Progress Report Manlin

You might also like

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 4

I.

Reporting Period

Reporting period: January 2018 Report submitted on (date):


Due date:
Planned project duration: 10 days
Planned target date of implementation Actual date started: April 19, 2017
Total Project Cost: 21,200.00 Extended until:

II. IDENTIFYING INFORMATION

Project Title: Construction of Dirty Kitchen in Manlin Daycare Center

Type of Project: Cash for work within 10 days

Project Proponent/s: MCCT-IP in GIDA

Number of Beneficiaries: 12 MCCT-IP

Project Beneficiaries: MCCT-IP in GIDA


Project Partner stakeholders: BLGU

Location of Beneficiaries: Brgy. Manlin, Buug ZSP

Area of Project Implementation: Manlin Daycare Center

Project Cost:
a. Grants- 25,200.00
b. Local counterpart Contribution
c. BLGU/MLGU- sand, gravel, cement, wood, (construction materials)
d. Community/Individual contribution

Summary of the project progress (bullet type)


1. No. of days of implementation (applicable for CBLA/CFW)
 10 days
2. Activities completed (such as training conducted for ST)
3. No. of beneficiaries involved
 12
4. Physical accomplishment/activity accomplishment (descriptive)
 12 MCCT-IP beneficiaries have constructed the dirty kitchen of Manlin Daycare center; 5
male beneficiaries were the ones who did the dirty kitchen while the 7 female
beneficiaries did the transferring of the materials from barangay hall to the daycare
center. They also did the school backyard gardening and fencing.
5. Issues/gaps/problems/challenges encountered during the implementation
 Lack of materials.
6. Actions taken and needed assistance

 The daycare will continue to maintain the dirty kitchen. For the fencing, the beneficiaries
contributed the bamboo.

Photo documentation (beneficiaries in action, before and during implementation of the activity/pictures
showing accomplishments):

The MCCT-IP Beneficiaries gathered mangrove seedlings ready for planting and cleaned the
project site.
Prepared By: Reviewed By: Noted By:

KALYN M. TAYCO LEONNIEL C. LAMPERO FLORDELIZA ALAR-ATUY


CF SWO III Provincial Link

You might also like