C.

HARGA SATUAN DASAR BAHAN DAN


MATERIAL

STANDAR BIAYA BAHAN/MATERIAL


BANGUNAN

HARGA
SPESIFIKASI SATUAN
NO BAHAN / MATERIAL SAT
BAHAN HARGA
KONTRAKTUAL
A. Agregat Kasar, Bahan Perekat & Bahan Jadinya

1 Pasir Urug m3 237.518,33 261.270,17

2 Tanah Urug Pilihan m3 183.900,33 202.290,37

3 Sirtu m3 239.870,00 263.857,00

4 Pasir Teras m3 180.000,00 198.000,00

5 Pasir Pasang Kali m3 206.946,67 227.641,34

6 Pasir Beton m3 289.255,00 318.180,50

7 Abu Batu m3 298.661,67 328.527,83

8 Koral Beton m3 216.353,33 237.988,67

9 Batu Gosok (Apung) Kg 29.913,20 32.904,52

10 Batu Pecah Mesin 1/2 m3 315.123,33 346.635,67

11 Batu Pecah Mesin 2/3 m3 348.752,17 383.627,38

12 Batu Pecah Mesin 3/5 m3 293.958,33 323.354,17

13 Batu Pecah Mesin 5/7 m3 283.305,28 311.635,81

14 Batu Belah Pondasi m3 265.738,33 292.312,17


Batu Bronjol (Untuk
15 Bronjong) m3 309.009,00 339.909,90

16 Batu Koral Beton Kali m3 316.534,33 348.187,77

17 Batu Tempel Hitam m2 266.208,67 292.829,53


18 Batu Pinggir Beton 10 x 20 x 35 buah 24.692,50 27.161,75

19 Batu Pinggir Beton 15 x 35 x 50 K-225 buah 88.893,00 97.782,30

20 Batu Telor m3 124.168,00 136.584,80

21 Batako Kecil 8 x 10 x 20 buah 2.586,83 2.845,52


Batako Besar 8 x 20 x
22 30 buah 3.527,50 3.880,25

23 Con Block 8 x 20 x 40 buah 7.407,75 8.148,53


Bata Merah Bakar
24 Kelas I buah 1.152,32 1.267,55
Bata Merah Bakar
25 Kelas II buah 905,39 995,93
Bata Merah Oven
26 (Klingker) buah 1.105,28 1.215,81

27 Bata Ringan buah 9.222,50 10.144,75

28 Rooster Beton 20 x 20 buah 13.263,40 14.589,74

29 Rooster Beton 30 x 30 buah 9.877,00 10.864,70

30 Rooster Jalusi 39 x 18,5 x 9 buah 11.993,50 13.192,85

31 Rooster Motif 20 x 20 buah 25.398,00 27.937,80

32 Rooster Polos 20 x 20 buah 20.812,25 22.893,48

33 Rooster Silang 20 x 20 buah 23.634,25 25.997,68

34 Rooster Espana buah 31.747,50 34.922,25


Rooster / Bata
35 Kerawang buah 8.254,35 9.079,79

36 Rooster Keramik 30 x 30 buah 49.385,00 54.323,50

37 Rooster Keramik 20 x 20 buah 35.275,00 38.802,50

38 Rooster Keramik 18 x 18 buah 33.158,50 36.474,35

39 Grass Block 20 x 20 buah 21.494,23 23.643,66


40 Grass Block 30 x 30 buah
24.974,70 27.472,17

41 Paving Blok Natural 8 cm m2 114.667,27 126.133,99

42 Paving Blok Warna 8 cm m2 134.374,23 147.811,66

43 Paving Blok Natural 6 cm m2 97.594,17 107.353,58

44 Paving Blok Warna 6 cm m2 112.174,50 123.391,95

45 Canstin Paving Blok m' 110.481,30 121.529,43

46 Semen PC/ 50 Kg zak 82.000,00 90.200,00

47 Semen Putih zak 130.517,50 143.569,25


Semen Mortar Utama
48 (MU) Zak 84.660,00 93.126,00
Kanstin Jalan Ukuran
49 Besar (Bina Marga) 1 buah
65.000,00 71.500,00
buah = 60 cm
50
K550, Tanpa
Readymix Beton m3 1.622.650,0
Pompa (Selang)
51 0 1.784.915,00
K500, Tanpa
Readymix Beton m3 1.552.100,0
Pompa (Selang)
52 0 1.707.310,00
K400, Tanpa
Readymix Beton m3 1.340.450,0
Pompa (Selang)
53 0 1.474.495,00
K350, Tanpa
Readymix Beton m3 1.251.086,6
Pompa (Selang)
54 7 1.376.195,33
K300, Tanpa
Readymix Beton m3 1.213.460,0
Pompa (Selang)
55 0 1.334.806,00
K250, Tanpa
Readymix Beton m3 1.171.130,0
Pompa (Selang)
56 0 1.288.243,00
K225, Tanpa
Readymix Beton m3 1.145.261,6
Pompa (Selang)
57 7 1.259.787,83
K175, Tanpa
Readymix Beton m3 1.126.448,3
Pompa (Selang)
58 3 1.239.093,17
K125, Tanpa
Readymix Beton m3 1.072.360,0
Pompa (Selang)
59 0 1.179.596,00
Kapur Pasang/kapur
60 Tembok m3 485.054,77 533.560,24

61 Kapur Sirih kg 13.169,33 14.486,27

62 Semen warna kg 13.639,67 15.003,63

63 Tanah Liat m3 76.723,13 84.395,44

64 Air liter 689,47 758,42

65 Formite/spacer buah 28.220,00 31.042,00

66 Hollow/Con Blok 8 x 20 x 40 buah 5.538,18 6.091,99

67 Hollow/Con Blok 8 x 15 x 40 buah 6.490,60 7.139,66

68 Hollow/Con Blok 8 x 10 x 40 buah 5.996,75 6.596,43

69 Semen Nat kg 9.000,00 9.900,00

70 Kapur padam m3 82.300,00 90.530,00

71 Semen merah m3 300.000,00 330.000,00

72 kerikil kg 1.700,00 1.870,00

73 Batu Granit kg 3.900,00 4.290,00

74 Batu Teraso kg 2.400,00 2.640,00

75 alat bantu lot 66.000,00 72.600,00

B. Laburan, Pengisi dan Alatnya

1 Plamir Tembok kg 51.148,75 56.263,63


Cat Tembok ICI
2 Eksterior (Beton) liter 130.517,50 143.569,25
3 Cat Tembok ICI Interior liter
(Plafon dan Dinding) 91.715,00 100.886,50

4 Cat Tembok Vinilex Kg 30.900,00 33.990,00


Cat dasar ICI untuk
5 liter
Interior (2 pelapis) 138.278,00 152.105,80

6 Cat Tembok Sanlex kg 21.635,33 23.798,86

7 Cat dasar kg 33.581,80 36.939,98

8 Cat Tahan Asam liter 126.990,00 139.689,00

9 Cat Genteng liter 65.611,50 72.172,65

10 Weatershield liter 303.365,00 333.701,50


Pelapis Alkali ICI (Cat
11 kg
Dasar Beton Eksterior) 190.485,00 209.533,50

12 Cat Marka/Spotlight kg 117.254,10 128.979,51

13 Water Profing Emulsion kg 90.304,00 99.334,40


Water Profing
14 Membrance ml 112.880,00 124.168,00

15 Rol Cat Tembok buah 35.275,00 38.802,50

16 Kape Tembok buah 12.699,00 13.968,90

17 Kape Kayu buah 10.582,50 11.640,75

18 Soligneum 1 blek kg 39.508,00 43.458,80

19 Plincote m3 38.449,75 42.294,73

20 Pengawetan Kayu m3 423.300,00 465.630,00

21 Pengopenan Kayu buah 634.950,00 698.445,00

22 Kwas 3" buah 18.343,00 20.177,30

23 Oker bks 25.398,00 27.937,80

24 Oyan bks 2.822,00 3.104,20

25 Oten (Pewarna Plitur) liter 5.644,00 6.208,40


26 Spirtus kg 14.815,50 16.297,05
Bahan Pelitur Kripik
27 (Sirlak India) kg 64.906,00 71.396,60

28 Dempul Lilin kg 38.802,50 42.682,75

29 Dempul Plitur kg 43.741,00 48.115,10


Dempul Halus / Impra
30 (Wood Filler) liter 38.097,00 41.906,70

31 Dempul Jadi kg 35.275,00 38.802,50

32 Politur liter 64.906,00 71.396,60

33 Politur Jadi liter 66.317,00 72.948,70

34 Terpentin kg 20.459,50 22.505,45

35 Tiner A kg 28.220,00 31.042,00

36 Tiner B liter 23.987,00 26.385,70

37 Kumpon lbr 93.831,50 103.214,65

38 Melamik kg 67.728,00 74.500,80

39 Dempul Plastik kg 61.378,50 67.516,35

40 Dempul Duco kg 40.919,00 45.010,90

41 Ampelas lbr 4.233,00 4.656,30


Dempul kayu cap
42 Kucing kg 31.747,50 34.922,25

43 Meni Kayu / Besi kg 24.692,50 27.161,75

44 Sincromat kg 46.563,00 51.219,30

45 Cat Kayu Sieve liter 68.786,25 75.664,88

46 Cat Besi liter 65.258,75 71.784,63


Cat Besi Duco
47 Danaglos / ICI buah 112.880,00 124.168,00
48 Cat Bron kg
88.187,50 97.006,25

49 Karet Lis buah 21.165,00 23.281,50

50 Minyak Cat kg 35.275,00 38.802,50

51 Glass Beet kg 25.398,00 27.937,80

52 Residu liter 35.275,00 38.802,50

54 Vernis ltr 104.300,00 114.730,00

55 Kuas Roll 9" buan 25.000,00 27.500,00

C. BAHAN KAYU BERIKUT BAHAN JADINYA

1 Bambu 5 s/d 7 btg 15.000,00 16.500,00

2 Bambu 7 s/d 10 btg 20.000,00 22.000,00

3 Bambu Gombong btg 53.712,07 59.083,27


Kayu Kamper Singkil / Kayu Samarinda Kls
4 m3 8.867.664,6
kapur II
7 9.754.431,13

6.100.223,3
5 Kayu Balok Borneo Super m3 3 6.710.245,67

6.255.433,3
6 Kayu Papan Borneo Super m3 3 6.880.976,67

8.075.623,3
7 Kayu Balok Kamper Medan (Kruing) m3 3 8.883.185,67

8.748.200,0
8 Kayu Papan Kamper Medan (Kruing) m3 0 9.623.020,00

8.040.348,3
9 Kayu Balok Kamper Banjar m3 3 8.844.383,17

8.604.748,3
10 Kayu Papan Kamper Banjar m3 3 9.465.223,17

11 Kayu Balok Kamper Samarinda m3 10.606.016, 11.666.618,33


67

11.290.822,
12 Kayu Papan Kamper Samarinda m3 00 12.419.904,20

3.922.580,0
13 Kayu Balok Rasamala m3 0 4.314.838,00

14.506.961,
14 Kayu Jati Jatim Tua dia. 40 cm m3 33 15.957.657,47

22.719.922,
15 Kayu Jati Jateng Tua 40 cm m3 00 24.991.914,20

11.982.212,
16 Kayu Jati Jabar Tua dia. 40 cm m3 00 13.180.433,20

10.380.021,
17 Kayu Jati Jabar Tua dia. 40 cm Kebawah m3 50 11.418.023,65
Segeng, Mahoni,
18 Kayu Hutan Kelas I m3 3.527.500,0
Laban
0 3.880.250,00

2.822.000,0
19 Kayu Balok Albasia Kayu Balok Albasia m3 0 3.104.200,00

2.963.100,0
20 Kayu Papan Albasia Kayu Papan Albasia m3 0 3.259.410,00

21 Dolken 5 s/d 7 Dolken 5 s/d 7 btg 21.306,10 23.436,71

22 Dolken 7 s/d 10 Dolken 7 s/d 10 btg 43.458,80 47.804,68

23 List Profil Kamper 1 cm 1 cm m' 11.852,40 13.037,64

24 List Profil Kamper 2 cm 2 cm m' 14.251,10 15.676,21

25 List Profil Kamper 4 cm 4 cm m' 15.521,00 17.073,10

26 List Profil Kamper 5 cm 5 cm m' 29.866,17 32.852,78


List Profil Kamper 10
27 cm 10 cm m' 55.029,00 60.531,90
Pegangan Tangga
28 Profil Jati m' 177.550,83 195.305,92
Pegangan Tangga
29 Profil Kamper m' 68.433,50 75.276,85

4.938.500,0
30 Kayu Kaso 4/6 m3 0 5.432.350,00

4.938.500,0
31 Kayu Kaso 5/7 m3 0 5.432.350,00
Kayu Reng 2/3 Borneo
32 Super m' 22.000,00 24.200,00
Kayu Reng 2/3 Kamper
33 Banjar m' 10.000,00 11.000,00
Kayu Reng 3/4 Kamper
34 Banjar m' 35.000,00 38.500,00

3.019.540,0
35 Kayu Papan Terentang m3 0 3.321.494,00

2.222.325,0
36 Kayu Balok Terentang m3 0 2.444.557,50

37 Batang Kelapa btg 846.600,00 931.260,00

38 Tali Ijuk kg 21.165,00 23.281,50


Lapisan Ijuk tebal 10
39 cm tebal 10 cm m2 21.165,00 23.281,50

40 Venetion Blind m2 268.090,00 294.899,00

41 Vertikal Blind m2 615.196,00 676.715,60

Kayu papan 3.000.000,0


42 Kelas I m3 0 3.300.000,00

Kayu Balok 3.000.000,0


43 Kelas I m3 0 3.300.000,00

Kayu Papan 2.600.000,0


44 Kelas II m3 0 2.860.000,00

Kayu Balok 2.500.000,0


45 Kelas II m3 0 2.750.000,00

Kayu papan 1.500.000,0


46 Kelas III m3 0 1.650.000,00
Kayu Balok 1.500.000,0
47 Kelas III m3 0 1.650.000,00
Dolken Kayu Galam Panjang 4 meter
48 ukuran 8-10 btg 22.000,00 24.200,00

Kayu Papan 3/20 4 m 2.100.000,0


49 m3 0 2.310.000,00

D. BAHAN PENUTUP RANGKA PLAFOND

1 Plafond Enternit 4 mm m2 28.220,00 31.042,00

2 Plafond Hardpleks 5 mm 120 x 240 lbr 80.427,00 88.469,70

3 Plafond Asbes Semen 5 mm m2 72.666,50 79.933,15

4 Plafond Asbes Semen 3,5 mm m2 22.576,00 24.833,60


120 x 240 t = 9 mm
5 Gypsum ex DN lbr 88.187,50 97.006,25
120 x 240 t = 9 mm
6 Gypsum ex Luar lbr 107.236,00 117.959,60

7 Tepung Gypsum kg 70.550,00 77.605,00

8 Acustik Amstrong 60 x 120 lbr 208.122,50 228.934,75

9 Cotton Plester buah 14.110,00 15.521,00


(120 x 240) cm, t =
10 GRC 4 mm lbr 72.666,50 79.933,15

11 Cornice Coumpound zak 119.935,00 131.928,50

12 List Gypsum m' 5.644,00 6.208,40

E. BAHAN KAYU LAPIS

1 Triplek 3 mm 120 x 240 lbr 67.492,83 74.242,12

2 Triplek 4 mm 120 x 240 lbr 84.895,17 93.384,68

3 Triplek 4 mm ukuran pintu lbr 64.906,00 71.396,60


4 Triplek 6 mm 120 x 240 lbr 125.579,00 138.136,90

5 Triplek 9 mm 120 x 240 lbr 184.841,00 203.325,10

6 Jabar Wood 4 mm lbr 131.223,00 144.345,30


Bilik Bambu (Tanpa
7 Kulit) m2 25.398,00 27.937,80
Bilik Bambu (dengan
8 Kulit) m2 32.453,00 35.698,30
Bilik Bambu Hitam
9 Variasi m2 40.213,50 44.234,85

10 Wall Paper (kelas Biasa) m2 35.275,00 38.802,50


(kelas
11 Wall Paper Menengah/sedang) m2 88.187,50 97.006,25

12 Wall Paper (kelas Baik) m2 134.045,00 147.449,50

13 Multiplek 9 mm 120 x 240 lbr 194.718,00 214.189,80

14 Multiplek 12 mm 120 x 240 lbr 255.391,00 280.930,10

15 Multiplek 18 mm 120 x 240 lbr 347.811,50 382.592,65

16 Plywood 18 mm 120 x 240 lbr 401.429,50 441.572,45

17 Plywood 9 mm 120 x 240 lbr 176.375,00 194.012,50

18 Plywood 4 mm 120 x 240 lbr 236.190,82 259.809,90

19 TeakWood 3 mm 120 x 240 lbr 93.126,00 102.438,60

20 TeakWood 4 mm 120 x 240 lbr 165.792,50 182.371,75


3 mm 120 x 240 Uk.
21 TeakWood Pintu lbr 134.045,00 147.449,50

22 TeakWood ukuran pintu 4 mm lbr 124.873,50 137.360,85

23 Tacon (Bahan Bakar) m2 131.928,50 145.121,35

24 Supercon m2 74.783,00 82.261,30

25 Melamin 4 mm 120 x 240 lbr 130.517,50 143.569,25


26 Melamin TOK 4 mm lbr
186.252,00 204.877,20

27 Formika 120 x 240 lbr 227.171,00 249.888,10

28 Formika Ukuran Pintu lbr 172.142,00 189.356,20

29 Formika Warna 4" x 8" lbr 315.076,30 346.583,93

F. BAHAN LANTAI DAN PELAPIS DINDING

1 Tegel PC 20 x 20 20 x 20 buah 1.566,21 1.722,83

2 Plin Tegel PC 20 x 20 20 x 20 buah 1.298,12 1.427,93

3 Tegel PC 30 x 30 30 x 30 buah 3.200,93 3.521,02

4 Plin Tegel PC 15 x 30 15 x 30 buah 999,46 1.099,41

5 Tegel Warna 20 x 20 20 x 20 buah 3.703,88 4.074,26


Plin Tegel Warna 10 x
6 20 10 x 20 buah 1.500,00 1.650,00

7 Tegel Warna 30 x 30 30 x 30 buah 4.233,00 4.656,30


Plin Tegel Warna 15 x
8 30 15 x 30 buah 1.148,60 1.263,46

9 Tegel Wafel PC 20 x 20 20 x 20 buah 4.671,82 5.139,00


Tegel Wafel Warna 20 x
10 20 20 x 20 buah 3.527,50 3.880,25
Tegel Badak PC 30 x
11 30 30 x 30 buah 5.323,70 5.856,07
Poslin 11 x 11 warna 11 x 11 warna
12 standar DN standar DN buah 1.411,00 1.552,10
Poslin 11 x 11 Warna 11 x 11 Warna
13 Khusus DN Khusus DN buah 1.411,00 1.552,10
10 x 20 dan 20 x 20
14 Keramik KW 1 DN
Putih/polos Mulia buah 3.094,75 3.404,23
10 x 20 KW 1
15 Keramik Corak/Warna/ Anti
slip Mulia buah 2.920,00 3.212,00
20 x 20 (KM) KW 1
DN
16 Keramik
Corak/Warna/Anti
Slip Mulia buah 2.822,00 3.104,20
20 x 20 (KM) KW 1
17 Keramik DN Putih polos
Mulia buah 2.892,52 3.181,77
20 x 25 Dinding
18 Keramik (KM) KW 1 DN
Corak Mulia buah 3.703,86 4.074,25
30 x 30 KW 1 Dn
19 Keramik
Putih Polos Mulia buah 5.836,41 6.420,05
30 x 30 KW 1
20 Keramik Warna/Corak (Anti
Slip) Mulia buah 7.568,09 8.324,90
40 x 40 KW 1 DN
21 Keramik
Putih Polos Mulia buah 11.288,00 12.416,80
40 x 40 KW 1 DN
22 Keramik Warna/Corak (Anti
Slip) Mulia buah 13.639,67 15.003,64
10 x 20 dan 20 x 20
23 Keramik KW 1 DN
Putih/polos Roman buah 2.822,00 3.104,20
10 x 20 KW 1 DN
24 Keramik Corak/Warna/Anti
Slip Roman buah 3.259,41 3.585,35
20 x 20 (KM) KW 1
DN
25 Keramik
Corak/Warna/Anti
Slip Roman buah 3.866,14 4.252,75
20 x 20 (KM) KW 1
26 Keramik Dn Putih Polos
Roman buah 5.079,60 5.587,56
20 x 25 Dinding
27 Keramik (KM) KW 1 DN
Coarak Roman buah 3.950,80 4.345,88
Keramik 30 x 30 KW 1 DN
28 Polos Roman buah 9.428,05 10.370,86
30 x 30 KW 1 DN
29 Keramik Warna/Corak (Anti
Slip) Roman buah 7.439,82 8.183,80
Keramik 40 x 40 KW 1 DN
30 Polos Roman buah 11.523,17 12.675,49
40 x 40 KW 1 DN
31 Keramik Warna/Corak (Anti
Slip) Roman buah 8.979,09 9.877,00
Keramik 60 x 60 (Masterina
32 Polos) buah 30.571,67 33.628,84
Keramik 60 x 60 (Masterina
33 Corak) buah 37.302,14 41.032,35
Keramik 60 x 60 (Masterina
34 Muda) buah 50.448,42 55.493,26
60 x 60 (Masterina
Keramik
35 Tua) buah 52.186,78 57.405,46
60 x 60 (Roman
Keramik
36 Polos) buah 40.416,67 44.458,34
60 x 60 (Roman
Keramik
37 Corak) buah 47.551,17 52.306,29
Keramik
38 60 x 60 (KIA Polos) buah 31.000,00 34.100,00
Keramik
39 60 x 60 (KIA Corak) buah 33.028,69 36.331,56
60 x 60 (Mulia
Keramik
40 Polos) buah 29.153,61 32.068,97
60 x 60 (Mulia
Keramik
41 Corak) buah 32.775,18 36.052,70

42 Plin Keramik 60 x 60 buah 48.021,97 52.824,17


10 x 60 cm
43 Plin Ubin Granito
(berbagai ukuran) buah 5.910,40 6.501,44
44 Stepnosing Keramik
(Berbagai ukuran) buah 6.000,00 6.600,00
Stepnosing Granito
45 (kelas Baik) buah 6.036,43 6.640,07

46 Vinyl Lantai Dasar m2 86.917,60 95.609,36

1.534.095,6
47 Karpet kelas baik LN m2 4 1.687.505,20
Karpet Kelas sedang
48 LN m2 511.035,98 562.139,58

49 Parquet Jati m2 468.159,92 514.975,92


Stairnosing Keramik
50 10/20 buah 1.675,35 1.842,89

51 Stairnosing Fiber m 24.880,16 27.368,18


52 Taraso Kerang 30 x 30 m2 41.503,15 45.653,47

53 Plin Taraso 10 x 30 buah 34.441,10 37.885,21

Graniit Alam LN Ukuran 1.975.400,0


54 Besar m2 0 2.172.940,00
Graniit Alam LN Ukuran
55 Kecil m2 917.150,00 1.008.865,00

Graniit Alam DN Ukuran 1.889.075,0


56 Besar m2 2 2.077.982,52

Graniit Alam DN Ukuran 1.650.130,6


57 Kecil m2 4 1.815.143,70
58 Granito Tile Essenza ukuran 40 x 40 Polis m2
113.820,67 125.202,73
Granito Tile Essenza
59 ukuran 30 x 30 m2 93.126,00 102.438,60
ukuran 40 x 40
60 Granito Tile Essenza m2
Unpolis 95.242,50 104.766,75

61 Marmer m2 660.065,80 726.072,38


Lampung ukuran
62 Marmer Alam Besar m2 772.522,50 849.774,75
Lampung ukuran
63 Marmer Alam Kecil m2 613.785,00 675.163,50

64 Marmer Alam ukuran Besar m2 518.542,50 570.396,75

65 Marmer Alam ukuran Kecil m2 317.475,00 349.222,50

66 Marmer Sintesis m2 285.727,50 314.300,25

67 Granito Tile Essenza 60 x 60 Polis m2 677.280,00 745.008,00

68 Granito Tile Essenza 60 x 60 Unpolis m2 571.455,00 628.600,50

69 Batu Tempel Hitam m2 335.393,29 368.932,62

70 Bata Karawang buah 23.793,69 26.173,06


Campuran untuk Kedap
71 Air (AM) liter 493.800,62 543.180,68

72 Plin Keramik 10 x 20 buah 18.343,00 20.177,30


73 Plin Keramik 10 x 25 buah 18.343,00 20.177,30

74 Plin Keramik 10 x 30 buah 18.343,00 20.177,30

75 Plin Keramik 10 x 40 buah 5.975,59 6.573,14

76 Plin Keramik 15 x 30 buah 6.410,17 7.051,19

77 Plin Keramik 15 x 40 buah 2.328,15 2.560,97

78 Plin Granito 10 x 30 buah 13.472,23 14.819,45

79 Plin Granito 10 x 40 buah 14.993,29 16.492,61

80 Plin Granito 15 x 30 buah 16.514,34 18.165,78

81 Plin Granito 15 x 40 buah 21.294,81 23.424,29

82 Keramik Artistik 10 X 20 Cm buah 960,00 1.056,00

83 Keramik Artistik 5 X 20 Cm buah 1.860,00 2.046,00

84 Ubin Keramik 10 x 20 buah 1.050,00 1.155,00


Ubin Keramik (10 x 10)
85 atau (5 x 20) cm buah 560,00 616,00
Ubin Keramik 33 x 33
86 cm buah 4.500,00 4.950,00
Ubin Keramik 10 x 33
87 cm, variasi/border buah 1.400,00 1.540,00
Mozaik
88 30 x 30 Cm buah 30.000,00 33.000,00
Ubin Teraso
89 30 x 30 Cm buah 5.348,00 5.882,80
underlayer / Rubber
90 Corrugated m2 85.000,00 93.500,00

91 Gymfloor m2 125.000,00 137.500,00

92 Vinyl buah 17.000,00 18.700,00

93 Vinyl karet (15 x 30) cm buah 55.000,00 60.500,00

Vinyl Kayu Kelas II (2 x 7.750.000,0


94 10) cm m2 0 8.525.000,00
95 Floor hardener kg 28.000,00 30.800,00

96 Plin Keramik Artistik 10 x 10 cm buah 10.000,00 11.000,00

97 Plin Keramik Artistik 5 X 20 Cm buah 5.000,00 5.500,00

98 Plin Teraso 10 X 30 Cm buah 3.480,00 3.828,00

99 Internal cove (5 x 5 x20) cm buah 6.500,00 7.150,00

G. BAHAN SALURAN AIR KOTOR / BERSIH

1 Grafel U 20 cm' m' 42.330,00 46.563,00

2 Grafel U 30 cm' m' 56.440,00 62.084,00

3 Grafel U 40 cm' m' 126.990,00 139.689,00

4 Buis Beton 20 cm (1 m') m' 66.787,33 73.466,07

5 Buis Beton 30 cm (1 m') m' 92.890,83 102.179,92

6 Buis Beton 40 cm (1 m') m' 122.757,00 135.032,70

7 Buis Beton 50 cm (1 m') stk 169.320,00 186.252,00

8 Buis Beton 60 cm (1 m') stk 221.997,33 244.197,07

9 Buis Beton 100 cm (0.50 m') stk 564.400,00 620.840,00

10 Buis Beton 80 cm (0.50 m') stk 409.190,00 450.109,00

11 Buis Tanah 10 cm (0.50 m') stk 16.932,00 18.625,20

12 Buis Tanah 15 cm (0.50 m') stk 21.165,00 23.281,50

13 Buis Tanah 20 cm (0.50 m') stk 28.220,00 31.042,00

14 Buis Tanah 25 cm (0.50 m') stk 35.275,00 38.802,50

15 Injuk Gulung 9.524,25 10.476,68

H. BAHAN LOGAM DAN BAHAN JADINYA


1 Besi Beton U-24 Rata-rata kg 15.000,00 16.500,00
U-39 / U-32 Rata-
2 Besi Beton rata kg 21.400,00 23.540,00
U-24 dia. 10 mm,
3 btg
Besi Beton panjang 12 m 65.000,00 71.500,00
U-24 dia. 12 mm,
4 btg
Besi Beton panjang 12 m 95.000,00 104.500,00
U-24 dia. 16 mm,
5 btg
Besi Beton panjang 12 m 165.000,00 181.500,00
U-24 dia. 19 mm,
6 btg
Besi Beton panjang 12 m 218.500,00 240.350,00
Pagar BRC lengkap
7 m2
tiang (tanpa Pondasi) 176.375,00 194.012,50

8 Bondek m2 184.135,50 202.549,05

9 Besi WF ex DN SII kg 13.686,70 15.055,37

10 Besi WF ex Jepang kg 29.008,75 31.909,62

11 Besi Profil Dn SII kg 15.521,00 17.073,10

12 Besi Profil ex LN kg 18.343,00 20.177,30

13 Besi C Lip Chanel kg 15.521,00 17.073,10

14 Ongkos Galfanis Besi kg 22.815,87 25.097,46

15 Kawat Beton kg 21.165,00 23.281,50

16 Kawat Duri kg 51.501,50 56.651,65

17 Kawat Pengikat m' 16.932,00 18.625,20

18 Kawat Bronjong 4 mm kg 31.747,50 34.922,25

19 Kawat Tembaga kg 37.038,75 40.742,63

20 Ram Nyamuk Hijau m2 32.100,25 35.310,28


Ram Kawat 1 x 1
21 (Putih) m2 21.517,75 23.669,53
22 Ram Ayam m2 20.106,75 22.117,43
Kawat Kasa 1 x 1
23 (Putih) m2 25.750,75 28.325,83

24 Kawat Harmonika 4 cm m2 38.802,50 42.682,75

25 Kawat Harmonika 2 cm m2 48.679,50 53.547,45

26 Kawat Las Listrik kg 38.802,50 42.682,75

27 Wiremess M8 m2 476.212,50 523.833,75

28 Wiremess M6 m2 297.015,50 326.717,05

29 Timah kg 35.275,00 38.802,50

30 Timah Hitam kg 56.440,00 62.084,00


Ram Nyamuk
31 Alluminium m2 28.220,00 31.042,00
Plat Strip θ 2 x 30 mm
32 (6 m') θ 2 x 30 mm (6 m') btg 45.152,00 49.667,20
Plat Strip θ 3 x 30 mm
33 (6 m') θ 3 x 30 mm (6 m') btg 61.378,50 67.516,35

34 Plat Strip btg 49.108,44 54.019,29

35 Besi Strip kg 55.518,62 61.070,48

36 Plat Alluminium 0.2 mm 0.2 mm m2 82.543,50 90.797,85

37 Plat Alluminium 0.3 mm 0.3 mm m2 148.155,00 162.970,50

38 Plat Alluminium 0.4 mm 0.4 mm m2 180.608,00 198.668,80

39 Plat Alluminium 0.5 mm 0.5 mm m2 214.472,00 235.919,20

40 Plat Alluminium 0.6 mm 0.6 mm m2 248.336,00 273.169,60

41 Plat Alluminium 0.1 mm 0.1 mm m2 70.550,00 77.605,00


Kusen Aluminium
1.3 mm t = 1,3 mm
42 Natural 1.3 mm t = 1,3 m'
(4")
mm (4") 75.000,00 82.500,00
Kusen Aluminium 1.3 mm t = 1,3 mm
43 m'
Warna 1.3 mm t = 1,3 (4")
85.000,00 93.500,00
mm (4")

Kusen Aluminium
1.3 mm t = 1,3 mm
44 Natural 1.3 mm t = 1,3 m'
(3")
mm (3") 60.000,00 66.000,00
Kusen Aluminium
1.3 mm t = 1,3 mm
45 Warna 1.3 mm t = 1,3 m'
(3")
mm (3") 75.000,00 82.500,00
Daun Jendela
Aluminium Natural
46 m2
(tanpa kaca dan
accesoris) 115.000,00 126.500,00
Daun Jendela
Aluminium Warna
47 m2
(tanpa kaca dan
accesoris) 132.000,00 145.200,00
Daun Pintu Aluminium
48 Natural (tanpa kaca dan m2
accesoris) 115.000,00 126.500,00
Daun Pintu Aluminium
49 Natural (tanpa kaca dan m2
accesoris) 132.000,00 145.200,00
Pintu PVC (Kualitas
50 Sedang) buah 290.877,65 319.965,42
Pintu PVC (Kualitas
51 Baik) buah 335.719,23 369.291,15
Handle Aluminium
52 (Tarikan Pintu buah
Aluminium) 352.750,00 388.025,00

53 Kait angin Aluminium ps 155.691,15 171.260,27


Karet Accesoris
54 m'
Kusen/Pintu Aluminium 30.638,45 33.702,30

55 Jalusi Aluminium m' 59.755,85 65.731,44

56 Sunscreen Aluminium m2 521.505,60 573.656,16


Seng Plat BJLS 30 60
57 cm (100 m') 30 60 cm (100 m') roll 21.165,00 23.281,50
Seng Plat BJLS 30 90
58 cm (100 m') 30 90 cm (100 m') roll 32.453,00 35.698,30

59 Plat Besi Tipis 1 mm 1 mm kg 19.754,00 21.729,40


60 Plat Besi Tipis 0.5 mm 0.5 mm kg 21.165,00 23.281,50
Plat Besi 2 mm s/d 5
61 mm 2 mm s/d 5 mm kg 16.932,00 18.625,20
Plat Besi 6 mm s/d 10
62 mm 6 mm s/d 10 mm kg 16.932,00 18.625,20
Plat Besi 10 mm
63 keatas 10 mm keatas kg 16.932,00 18.625,20

64 Kabel Presstress polos kg 36.070,80 39.677,88

65 Jaring Kawat baja kg 100.498,48 110.548,32

66 Lem Kuning (Aibond) kg 88.893,00 97.782,30

67 Lem Fox kg 40.919,00 45.010,90

68 Lem Vinyl kg 28.220,00 31.042,00

69 Besi Strip Kaca Nako kg 50.086,27 55.094,89

70 Profil Aluminium m' 25.532,05 28.085,25


Besi Hollow ( 2 x 4 x 4 ) ( 2 x 4 x 4 ) cm (400
71 cm (400 cm) cm) btg 15.521,00 17.073,10
Besi Hollow 4 x 4 cm
72 (400 cm) 4 x 4 cm (400 cm) btg 36.686,00 40.354,60

73 Besi Rail Pengamanan kg 706.205,50 776.826,05

74 Jendela Besi m2 493.850,00 543.235,00

75 Jendela Besi Tahan Api m2 663.522,75 729.875,03

76 Pintu Gulung Besi m2 597.636,11 657.399,72

77 Pintu Rolling Door m2 455.036,92 500.540,61


Jendela Nako Kaca
78 Ryben + Tralis 6 klips set 273.674,03 301.041,44
Jendela Nako Kaca
79 Ryben + Tralis 7 klips set 304.172,80 334.590,08
Jendela Nako Kaca
80 Ryben + Tralis 8 klips set 337.814,57 371.596,02
81 Jendela Nako Kaca 10 klips set
Ryben + Tralis 471.450,38 518.595,41
Jendela Nako Kaca
82 4 klips set
Bening + Tralis 209.300,69 230.230,75
Jendela Nako Kaca
83 5 klips set
Bening + Tralis 206.739,72 227.413,69
Jendela Nako Kaca
84 6 klips set
Bening + Tralis 244.106,53 268.517,18
Jendela Nako Kaca
85 7 klips set
Bening + Tralis 313.136,18 344.449,79
Jendela Nako Kaca
86 8 klips set
Bening + Tralis 333.507,49 366.858,24
Jendela Nako Kaca
87 10 klips set
Bening + Tralis 424.887,38 467.376,11

88 Hollow 60 x 60 x 1.8 btg 156.917,31 172.609,04

89 Hollow 60 x 60 x 1.6 btg 314.300,25 345.730,28

90 Hollow 50 x 50 x 2.5 btg 220.962,60 243.058,86

91 Hollow 50 x 50 x 1.0 btg 117.338,76 129.072,64

92 Hollow 50 x 50 x 1.6 btg 205.723,80 226.296,18

93 Hollow 50 x 50 x 1.3 btg 156.959,64 172.655,60

94 Hollow 40 x 60 x 2.0 btg 217.914,84 239.706,32

95 Hollow 40 x 60 x 1.6 btg 198.104,40 217.914,84

96 Hollow 40 x 40 x 1.8 btg 167.626,80 184.389,48

97 Hollow 40 x 40 x 1.6 FL btg 234.444,71 257.889,18

98 Hollow 40 x 40 x 1.6 btg 164.579,04 181.036,94

99 Hollow 40 x 40 x 1.3 btg 124.958,16 137.453,98

100 Hollow 40 x 40 x 1.0 btg 102.099,96 112.309,96

101 Hollow 40 x 40 x 1.0 B btg 122.227,88 134.450,66

102 Hollow 40 x 40 x 0.8 / 4 m btg 174.029,21 191.432,13

103 Hollow 30 x 60 x 1.8 btg 198.104,40 217.914,84


104 Hollow 30 x 60 x 1.6 btg 182.865,60 201.152,16

105 Hollow 30 x 30 x 2.0 btg 131.053,68 144.159,05

106 Hollow 30 x 30 x 1.6 btg 121.910,40 134.101,44

107 Hollow 30 x 30 x 1.3 btg 92.956,68 102.252,35

108 Hollow 30 x 30 x 1.0 btg 68.574,60 75.432,06

109 Hollow 30 x 30 x 1.0 B btg 105.232,38 115.755,62

110 Hollow 30 x 30 x 1.0 C btg 116.058,28 127.664,11

111 Hollow 30 x 30 x 0.8 / 4 m btg 58.669,38 64.536,32

112 Hollow 20 x 40 x 1.8 btg 138.673,08 152.540,39

113 Hollow 20 x 40 x 1.8 B btg 140.211,07 154.232,18

114 Hollow 20 x 40 x 1.6 btg 122.672,34 134.939,57

115 Hollow 20 x 40 x 1.6 B btg 173.796,40 191.176,04

116 Hollow 20 x 40 x 1.3 btg 92.956,68 102.252,35

117 Hollow 20 x 40 x 1.3 B btg 165.827,78 182.410,55

118 Hollow 20 x 40 x 1.0 btg 89.908,92 98.899,81

119 Hollow 20 x 40 x 1.0 B btg 892.729,12 982.002,03

120 Hollow 20 x 40 x 0.8 / 4 m btg 60.955,20 67.050,72

121 Hollow 50 x 25 x 2.0 btg 175.246,20 192.770,82

122 Hollow 50 x 25 x 1.6 btg 146.292,48 160.921,73

123 Hollow 50 x 25 x 1.3 btg 115.814,88 127.396,37

124 Hollow 50 x 25 x 1.0 btg 85.337,28 93.871,01

125 Hollow 50 x 25 x 0.8 / 4 m btg 113.264,50 124.590,95

126 Hollow 20 x 20 x 2.0 btg 89.146,98 98.061,68


127 Hollow 20 x 20 x 1.6 btg 77.717,88 85.489,67

128 Hollow 20 x 20 x 1.3 btg 62.479,08 68.726,99

129 Hollow 20 x 20 x 1.0 btg 44.192,52 48.611,77

130 Hollow 20 x 20 x 0.8 / 4 m btg 32.904,52 36.194,97

131 Besi Siku L 30 x 30 x 3 kg 48.000,00 52.800,00

132 Scuare Tube m 24.100,00 26.510,00

133 Pintu Folding Door m2 429.990,00 472.989,00


Pengelasan teralis
134 jendela,pintu,roster,void cm
150.000,00 165.000,00
ukuran (100 x 50) cm

135 Pengelasan pagar m2 350.000,00 385.000,00

136 Pengelasan kanopi m2 285.000,00 313.500,00

137 Pintu aluminium natural m2 211.800,00 232.980,00

Pintu aluminium swing 1.000.000,0


1.100.000,00
138 + kaca polos 5 mm m 0
Pintu Frameless
(tempered 12 mm
139 m 3.000.000,0
polos) floor hinge 3.300.000,00
0
dorma BTS 84
Pintu fitting (tempered
140 12 mm polos) floor m 3.750.000,0
4.125.000,00
hinge dorma BTS 84 0
powder coating
aluminium berbagai m'
20.000,00
141 warna 22.000,00
tirai (Venetion blind and
m2
142 vertical blind) 537.300,00 591.030,00
folding gate 0.5 mm m2
143 400.000,00 440.000,00
Baja Strip 0,2 X 2 cm btg
144 22.396,80 24.636,48
Besi Strip Kaca kg
145 50.710,00 55.781,00
I. BAHAN KACA

Kaca Polos 2 mm
1 (ASAHI) m2 107.706,33 118.476,97
Kaca Polos 3 mm
2 (ASAHI) m2 112.409,67 123.650,63
Kaca Polos 5 mm
3 (ASAHI) m2 124.168,00 136.584,80
Kaca Polos 8 mm
4 (ASAHI) m2 207.417,00 228.158,70
Kaca Polos Sanblas 5
5 mm m2 317.475,00 349.222,50

6 Kaca Biasa 6 mm m2 294.743,79 324.218,17


Kaca Reyband 5 mm
7 (ASAHI) m2 169.320,00 186.252,00

8 Kaca Reyband 6 mm m2 310.420,00 341.462,00


Kaca Reyband 8 mm
9 (ASAHI) m2 423.300,00 465.630,00
Kaca Reyband 12 mm
10 (ASAHI) m2 846.600,00 931.260,00

11 Kaca Es / Susu 3 mm m2 137.882,92 151.671,21

12 Kaca Es / Susu 5 mm m2 229.804,00 252.784,40

13 Kaca Cermin 5 mm m2 285.727,50 314.300,25

14 Kaca Cermin 6 mm m2 277.049,85 304.754,84

15 Kaca Cermin 8 mm m2 333.329,00 366.661,90

Kaca Patri Lokal 2.058.973,5


16 Terpasang (ASAHI) m2 3 2.264.870,88

Kaca Patri ex Luar 5.284.195,0


17 Negeri Terpasang m2 0 5.812.614,50

1.844.177,0
18 Kaca 6 mm Gravver m2 0 2.028.594,70
19 Kaca Lukis Terpasang m2
138.439,59 152.283,55
Glass Block DN 20 x 20
20 (Kedawung) buah 32.453,00 35.698,30
Glass Block DN 20 x 20
21 ex LN buah 125.579,00 138.136,90

22 Sealant kg 197.540,00 217.294,00


buah
23 Jendela Nako 49.385,00 54.323,50

J. BAHAN PAKU DAN MUR BAUT

1 Paku 1 cm s/d 3 cm kg 21.870,50 24.057,55

2 Paku 4 cm s/d 7 cm kg 16.932,00 18.625,20

3 Paku 8 cm s/d 15 cm kg 16.932,00 18.625,20


Paku Beton 2 cm s/d 5
4 cm buah 3.174,75 3.492,23

5 Paku Kait Lengkap buah 2.116,50 2.328,15

6 Paku Cacing kg 79.016,00 86.917,60


Besi Beugeul Kuda-
7 kuda kg 22.576,00 24.833,60

8 Duk Angker buah 25.398,00 27.937,80


Angker Mur Baut dia.
9 19 / Panjang 60 cm buah 8.466,00 9.312,60
Mur Baut HTB dia. 19
10 s/d 16 (5 cm) buah 10.582,50 11.640,75
Mur Baut Biasa dia. 19
11 s/d 16 (5 cm) buah 7.055,00 7.760,50

12 Piser dia. 12 s/d 20 cm buah 14.110,00 15.521,00

13 Paku Sekrup 3" buah 1.058,25 1.164,08

14 Ramset / Dinabolt buah 4.233,00 4.656,30

15 Baut Besar buah 11.288,00 12.416,80

16 Baut Kecil buah 1.411,00 1.552,10


17 Paku GRC kg 36.686,00 40.354,60

18 Paku Gypsum kg 35.275,00 38.802,50

19 Sekrup Fixer buah 1.411,00 1.552,10

20 Paku Skrup 5 cm kg 13.000,00 14.300,00

21 Paku Seng kg 18.000,00 19.800,00

22 Cotton Plaster buah 67.650,00 74.415,00

23 Cornice Coumpound zak 91.300,00 100.430,00

24 Paku Hak Panjang 15 cm kg 13.300,00 14.630,00

K. BAHAN PERPIPAAN

Besi Pipa untuk Hydrant


1 BSP 1" btg 224.349,00 246.783,90
Besi Pipa untuk Hydrant
2 BSP 1.15" btg 256.802,00 282.482,20
Besi Pipa untuk Hydrant
3 BSP 1.5" btg 304.776,00 335.253,60
Besi Pipa untuk Hydrant
4 BSP 2" btg 410.601,00 451.661,10
Besi Pipa untuk Hydrant
5 BSP 2.5" btg 701.972,50 772.169,75
Besi Pipa untuk Hydrant
6 BSP 3" btg 809.208,50 890.129,35

Besi Pipa untuk Hydrant 1.077.298,5


7 BSP 4" btg 0 1.185.028,35

Besi Pipa untuk Hydrant 2.225.147,0


8 BSP 6" btg 0 2.447.661,70
Besi Pipa Hitam 1" t = 2
9 mm btg 138.905,90 152.796,48
Besi Pipa Hitam 2" t = 2
10 mm btg 270.206,50 297.227,15
Besi Pipa Hitam 3" t = 2
11 mm btg 465.747,58 512.322,34
Besi Pipa Hitam 4" t = 2
12 mm btg 565.928,58 622.521,44

Besi Pipa Hitam 6" t = 2 1.030.030,0


13 mm btg 0 1.133.033,00
Pipa GIP Medium A
14 1/2" (6 m') btg 211.650,00 232.815,00
Pipa GIP Medium A
15 3/4" (6 m') btg 268.090,00 294.899,00
Pipa GIP Medium A 1"
16 (6 m') btg 306.892,50 337.581,75
Pipa GIP Medium A 1
17 1/4" (6 m') btg 380.970,00 419.067,00
Pipa GIP Medium A 1
18 1/2" (6 m') btg 359.805,00 395.785,50
Pipa GIP Medium A 1
19 3/4" (6 m') btg 486.795,00 535.474,50
Pipa GIP Medium A 2"
20 (6 m') btg 684.335,00 752.768,50
Pipa GIP Medium A 2
21 1/2" (6 m') btg 846.600,00 931.260,00

Pipa GIP Medium A 4" 1.502.715,0


22 (6 m') btg 0 1.652.986,50

Pipa GIP Medium A 3" 1.171.130,0


23 (6 m') btg 0 1.288.243,00
Macam-macam
24 Sambungan GIP 1/2" buah 9.524,25 10.476,68
Macam-macam
25 Sambungan GIP 3/4" buah 11.993,50 13.192,85
Macam-macam
26 Sambungan GIP 1" buah 17.284,75 19.013,23
Macam-macam
27 Sambungan GIP 1 1/4" buah 23.281,50 25.609,65
Macam-macam
28 Sambungan GIP1 1/2" buah 27.161,75 29.877,93
Macam-macam
29 Sambungan GIP 1 3/4" buah 31.042,00 34.146,20
Macam-macam
30 Sambungan GIP 2" buah 56.440,00 62.084,00
Macam-macam
31 Sambungan GIP 2 1/2" buah 67.022,50 73.724,75
Macam-macam
32 Sambungan GIP 3" buah 106.370,35 117.007,39
Macam-macam
33 Sambungan GIP 4" buah 140.538,77 154.592,65
Pipa PVC RUCIKA type
34 AW 1/2" btg 42.330,00 46.563,00
Pipa PVC RUCIKA type
35 AW 3/4" btg 59.967,50 65.964,25
Pipa PVC RUCIKA type
36 AW 1" btg 57.851,00 63.636,10
Pipa PVC RUCIKA type
37 AW 1 1/4" btg 81.838,00 90.021,80
Pipa PVC RUCIKA type
38 AW 1 1/2" btg 97.711,75 107.482,93
Pipa PVC RUCIKA type
39 AW 2" btg 128.401,00 141.241,10
Pipa PVC RUCIKA type
40 AW 2 1/2" btg 156.973,75 172.671,13
Pipa PVC RUCIKA type
41 AW 3" btg 240.222,75 264.245,03
Pipa PVC RUCIKA type
42 AW 4" btg 385.908,50 424.499,35

Pipa PVC RUCIKA type 1.008.865,0


43 AW 6" btg 0 1.109.751,50

Pipa PVC RUCIKA type 1.242.385,5


44 AW 8" btg 0 1.366.624,05
Pipa PVC MASPION
45 ABU type AW 1/2" btg 37.391,50 41.130,65
Pipa PVC MASPION
46 ABU type AW 3/4" btg 159.301,90 175.232,09
Pipa PVC MASPION
47 ABU type AW 1" btg 122.895,28 135.184,81
Pipa PVC MASPION
48 ABU type AW 1 1/4" btg 45.152,00 49.667,20
Pipa PVC MASPION
49 ABU type AW 1 1/2" btg 48.679,50 53.547,45
Pipa PVC MASPION
50 ABU type AW 2" btg 69.844,50 76.828,95
Pipa PVC MASPION
51 ABU type AW 2 1/2" btg 158.737,50 174.611,25
Pipa PVC MASPION
52 ABU type AW 3" btg 218.705,00 240.575,50
Pipa PVC MASPION
53 ABU type AW 4" btg 331.585,00 364.743,50
Macam-macam
Sambungan Paralon
54 1/2" buah 4.938,50 5.432,35
Macam-macam
Sambungan Paralon
55 3/4" buah 6.702,25 7.372,48
Macam-macam
56 Sambungan Paralon 1" buah 7.407,75 8.148,53
Macam-macam
Sambungan Paralon 1
57 1/4" buah 9.877,00 10.864,70
Macam-macam
Sambungan Paralon 1
58 1/2" buah 13.404,50 14.744,95
Macam-macam
Sambungan Paralon 1
59 3/4" buah 13.404,50 14.744,95
Macam-macam
60 Sambungan Paralon 2" buah 21.870,50 24.057,55
Macam-macam
Sambungan Paralon 2
61 1/2" buah 32.453,00 35.698,30
Macam-macam
62 Sambungan Paralon 3" buah 40.919,00 45.010,90
Macam-macam
63 Sambungan Paralon 4" buah 60.673,00 66.740,30
Sambungan Pipa PVC
64 Jenis AW 4" TY buah 123.462,50 135.808,75

65 Lem Paralon tube 14.110,00 15.521,00

66 Solatif Ledeng gl 5.644,00 6.208,40


Pipa PVC 4" Berlobang
67 Jenis AW m' 80.779,75 88.857,73
PVC Waterstop Lebar
68 150 m' 70.077,32 77.085,05
PVC Waterstop Lebar
69 200 m' 69.316,79 76.248,46
PVC Waterstop Lebar
70 230 m' 80.290,13 88.319,15
PVC Waterstop Lebar
71 250 m' 90.285,66 99.314,22
PVC Waterstop Lebar
72 300 m' 101.910,89 112.101,97
PVC Waterstop Lebar
73 320 m' 109.624,82 120.587,31

74 Strorox - 100 kg 38.500,00 42.350,00

75 Pipa Tanah buah 10.850,00 11.935,00

76 Pipa Beton buah 49.000,00 53.900,00


L. BAHAN SANITAIR

1 Stop Kran 3/4" KIT buah 112.880,00 124.168,00

2 Stop Kran 1" KIT buah 159.443,00 175.387,30

3 Stop Kran 1 1/2" KIT buah 318.886,00 350.774,60

4 Stop Kran 2" KIT buah 486.089,50 534.698,45

1.223.337,0
5 Stop Kran 2 1/2" KIT buah 0 1.345.670,70

1.579.614,5
6 Stop Kran 3" KIT buah 0 1.737.575,95

7 Check Valve 1/2" buah 94.537,00 103.990,70

8 Double Neple 1/2" buah 57.145,50 62.860,05

9 Water Mur 1/2" buah 50.090,50 55.099,55

10 Gate Walve 1/2" buah 74.077,50 81.485,25


Saringan Air Lt. KM
11 Stainless Steel buah 70.902,75 77.993,03

12 Apooer Bath Tube buah 232.815,00 256.096,50


Kran Stainless Lokal
13 Kait buah 56.440,00 62.084,00
14 Shower dengan Tiang buah 226.465,50 249.112,05

15 Shower Tanpa Tiang buah 123.462,50 135.808,75


Kran Tembok Sun Eui
16 dia. 1/2" buah 82.543,50 90.797,85
Kran Tembok ITAP dia.
17 1/2" buah 45.857,50 50.443,25
Kran Bebek Sun Eui
18 1/2" buah 144.274,75 158.702,23

19 Kran Bebek ITAP 1/2" buah 75.841,25 83.425,38


Kran Panas Dingin Sun
20 Eui Standard buah 330.174,00 363.191,40

3.342.659,0
21 Bath Cape Washteren unit 0 3.676.924,90

22 Tempat Sabun Poslin buah 76.899,50 84.589,45

Wastafel Lengkap 1.329.162,0


23 TOTO LW 230 unit 0 1.462.078,20

24 Wastafel Lengkap INA unit 804.270,00 884.697,00


Closet Jongkok Poslin
25 Warna TOTO unit 321.002,50 353.102,75
Closet Jongkok
26 Standard Putih Poslin unit
TOTO 283.611,00 311.972,10
Closet Jongkok
27 Lengkap Sistem Jet unit 2.803.657,0
TOTO 0 3.084.022,70
Closet Duduk Warna
28 Standard TOTO C 240 unit 2.522.868,0
Lengkap 0 2.775.154,80

29 Closet Jongkok KIA buah 169.117,94 186.029,74


Closet Jongkok INA
30 (Wanan gelap) buah 271.617,50 298.779,25

31 Closet Duduk KIA unit 854.656,81 940.122,49

Closet Dudduk Ina 1.692.720,2


32 (Warna Gelap) buah 6 1.861.992,29
Wastafel Bulat Warna 1.434.987,0
33 Standard Lengkap unit 0 1.578.485,70
Wastafel Type Amerika
34 Standard buah 115.560,90 127.116,99

35 Wastafel Meja buah 795.228,66 874.751,53

Closet Duduk Warna 1.891.445,5


36 Standar INA Lengkap buah 0 2.080.590,05

Urinoir Lengkap TOTO 2.735.929,0


37 Warna Standard unit 0 3.009.521,90
Penyekat Poslin Urinoir
38 TOTO lbr 846.600,00 931.260,00
Kitchen Zink Stainless
39 Standard Lokal ( 1 buah
Lubang) 546.057,00 600.662,70
Kitchen Zink Stainless
40 Non Standard Franke( 1 buah 1.413.116,5
Lubang) 0 1.554.428,15
Kitchen Zink Stainless
41 Non Standard Franke( 1 buah 1.596.546,5
Lubang) 0 1.756.201,15

42 Talang PVC U-15 cm btg 63.495,00 69.844,50

Water Drain + 1.250.526,9


43 Acsesoris set 7 1.375.579,67

44 Clean Out buah 885.374,28 973.911,71


Septictank Biofil (Type
45 unit 6.750.000,0
BF-03, BF-06-08, dst) 7.425.000,00
0
Septictank Ipal Biofil
46 unit 13.600.000,
(Type R-05, R-10, dst)
00 14.960.000,00

M. BAHAN PENUTUP ATAP


Atap Plastik Gelombang
1 80 x 180 lbr 84.448,35 92.893,19
Atap Fiber Glass Tipis
2 lbr
80 x 180 (Gelombang) 84.660,00 93.126,00
Atap Fiber Glass Tebal
3 lbr
80 x 180 (Gelombang) 82.543,50 90.797,85
Atap Aluminium Natura
4 USR 26 (JAINDO) m2 149.566,00 164.522,60
Atap Aluminium Warna
5 USR 26 (JAINDO) m2 251.158,00 276.273,80
Atap Asbes Gel. Kecil
6 80 x 180 x 4 mm lbr 91.715,00 100.886,50
Atap Asbes Gel. Besar
7 80 x 180 x 4 mm lbr 125.579,00 138.136,90
Atap Seng Gelombang
8 lbr
80 cm x 180 cm x 3 mm 70.550,00 77.605,00
Atap Seng Gelombang
9 lbr
80 cm x 180 cm x 5 mm 91.009,50 100.110,45
Atap Seng Gelombang
10 270 cm x 106 cm x 4 lbr
mm 110.763,50 121.839,85
Atap Seng Gelombang
11 240 cm x 105 cm x 4 lbr
mm 98.064,50 107.870,95
Atap Seng Gelombang
12 210 cm x 105 cm x 4 lbr
mm 87.482,00 96.230,20
Atap Seng Gelombang
13 150 cm x 105 cm x 4 lbr
mm 63.495,00 69.844,50
Atap Seng Gelombang
14 150 cm x 102 cm x 5 lbr
mm 63.495,00 69.844,50
Atap Seng Gelombang
15 180 cm x 102 cm x 5 lbr
mm 128.203,46 141.023,81
Atap Seng Gelombang
16 300 cm x 105 cm x 4 lbr
mm 123.462,50 135.808,75
Atap Tegola Kubota,
17 lengkap m2 759.118,00 835.029,80
Atap Tegola Kubota
18 Kwalitas sedang m2 420.478,00 462.525,80

19 Aluminium Foil m2 27.161,75 29.877,93


Atap Genteng Plentong
20 Pres Bakar KW 1 buah 2.645,63 2.910,19
Atap Genteng Plentong
21 buah
Pres Molen Oven KW 2 2.645,63 2.910,19
Atap Genteng Flam
22 pres Molen Oven buah
Jatiwangi 2.645,63 2.910,19
Bubung Genteng pres
23 Bulat ex Jatiwangi buah 7.055,00 7.760,50
Genteng Bubungan ex
24 Jatiwangi Segitiga buah 4.233,00 4.656,30
Genteng Bubungan
25 Beton buah 14.124,11 15.536,52
Genteng Metal
26 (Rainbow Roof) m2 81.838,00 90.021,80

27 Genteng Metal Hana m2 228.375,99 251.213,59


Nok Atas Metal
28 (Rainbow Roof) lbr 135.456,00 149.001,60

29 Nok Atas Metal Hana lbr 118.524,00 130.376,40


Nok Pinggir Metal
30 (Rainbow Roof) lbr 99.475,50 109.423,05

31 Nok Pinggir Metal Hana lbr 148.155,00 162.970,50


Wall Flasing (Rainbow
32 Roof) lbr 150.977,00 166.074,70

33 Wall Flasing Hana lbr 117.113,00 128.824,30


Atap Genteng Beton
34 Warna 14.5/m2 m2 130.517,50 143.569,25

35 Genteng Beton Natural m2 91.715,00 100.886,50

36 Sirap Kelas 1 buah 155.210,00 170.731,00


Genteng Keramik
37 Natural Intan 14.5/m2 m2 130.500,00 143.550,00
Genteng Keramik
38 Glasur Standard m2
14.5/m2 137.750,00 151.525,00
Genteng Keramik
39
Glasur Spesial 14.5/m2 m2 100.886,50 110.975,15
Genteng Keramik
40 Glasur Premium m2
14.5/m2 112.174,50 123.391,95
Genteng Murando
41 Natural 1 m2 = 18 buah buah 4.500,00 4.950,00
Genteng Murando
42 Glasur 1 m2 = 18 buah buah 6.000,00 6.600,00
Bubung Murando
43 Natural buah 9.171,50 10.088,65
Bubung Murando
44 Glasur buah 11.640,75 12.804,83
Bubungan Genteng
45 Keramik buah 24.692,50 27.161,75

46 Atap Genteng Kodok buah 3.574,53 3.931,99


Bubungan Genteng
47 Kodok buah 7.055,00 7.760,50
Bubungan Genteng
48 Plentong buah 7.055,00 7.760,50
Bubungan Stel
49 Gelombang buah 13.363,58 14.699,94

50 Nok Genteng Metal lbr 75.770,70 83.347,77

51 Nok Atap Seng lbr 50.846,80 55.931,48


Nok Standar 40 cm 18,
52 SWG 22 m2 74.423,20 81.865,51

53 Pelat Asbes tebal 4 mm lbr 21.165,00 23.281,50


Pelat Asbes tebal 3.5
54 mm lbr 30.964,40 34.060,83
Trusses ZAM-75 t = 0.8
55 Rangka Utama m' 36.722,69 40.394,95
Trusses ZAM-75 t = 0.8
56 Rangka Utama m' 37.157,27 40.873,00
Reng 16-DB Roof
57 Battens t = 0.48 mm m' 47.974,00 52.771,40

58 Foot Plate t = 1.22 mm m' 13.037,64 14.341,40

59 PLD - Diafragma Plate buah 6.301,53 6.931,68

60 Wind Bracing m' 3.042,12 3.346,33


Tensioner (Pengaku
61 Tali Angin) buah 9.343,64 10.278,01

62 Acrilic m2 1.273.145,3 1.400.459,83


0

1.273.145,3
63 Policarbonate m2 0 1.400.459,83

64 Atap Zingkalum m2 108.647,00 119.511,70

65 Atap Spandek m2 121.467,35 133.614,08

66 Atap Superdek m2 144.935,10 159.428,61

67 Atap Bondek m2 159.276,50 175.204,15


Bubungan Atap
68 Zingkalum m' 100.607,12 110.667,83
Bubungan Atap
69 Spandek m' 249.562,16 274.518,37
Bubungan Atap
70 Superdek m' 117.664,70 129.431,17

71 Bubungan Atap Bondek m' 60.190,44 66.209,48


Genteng Keramik
72 setara KIA (S-1 buah
Standard Unglassed) 10.000,00 11.000,00
Genteng Keramik
73 setara KIA (S-1 buah
Standard Natural) 10.000,00 11.000,00
Genteng Keramik
74 setara KIA (S-1 buah
Standard Standard) 11.299,29 12.429,22
Genteng Keramik
75 setara KIA (S-1 buah
Standard Spesial) 14.124,11 15.536,52
Genteng Keramik
76 setara KIA (S-1 buah
Standard Premium) 19.339,17 21.273,08
Genteng Keramik
77 setara KIA (S-1 buah
Standard Exlusive) 21.077,52 23.185,27
Genteng Keramik
78 setara KIA (S-2 Nok buah
Unglassed) 21.620,75 23.782,83
Genteng Keramik
79 setara KIA (S-2 Nok buah
Natural) 22.163,99 24.380,39
Genteng Keramik
80 setara KIA (S-2 Nok buah
Standard) 26.075,28 28.682,81
Genteng Keramik
81 setara KIA (S-2 Nok buah
Spesial) 28.791,46 31.670,60
Genteng Keramik
82 setara KIA (S-2 Nok buah
Premium) 31.398,98 34.538,88
Genteng Keramik
83 setara KIA (S-2 Nok buah
Exlusive) 36.505,39 40.155,93
Genteng Keramik
84 setara KIA (S-3 List buah
Plang Kiri Unglassed) 31.181,69 34.299,86
Genteng Keramik
85 setara KIA (S-3 List buah
Plang Kiri Natural) 26.401,22 29.041,34
Genteng Keramik
86 setara KIA (S-3 List buah
Plang Kiri Standard) 27.053,10 29.758,41
Genteng Keramik
87 setara KIA (S-3 List buah
Plang Kiri Spesial) 28.030,93 30.834,02
Genteng Keramik
88 setara KIA (S-3 List buah
Plang Kiri Premium) 30.964,40 34.060,83
Genteng Keramik
89 setara KIA (S-3 List buah
Plang Kiri Exlusive) 35.527,57 39.080,33
Genteng Keramik
90 Setara. M-Class (M-1 bh
Standard Natural) 10.104,17 11.114,59
Genteng Keramik
91 Setara M-Class (M-1 bh
Standard Standard) 10.104,17 11.114,59
Genteng Keramik
92 Setara M-Class (M-1 bh
Standard Special) 12.820,35 14.102,38
Genteng Keramik
93 Setara M-Class (M-1 bh
Standard Premium) 16.405,70 18.046,27
Genteng Keramik
94 Setara M-Class (M-2 bh
NOK Natural) 23.141,81 25.455,99
Genteng Keramik
95 Setara M-Class (M-2 bh
NOK Standard) 25.966,63 28.563,30
Genteng Keramik
96 Setara M-Class (M-2 bh
NOK Special) 29.443,34 32.387,67
Genteng Keramik
97 Setara M-Class (M-2 bh
NOK Premium) 34.875,69 38.363,26
Genteng Keraxnik
98 Setara M-Class (M-3 bh
List Plang Kiri Natural) 30.529,81 33.582,79
Genteng Keramik
Setara. M-Class (M-3
99 bh
List Plang Kiri
Standard) 21.403,46 23.543,80
Genteng Keramik
100 Setara M-Class (M-3 bh
List Plang Kiri Special) 23.902,34 26.292,57
Genteng Keramik
101 Setara M-Class (M-3 bh
List Plang Kiri Premium) 27.704,99 30.475,48
Genteng Beton Garuda
102 bh
Natural (9.5 Bh/m2) 24.336,93 26.770,62
Genteng Beton Garuda
103 bh
Cat Minyak (9.5 Bh/m2) 48.891,15 53.780,27
Genteng Beton Garuda
104 bh
Cat Air (9.5 Bh/m2) 37.157,27 40.873,00
Genteng Beton Flat
105 bh
Natural (10 Bh/m2) 32.702,75 35.973,02
Genteng Beton Flat Cat
106 bh
Minyak (10 Bh/m2) 22.163,99 24.380,39
Genteng Beton Flat Cat
107 bh
Air (10 Bh/m2) 18.144,05 19.958,45
Genteng Beton Nok
108 Bulat Besar (NBB, P-D bh
91 cm -19 cm) 73.336,73 80.670,40
Genteng Beton Nok
109 Atas Besar (NAB, P-L-T bh
91 cm - 8 cm - 10 cm) 179.376,20 197.313,82
Genteng Keramik
110 Setara SAHARA (S-1 bh
Standard Unglazed) 62.472,03 68.719,23
Genteng Keramik
111 Setara SAHARA (S-1 bh
Standard Natural) 11.299,29 12.429,22
Genteng Keramik
112 Setara SAHARA (S-1 bh
Standard Standard) 12.928,99 14.221,89
Genteng Keramik
113 Setara SAHARA (S-1 bh
Standard Khusus) 16.731,64 18.404,80
Genteng Keramik
114 Setara SAHARA (S-1 bh
Standard Premium) 21.403,46 23.543,80
Genteng Keramik
115 Setara SAHARA (S-2 bh
NOK Unglazed) 24.988,81 27.487,69
Genteng Keramik
116 Setara SAHARA (S-2 bh
NOK Natural) 26.401,22 29.041,34
Genteng Keramik
117 Setara SAHARA (S-2 bh
NOK Standard) 32.702,75 35.973,02
Genteng Keramik
118 Setara SAHARA (S-2 bh
NOK Khusus) 38.786,98 42.665,68
Genteng Keramik
Setara SAHARA (S-3
119 bh
List Plang Kiri
Unglazed) 33.897,86 37.287,65
Genteng Keramik
120 Setara SAHARA (S-3 bh
List Plang Kiri Natural) 21.946,69 24.141,36
Genteng Keramik
Setara SAHARA (S-3
121 bh
List Plang Kiri
Standard) 31.507,63 34.658,39
Genteng Kerarnik
122 Setara SAHARA (S-3 bh
List Plang Kiri Khusus) 36.396,75 40.036,42
Genteng Keramik
123 Setara SAHARA (S-3 bh
List Plang Kiri Premium) 39.004,27 42.904,70
Genteng Keramik
Setara GRAND (Type
124 Elabana, P=420 mm, bh
L=335 mm, Isi=9/m2,
Berat=4.20 Kg) 59.755,85 65.731,44
Genteng Keramik
Setara GRAND (Type
Garuda Besar, P=420
125 bh
mm, L=335 mm,
Isi=9/m2, Berat=4.20
Kg) 36.939,98 40.633,98
Genteng Keramik
Setara GRAND (Type
126 Centurion, P=420 mm, bh
L=335 mm, Isi=9/m2,
Berat=4.20 Kg) 8.365,82 9.202,40
Genteng Keramik
Setara GRAND (Type
127 Royal, P=368 mm, bh
L=300 mm, Isi=13/m2,
Berat = 3.20 Kg) 6.627,47 7.290,21
Genteng Keramik
Setara GRAND (Type
Garuda Kecil, P=392
128 bh
mm, L=292 mm,
Isi=9/m2, Berat=3.20
Kg) 5.541,00 6.095,10
Nok Bulat Standard
129 (NBS, P-D 37.5 cm - 12 bh
cm) 90.177,01 99.194,71
Nok Atas Standard
130 (NAS, P-L-T 91 cm - 5 bh
cm - 6.5 cm) 83.440,90 91.784,99
Nok Pinggir (NPG, P-L-
131 T 91.4 cm - 10 cm - 7 bh
cm) 60.190,44 66.209,48
132 Asbes Motif Genteng lbr
95.609,36 105.170,30
Nok Stel Gelombang
133 Ibr
1000 mm 68.121,67 74.933,84
134 Nok Stel Rata lbr
68.990,85 75.889,93
135 Nok Paten Gelombang lbr
59.103,97 65.014,36
136 Nok Paten Rata Ibr
37.591,86 41.351,05
137 Hipcapping Besar lbr
450.885,05 495.973,56
138 Ujung Nok lbr
637.214,66 700.936,12
139 Shednok Natural 6 lbr
58.017,50 63.819,25
140 Penutup Atas lbr
129.289,93 142.218,92
141 Penutup Bawah Type B lbr
128.746,70 141.621,36
142 Penutup Bawah Type C lbr
123.857,58 136.243,34
143 Lisplang Simetris lbr
923.499,50 1.015.849,45

144 Lisplang Siku-siku lbr 2.645.554,4


5 2.910.109,90
(3000 x 200 x 8.0
145 Lisplang Kalsiplang lbr
mm) 50.372,70 55.409,97
(2400 x 200 x 8.0
146 Lisplang Kalsiplang lbr
mm) 40.001,85 44.002,04
(3000 x 200 x 12.0
147 Lisplang Kalsiplang lbr
mm) 75.559,05 83.114,96
(2400 x 200 x 12.0
148 Lisplang Kalsiplang lbr
mm) 60.743,55 66.817,91
(3000 x 300 x 8.0
149 Lisplang Kalsiplang lbr
mm) 75.559,05 83.114,96
(2400 x 300 x 8.0
150 Lisplang Kalsiplang lbr
mm) 60.002,78 66.003,05
(3000 x 300 x 12.0
151 Lisplang Kalsiplang lbr
mm) 113.338,58 124.672,43
(2400 x 300 x 12.0
152 Lisplang Kalsiplang lbr
mm) 91.856,10 101.041,71
120 x 240 (t = 12
153 Papan Gypsum lbr
mm Ex. DN) 78.522,15 86.374,37
120 x 240 (t = 12
154 Papan Gypsum lbr
mm Ex. LN) 80.003,70 88.004,07
List Plafond Gypsum (Setara Jaya Board
155 Btg
Polos Siku Panjang 2 m) 54.944,34 60.438,77
List Plafond Gypsum (Setara Jaya Board
156 Btg
Polos Siku Panjang 5 m) 29.567,51 32.524,26
List Plafond Gypsum (Setara Jaya Board
157 Btg
Polos Siku Panjang 10 m) 32.012,06 35.213,27
List Plafond Gypsum (Setara Jaya Board
158 Btg
Polos Siku Panjang 15 m) 32.244,88 35.469,37
List Plafond Gypsum (Setara Jaya Board
159 Big
Polos Panjang 2 m) 16.297,05 17.926,76
List Plafond Gypsum (Setara Jaya Board
160 Btg
Polos Panjang 5 m) 17.778,60 19.556,46
List Plafond Gypsum (Setara Jaya Board
161 Btg
Polos Panjang 10 m) 20.741,70 22.815,87
List Plafond Gypsum (Setara Jaya Board
162 Btg
Polos Panjang 15 m) 26.667,90 29.334,69
List Plafond Gypsum (Setara Jaya Board
163 Btg
Ombak Panjang 2 m) 217.837,24 239.620,96
List Plafond Gypsum (Setara Jaya Board
164 Btg
Ombak Panjang 5 m) 96.369,89 106.006,88
List Plafond Gypsum (Setara Jaya Board
165 Btg
Ombak Panjang 10 m) 97.130,42 106.843,46
List Plafond Gypsum (Setara Jaya Board
166 Btg
Ombak Pandang 15 m) 103.323,30 113.655,63
167 Genteng Plentong buah
1.550,00 1.705,00
168 Jabesmen gelombang 150x105 mm buah
40.000,00 44.000,00
169 Jabesmen gelombang 180x105 mm buah
46.000,00 50.600,00
170 Jabesmen gelombang 210x105 mm buah
52.000,00 57.200,00
171 Jabesmen gelombang 240x105 mm buah
60.000,00 66.000,00
172 Jabesmen gelombang 270x105 mm buah
68.000,00 74.800,00
173 Jabesmen gelombang 300x105 mm buah
76.000,00 83.600,00

N. BAHAN MEKANIKAL

Jockey Pump kap. 80


1 gln/menit 100 ml (18.6 unit 84.287.552,
92.716.307,68
kW) 44
Electrical Pump kap.
2 750 gln/menit 120 ml unit 353.531.03
388.884.141,67
(90 kW) 7,89
Diesel Pump kap. 750
3 gln/menit 120 ml (105 unit 883.828.30
972.211.134,11
kW) 3,74
Presure Tank kap. 500
4 unit 51.681.014,
liter lengkap
48 56.849.115,92
Hydran Box dlm
5 unit 9.163.471,4
Gedung ( Lengkap )
1 10.079.818,55
Fire House 1.5 x 30 m +
6 unit 7.371.049,8
nose
9 8.108.154,88

7 Exhose Fan H 360 W 60 x 60 cm unit 7.610.701,1


9 8.371.771,30
H 380 W CFM 55 x
8 Exhose Fan unit 8.579.232,7
55 cm
5 9.437.156,03

9 Exhose Fan H 100 W 40 x 40 cm unit 1.351.406,4


2 1.486.547,06
3 PK Setara
10 AC Split unit 30.941.028,
TOSHIBA
84 34.035.131,72
2 PK Setara
11 AC Split unit 17.898.535,
TOSHIBA
00 19.688.388,50
1 PK Setara
12 AC Split unit 4.642.190,0
TOSHIBA
0 5.106.409,00
Mesin AC Split DAIKIN
13 1 BTU 19.559.620,
(Indoor / Outdoor Unit)
64 21.515.582,70

O. BAHAN ELEKTRIKAL
Kabel NYA 1 x 1.5
1 ROLL
Prima ( 1 rol = 50 m' ) 158.361,23 174.197,36
Kabel NYA 1 x 2.5
2 ROLL
Prima ( 1 ml = 50 m' ) 241.995,91 266.195,50
Kabel NYM 2 x 1.5
3 m'
Prima ( 1 ml = 50 m' ) 7.574,72 8.332,19
Kabel NYM 3 x 1.5
4 m'
Prima ( 1 rol = 50 m' ) 9.563,76 10.520,13
Kabel NYM 2 x 2.5
5 m'
Prima ( 1 ml = 50 m' ) 12.552,73 13.808,00
Kabel NYM 3 x 2.5
6 m'
Prima ( 1 rol = 50 m' ) 15.488,55 17.037,40
Kabel NYM 4 x 2.5
7 m'
Prima ( 1 ml = 50 m' ) 8.978,19 9.876,01
Kabel NYM 2 x 4 Prima
8 m'
( 1 rol = 50 m' ) 7.553,08 8.308,39
Kabel NYM 3 x 4 Prima
9 m'
( 1 rol = 50 m' ) 18.832,15 20.715,36
Kabel NYM 4 x 4 Prima
10 m'
( 1 rol = 50 m' ) 25.413,99 27.955,39
Kabel NYM 2 x 6
11 Supreme ( 1 rol = 50 m' m'
) 13.538,55 14.892,40
Kabel NYM 3 x 6
12 Supreme ( 1 rol = 50 m' m'
) 17.813,88 19.595,26
Kabel NYM 4 x 6
13 Supreme ( 1 ml = 50 m' m'
) 29.317,76 32.249,53
Kabel NYM 2 x 10
14 m'
Supreme (1 rol = 50 m') 22.374,23 24.611,65
Kabel NYM 3 x 10
15 m'
Supreme (1 rol = 50 m') 29.642,29 32.606,52
Kabel NYM 4 x 10
16 m'
Supreme (1 rol = 50 m') 32.635,02 35.898,52
Kabel NYM 4 x 16
17 m'
Supreme (1 rol = 50 m') 44.605,94 49.066,54
Kabel NYY 2 x 4
18 Supreme ( 1 rol = 50 m' m'
) 13.538,55 14.892,40
Kabel NYY 3 x 4
19 Supreme ( 1 rol = 50 m' m'
) 20.624,12 22.686,53
Kabel NYY 4 x 4
20 Supreme ( 1 ml = 50 m' m'
) 30.438,09 33.481,90
Kabel NYY 2 x 6
21 Supreme ( 1 rol = 50 m' m'
) 13.396,03 14.735,64
Kabel NYY 3 x 6
22 Supreme ( 1 rol = 50 m' m'
) 26.580,42 29.238,46
Kabel NYY 4 x 6
23 Supreme ( 1 rol = 50 m' m'
) 27.647,13 30.411,85
Kabel NYY 2 x 10
24 Supreme ( 1 rol = 50 m'
m') 23.799,34 26.179,27
Kabel NYY 3 x 10
25 Supreme ( 1 rol = 50 m'
m') 32.492,51 35.741,76
Kabel NYY 4 x 10
26 Supreme ( 1 rol = 50 m'
m') 50.119,66 55.131,63
Kabel NYY 4 x 16
27 Supreme ( 1 rol = 50 m'
m') 63.559,91 69.915,90

28 NSFB FUJI EA - 100 A bh 1.254.096,8


0 1.379.506,48

29 NSFB FUJI EA - 150 A bh 2.565.198,0


0 2.821.717,80
Rumah Panel 30 x 60
30 unt
cm ( Kosong ) 213.766,50 235.143,15
31 Skring Kas 2 grop Biasa unt
267.337,47 294.071,21
32 Skring Kas 3 grop Biasa unt
327.380,22 360.118,24
33 Skring Kas 5 grop Biasa unt
672.134,55 739.348,01
34 MCB 1 PAS bh
71.255,50 78.381,05
35 MCB 3 PAS bh
86.931,71 95.624,88
36 Tahanan 50 A Merk Fuji bh
766.709,18 843.380,10
Saklar Broko Tunggal
37 bh
Standard ( 1 Phase ) 26.649,09 29.314,00
Saidar Broko Seri
38 bh
Standard ( 1 Phase ) 29.508,71 32.459,58
Stop Kontak Broko
39 bh
Standard ( 1 Phase ) 29.217,11 32.138,82
Stop Kontak Broko 3
40 bh
Phase (Out Bow) 121.134,35 133.247,79
Stop Kontak Broko 3
41 bh
Phase ( In Bow) 205.215,84 225.737,42
Stop Kontak Handle 3
42 bh
Phase 119.709,24 131.680,16
Instalasi Titik Lampu /
43 Stop Kontak (Upah dan ttk
Alat) 179.600,00 197.560,00
Lampu pijar 25 Watt s/d
44 bh
100 Watt 13.519,73 14.871,70
Lampu Neon Phillips 20
45 bh
Watt 45.246,07 49.770,67
Lampu Neon Phillips 40
46 bh
Watt 62.272,13 68.499,35
Trapo TL 20 W
47 bh
(Phillips) 67.692,73 74.462,00
Trapo TL 40 W
48 bh
(Phillips) 71.255,50 78.381,05
49 Trapo TL 20 W (Sinar) bh
35.627,75 39.190,53
50 Trapo TL 40 W (sinar) bh
42.753,30 47.028,63
51 Stater Neon Phillips bh
7.125,55 7.838,11
52 Stater Neon Biasa bh
4.987,89 5.486,67
Rumah TL In Bow / Out
53 Bow 2 x 20 W bh
178.138,75 195.952,63
(kosongan Sonora)
54 Down Light + SL 25 W bh
413.281,90 454.610,09
55 Lampu SL Philip 25 W bh
178.138,75 195.952,63
Lampu Sirkel TL 20 W
56 bh
Lengkap 149.636,55 164.600,21
57 Lampu Mercuri 80 W bh
171.746,92 188.921,61
Lampu Taman + Tiang
58 bh
+ Lampu 1 Buah 541.541,80 595.695,98
Lampu Baret 30 cm +
59 bh
Neon 285.022,00 313.524,20
Lampu Neon Arcrilik 2 x
60 bh 1.054.581,4
40 W Lengkap
0 1.160.039,54
Jarum Penangkal Petir
61 bh
16 135.385,45 148.924,00
62 Kawat BC ( Tembaga ) kg
57.004,40 62.704,84
Pentanahan Penangkal
63 ttk
Petir 598.546,20 658.400,82
64 Pentanahan Panel ttk
256.519,80 282.171,78

65 Balk TL 1 x 18 W bh 1.061.372,5
4 1.167.509,80

66 Balk TL 1 x 36 W bh 1.116.999,8
1 1.228.699,79
67 TKO TL 1 x 18 W bh
43.360,03 47.696,03
68 TKO TL 2 x 18 W bh
58.866,92 64.753,61
69 TKO TL 1 x 36 W bh
91.698,07 100.867,87
70 TKO TL 2 x 36 W bh
115.491,76 127.040,94
71 Kabel NYGBY ml
155.147,92 170.662,71
Panel ACB 4 Pase ACB Jenis Tarik 1000 A
72 bh 31.393.254,
Ml0H1 4P Tanpa Unit Trip MG 34.532.579,77
34
Panel ACB 4 Pase ACB Jenis Tetap 1000 A
73 bh 31.238.580,
Ml0H1 4P Tanpa Unit Trip MG 34.362.438,57
52
Panel ACB 4 Pase ACB Jenis Tetap 1250 A
74 bh 31.038.670,
Ml0H1 4P Tanpa Unit Trip MG 34.142.537,04
04
Panel ACB 4 Pase ACB Jenis Tetap 1250 A
75 bh 32.030.419,
Ml0H1 4P Tanpa Unit Trip MG 35.233.461,57
61
Panel ACB 4 Pase ACB Jenis Tetap 2500 A
76 bh 55.250.752,
Ml0H1 4P Tanpa Unit Trip MG 60.775.828,04
76
Panel ACB 4 Pase ACB Jenis Tetap 2500 A
77 bh 56.244.971,
Ml0H1 4P Tanpa Unit Trip MG 61.869.468,74
58
Panel ACB 4 Pase ACB Jenis Tetap 1000 A
78 bh 31.474.344,
Ml0H1 4P Tanpa Unit Trip MG 34.621.778,96
51
Panel ACB 4 Pase ACB Jenis Tetap 3200 A
79 bh 60.870.271,
Ml0H1 4P Tanpa Unit Trip MG 66.957.299,10
91
Panel MCCB 3 Pase 125 - 160 A, 36 KA
80 bh 4.392.795,7
MCCB (NS160N) MG 4.832.075,33
5
Panel MCCB 3 Pase 50 - 63 A, 25 KA
81 bh 4.334.422,6
MCCB (NS100N) MG
8 4.767.864,95
Panel MCCB 3 Pase 40 - 50 A, 25 KA
82 . bh 1.088.149,0
MCCB (NS100N) MG
9 1.196.964,00
Panel MCCB 3 Pase 32 - 50 A, 25 KA
83 bh
MCCB (NS100N) MG 790.160,00 869.176,00
Panel MCCB 3 Pase 32 - 50 A, 10 KA
84 bh 6.026.254,0
MCCB (NC45H) MG
1 6.628.879,41
Panel MCCB 3 Pase 20 - 10 A, 10 KA
85 bh 3.970.060,1
MCCB (NC45H) MG
5 4.367.066,17
Panel MCCB 3 Pase 160 - 200 A, 36 KA
86 bh 3.997.616,9
MCCB (NS250N) MG
8 4.397.378,68
Panel MCCB 3 Pase 80 - 100 A, 26 KA
87 bh 2.477.250,3
MCCB (NS100) MG
7 2.724.975,41
Panel MCCB 3 Pase 20 - 25 A, KA
88 bh
MCCB (NS100) MG 397.549,25 437.304,18
Panel MCCB 3 Pase 13 - 16 A, KA
89 bh
MCCB (NS100) MG 405.036,02 445.539,62
Panel MCCB 3 Pase 16 A, 5 KA (NC45a)
90 bh
MCCB MG 344.628,28 379.091,11
Panel MCCB 3 Pase 10 A, 5 KA (NC45a)
91 bh
MCCB MG 319.313,53 351.244,89
Panel MCCB 3 Pase 6 A, 5 KA (NC45a)
92 bh
MCCB MG 159.602,44 175.562,69
Panel MCCB 3 Pase 25 A, 25 KA
93 bh
MCCB (NS100N) MG 87.608,99 96.369,89
Panel MCCB 3 Pase 16 A, 5 KA
94 bh 3.761.260,3
MCCB (NS100N) MG
7 4.137.386,41
Panel MCCB 3 Pase
95 32 A, 25 KA MG bh 3.801.558,5
MCCB
3 4.181.714,38
Panel MCCB 3 Pase 80 - 100 A, 25 KA
96 bh
MCCB (NS100) MG 585.212,25 643.733,48
Panel MCCB 3 Pase 50 - 63 A,(NS100)
97 bh
MCCB MG 549.101,94 604.012,13
350 - 500 A / 70 KA
Panel MCCB 3 Pase
98 / 3 Pole NS630 bh
MCCB
bN/H/L 583.651,68 642.016,85
224 - 320 A / 70 KA
Panel MCCB 3 Pase
99 / 3 Pole NS400 bh
MCCB
bN/H/L 560.944,46 617.038,91
175 -.250 A / 70 KA
Panel MCCB 3 Pase
100 / 3 Pole NS250 bh
MCCB
bN/H/L 564.964,40 621.460,84
160 - 300 A / 70 KA
Panel MCCB 3 Pase
101 / 3 Pole NS400 bh
MCCB
bN/H/L 569.201,63 626.121,80
Panel MCCB 3 Pase 64 - 80 A / 70 KA / 3
102 bh
MCCB Pole NS100 bN/H/L 549.753,82 604.729,20
Panel MCCB 3 Pase 44 - 63 A / 70 KA / 3
103 bh
MCCB Pole NS100 bN/H/L 639.170,30 703.087,33
Panel MCCB 3 Pase 32 - 40 A / 70 KA / 3
104 bh
MCCB Pole NS100 bN/H/L 651.990,65 717.189,71
Panel MCCB 3 Pase 400 A / 3 Pole LCI -
105 bh 1.648.718,2
Contraktor F3304
3 1.813.590,05
Panel MCCB 3 Pase 250 A / 3 Pole LCI -
106 bh 2.485.082,8
Contraktor F1504
3 2.733.591,11
Panel MCCB 3 Pase 200 A / 3 Pole LCI -
107 bh
Contraktor F1154 560.025,90 616.028,49
Panel MCCB 3 Pase 160 A / 3 Pole LCI -
108 bh
Contraktor F1154 571.048,63 628.153,50
Panel MCB 3 Pase 16 A, 5 KA (NC45a)
109 bh
MCB MG 401.993,90 442.193,29
Panel MCB 3 Pase 10 A, 5 KA (NC45a)
110 bh
MCB MG 396.452,90 436.098,19
Panel MCB 3 Pase 6 A, 5 KA (NC45a)
111 bh
MCB MG 260.329,50 286.362,45
Panel MCB 3 Pase 10 A, 6 KA, 10 A, 6
112 bh
MCB K MG 260.329,50 286.362,45
Panel MCB 3 Pase 50 A, 10 A
113 bh
MCB (NC100H) MG 591.209,00 650.329,90
Panel MCB 3 Pase 16 A, 6 KA
114 bh
MCB (NC45aD) MG 260.329,50 286.362,45
Panel MCB 3 Pase 6 A, 6 KA (NC45aD)
115 bh
MCB MG 311.831,00 343.014,10
Panel MCB 3 Pase 63 A, 10 KA
116 bh
MCB (NC100H) MG 591.209,00 650.329,90
Panel MCB 3 Pase 32 A, 10 KA
117 bh
MCB (NC100H) MG 302.659,50 332.925,45
Panel MCB 3 Pase 16 A, 8 KA
118 bh
MCB (NC10014) MG 301.650,64 331.815,70
Panel MCB 3 Pase 16 A, 5 KA (NC45N)
119 bh
MCB MG 302.038,66 332.242,53
Panel MCB 3 Pase 16 A, 10 KA
120 bh
MCB (NC100H) MG 301.340,22 331.474,24
Panel MCB 3 Pase 25 A, 8 KA (NC45N)
121 bh
MCB MG 285.353,59 313.888,94
Panel MCB 3 Pase 40 A, 8 KA L
122 bh
MCB (NC45N) MG 262.149,69 288.364,66
Panel MCB 3 Pase 10 A, 8 KA (NC45N)
123 bh
MCB MG 283.491,07 311.840,17
Panel MCB 1 Pase 20 A, 10 KA
124 bh
MCB (NC45N) MG 130.609,22 143.670,14
Panel MCB 1 Pase 10 A, 8 KA (NC45N)
125 bh
MCB MG 62.860,05 69.146,06
Panel MCB 1 Pase 6 A, 8 KA (NC45N)
126 bh
MCB MG 55.029,00 60.531,90
Panel MCB 1 Pase 20 A, 8 KA (NC45N)
127 bh
MCB MG 55.029,00 60.531,90
Panel MCB 1 Pase 20 A, 5 KA
128 bh
MCB (NC45Na) MG 62.860,05 69.146,06
Panel MCB 1 Pase 10 A, 5 KA
129 bh
MCB (NC45Na) MG 64.955,39 71.450,92
Panel MCB 1 Pase 6 A, 5 KA (NC45Na)
130 bh
MCB MG 65.809,04 72.389,94
Panel MCB 1 Pase 25 A, 5 KA
131 bh
MCB (NC45Na) MG 71.862,23 79.048,45
Panel MCB 1 Pase 16 A, 5 KA
132 bh
MCB (NC45Na) MG 65.653,83 72.219,21
Panel MCB 1 Pase 16 A, 5 KA (NC45N)
133 bh
MCB MG 65.110,60 71.621,65
Panel MCB 1 Pase 6 A, 6 KA (NC45aD)
134 bh
MCB MG 65.809,04 72.389,94
Panel MCB 1 Pase 20 A, 8 KA (NC45N)
135 bh
MCB MG 65.809,04 72.389,94
Panel MCB 1 Pase 10 A, 8 KA (NC45N)
136 bh
MCB MG 65.809,04 72.389,94
Panel MCB 1 Pase 16 A, 5 KA (NC45N)
137 bh
MCB MG 65.809,04 72.389,94
Panel MCB 1 Pase 6 A, 5 KA (NC45N)
138 bh
MCB MG 158.857,44 174.743,18
Panel MCB 1 Pase 25 A, 5 KA (NC45N)
139 bh
MCB MG 156.529,29 172.182,21
Panel MCB 1 Pase 50 A, 10 KA
140 bh
MCB (NC100H) MG 656.383,09 722.021,40

P. BAHAN ALAT PENGANTUNG DAN KUNCI


Kunci Silinder ALFA
1 bh
untuk Pintu Alumunium 451.131,98 496.245,17
Tarikan Pintu
2 bh
Alumunium 460.973,70 507.071,07
3 Kunci 2 Slaag ROYAL bh
184.666,98 203.133,67
Rel Henderson
4 bh 1.198.722,1
Lengkap
1 1.318.594,32
5 Rel maraton I Pintu unt
257.789,70 283.568,67
Kunci 2 Slaag Silinder Tipe 210 s/d type
6 bh
SEIS Asli 226 408.366,92 449.203,61
Kunci 2 Slaag Ancor
7 bh
Asli 198.433,63 218.277,00
8 Kunci 2 Slaag ISO bh
260.654,03 286.719,43
Kunci KM Bulat Kualitas
9 bh
Biasa 94.687,51 104.156,26
10 Kunci kM Bulat ALFA bh
78.769,08 86.645,98
Kunci 2 Slaag Silinder
11 bh
Utama Standard 771.936,94 849.130,63
12 Kunci Gembok Besar bh
93.586,93 102.945,62
Kunci 2 Slaag Kuda
13 bh
Terbang 118.869,70 130.756,66
14 Kunci Lemari bh
113.613,72 124.975,09
15 Espangolet ps
60.602,45 66.662,70
16 Espangolet St. Steel bh
533.358,00 586.693,80
17 Casement ps
75.000,00 82.500,00
18 Grendel 15 cm bh
42.475,80 46.723,38
19 Grendel 5 cm bh
13.075,27 14.382,79
20 Grendel 7 cm bh
88.469,70 97.316,67
Hak Angin Kait Jendela
21 ps
Biasa 22.787,65 25.066,42
Hak Angin Jendela
22 ps
Antik 32.899,82 36.189,80
Hak Angin Sendok
23 bh
Stainless / Kuningan 43.693,97 48.063,36
Sloot Pintu Berikut
24 bh
Rantai 34.549,75 38.004,72
25 Sloot Jendela Tunggal bh
30.944,64 34.039,11
26 Sloot Handle Jendela bh
24.554,22 27.009,64
Engsel Pintu Union
27 ps
Standard 15.000,00 16.500,00
28 Engsel Jendela Unilon ps
35.000,00 38.500,00
29 Engsel Patrun ps
14.251,10 15.676,21
30 Engsel Harmonika ps
20.142,03 22.156,23

31 Floor Hinge ps 3.259.410,0


0 3.585.351,00
Door Closer Kelas
32 Standard ( Kelas unt
Sedang ) 646.238,00 710.861,80
Door Closer Kelas
33 unt
Standard ( Kelas Balk) 675.869,00 743.455,90
Door Closer Kelas
34 unt
Rendah 265.268,00 291.794,80
35 Door Holder unt
88.300,00 97.130,00
36 Door Stoper unt
88.300,00 97.130,00
Tarikan Almari Rata-
37 bh
rata 21.400,17 23.540,18
38 Rambuncis bh
25.000,00 27.500,00
Seng BJLS 30 Lebar 60
39 ml
cm ( 1 rol 50 m' ) 123.205,70 135.526,27
Seng BJLS 30 Lebar 90
40 ml
cm ( 1 rol 50 m' ) 70.077,32 77.085,05
Seng BJLS 30 / 3 x 0.3
41 lbr
mm 103.214,65 113.536,12
42 Seng Plat lbr
69.751,37 76.726,51
Waterstop Lebar 200
43 ml
mm 71.055,14 78.160,65
44 Kunci Tanam biasa buah
132.400,00 145.640,00
45 Kunci Tanam antik buah
150.000,00 165.000,00
Kunci Tanam Kamar
46 buah
Mandi 63.500,00 69.850,00

Q. BAHAN PENGIKAT UNTUK KONSTRUKSI JALAN

1 Aspal Bitumen kg
47.974,00 52.771,40
Aspal ( ESO ) 1 Drum
2 kg
155 kg 13.404,50 14.744,95
3 Aspal Emulsi kg
16.106,55 17.717,21
4 Aspal Curah kg
18.173,68 19.991,05
Aspal Concrete / Laston
5 ton 1.624.815,8
(AC -WC)
9 1.787.297,47
Aspal Threated Base (
6 ton
ATB ) 1.580.320,0 1.738.352,00
0

Lataston / Hot Rolls


7 ton 1.855.465,0
Sheet ( HRS )
0 2.041.011,50

8 Asphal RC 70 (Cilacap) Kg 15.521,00 17.073,10

Asphal Concrete (ATB) 1.552.100,0


9 AC Base Ton 0 1.707.310,00

Asphal Concrete (ATB) 1.693.200,0


10 AC -BC Ton 0 1.862.520,00
Asphal Concrete
Wearing Course / AC- 1.664.980,0
11 WC Ton 0 1.831.478,00
Lapis Asphal Resap
12 Pengikat Ton 22.576,00 24.833,60

13 Lapis Asphal Perekat Ton 19.754,00 21.729,40

1.312.230,0
14 Beton Mortar M3 0 1.443.453,00

1.058.250,0
15 Beton BO M3 0 1.164.075,00

1.086.470,0
16 Beton K 100 M3 0 1.195.117,00

1.087.175,5
17 Beton K 125 M3 0 1.195.893,05

1.107.635,0
18 Beton K 150 M3 0 1.218.398,50

1.243.443,7
19 Beton K 175 M3 5 1.367.788,13

1.299.389,9
20 Beton K 200 M3 0 1.429.328,89

1.325.493,4
21 Beton K 225 M3 0 1.458.042,74
22 Beton K 250 M3
1.342.284,3 1.476.512,73
0

1.359.039,9
23 Beton K 275 M3 3 1.494.943,92

1.408.530,7
24 Beton K 300 M3 5 1.549.383,83

1.426.450,4
25 Beton K 325 M3 5 1.569.095,50

1.451.742,6
26 Beton K 350 M3 3 1.596.916,89

1.484.089,8
27 Beton K 375 M3 0 1.632.498,78

1.505.572,2
28 Beton K 400 M3 8 1.656.129,50

1.529.538,1
29 Beton K 425 M3 1 1.682.491,92

1.589.511,9
30 Beton K 450 M3 6 1.748.463,16

1.411.000,0
31 Beton K 475 M3 0 1.552.100,00

1.672.035,0
32 Beton K 500 M3 0 1.839.238,50

1.552.100,0
33 Beton K 550 M3 0 1.707.310,00

1.693.200,0
34 Beton K 600 M3 0 1.862.520,00

1.834.300,0
35 Beton K 650 M3 0 2.017.730,00

R. BAHAN PENGISAP AIR SUMUR DALAM

1 Pompa Kodok unit


270.912,00 298.003,20
2 Pompa Dragon Tegal unit
499.494,00 549.443,40

3 Pompa Dragon Asli unit 1.164.187,8


8 1.280.606,67
Mesin Pompa Air 100
4 unit 1.530.935,0
W - Sanyo
0 1.684.028,50
Mesin Pompa Air 150
5 unit 2.661.851,5
W - Sanyo
0 2.928.036,65
Pompa Zet Pump 250
6 unit 8.154.451,2
W - Sanyo
0 8.969.896,32
Pompa Zet Pump 450
7 unit 12.952.133,
W - Sanyo
40 14.247.346,74
Pompa. Submersible
8 kap. 150 liter / menit 3 unit 51.150.866,
KW 50 56.265.953,15
Gear Pump Kap. 60 liter
9 unit 23.210.950,
/ menit
00 25.532.045,00
Deep Well dengan
10 kelengkapannya kap. unit 202.644.236,
06 222.908.659,67
150 liter / menit

11 Hand Oil Pump unit 6.999.971,0


0 7.699.968,10

S. BAHAN PENAMPUNG AIR

Tangki Air Fiber Glass


1 bh 1.058.250,0
0.5 m3 ( Excel )
0 1.164.075,00
Tangki Air Fiber Glass 1
2 bh 1.693.200,0
m3 ( Excel )
0 1.862.520,00
Tangki Air Fiber Glass 2
3 bh 3.245.300,0
m3 ( Excel )
0 3.569.830,00
Tangki SST Tanpa Kaki
4 GS-700 TK (Volume unit 1.515.414,0
1.666.955,40
600 Liter, D-T 87 - 115) 0
Tangki SST Tanpa Kaki
5 GS-1000 TK (Volume unit 1.515.414,0
1.666.955,40
800 Liter, D-T 87 - 140) 0
Tangki SST Tanpa Kaki
GS-1500 TK (Volume
6 unit 1.752.462,0
1000 Liter, D-T 99 - 1.927.708,20
0
145)
Tangki SST Tanpa Kaki
GS-1800 TK (Volume
7 unit 1.752.462,0
1500 Liter, D-T 99 - 1.927.708,20
0
205)
Tangki SST Tanpa Kaki
GS-2000 TK (Volume
8 unit 1.752.462,0
1000 Liter, D-T 99 - 1.927.708,20
0
145)
Tangki SST Tanpa Kaki
GS-2500 TK (Volume
9 unit 1.752.462,0
1500 Liter, D-T 99 - 1.927.708,20
0
205)
Tangki SST Tanpa Kaki
GS-3000 TK (Volume
10 unit 3.555.720,0
2100 Liter, D-T 145 - 3.911.292,00
0
150)
Tangki SST Tanpa Kaki
GS-4000 TK (Volume
11 unit 5.308.182,0
3100 Liter, D-T 145 - 5.839.000,20
0
210)
Tangki SST Tanpa Kaki
GS-5000 TK (Volume
12 unit 17.483.475,
4000 Liter, D-T 145 - 19.231.822,76
24
265)
Tangki SST Tanpa Kaki
GS-6000 TK (Volume
13 unit 20.673.139,
5000 Liter, D-T 145 - 22.740.453,46
51
325)
Tangki SST Pakai Kaki
14 700 TK (Volume 660 unit 2.879.145,5
3.167.060,05
Liter, D-T 87 - 155) 0
Tangki SST Pakai Kaki
15 1000 TK (Volume 800 unit 3.498.433,4
3.848.276,74
Liter, D-T 87 - 175) 0
Tangki SST Pakai Kaki
16 1500 TK (Volume 1100 unit 4.128.586,0
4.541.444,60
Liter, D-T 99 - 180) 0
Tangki SST Pakai Kaki
17 1800 TK (Volume 1500 unit 5.627.914,6
6.190.706,06
Liter, D-T 99 - 240) 0
Tangki SST Pakai Kaki
18 2000 TK (Volume 1100 unit 4.878.250,3
5.366.075,33
Liter, D-T 99 - 180) 0
Tangki SST Pakai Kaki
19 2500 TK (Volume 1500 unit 6.627.467,0
7.290.213,70
Liter, D-T 99 - 240) 0
Tangki SST Pakai Kaki
20 3000 TK (Volume 2300 unit 9.813.787,2
10.795.165,92
Liter, D-T 145 - 195) 0
Tangki SST Pakai Kaki
21 4000 TK (Volume 3200 unit 13.867.308,
15.254.038,80
Liter, D-T 145 - 250) 00
Tangki Silinder Excel
22 GE - 250 (Volume 250 unit
906.433,46 997.076,80
Liter)
Tangki Silinder Excel
23 GE - 300 (Volume 300 unit
906.433,46 997.076,80
Liter)
Tangki Silinder Excel
24 GE - 550 (Volume 550 unit 1.417.067,3
1.558.774,03
Liter) 0
Tangki Silinder Excel
25 GE - 600 (Volume 600 unit 1.414.245,3
1.555.669,83
Liter) 0
Tangki Silinder Excel
26 GE - 700 (Volume 700 unit 1.509.064,5
1.659.970,95
Liter) 0
Tangki Silinder Excel
27 GE - 800 (Volume 800 unit 1.889.329,0
2.078.261,90
Liter) 0
Tangki Silinder Excel
28 GE - 1100 VB (Volume unit 2.278.059,5
2.505.865,45
1050 Liter) 0
Tangki Silinder Excel
29 GE - 1200 VB (Volume unit 2.278.059,5
2.505.865,45
1050 Liter) 0
Tangki Silinder Excel
30 GE - 1100 (Volume unit 2.458.526,4
2.704.379,04
1150 Liter) 0
Tangki Silinder Excel
31 GE - 1100 GT (Volume unit 2.458.526,4
2.704.379,04
1150 Liter) 0
Tangki Silinder Excel
32 GE - 1600 (Volume unit 3.336.450,6
3.670.095,66
1600 Liter) 0
Tangki Silinder Excel
33 GE - 2000 (Volume unit 4.364.349,9
4.800.784,99
2000 Liter) 9
Tangki Silinder Excel
34 GE - 2250 (Volume unit 4.801.350,8
5.281.485,88
2250 Liter) 0
Tangki Silinder Excel
35 GE - 3100 (Volume unit 6.422.872,0
7.065.159,20
3100 Liter) 0
Tangki Silinder Excel
36 GE -3250 (Volume unit 83.021.829,
91.324.011,90
3250 Liter) 00
Tangki Silinder Excel
37 GE - 5200 (Volume unit 10.246.569,
11.271.226,03
5200 Liter) 12
Tangki Sunder Excel
38 GE - 11000 (Volume unit 24.224.824,
26.647.306,46
11000 Liter) 05
Tangki Silinder Dapat
Disusun Excel GE -
39 unit 2.669.456,7
1000 SN (Volume 1000 2.936.402,47
9
Liter)
Tangki Silinder Dapat
Disusun Excel GE -
40 unit 4.448.883,0
2000 SN (Volume 2000 4.893.771,30
0
Liter)
Tangki Silinder Dapat
Disusun Excel GE -
41 unit 7.519.219,0
3000 SN (Volume 3000 8.271.140,90
0
Liter)
Tangki Tanam /
Pendam (Dengan
42 Pelindung Beton) Excel unit 1.938.714,0
2.132.585,40
Lumba-Lumba GE - 550 0
K (Volume 550 Liter)
Tangki Tanam /
Pendam (Dengan
Pelindung Beton) Excel
43 unit 3.622.037,0
Lumba-Lumba GE - 3.984.240,70
0
1100 K (Volume 1100
Liter)
Tangki Tanam /
Pendam (Dengan
Pelindung Beton) Excel
44 unit 6.990.094,0
Lumba-Lumba GE - 7.689.103,40
0
2100 K (Volume 2100
Liter)
Tangki Tanam /
Pendam (Dengan
Pelindung Beton) Excel
45 unit 8.985.248,0
Lumba-Lumba GE - 9.883.772,80
0
2500 K (Volume 2500
Liter)
Tangki Tanam /
Pendam (Langsung
46 unit 1.938.714,0
Pendam) GE - 550 ST 2.132.585,40
0
(Volume 550 Liter)
Tangki Tanam /
Pendam (Langsung
47 unit 3.622.037,0
Pendam) GE - 1100 ST 3.984.240,70
0
(Volume 1100 Liter)
Tangki Tanam /
Pendam (Langsung
48 unit 6.990.094,0
Pendam) GE - 2100 ST 7.689.103,40
0
(Volume 2100 Liter)
Tangki Tanam /
Pendam (Langsung
49 Pendam) GE - 2500 ST unit 8.985.248,0
9.883.772,80
(Volume 2500 . 0
Liter)
Tangki Horisontal GE -
50 5000 H (Volume 550 unit 16.600.415,
18.260.456,50
Liter) 00
51 Bak KM Fiber 60 x 60 bh
352.750,00 388.025,00
52 Bak Taraso WC 40 x 40 bh
70.550,00 77.605,00
53 Bak KM Taraso 60 x 60 bh
203.184,00 223.502,40
T. ALAT TUKANG

1 Palu 0.5 kg bh
90.304,00 99.334,40
2 Cangkul bh
97.359,00 107.094,90
3 Singkup bh
90.304,00 99.334,40
4 Sekrop bh
97.359,00 107.094,90
5 Pengki bh
21.165,00 23.281,50
6 Linggis bh
97.359,00 107.094,90
Rool Meter 30 meter (
7 bh
Bahan Plastik ) 128.401,00 141.241,10
Rool Meter 5 meter (
8 bh
Bahan Besi ) 36.686,00 40.354,60
Selang Plastik untuk
9 m
Water Pas dia. 0.5cm 2.822,00 3.104,20
Water Pas Alumunium
10 bh
60 cm 60.673,00 66.740,30

U. BAHAN BAKAR DAN PELUMAS

1 Minyak Tanah lt
28.220,00 31.042,00
Kayu Bakar dari Kayu
2 m3
Karet 98.770,00 108.647,00
3 Bahan Bakar Residu lt
8.466,00 9.312,60
4 Minyak Solar lt
8.500,00 9.500,00
5 Bensin Premium lt
9.000,00 9.900,00
6 Plus Oil lt
56.440,00 62.084,00
7 Oil Mesran 40 SAE lt
56.440,00 62.084,00
8 Elpiji / botol 15 kg
173.553,00 190.908,30
15.1
9 Asitilin / Botol
kg btl 148.155,00 162.970,50
10 Angin ( 02 ) / botol btl
98.770,00 108.647,00
11 Karbit kg
17.637,50 19.401,25
12 Minyak Bekisting ltr
48.456,56 53.302,22
13 Rapidrant Gln
27.704,99 30.475,48
14 Soda Api kg
41.285,86 45.414,45
15 Sabun kg
10.104,17 11.114,59
16 Arang Kayu kg
10.973,35 12.070,68
17 Kawat Las bh
35.275,00 38.802,50

V. BAHAN PAGAR

1 Panel Beton Pracetak lbr


183.430,00 201.773,00
2 Kolom Beton Pracetak btg
406.368,00 447.004,80

W. BAHAN PENANGKAL PETIR


EF Lighting Terminal
1 unit
Radius > 110 m2 714.354,03 785.789,43
2 Counecting Sleeve bh
214.795,12 236.274,63
3 EF Coaxcial Cable ml
695.340,80 764.874,88
Grounding Terdiri Dan
Earth Steel Coppir Rod
5/8", Earth Road
4 unit
Camping, Earth Road
Clomp, Driving TIP & 46.935.504,
Driving Stud 00 51.629.054,40
Indelek Prevectron 2
5 unit 3.969.309,5
Type S 4.50
0 4.366.240,45
Grounding System Max.
6 unit
2 OHM + Box 209.471,42 230.418,56
7 Biaya Instalasi unit
7.212.284,1 7.933.512,59
7

X. FIRE ALARM

1 Alarm Bell unit


289.109,67 318.020,63
Manual Break Glass
2 unit
Push Button 573.982,10 631.380,31
3 Sirine unit
473.483,63 520.831,99
4 Smoke Detector unit
310.839,07 341.922,97
5 Heat Detector unit
170.249,85 187.274,83

Y. BIDANG PERTAMANAN

1 Aglonema batang
63.914,86 70.306,34
2 Bambu krisik/jepang batang
63.914,86 70.306,34
3 Furadan kg
28.356,87 31.192,55
Kompos/pupuk
4 karung
kandang 32.050,87 35.255,95
5 M atoa (2 m) batang
44.762,56 49.238,82
Palm (botol, ekor tupai,
6 batang
putri, dll) tinggi 2 m 135.156,87 148.672,55
7 Philo batang
96.695,83 106.365,41
Pohon pelindung
8 (angsana, mahoni, batang
kamboja dll) tinggi 2m 29.117,40 32.029,14
Pohon perdu (kaca
9 piring, puring, mawar, batang
melati, dll) 16.948,93 18.643,83
10 Rumput gajah mini m2
21.294,81 23.424,29

Z. BIDANG PENGAIRAN
1 Batu Belah 10 - 15 cm M3
216.997,69 238.697,46
2 Batu Pecah 5 - 7 cm M3
282.200,00 310.420,00
3 Batu Pecah 0,5 - 1 cm M3
292.570,85 321.827,94
4 Batu Pecah tersaring A M3
241.097,57 265.207,33
5 Batu Pecah tersaring B M3
233.294,74 256.624,21
6 Timbunan Pilthan M3
198.132,62 217.945,88
7 Makadam M3
114.079,35 125.487,29

8 Kayu Damar Laut M3 7.231.248,0


1 7.954.372,81

9 Kayu Klas I M3 5.974.794,8


4 6.572.274,32

10 Kayu Klas III M3 2.671.333,4


2 2.938.466,76
11 Kayu Kano 4/6 BTG
72.497,18 79.746,90
12 Papas 2/20 x 4 LBR
91.461,02 100.607,12
Balok Kayu 6 - 8 - 10 /4
13 BTG
m 399.327,11 439.259,82
14 Batang Kelapa 13TG
576.125,41 633.737,95
15 Lempengen rumput M2
48.002,22 52.802,44
16 Triplek tb. 3 mm LBR
67.492,83 74.242,12
17 Triplek tb. 4 mm LBR
84.895,17 93.384,68
18 Triplek tb. 6 mm LBR
64.906,00 71.396,60
19 Triplek tb. 9 mm LBR
125.579,00 138.136,90
20 Multiplek 12 mm LBR
177.687,23 195.455,95
Seng gelombang BJLS
21 LBR
30 33.864,00 37.250,40
Seng Plat 3 x 6 BWG
22 M2
30 49.385,00 54.323,50
23 Conblock M2
53.928,42 59.321,26
24 Batako PSPM BH
5.432,35 5.975,59
Pipa Beton Tidak
25 M'
Bertulang dia 0,50 m 151.710,72 166.881,79
Pipa Beton Tidak
26 M'
Bertulang dia 0,60 m 183.712,20 202.083,42
Pipa Beton Tidak
27 M'
Bertulang dia 0,80 m 261.246,65 287.371,32
Pipa Beton Tidak
28 M'
Bertulang dia 1,00 m 339.077,41 372.985,15
Pipa Beton Bertulang
29 M'
dia 0,50 m 160.698,79 176.768,67
Pipa Beton Bertulang
30 M'
dia 0,60 m 205.441,60 225.985,76
Pipa Beton Bertulang
31 M'
dia 0,80 m 399.919,73 439.911,70
Pipa Beton Bertulang
32 M'
dia 1,00 m 265.493,76 292.043,14
Besi Beton U24 dia. 14
33 BTG
mm 125.536,67 138.090,34
Besi Beton U24 dia. 22
34 BTG
mm 287.321,93 316.054,12
Besi Beton U24 dia. 25
35 BTG
mm 366.634,24 403.297,66
Besi Beton U32 dia. 10
36 BTG
mm 228.158,70 250.974,57
Besi Beton U32 dia. 12
37 BTG
mm 130.376,40 143.414,04
Besi Beton U32 dia. 16
38 BIG
mm 167.711,46 184.482,61
Besi Beton U32 dia. 19
39 BIG
mm 266.185,15 292.803,67
Besi Beton U32 dia. 22
40 BIG
mm 336.805,70 370.486,27
Besi Beton U32 dia. 25
41 BTG
mm 380.264,50 418.290,95
42 Besi Beton Ulir 10 BIG
103.412,19 113.753,41
43 Besi Beton Ulir 12 BIG
135.216,13 148.737,74
44 Besi Beton Ulir 16 BTG
201.490,80 221.639,88
45 Besi Beton Ulir 19 BIG
270.432,26 297.475,49
46 Besi Beton Ulir 22 BIG
366.140,39 402.754,43
47 Besi Beton Ulir 25 BTG
475.182,47 522.700,72
48 Baja U 24 KG
77.336,91 85.070,60
49 Baja U 32 KG
36.544,90 40.199,39
50 Baja U 36 KG
82.966,80 91.263,48
51 Baja U 42 KG
115.363,36 126.899,70
52 Wermes 06 M2
244.455,75 268.901,33
53 Wermes 08 M2
461.749,75 507.924,73
54 Wermes 10 M2
597.558,50 657.314,35
55 Besi Pofil 4x4 KG
26.075,28 28.682,81
56 Besi Struktur H- Beam KG
29.235,92 32.159,51
Besi C macam-macaw
57 KG
ukuran 16.297,05 17.926,76
Besi L macam-macam
58 KG
ukuran 22.815,87 25.097,46
59 Pipa Galvanis 2,5" BTG
309.643,95 340.608,35
60 Pipa Galvanis 3" BTG
543.235,00 597.558,50
61 Pipa Galvanis 4" BTG
706.205,50 776.826,05
62 Kawat Bronjong 3 mm KG
87.213,91 95.935,30
63 Kawat Bronjong 5 mm KG
125.339,13 137.873,04
64 Stempet / Gemuk KG
54.224,73 59.647,20
65 0li SAE 140 LTR
66.274,67 72.902,14
66 Oli SAE 90 LTR
71.114,40 78.225,84
67 Oli SAE 20 LTR
45.730,51 50.303,56

68 Laston SPC TONNE 1.303.764,0


0 1.434.140,40
69 Cat (untuk besi profil) KG
54.817,35 60.299,09
70 Meni KG
30.915,01 34.006,51
71 Glass Bead KG
14.124,11 15.536,52
Cat Marka Jalan
72 5 KG
(thermo pastic) 119.511,70 131.462,87
73 Kapur Hidrasi M3
9.235,00 10.158,49
74 Pipa PVC dia 5" BTG
554.099,70 609.509,67

75 Pipa PVC dia 12" BTG 1.035.702,2


2 1.139.272,44
Saluran Beton (Uditch)
76 M' 1.303.764,0
Stu 50/50 - 120
0 1.434.140,40
Saluran Beton (Uditch)
77 M' 1.521.058,0
Stu 60/60 - 120
0 1.673.163,80
Saluran Beton (Uditch)
78 M' 2.814.945,0
Stu 80/80 - 120
0 3.096.439,50
Saluran Beton (Uditch)
79 M' 4.291.556,5
Stu 100/100 - 120
0 4.720.712,15
Box Culvert BC 50-50-
80 M' 1.097.758,0
100
0 1.207.533,80
Box Culvert BC 60-60-
81 M' 1.207.533,8
100
0 1.328.287,18
Box Culvert BC 80-80-
82 M' 2.650.704,6
100
0 2.915.775,06
Box Culvert BC 100-
83 M' 3.230.766,7
100-100
0 3.553.843,37
Karet Penyambung
84 BH
Piga dia 50 cm 83.954,50 92.349,95
Karet Penyambung
85 BH
Piga dia 60 cm 105.387,59 115.926,35
Karet Penyambung
86 BH
Pipa dia 80 cm 146.673,45 161.340,80
Karet Penyambung
87 BH
Pipa dia 100 cm 239.023,40 262.925,74
Plat Penjepit 12x4x8
88 LBR 2.879.145,5
mm
0 3.167.060,05
Besi UNP 20 BTG/ 6
89
(200x80x7,5 mm) m 706.205,50 776.826,05
Besi Essentaal 1,5-64
90 KG
mm 59.755,85 65.731,44
91 Kuningan 3" KG
157.044,30 172.748,73
92 Bambu BH
31.507,63 34.658,39
93 Baud 1,5 BH
11.161,01 12.277,11
94 Baud Uk 3/4 - 7 cm BH
40.693,24 44.762,56
95 Baud Uk 3/4 - 17 cm BH
34.075,65 37.483,22
Cat Glotek Hitam
96 KG
(setara) 51.557,94 56.713,73
97 Cat Glotek Biru (setara) KG
53.138,26 58.452,09
98 Amplas LBR
5.531,12 6.084,23
99 Prasasti 40 can x 60 cm BH
651.882,00 717.070,20
100 Prasasti 20 cm x 30 cm BH
543.235,00 597.558,50

Tambahan Harga Bahan

Rangka hollow besi


1 Alucobond 40 x 60 x 40 x 60 x 2,1mm bt
41.388,86 45.527,75
2,1mm
Rangka hollow besi
2 Alucobond 40 x 40 x 40 x 40 x 1,1mm bt
19.919,09 21.911,00
1,1mm
Braket siku besi
Alucobond 40 x 40 x
3 4mm 40 x 40 x 4mm bt 7.760,50 8.536,55

4 Brazing Alucobond m2 62.084,00 68.292,40

5 Braket Alucobond m2 2.116,50 2.328,15


Aluminium Composite
6 Panel / ACP bh 260.752,80 286.828,08
Main frame 170cm (
7 STEGER ) bt 232.815,00 256.096,50

8 Cross Brace bh 70.550,00 77.605,00

9 Join Pin bh 7.055,00 7.760,50

PRODUK GALVALUM TRUSS

1 Truss Profil U, T min 0.83 mm m' 190.485,00 209.533,50

2 PROFIL U 75 TEBAL 0.53 mm m' 132.634,00 145.897,40

3 PROFIL U 100 TEBAL 0.53 mm m' 174.964,00 192.460,40

4 PROFIL U 100 TEBAL 0.83 mm m' 261.035,00 287.138,50

5 PROFIL U 60 TEBAL 0.53 MM m' 119.935,00 131.928,50

6 RENG 39 m' 63.495,00 69.844,50

7 RENG 36 m' 56.440,00 62.084,00

8 RENG 29 m' 49.385,00 54.323,50

9 PROFIL C75 TEBAL 0.6 MM m' 84.660,00 93.126,00

10 PROFIL C75 TEBAL 0.65 MM m' 90.304,00 99.334,40

11 PROFIL C75 TEBAL 0.7 MM m' 97.359,00 107.094,90

12 PROFIL C75 TEBAL 0.75 MM m' 100.181,00 110.199,10


13
PROFIL C75 TEBAL 0.95 MM m' 132.634,00 145.897,40
14 RENG m'
42.330,00 46.563,00

Semen Mortar Utama

1 MU-100 Plester Premium40 kg kg 2.116,50 2.328,15


MU-200 Acian Plester &
2 Beton 5 kg kg 6.067,30 6.674,03
MU-200 Acian Plester &
3 Beton 40 kg kg 5.591,09 6.150,20

4 MU-260 Acian Profil 25 kg kg 10.751,82 11.827,00

5 MU-270 Acian Putih 25 kg kg 8.804,64 9.685,10

6 MU-300 Pasangan Bata 40 kg kg 1.781,39 1.959,53


MU-301 Pas Bata &
7 Plester 10 kg kg 296,31 325,94
MU-301 Pas Bata &
8 Plester 40 kg kg 2.028,31 2.231,14
MU-380 Perekat Bata
9 Ringan 5 kg kg 5.926,20 6.518,82
MU-380 Perekat Bata
10 Ringan 40 kg kg 5.291,25 5.820,38
MU-400 Perekat
11 Keramik Dinding 5 kg kg 9.877,00 10.864,70
MU-410 Self Leveling
12 Floor 25 kg kg 14.392,20 15.831,42

13 MU-440 Perata Lantai 40 kg kg 1.940,13 2.134,14


MU-445 Perata Lantai
14 Premium 40 kg kg 3.703,88 4.074,26
MU-450 Perekat
15 Keramik Lantai 5 kg kg 9.453,70 10.399,07
MU-450 Perekat
16 Keramik Lantai 40 kg kg 57.851,00 63.636,10
MU-460 Perekat
17 Keramik Daerah Basah 25 kg kg 24.748,94 27.223,83
MU-470 White Tile
18 Addesive 25 kg kg 21.729,40 23.902,34
MU-480 Perekat
19 Keramik diatas Keramik 5 kg kg 21.306,10 23.436,71
MU-L500 Perekat
20 Mortar & Beton 2 kg karung 289.960,50 318.956,55
MU-600 Pelapis Kedap
21 Air 3 kg karung 162.265,00 178.491,50
MU-600 Pelapis Kedap
22 Air 30 kg kg 6.608,18 7.269,00

23 MU-700 Floor Hardener 25 kg kg 8.861,08 9.747,19


MU-800 Non-Shrink
24 Grout 40 kg kg 5.538,18 6.091,99
MU-830 Perbaikan
25 Permukaan Beton 40 kg kg 9.277,33 10.205,06
MU-840 Finish Coat
26 Repair 25 kg kg 18.343,00 20.177,30

Bahan Pabrikasi

Plavond PVC (setara


1 shunda, Flat Gloss Half m2
99.000,00 108.900,00
Silver

2 screw buah 350,00 385,00

3 Plat Bondex m2 140.000,00 154.000,00


Aluminum Composite
4 Panel type PVDF 0.3 m2
450.000,00 495.000,00
warna Silver
Water Proofing Coating
5 setara kg
42.500,00 46.750,00
Fosroc/Sika/Aquaproof
Rangkap baja ringan +
6 m2
Genteng metal pasir 190.000,00 209.000,00

7 Spardek m2 110.700,00 121.770,00

1.500.000,0
8 Kayu Bekisting m3 0 1.650.000,00

Keterangan :
Untuk harga material di atas sudah termasuk keuntungan dan ketentuan pajak yang berlaku.