Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 10

END USER: CONSULTANT: MAIN CONTRACTOR: CIVIL SUB CONTRACTOR:

SIEMENS
SIMPLEX INFRASTRUCTURES
LIMITED

Main Contractor:

SIEMENS

Civil Contractor:

SIMPLEX INFRASTRUCTURES LIMITED

Project/Contract Ref: Construction of 132/11kv Substation (G+1) Saada Street, Plot no.-
3372212

Document Title: METHOD STATEMENT - SUBSTRUCTURE WATERPROOFING WORKS

Document No:

2 0 1 6 M S 03 0 0 0 0 Rev. 0

0 18/04/2016 Issue for Subir Lalit Mr Rajesh


approval Adhikari Talpada
Rev Date Purpose Prep. Check Approved Client Date

SUBSTRUCTURE WATERPROOFING WORKS SS/P2/MS/003/0 Page 1


END USER: CONSULTANT: MAIN CONTRACTOR: CIVIL SUB CONTRACTOR:

SIEMENS
SIMPLEX INFRASTRUCTURES
LIMITED
Document No: Project Rev : DATE:
Substation 0 18-04-2016
Title: METHOD STATEMENT - SUBSTRUCTURE WATERPROOFING WORKS

METHOD STATEMENT FOR SUBSTRUCTURE WATERPROOFING WORKS FOR SAADA STREET


132/11 KV SUBSTATION

CONTENTS

1.0 OBJECTIVE

2.0 SCOPE

3.0 APPLICABLE DOCUMENT OR REFERENCES

4.0 PREPARATION

5.0 CONTROL MEASURES

6.0 RESPONSIBILITY

7.0 WORK SEQUENCE

8.0 QUALITY/TESTING

9.0 PPE

10.0 MISCELLANEOUS

11.0 RESOURCES

12.0 SAFETY

13.0 SITE TIMING

SUBSTRUCTURE WATERPROOFING WORKS SS/P2/MS/003/0 Page 2


END USER: CONSULTANT: MAIN CONTRACTOR: CIVIL SUB CONTRACTOR:

SIEMENS
SIMPLEX INFRASTRUCTURES
LIMITED
Document No: Project Rev : DATE:
Substation 0 18-04-2016
Title: METHOD STATEMENT - SUBSTRUCTURE WATERPROOFING WORKS

1.0 OBJECTIVE

This method statement describes a work explanation of the method for carrying out
substructure waterproofing works on concrete surface at sites for DEWA substation projects
to ensure that during the entire execution stage, the work is done in line with good
engineering practices and in compliance with engineering standard practices, nation & local
codes.

2.0 SCOPE OF WORKS

The procedure shall be applicable to for all types of substructure waterproofing works on
concrete surface undertaken by the company for substructure works.

3.0 APPLICABLE DOCUMENT OR REFERENCES

 Contract / Project Specification.

 Drawing (3761500066/SAADAST/C/15/281A)

 Risk Assessment

4.0 PREPARATION

 Simplex will produce a programme of works such that Client are aware of proposed area of
works and can advise on logistical constraints imposed by other contractors.

5.0 CONTROL MEASURES

 Ensure all permissions and consents have been obtained.

 Ensure approval status of this Method Statement has received “1” or “2” status.

 Ensure drawing for substructure waterproofing works to be submitted for approval.

 Ensure all the materials for waterproofing works are approved prior to using at site.

SUBSTRUCTURE WATERPROOFING WORKS SS/P2/MS/003/0 Page 3


END USER: CONSULTANT: MAIN CONTRACTOR: CIVIL SUB CONTRACTOR:

SIEMENS
SIMPLEX INFRASTRUCTURES
LIMITED
Document No: Project Rev : DATE:
Substation 0 18-04-2016
Title: METHOD STATEMENT - SUBSTRUCTURE WATERPROOFING WORKS
 Ensure maintain a system of records that permit verification of any issued report before
and after work.

 Prepare necessary Toolbox talks.

 Ensure work area is cordoned off.

 Site briefings will be undertaken to induct all operatives in the detail of this method
statement. All personnel attending will sign the briefing sheet acknowledging they
understand the briefing given.

6.0 RESPONSIBILITY

6.1 The Project Manager along with his site team is responsible for entire substructure
waterproofing works of main building raft foundation to be done as per this Method
Statement.

6.2 The Site Engineer, Foremen are responsible for all the works and all associated
activities under this method statement at his assigned work location.

6.3 The QC Engineer is responsible for compliance of complete work as per the approved
method statement will offer for Consultants approval.

6.4 The Surveyor will mark along the areas where the substructure waterproofing work
needs to be done.

6.5 The Safety Officer is responsible to ensure all safety precautions are in place. Tool box
talks will be conducted for awareness of the operatives involved in the work and PPE are
worn at all time.

7.0 WORK SEQUENCE

The method statement included safety aspect during the work, preparation of the work, main
tools and equipment utilized, survey and all related necessary to complete the entire work.

SUBSTRUCTURE WATERPROOFING WORKS SS/P2/MS/003/0 Page 4


END USER: CONSULTANT: MAIN CONTRACTOR: CIVIL SUB CONTRACTOR:

SIEMENS
SIMPLEX INFRASTRUCTURES
LIMITED
Document No: Project Rev : DATE:
Substation 0 18-04-2016
Title: METHOD STATEMENT - SUBSTRUCTURE WATERPROOFING WORKS
WORK SEQUENCE FOR WATERPROOFING WORKS

7.1 Sequence of works :- Horizontal surface (bottom of Raft Foundation)

 Make sure concrete surface clean and free from contamination such as dust, oil, grease,
release agent and curing compounds.

 Existing concrete surface should be smooth and without any sharp edges, fill with
approved cementicious material if pot holes found at surface of concrete.

 Mix/Stir the Polyprime SB until a homogenous consistency is achieved.

 Apply Polyprime SB using a brush or roller to the prepared surface to give an even,
continuous, unbroken coating.

 Ensure top of primed surface should be clean before application of Bituplus E4270-SBS
Modified Bitumen Waterproofing Membrane-4mm thick. Single Layer

 Fix the membrane to the desired length and shape with a help of torch application,
allowing for a 100mm side lap and 100mm end lap on the rolls.

 Place the membrane on the area to be covered and check the pieces match as required
on the substrate.

 Subsequent rolls should be laid in a similar fashion, overlapping by 100mm long the side
selvedge & 100mm at the ends of the rolls to provide continuous waterproofing
membrane.

 Roll all overlaps to ensure full contact between rolls & with the primer.

 Continue to waterproof the entire area, extending by a minimum of 250mm beyond the
building line in order to create an overlap with the vertical membrane.

 After completion of waterproofing protect the membrane by laying of screed concrete.

SUBSTRUCTURE WATERPROOFING WORKS SS/P2/MS/003/0 Page 5


END USER: CONSULTANT: MAIN CONTRACTOR: CIVIL SUB CONTRACTOR:

SIEMENS
SIMPLEX INFRASTRUCTURES
LIMITED
Document No: Project Rev : DATE:
Substation 0 18-04-2016
Title: METHOD STATEMENT - SUBSTRUCTURE WATERPROOFING WORKS
7.2 Sequence of works :- Vertical surface (Walls)

 Make sure concrete surface clean and free from contamination such as dust, oil, grease
&release agent and curing compounds.

 Existing concrete surface should be smooth and without any sharp edges, fill with
approved cementicious material if pot holes found at surface of concrete.

 Fill the tie-rod holes with approved materials.

 Mix/Stir the Polyprime SB until a homogenous consistency is achieved.

 Apply Polyprime SB using a brush or roller to the prepared surface to give an even,
continuous, unbroken coating.

 Apply a 45-degree sand/cement fillet at floor/wall junctions and allow to cure.

 A 200mm wide reinforcing strip should be provided at all corners and changes in
direction such as floor/wall junctions, prior to the main membrane applications.

 Apply the Bituplus E4270-SBS Modified Bitumen Waterproofing Membrane-4mm tk.


Single Layer membrane vertically with a torch application in the same fashion as for
horizontal, however always waterproof from the lowest to the highest point, allowing for
an overlap of 100mm on end joints giving a weathered lap.

 Press the membrane onto the substrate from the centre to the sides, to ensure a good
bond to the primer and removal of any entrapped air, Roll all overlaps to ensure full
contact with the primer.

 Subsequent rolls should again be overlapped by 100mm along the sides using the
selvedge.

 Continue applying until the entire area is covered.

 Membranes to be terminate as per required level with the help of Bitumastic Bitumen
Rubber Mastic Sealant.

SUBSTRUCTURE WATERPROOFING WORKS SS/P2/MS/003/0 Page 6


END USER: CONSULTANT: MAIN CONTRACTOR: CIVIL SUB CONTRACTOR:

SIEMENS
SIMPLEX INFRASTRUCTURES
LIMITED
Document No: Project Rev : DATE:
Substation 0 18-04-2016
Title: METHOD STATEMENT - SUBSTRUCTURE WATERPROOFING WORKS
 Apply the 3.2mm tk. Bituboard protection board to protect the membrane on Vertical
Surface with the spot bonding system.

 Backfill the area with approved method statement to complete the waterproofing
system.

7.3 Main tools & equipment

 Crane – 1 No. (For shifting of materials)

 Mini Roller / Plate compactor – 01 No.

 Diesel Generators for Power supply.

 Wheel barrow

 Shovels/spades

 Scrapers

 Knife for cutting membranes

 Brush/Roller

 Electrical Air Blower

 Mixing Paddle

 Propane Gas Torch Machine

8.0 QUALITY/TESTING

 Visual inspection by Consultant / Client Representative.

 Site Engineer on site for conformance.

 The waterproofing work activities will be controlled using an Inspection Test Plan (ITP). The
ITP will be approved by the Consultants / Client and will include:

SUBSTRUCTURE WATERPROOFING WORKS SS/P2/MS/003/0 Page 7


END USER: CONSULTANT: MAIN CONTRACTOR: CIVIL SUB CONTRACTOR:

SIEMENS
SIMPLEX INFRASTRUCTURES
LIMITED
Document No: Project Rev : DATE:
Substation 0 18-04-2016
Title: METHOD STATEMENT - SUBSTRUCTURE WATERPROOFING WORKS
 Hold points for Consultant / Client Inspections.

 Frequency and Standard of Testing.

 Test Points for Independent Testing Agencies.

 Details of retained and non-retained documents.

 Applicator for the substructure waterproofing works will be certified from Manufacturer.

9.0 PPE

 Hand tools

 Barriers

 Hand Gloves (Rubber) & Safety Goggles

 Safety Boots (Gum Boots with Steel Toe

 Hard Hats

 Coverall/Uniform.

10.0 MISCELLANEOUS

 Small Tools

 Fire Extinguishers

11.0 RESOURCES

SITE ENGINEER - Ensure operatives confirm to Method Statement.


Direct surveyor on site.
Ensure that correct drawings are used on site.
SURVEYOR - Work with Engineer to establish levels for information.
Carry out as-built survey works as directed by the Engineer.
Set up and check rotating laser level and other level control.
Ensure that site instrumentation in maintained.

SUBSTRUCTURE WATERPROOFING WORKS SS/P2/MS/003/0 Page 8


END USER: CONSULTANT: MAIN CONTRACTOR: CIVIL SUB CONTRACTOR:

SIEMENS
SIMPLEX INFRASTRUCTURES
LIMITED
Document No: Project Rev : DATE:
Substation 0 18-04-2016
Title: METHOD STATEMENT - SUBSTRUCTURE WATERPROOFING WORKS
SUPERVISOR - Direct labour as requested by the Engineer.
Ensure operatives are working accordance with method statement.
OPERATIVES - Carry out work as directed by the Charge Hand & Engineer.

12.0 SAFETY

 Site safety induction will be carried out.

 All operative will receive a method statement briefing and this will be maintained as a site
record.

 All operative will maintain all the safety requirements for the project throughout the work
duration. This will include the wearing of Safety hats, High Visibility vests & Safety boots
and others as required for the job.

 Trained and Skilled Operators shall be employed for operating heavy machineries like
cranes, etc.

13.0 SITE TIMING

7:00 AM to 7:00 PM

SS—SUB STATION

P2—CONTROL OF RECORDS

MS—METHOD STATEMENT

SUBSTRUCTURE WATERPROOFING WORKS SS/P2/MS/003/0 Page 9


END USER: CONSULTANT: MAIN CONTRACTOR: CIVIL SUB CONTRACTOR:

SIEMENS
SIMPLEX INFRASTRUCTURES
LIMITED
Document No: Project Rev : DATE:
Substation 0 18-04-2016
Title: METHOD STATEMENT - SUBSTRUCTURE WATERPROOFING WORKS

SUBSTRUCTURE WATERPROOFING WORKS SS/P2/MS/003/0 Page 10

You might also like