Download as pdf or txt
Download as pdf or txt
You are on page 1of 20

Hong Kong International Airport- &c.

Instn Ciu E m ,
ciu Engng, Hong Kong
Znternaltoffal Aitpor! ,
construction Part l: airport, 1998,
126,3554
A. I. n o m s o ~ BSc,
, CEw, MICE, and D.E. Oakervee, CEw, FICE

The new Hong Kong International Airport was built on a remote island site at
Chek Lap Kok in just seven and a half years. This paper describes how con- dfsnrssion CIMS
15 November 1998
struction progressed from the initial advance works cohtract awarded in
January 1991 to the opening of the completed, shteof-theart airport and its
massive 515 000 m2 terminal building in July 1998.It details the Ha 44 bil-
lion package of contracts let by the main client, the Hong Kong Airport
Authority, and the methods of conskuction management used to ensure safe
completion both on time and within budget. It also addresses the unique con-
struction support facilities and services which were provided by the
Authority to support the 21 000 people working on site during the peak con-
struction phase.

On 29 November 1995 the airport committee of stepby-stepfunding had a signikant influence on


the SineBritishjoint liaison group signed agreed how the construction strategy developed. This
minutes on membership of the Hong Kong paper follows the chronoIogy of construction con-
Airport Authority (AA), which paved the way for bact awards and sequence of construction.
establishment of the AA on 1 December 1995. T h e airport is one of the ten projects that
Prior to this, the planning, design and construc- together make up the government's Airport Core
tion had been progressing on a phased basis Programme as described elsewhere in a compan-
under the auspices of the provisional airport ion paper.1 The factors which inauenced the
authority (PM)to complete the airport to the design of the various airport fadties are also
maximum extent possible by June 1997. described in a companion paper?
Any civil engineering project evolves on a logi- A list of all siwcant contractors employed in
cal progressive basis. The airport project evoIved the construction of the airport project is given in
over the years by taking account of,not only engi- Appendix 1.
neering logic, but also the incremental release of
funds to the P M as the project progressed.?his Fig. 1. Project comtmction firogamtne

'
1 1 Advanced works
2 Site preparation
3 Construction support facilities
4 lnrtial C ~ Iengineering
I works

5 Baggage handling system


6 Airport People mover
7 Terminal buildingsupwstructurdenvelope
8 Terminalbuilding iitout
9 Terminal building electrical and mechanicaf $

1 Landside infraslructurewar+
i tran---*attron centn

Hong l h g Airport
Authody
-
35

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
. ... , , .

THOMSON AND
OAKERVEE

Budget and programme


Consbuction of the airport was initially based
upon the recommendations of the New Ae'Mort
Master Platt.3 This envisaged a construction pro-
gramme starting at the beginning of 1992 with a
target date for opening of mid-1997, together with
a costed implementationprogramme which set
the project budget control total. It was not posd-
ble to implement fully these plans until the FAA
was reconstituted as the AA in December 1995. In
1996 the government announcedthe new airport
would open in April 1998, and at that time the
construction programme was revised and the
costed implementationprogramme was updated.
The consbuction programme Fig. 1) was imple-
mented in five phases

advance works
site preparation
initial contracts
main works
integration and trials.

Advance works
Advance works codract (AWCl
h 1991 the project site comprised two islands.
The larger one, Chek Lap Kok (302 ha), was
inhabited by three fishing villages and the smaller
one, Lam Chau (8 ha), was uninhabited..
Following rehousing of the villagers, an advance
works contract was awarded in January 1991.The
purpose of this contract was to provide basic
infrastructure on the otherwise barren island of
Chek Lap Kok. This was done by removing the
tops of the three highest hills from +l20m PD
(project datum) to form plateaux at about t95 m
PD. The material arising from this was used to
reclaim a bay to + 6 m PD, which is about 4.7 m
above mean sea level, in the northeast corner
2). Here a heavy-duty quay wall was built
together with a pair of 1MW electricity genera-
tors, a potable water treatmentplant, raw and sea-
water distribution systems, offices, accomoda-
tion blocks and a canteen. This was sufficient to to manufacture and deliver. Fig. 2. (top). Chek
provide facilities to support the AA's own staff and The duration of the SPC was not sufficient to L@ Kok avtd k m
the site preparation conWactor'sworkforce during allow such a lengthy mobilization period, so the Chau islaads at the
the intensive mobilization period. M decided to.buysome new plant which was time of the advance
The award of the site preparation contract novated to the successful SPC tenderer. This pre- works coprtmct
(SPC) was delayed by seven months due to fund- ordered plant comprised 17 Caterpillar 785 dump (February 19921.
ing dficulties but work was able to continue OD a kucks (136 t payload), four Demag 285 hydraulic
step-by-step basisby utilizing the dredging face shovels (19 m3 bucket capacity) and six
resources of the advance works conkactor. A Ingersoll-Rand DMM2 hydraulic drill machines Fig. 3. (above).
completion cerhfmte was issued for the AWC on (250 m m hole dia. capacity). All this plant was D e m q 285 shovel
the same day that the site preparation contract delivered, tested and commissioned on site before and Catefliihr 785
was awarded on 30 November 1992. the SPC was awarded (Fig. 3). truck assembly OH site
m part of the pre-
P r ~ r d w e dewthwopks plant Site prepamtion coniract (SPC) ordered plant
It was also recognized that the site prepamtion Six joint ventures were prequalified and invited (October 1992)
contractor would require a signXcant amount of in November 1991 to submit bids to undertake
large-scale earth-moving plant. This was not read- the site preparation works. The scope of the
ily available on the world market and purchase of works was to form a platform at about +6.5 m PD,
such equipment would have taken up to 6 months which was 1248 ha in size with a perimeter about

36

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION

17 km long. The works would involve dredging Tabls 1. Tyjical Chek LAP Kok driil-ad4last parameters
about €4 Mm3 of unsuitable marine mud,remov-
ing about 95 Mm3 from the island of Chek Lap Una
Kok,Lam Chau and the two Brothers Islands and
placing the material in reclamation, and importing
and placing about 86 Mm3 of marine sand. All
work had to be completed within 31 months of
the award of contract.
When tenders were returned in March 1992
they were significantly above the M's budget and
parallel tender e s b et.A way had to be found
for the AA to become less dependent on the
world's limited resource of trailer dredgers. This
was done by inviting tenderers to submit alterna-
tive tenders based on the use of a land borrow
area (instead of importing marine fill) and
increasing the contract periodto 41 months.The
alternative tenders were submitted in June 1992
and were withii budget and found to be competi-
tive. The P M did not have funds available to
award the contract but a letter of intent was sent
to the lowest and conforming alternative tenderer
in July 1992. The contract sum was HKS 9.1 bil-
lion. During the interregnum the AA negotiated
extensions to the scope of works with the advance
works contractor so that critical work to remove
marine muds could continue.
The joint-venture contractorwas able to mobi-
lize quickly using the facilities provided under the
AWC and the presrdered earthworksplant. The
joint-venture also had fully developed its sub-con-
trac!ing strategy during the tender period. Tbe
contractor was therefore in a position to award During a 36 month period a total of 70 M m 3 of mud Fig. 4. T h e j T J de
major sukontracts quickly for the dredging were removed from site,with the maximurn output Nral trailer metion
works, land excavation works, seawall conshc- of 14 M m 3 in one month. hopper dredger wwk-
tion and geotechnical instrumentation works. The land-basedearthworks was subcontracted ing rat Chek Lap Kok
Large earth-moving plant of the d e demanded into two approximately equal parts.The subcon- in 1994-the largest
by the SPC had never been used in Hong Kong tractor in the northern half adopted a philosophy capacity dredger b the
and it was necessary to bring skilled workers from of using a mixed fleet of new and old trucks of world at the time.
overseas, The Hong Kong government had inlm varying capacity but with a restricted speed limit.
duced a special labour importationscheme where The subconkactor in the southern part used a
by contractors could bring workers from overseas single size fleet of new trucks operating at a high-
for ked-term contracts to assist the construction er speed limit.Therefore, the two subcontractor's
of the Airport Core Programme projects. The k t operations were physically segregated to avoid
of these arrived in February 1993to coincide with safety problems thatwould have been associated
the start of production work on site. by mjxing the two philosophies. Consequently,the
The h t task was ta remove the unsuitable safety record was good although there was regret-
marine muds from the sea-bed to expose alluvial tably one fatal accident involving a haul truck.
material which had a net cone penetration test tip The joint venture subcontracted the supply of
resistance of more than 500 kpa The depth of explosives. This sukntractor provided a down-
water varies from zero, adjacent to Chek Lap Kok theole service to the two earthworks subcon-
and Lam Chau, to 15 m in places.The average tractors. Packaged explosives and detonators
thickness of mud which had to be removed was 8 were issued from a sitebased magazine under the
m, increasing to 15 m in places. Most of the mud supervision of the mines division of the Hong
had to be taken to the government marine dump Kong government.Ammonium nibate and fuel oil
south of Cheung Chau some 40 km away from the (ANFO) was manufactured in an emulsion plant
site. Grab dredgers had to be used in shallow on site and delivered to the face by 12 t capacity
waters. More economical M e r suction hopper mix-and-placetrucks. The geology of Chek Lap
dredgers (Fig. 4) were used in waters where the Kok is highly variable and therefore each blast
depth exceeded 5 m At peak production 10trailer had to be uniquely designed. Where 13 m bench-
dredgers were used for mud removal. These varied es were formed driH holes would be 216 mm dia.
in hopper capacity h m 2500 m3 to 14 OOO rn3. with 2.0 m sub-drill, 9 M of explosive column and

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
THOMSON AND
OAKERVEE

.-
.-
.-

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION

ing from Chek Lap Kok Filter layers and armour


rock was processed by taking product from the
blasted face and sorting using a combination of
grizzly screens, back h m and gnpples. The sort- MMMn
ed products were then haded on to barges and I 1 750 -I
towed to the sik and placed by grab -S. -
10 330
The contract& alternative tender was based on
10 1%
the importation of marine sand to provide the baJ
ancjng quantity of material required to complete
the platform.This was done usingfour borrow
areas at the Brothers Islands, east of Sha Chau, i
Urmston Road and Ninepins. A total of 46 M m 3 of
overburden mud had to be removed 50 as to
expose suitable fillingmaterial. A fleet of up to 18
trailer dredgers (Table 2) worked continuously for
20 months delivering material 24 hours a day, 7
days a week. This was known as the 'sand train'
and it delivered a total of 86 Mm3, same of which
was dumped in its h a lposition, some was rehap
dled by cutter dredger and some was pumped
ashore.
When dealing. with such wry large quantities of
material it is essential to monitor pmgress rigor-
ously to ensure programme objectives are being
achieved,This was done using stawf-theart 7.1
computer survey techniques.Hydrographic sur-
veys were carried out ulilizhgthe MS own dedi- 97-7
cated survey launch operating independently of
the conhctoA own survey units.h d excavation
and reclamation was surveyed by aerial phc-
tographs which were scanned to produce
orthophotos and digitalterrain models b m which
volumes and areas were readily calculated?
The h a laccount was settled for a sum within
budget some 37 months after award of contract
which was four months before the planned can-
tract completion date. This success was due to a
number of factors where the AA and the contrac-
tor worked together, such as

high technical and managerial skills


overall quantities were not varied from those
initially contracted
continuity of work for the dredgers and earth-
works plant
pragmatic utilization of land-based materials
'as dug'
quick and accurate volume surveys to monitor
progress.

Construction support
The airport at Chek Lap Kok had characterb
tics that were unique in the history of consiruc-
tion industry of Hong Kong, some of which are

it was an offshore site


it was remote from the urban areas
no irhastructure or municipal services were
available
a workforce in excess of 21 000 existed
overfull employment in construction industry
was predicted
I
39

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
THOMSONAND
OAKERVEE

its reliance on large numbers ofimported a project site seutrity system and m n n e l F&, 6.F m y a
d brrs
workers for identifying and screening all personnel iwWchagefor con-
there was a multitude of conmctm working arriving at the site shctim &m?
for many developers. a docking and marine cargo handling manage commfm (..ay
ment system 19961
The AA chose to manage these factors'positively h @hting and emergency rescue team avail-
and not merely allow conmctors to fend for them- able 24 hours a day, 365 days a year
selws.This was done by the BA constructingW- advice on de@, environment and industrial
ilks and providiag services which colklively were relations matters
known as 4 c o support' and the AA h
n s t r ~ d i ~ ~ cleauing and maintenance of common areas.
effecth a m e a managementcontractor who p m
vided primaryservices to aII conkactom, develop The AA awarded a number of consbudion sup-
m and other third pties working on the project port licences (Appendix D following an open
site. These services were provided by the AA compditive tendeing process. The successful
when it was better placed to do so than contractors Iicensees were able to sell goods and services at
for reasons of economy of scale, safety and W& controlled prices. Generally, construction contrac-
ness ofa v a i W i Construction support fadlilies tors were not campelled to use these services but
that were provided are shown in Table 3. could set up their own facilities (but not sen to
The AA provided h e following services free of others) if they chose to do 50.Thus healthy corn
charge to contrad~rs which resulted in lower ten- petitive markets were established on site.'Xhefor
der prices for conslmctjon contracts lowing licences were awarded
a chartered ferry service which delivered up a rock crushing licence to sell 8 Mt of
to 12 000 workers to the site by boat daily crushed rock product
(Fig-6) two ready-mixed concrete batching plants

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
two worldorce accommodation camp opera- for the design and construction contracts was the
tion and catering licences Architectural Services Department(ASD) . The
a primary health care service staffed with doc- Authority was responsible for management of cc-
tors and registered nurses ordination issues and interfaces and the provision
two fuel suppliers of construction support services in MD's con-
a materials testing facility tractors. Liaison with ASD was via the AA's repre-
a waste disposal service sentative and his delegates.
a land transportation service Franchisees were responsible for the design
printing services. and construction of various aviation-related
facilities which were essential to the operation
In addition, consbuction supportprovided assis- of the airport and in which private enterprise
tance to the AA's own project staff thus relieving was willing to make an investment.These facili-
them of this burden so as to concentrate on their ties comprised
core mission of construction of the permanent
works. Such support included the following two air cargo handling facilities
three aircraft caterers
operating and maintaining the All's marine one Iuel delivery, storage and hydrant distrib
fleet of 14 vessels utor
operating and maintaining the AA's fleet of a base maintenance operator
200 land-based vehicles three line maintenance operators.
9 maintaining the AA's portfolio of 100 site
buildings Again, the AA's construction management role
operating and maintaining 200 radios and was primarily one of cc-ordination and interface
mobile telephones management. This was quite substantial as each
providing an escort service and logistics sup site was an island within an island which had to
port to up to 2000 visitors who visited the con- form a cohesive whole. Each franchise agreement
struction site weekly. included a construction schedule whichwas
administered by an AA representative who had
Construction contract packages powers to instruct variations, value such variations
The framework for the contracting strategy was and award extensions of time to the franchisee.
based on the New Airjort Master Plan. There The franchisee entered into construction contracts
were fourgroups of developers which were with its own conmactors.
responsible for the various construction contracts Other business partners provided airport-relat-
which cornprised the overall airport project ed services;many of these were not essential to
{Appendix 1) be in place before the opening of the new airport
but were vital for its commercial success. Such
the AA enterprises included an hotel, airline headquar-
the Hong Kong government ters, a freight forwarding centre and over 120
the aviation franchisees retail tenancies in the terrninal building. These
the colmzercial partners. agreements also contained construction sched-
ules and details of designated AA representatives
The largest developer on the project was the who had similar powers EO those in the franchise
AA. It had to provide a passenger terminal build- agreements.
ing, one runway together with associated taxiways The contracting strategy was continually adapt-
and aprons, a road expressway, a railway corridor, ed as funds were released to the PAA under the
a primary and secondary roaddistribution system, stepby-step financing arrangement which contin-
utilities, storm water systems, waste and grey ued until both the government's financial support
water systems, conmunications systems,sea-cool- agreement was in place and the AA itself was
ing water systems and a ground transportation properly established in December 1995. This
centre. The budget of design and construction of meant that contracts were funded and awarded on
the AA's direct works was established in February a just-in-timebasis in order to preserve the date
1994 at HKS 44.447 billion and was never changed. for airport opening. This stop-go scenario, where
The Hong Kong government was responsible contracts were awarded on a s h d alone basis,
for the design and constructionof the was both more complex and more challenging to
the AA than if the whole project could have been
air traffic control complex financed and planned as a total entity. This can be
government flying service facility illust~ntedby the terminal building which was
air mail centre designed, and tenderpackages prepared, on the
regionalpolice headquarters basis of four major components
landside fire station.
the structural and builder works
The government works department responsible the building services

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
THOMSONAND
OAKERVEE

the fihut works required a long offshore manufacturing phase. It Fig. Z Eastern vdic-
the communication systems. was also important to award three civil works alar tunnel beileg con-
contracts early. T h e airfield tunnels were needed sdructed b e n e h the
In the went the termind building was contract- to take aircraft servicing vehicles under the soacthem mnway
ed quite differently with southern runway, andit was necessary to award (December 19951
this contract in advance before the design of the
a foundations coniract runways and taxiways was complete (Fig. 7).
a superstructure contract Similarly,it was necessary to award an early con-
the building services contract tract for the construction of 25 km of storm water
over 20 direct or nominated suhontract fit- cuherts. These were obviously in the deepest
out packages excavations on the site and had to be installed
nine direct systems contracts. first. The third contract was t o build a primary
electsical substation for the electricity supply
Initial contracts compmy-wrmanent electricity distribution was
There were five contracts which were awarded needed early for t e s k g and commissioning the
early as it was envisioned that these needed to be electrical equipment.
brought to an advanced stage at the earliest The construction packaging strategy was devel-
opportunity, either because they had a long peri- oped based on three main factors
od for offshore development and manufacture or
their site works had a signiscant impact on other engineering discipline
works. The first contracts to be awarded follow- system or structural completeness
ing the SPC were the automated people mover geographical location.
and the baggage handling systems contracts.
Both systems had to be developed to meet the The M's general conditionsofcontract have a
unique demands of Chek Lap Kok and both project manager (who is an AA employee) t o

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION

administer each contract impartially. The duties


and powers of the project manager are loosely
based on those of the engineer under the
Institution of Civil Engineers Cmditium of
Coztrract.T h e individual contracts were allocated
to one of three project managers depending on
the predominant engineering discipline of civil
works, electrical and mechanical works or build-
ing works. Contracts were also sensibly packaged
so that wherever possible a whole system would
be the complete responsibility of a single contrac-
tor. Finally, the whole of the &was divided into
four major geographical areas and a major con-
tract was awarded for each of these, namely

the terminal building


the airfield works
landside infraslructureworks
the ground transportation centre WO&.

Each of these geographical areas was under the


control of one of the AA's construction managers,
who in turn reportedto a project manager. The
construction manager was responsible for all c*
ordination issues arising from dl contractorswith-

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
THOMSON AND
OAKERVEE

in the geographical area notwithstanding the c m - whole of the Airport Core Programme; however, Fig. 10, Roof modules
tractor was in contract with the AA itself, the gov-it should be noted that almost 50% of this total being placed i H the
ernment or a business partner. Each geographical was for primecost sums for subcontracts to be passenger tmniloal
area had in the order of about 20 main contractors. awarded later once funding was available.The bzddhg (July 1996)
contractor was a joint venture comprising compa-
Terminal building nies from the UK,the People's Republic of China,
The contract to build the foundations of the ter- Japan and Hong Kong. 'he contract also included
minal building was awarded in June 1994.The options for a scheme to widen the concourses,
works comprises 460 bored piles, 450 driven H- which increased the gross floor area from 490 000
piles, 2600 tension anchors, a 280 m long multi- m2 to 516 000 rn2, and these were exercised with
cell tunnel 36 m wide by 10 m high, 50 000 m2 of in 28 days of the award of contract.
ground slab and associated cast-in services (Fig. There was a relatively long mobilization period
S). The terminal building is located on the shore while the joint venture procured special table
line of the original i s h d of Chek Lap Kok and formwork, awarded sub-contracts for concrete
extremely variable ground conditions were works and obtained visas for imported workers.
encountered. This resulted in variations to the The first permanent works concrete was placed in
design to the foundations as the works pro- May 1995 and peak production rates of 10 000
gressed.The original duration of the contract was m3/week was achieved in December 1995.
set at 11 months but extensions of W e were lJl!imately, a total of 240 000 m3 of concrete was
awarded and the actual constructionperiod placed by the time concreting operations were
extended to 19 months. completed in December 1996. By civil engineer-
In January 1995, the contract was awarded for ing standards this is not an exceptionally large
the construction of the remainder of the passen- amount of concrete but the total number of pours
ger terminal building (FIB). At HKS 10.1 billion it was in the order of 10 000 and gives some idea of
was the highest value contract awarded in the the complexity of the building,and good planning

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
, .. .

CONSTRUCTION

was required to achieve these production rates. cycle time for the main assembly of a module was Fig. 11. cbelow med bot-
All concrete was provided using on-sitebatching 23 days followed by six days for painting. A corn- tom). Roof module being
plants and using Chek Lap Kok aggregates. The pleted moduIe was Wed from the jig by a 1000 t h - indo position
quality of the concrete was of a high standard and crawler mane and placed in an adjacent paint srsing laacncking beam
the great majority was fair-facedconcrete with a shop where it received two coats of white epoxy tmuem'llg tu the centre
painted surface coating. paint. The crane Wed it from the shop and placed ofthrpmmgw t m i -
One of the more technically challenging parts it on two harnessed pairs of multi-wheeled trans noE building (July 1996)
of the contract was the fabrication of the steeI
frame for the roof of the FI'B. The roof structure
was designed to be formed from orthogrid space
frames forming barrel-vaultmodules designed to
span 36 m from column to column. The bottom
flange of each beam is exposed in its final condi-
tion and this architectural requirement imposed
engineering constraints on the size of the frame
members. It meant that the width and depth of
every beam had to be the same and varying loads
could only be catered for by varying the flange
thickness. This meant that the quality of fabrica-
tion and welding had to be of a high standard.
Steel for the roof was fabricated in England and
Singapore prior to receiving a h t coat of paint
before being shipped to Hong Kong,where it w a s I-- -

assembled. The contractor set up five jigs on site,


the largest one being capable of holding a 36 m x
54 m long module with the rise on the barrel
vault being 6 m (FE.9). The smooth-flowing
alignment of the geometry of the roof demanded
good dimensional tolerance conkol. The average

45

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
THOMSON AND
OAKERVEE

F*. 12. Roof Of pm-


senger denniprat com-
pleted and weather-

l
tight (lune 1997)

I .

porters, whichtook it to store where it was fitted form a stitch beetween adjacent roof moduIes. The
out with purlins, roof sheeting,walkways and sky- final module was lifted into position on 23
lights. December 1996.
In total 136 modules were assembled, each T h e roof covering comprised layers of metal
weighing mythiig between 40 and 140 t The fist decking, cementitious boarding to provide a
module was l i d into position on 31 December sound insulation layer, thermal insulation, a
1995 using another 1000 t crawler crane (Fig. 10). vapour barrier and two layers of W C waterproof Fig. 13. Roofcm-
A beam launcher supported by temporary towers membrane @g. 12). The perimeter of the building tihuering 36 m otct
was used to move modules laterally into the cen- was then glazed at departure level and a propri- h m the pmmger fer-
tre of the building where they could not be placed etary panel cladding system was fixed at arrivals milnal building to
directly using the large cranes (F
' ig.11). and apron levels. couw the deparfasra
Individual members were then welded in sik to There are 38 frontal gates which comprise a forecourt

46

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION

bifurcated k e d link to separate arriving and tal, ventilation, fie and hydraulic services.These
departing passengers, each connected to pairs of two major contracts were awarded on the same
apron drive airbridges. The k e d links were fabri- day because of the close dependency of one upon
cated and erected i~ situ whereas the apron dri- the other, both as to the need for the works to
ves were manufactured offshore and brought progress in parallel and for each contractor to
complete to Hong Kong. assist the project manager to cmrdmate the
The building services contract was awarded on design and construction of the works.
30 January 19995 on the same day as the passen- The tendering of nominated fit-out sukonkacts
ger terminal building contract At H Q 1.88 bdlion was delayed because funding was not available
it was reputed to be one of the largest single until the AA was established in December 1995.
building services contracts ever awarded. The This resulted in the AA not being able to nominate
works comprised four major disciplines of electri- the 6rst packages until May 1996, at which time
the contractor objected to the nominations collec-
tively because of the lateness and their incornpa&
bility with his own contract programme. This
impasse was broken by the AA negotiatingterms
for the withdrawal of the notice of objection.
These included a comercid settlement for all
claims submitted up ta July 1996 and agreement to
work to a new programme to completion which
would ensure an April 1998 airport opening date.
A supplemental agreement was signed by the AA
and the conkactor in September 1996 which set-
tled these matters. It was necessary to negotiate
concurrently a separate agreement with the build-
ing services contractor to ensure both would be
working to the same programme to completion.
Ultimately there were 22 nominated subcon-
tracts, two domestic sub-contractsand eight
direct contracts for what were all originally
included as prime-cost sums in the passenger ter-
minal building contract. These,together with the

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
THOMSON AND
OAKERVEE

Fig, 15. Dynamic


compactioA roller

12 other direct contractors working for the A4 in earth was rehandled by using a mixed fleet of
the FIE, gave the project manager's teaman self propelled scrapers and articulatedtrucks
enormous task to carry outhis duty to coordi- loaded by back-hoes. Compaction of the marine
nate the design and constructionactivities of all sand was achieved by using up to 40 passes of a
contractors. For example, the nominated sub-con- 20 t high-energy impact roller towed by four-
tractor for the internal metal walling in public wheel drive eactors ( F i g 15). The final com-
areas had to be given aIl the interface require- paction was carried out by watering and four pass
ments by the project manager who gathered the es of a towed 15 t vibrating roller. All formations
information from all other contracts before the were proven by the passage of a pneumatic-tyred
design of the panelling designcould be finalized 200 t proof roller, which simulated the maximum
and be released for offshore manufacture. Some aircraft wheel loadings.
idea of the magnitude of this problem can be Runway pavement conskuction comprised a
imagined when the total length of wall cladding to 400 m m thick layer of crushed aggregate base
be installed under this package was over 40 km. course (CABC). The specified minimum 10%
The fit-out works were substantiallycomplete by h e s values of 180 kN for this material could not
February 1998 (Figs 13 and 14). be guaranteed from the aggregates arising from
Chek Lap Kok, and the contractor had to import
Airfield works 3 Mt of aggregates from China to produce the
The contract €or the airfield works was award- CABC and other materials requiring this higher
ed in the sum of HK$ 2.4 billion on April 1995. quality aggregate. The contractor set up a
The major works comprised the construclion of marine aggregate unloading facility to handle
the southern runway (3800 m long by 60 m materials brought to h e site by barge. From
wide), three parallel taxiways, two cross-field there the aggregates were blended to the right
taxiways, the passenger aircraft aprons and the proportions using one of three pug mills, each
cargo aprons, giving a total paved area of 370 having the capacity to process 200 t/h of materi-
ha. The runway had t o be complete within 17 al. The pug mills loaded product intothe back of
months to allow instrument landing systemCali- articulated dumptrucks which delivered the
bration flights to start in November 1996 to CABC to pavers which spread the material in
match the programme for commissioning the specified thickness which were compacted using
overall air traffic control systems for the new vibrating rollers.
airport. The contractor set up a hot mix asphalt plant
The site preparation of the runway area had on site which had a capacity to produce 200 t/h,
been left unprofiled and in flat platforms compact- which was delivered to three paving machines.
ed to 95%standard Procter dry density. The first The total quantity of asphalt placedwas 480 000 t
operation was to profile the earthworks by relo- and the maximum production recorded in a
cating 2 Mm3 of material and improving the densi- seven-day period was 12 000 t.

- 48
ty to 95%and 98%modified Procter dry density to
depths of 2 m and 300 mm, respectively. The
The third form of paving employed was con-
crete block paviors which wereused where con-

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
ensure good interlocking properties.The total
quantity of blocks placed was 400 000 m2 and the
maximum production achieved in a sevm-day
period ~ 8 8OOO
8 NP-. Outputs W R vety m-
cantlylowerthanthisintirnesofrainaudalso
where theareaswere small, irregular in shape or
had inserts such as mmhola.
The runway contractor was also responsible for
the fuel hydrant and distribution system works.
This comprised 18 km of 6430 mm dia. pipework
with 13 mm wall thickness. pipes were manufac-
tured in 10 m lengths in the USA and sprayed
internally with epoxy coating and wrapped with
protective hpe externalb in Malaysia The pipes
were welded together at the side of the trench
and then lowered into position followingX-ray
inspection of every weld. The whole system was
charged with aviation fuel and tested to a pre4
sure of up to 28 bar.
The main contractorwas also responsible for
the M e l d ground lighting, the high mast light-

49

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
THOMSON AND
OAKERVEE

ing and the grassing works. The ground lighting and depart by high-speed train, by private car, by Fig 18. Sou#hksrn
contractor had to coordinate closely the installa- taxi, by tour coach or by bus. All these works commercial area
tion of the base cans,which house the lights, into were awarded to a single contractor on l January (December 19971
the subbase works as this proceeded.The 1996 following the completion of a separate COP
asphalt was then placed before coring at the loca tract for the piling works.
tion of the cans and the light fitting installed. The design and construction of the railway
There were 7000 lights in the contract which works on Chek Lap Kok were entrusted to the AA
were wired in series on a constant current with by the Mass Transit Railway Corporation
voltage up to 6Ooo v. WTRC), which was responsible for the design,
The first aeroplane to land on the new runway construction and operation of the whole of the
touched down on 20 February 1997. This was hi- new airport express railway.The railway station
lowed by a daily test plan whereby a Federal itself was of reinforced concrete and built on
Aviation Adminisbation aircraft made a series of three floor Ievels with a concrete roof covered by
landings, flights and takeoffs to test the air traffic duminium cladding FE.17). Passengers are
control systems installed and operated by the enclosed in an air-conditioned environmentby a
Civil Aviation Department (Fig. 16). curved glazed atrium and are able to walk m o s s
bridges and ramps to and from the passenger ter-
Ground transportation centre minal building protected from the weather. The
The passenger terminal buildingand the air- main contractor was also responsible for the
field works are used to process and transport pea building servicesworks and the fit out works car-
ple who are travelling by air.There is an equal ried out by two nominated sukontractors.
chdenge to process and transport people on the Other railway works constructed by the AA
pound; at Chek h p Kok h s is done at a ground included a traction sub-station,the iack formation
transportation centre immediately adjacent to the at grade, the approach and departures viaducts
passenger terminal. This allows people to arrive and a cleaning platform at the end of the lines.

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION

The back-related works were subsequently wide and 20 m above ground Iwel. T h e lower Fig, 19. Airport sub-
installed by the MTRC systemwide contractors. deck is used as a m s f e r area for pedestrians to stantially comfileted
The works also included the provision of facib circulate. Below this is a service road at grade and (March 1998)
ties for motor vehicular transport. Vehicles wiU below the service road lies the utilities corridor
arrive at Chek Lap Kok by means of a six-lane which provides all the services necessary to sup
expressway elevated to departures ievei by an port the PTB. Construction of this part of the
, -
approach ramp which is seven spans long, M) m works was h-oublesomebecause of the multi-layer
nature of the work which had to be carried out in
a long and narrow congested works area with lim
ited access.
The vehicles are brought down to ground level
from kerb level by way of another post-tensioned
concrete viaduct. Vehicles can then rejoin the
expressway at grade, go to a multi-storey car
park, a coach park or taxi stand or join the local at
grade road disfribution system. Arriving passen-
gers find all their land mnsportation at facilities
provided at grade which were constructed by the
main contractor for this package of work.

Infrastructure works
An international airport needs extensive infra-
structure support facilities, notably a road and
utility distribution system on the scale of a small
town. A iarge contract to provide infrastructure

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
THOMSON AND
OAKERVEE

facilities to the south and eastern parts of the contractors and fitted out with the standard of fin-
island was let in September 1995 @g. 18). ish and facilities normally found in any computer
This contract was not technically dirficult but room. The primary and secondary nodes were
the logistics and coordination management equipped with the airport operational database
required provided the main challenges. Key quan- (AODB)computers which provided the nerve
tities are given in Table 4. centres. The nodes are connected together by a
In addition to this package the AA managed a local area network which comprises fibre optic
number of other stand-alone constructioncon. and copper cables laid in the ducts and other
bads which had to be awarded individually for cable containment provided by other contractors.
programming or logistical reasons.These were This provided the backbone links which the other
for the following - facilities systems contractors could hook on to by connec-
tion into the cable terminationpoints.
33 kV primary electrical substation contain- Each system was tested and commissioned on a
ing imnsformers and switch gear standalone basis before they were all integrated
sea-water pumping station to house four 900 and tested together. To assist this a speciaI build-
mm dia. pumps ing was constructed and fitted out on site to carry
sea-water pumps (22 ranging 6-om 70 l/s to out as much testingand integration as possible
680 V s ) using simulation.This dowed much of the com-
33 kV electricity supplysystem for 81 MVA puter software to be debugged in advance of the
capacity hardware being hmsferred and installed in the
25 km of high voltage and 17 km of low vok works and helped shorten the period during which
age distribution the systems works were on the critical path.
13 km of gas distribution system
1600 street rights and 193km of associated Concluding remarks
cable works The Hong Kong construction industry has an
one grey-water treatmentplant of 4900 excellent record in overcoming enormous chal-
&/day capaciw. lenges in order to complete major projects on
time and within budget. Nowhere is this better
Communications systems illuskated than the achievements seen on the air-
A modern internationalairport requires an port projectand on the Airport CoreProgramme
uptc-date integrated communicationssystem. as a whole. The challenges were made even
This comprises two major parts: that which is greater when itwas announced in late 1996 that
inside the passengerterminal building and that construction of the second runway and an exten-
which cover the rest of the airport site. The sion to the passenger terminal building should
overall design resulted in a seamless link start before opening of the airport. Due to Bong
between the two parts to produce a single inte- Kong’s continued economic growth, it is planned
grated communication system. This design was that the second runway should be operational
packaged and let in ten contracts for the before the end of 1998, to be followed shortly
detailed design, manufacturing, installation, test- thereafter by opening of the north-west concourse
ing and commissioning. The packages and some extension to the passenger terminal building.
of the items provided are (see Appendix 1)
References
flight information display system 1. LAM B. C. L Management and procurement of the
public address system Hong Kong Airport Core Programme Pruceedings
telephone system of the Instifulfoopnof Civil Etlginem, Civil
E ~ g i t t ~ & gHong
, Kong Internatioml Airport Part
trunk mobile radio systems
1: airport, 126,1998, 514.
closed-circuit teIevision system 2. G. and O ~ V E D. E Hong Kong International
access detection and conwol system Airport-civil engineering design. Procedings offha
building management system and SCADA Insfifartionof Civil Engittem, Civil Engineen-%,
fibre-optic and copper cabling Hong K o ~ g lnternatimtaiAirport Part l :ahport,
systems integration 126,1998, 15-34.
traffic surveillance and controlsystem. 3. New Ai@ort Master Plan Final Report, Greiner
Maunsell, 1991.
Basically, the system comprised a network Imk- 4. AWN I. J. Survey aspects in the construction of
ing fourprimary nodes, ten secondary nodes and Hong Kong’s new airport of Chek Lap Kok,Technkd
fiffy user nodes. A node in simple terms is a corn Proceeditw of the 5th South East Asiatt a d 36th
Alrstralian Surueyors Con,ym, Singapore, 1995.
puter room which has been constructed by other

52

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
CONSTRUCTION

Afipmdix 1: List of all coatmetors and nominated sub-contractom

'

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.
,. , .. . ,

THOMSON AND
OAKEKVEE

Downloaded by [ Indian Institute of Technology Roorkee] on [15/10/19]. Copyright © ICE Publishing, all rights reserved.

You might also like