 fabrication Absence of skilled wokers
9 heavy Erection/ fabrication Machine/Crane Breakdowns
10 Stores Damage of material while handling and transfering
11 Stores Minimum stock level
12 stores Operational risk
13 Purchase Delay in receiving material
14 Purchase Rate selection criteria
15 Site Erection Delay in Erection due to shortages
16 Site Erection Labour Issue
17 Tender /Contracting Understanding customer requirements
18 Development Delay in development
19 Planning Delay in advance plan from customer
20 Planning Delay Store stock report
RPN
NO Likelihood Severity
1 Very unlikely Minor impact on cost, schedule, performance, etc.
2 Somewhat likely Moderate impact on cost, schedule, performance, etc.
3 50/50 Chance Significant impact on project baselines
4 Highly likely Very significant impact on project baselines
5 Nearly Certain Disastrous impact, probable project failure
Probability (of risk occurring)
Occuran
Likelihood Previous Occurrences
ce
Level of Control
Essentially avoidable through selected risk mitigation actions
Highly controllable through organization or project actions
Moderately controllable through organization or project actions
Largely uncontrollable by the organization or project actions
Uncontrollable by the organization or the project
Consequence (if risk is encountered)
Potential Risk
Potential Impact Est. Cost Factor
Inability Potential Cons.
Loss of Potential on of ( occx
to Meet Violation Rating
Custome Risk to Compan Correctio sevxcont
severity Control Immediat of
r or Human y n/ )
e Job Regulati
Entire Health Reputati Financial
Require ons
Contract on Penalty
ments
2 2 modreate very high None modreate modreate 48 8
4 4 very high Definite very high modreate 27 16
2 2 N.A modreate None N.A 16 8
3 3 modreate None N.A 12 9
3 2 Minor minor None N.A 9 12
3 2 Minor minor None N.A 9 12
2 2 N.A modreate None N.A 9 4
3 3 Minor modreate None N.A 8 27
2 2 modreate very high None N.A 8 4
2 2 Minor modreate None N.A 8 4
2 2 Minor minor None N.A 8 8
2 2 Minor modreate None N.A 8 4
2 2 Minor minor None N.A none none 8 8
2 2 Minor modreate None N.A 8 8
3 3 modreate modreate None N.A 4 9
4 4 modreate very high None N.A 4 48
0 0 modreate minor None N.A 4 0
0 0 modreate modreate None N.A 4 0
2 2 N.A modreate None N.A 0 8
2 2 N.A minor None N.A 0 8
Needs to
valodate
as per
praticle
situations
Mitigatio
n Plan
0 Risk
Factor
after
Mitigatio
n
LIST OF INTERES
#VALUE!
Internal/ Issue/ Reason for
S.No. Interested Party Needs
External Consideration
Availbilty of Resources as
required by contracts
vendors/Suppliers External
Prepared By
LIST OF INTERESTED PARTIES and Risks and Oppurtunties
Occurance ( 1-5 Severity Detection
Expectations Opportunity Risk/
) ( 1-5) ( 1-5)
Compliance of QHSE Withdrawl /Suspension of
STDS certificate 2 3 2
No major Non confirmities
Major Non Confirmities
2 3 2
2 4 2
100% compliance to HSE
and legal Customer satisfaction
Norms/requirements 2 4 2
Quality Norms as per
contracts and time to time
Customer satisfaction
audits/inspection
requirements 2 4 2
100% compliance to HSE Legal non compliance due to not
identification of all legal
and legal identifying any legal 2+I13:L19N17I13:
and statuary requirements
Norms/requirements requirement L20I13:L24 5 2
Delay in submission of
No delay in submission of
Legal compliance ESI/PF/BOCW/Fire NOC and
Returns
Other applicable requirements
2 5 2
monitoring mechanism of
vendor /supplier rating on selection of wrong
SCM
quality/delivery and cost supplier/vendor
parmeters
2 4 2
monitoring mechanism
of /supplier rating on selection of wrong
QUALITY
quality/delivery and cost supplier/vendor
parmeters
2 4 2
Legal compliance
assistance
QUALITY/SAFETY legal adherance
2 5 2
Timely disbursement of
dues and oppurtunties for Attendance record/ salry
HR
promotion and deployments /Esi/PF records
as per skill requirements
2 5 2
Timely disbursement of
dues and oppurtunties for Attendance record/ salry
HR
promotion and deployments /Esi/PF records
as per skill requirements
2 5 2
MANAGEMENT
Trends on performance Objective monitoring
OBJECTIVES 2 4 2
MANAGEMENT
plan vs actual data
OBJECTIVES
Buisness plan
2 4 2
MANAGEMENT
OBJECTIVES
MOM MRM Minutes 2 4 2
MANAGEMENT
Legal register/reprts of
OBJECTIVES compliance or
Legal compliance shortcomings and action
status report plans 2 4 2
Approved By-
nties
Risk Priority Number
( RPN No- Occ x Sev x Actions Record Reference / Notes Remarks
Det
12 Periodic Internal & third party IMS MANUAL AND IMS
Audits for ISO and OHSMS PROCEDURE and records as per
compliance master list
12
12
16
16
Meet customer spec., applicable
legal requirements and EHS Legal Compliance register
16 compliance
16
Test reports /performance ratings compliance reports
16
16
20