Professional Documents
Culture Documents
1.1 Background of KG Basin Pipeline Network
1.1 Background of KG Basin Pipeline Network
Under Phase – II , i.e., in the year 2001, another 278 KMs of pipeline was laid,
which includes 18’’, 204 KMs long Tatipaka – Kondapalli (near Vijayawada) pipeline
for supplying gas to Lanco Kondapalli power plant &18’’, 10 KMs long pipeline for
9
supplying gas to Reliance Energy Ltd, Samalakot.
During the year 2005, another 80 KMs of pipelines was added to supply gas to
four new IPP (Independent Power Producers) and for City gas distribution and CNG
outlets at Vijayawada (through BGL) from the trunk pipeline. All these pipelines were
commissioned and came into operation during the financial year 2005-2006.
Based on the increased availability of RIL D–6 gas, 30 KM P/L was added to
supply more gas. GAIL has started transporting the RIL D–6 gas w.e.f April 2009.
Presently, [1] & [2] 18” pipelines are being replaced with 24” new pipelines.
COMPOSITION:
Methane : 98.7901
9
Ethane. : 0.2567
Nitrogen : 0.2144
Propane : 0.1305
Hexane : 0.0914
n-Butane : 0.0437
i-Pentane : 0.0225
i-Butane : 0.0192
No traces of Heptane, Octane, Nonane, Decane, H2S, Water, Helium, Oxygen, CO,
Hydrogen and Argon.
PROPERTIES:
Viscosity : 0.01026 cp
PIPELINES:
(Inches) (KM)
3. TATIPAKA-NARASAPUR 14 25.600
4. NARASAPUR-APSEB 12 61.900
5. TATIPAKA-KCHERUVU 18 44.500
9
6. ADAVIPALEM-KADALI 8 10.500
8. SYANAM-GUDALA 16 9.800
9. MORI-DINDI 12 9.000
9
1.4 TERMINALS:
2. SV-1 PASARLAPUDI
5. SV-2 ALLAVARAM
9. SV-3 TOTTARAMUDI
12. SEIL
13. HITECH
14. RCL
20. SVPPL
9
22. MORI RECEIVING TERMINAL
MORI : 938818
MANDAPETA(W) : 35267
ODALARAVU : 784413
GMA : 32623
PSP#8 : 323772
KAIKALURU : 1872
NSP : 65482
NANDHIGAM : 21735
HITECH : 15190
SVPPL : 36748
SEIL-I : 22784
SEIL-II : 31566
9
Figure 1: process flow diagram of Tatipaka terminal
9
Figure 2: key map showing incoming sources of Tatipaka terminal
9
FIRE & SAFETY
Major Gas Receiving terminals are provided with the following fire protection system
as per OISD guidelines:
Minor Gas Receiving Terminals are provide with portable fire extinguishers as per the
OISD 116 guidelines.
5) Inform the MCR/OIC GAIL officers and the customer control room & fire
station
3) BIC shall rush to the site with necessary fire extinguishers, retaining one
9
coordinator at the terminal and extinguish the fire
5) BIC shall asses the nature of fire and accordingly inform the MCR/OIC
GAIL Rajahmundry & State Govt. Authorities
1) In case of any accidents occurred in the installation provide the first aid to the
injured person immediately
2) If the accident is of major in nature provide first aid to the person and then
refer him 1 the customer dispensary or to the hospital
3) All minor/Major accidents shall be reported to the safety officer and BIC.
The district crisis group under the chairman of collector has prepared offsite
emergency action plan for east and west districts to meet any off site emergency
occurs due to uncontrolled incidents by a particular gas stations
Detailed emergency action plan may be referred to Disaster Management plan (DMP)
10
2.5 On site emergency action plan
The emergency occurring within the plant, which may cause injuries or loss of life or
damage to property the situation thus created is called on site emergency. This type
of emergency is contained to a particular place and doesn’t affect the
neighbourhood & Surrounding places.
If the emergency becomes uncontrollable and leads to damage to life and property in
the installation and throughout the pipeline and its neighbourhood and requires the
assistance of outside agencies to handle the situation. That is called off site
emergency. Handle of offsite emergency is within the purview of the district
authorities.
11
THE SEQUENCE OF ACTIVITIES INVOLVED IN LAYING NEW
PIPELINE
1.LAND ACQUISATION
2. ROW CLEARANCE
3. GRADING
4. TRENCHING
5. WELDING
6. STRINGING
7. RADIOGRAPHY
8. JOINT COATING
9. HOLIDAY TESTING
10. LOWERING
12. HYDROTESTING
3.1 TRENCHING:
In cultivable land, to strip top soil (30 cm depth) & store separately along ROW
for replacement on top of backfilled ditch.
12
Provide suitable crossings across open ROW for land owners/ public.
3.2 WELDING:
Polarity : DCRP
13
b) Hot pass : E 8010 Lincoln 4.00mm dia
Preheating : 200°c
Position : 5G
Polarity : DCRP
14
Preheating : 200°c
Position : 5G
For pipes of 8” and below, TIG Welding is done followed by ARC Welding.
Mode of Operation:
Arc melts parent plate and electrode to form a weld pool that is
protected by the flux cover. Operator adjusts the electrode feed rate,
i.e. hand movement, to keep the arc length constant. Slag must be
removed after depositing each bead. Normally a small degree of
penetration, requiring plate edge preparation. Butt welds in thick plate
15
or large fillets are deposited in a number of passes. The process can
also be used to deposit metal to form a surface with alternative
properties.
Equipment:
a. Welding Sets:
Manual metal arc sets are manufactured in a range of sizes,
usually distinguished by current – note the duty cycle at which the
current is quoted when comparing sets. Engine powered generators
allow operation away from mains supplies. Electrical input is single-
phase at 240 volts for smaller sets, and 415 volts (2 live phases of a
three-phase supply) for larger sets.
b. Power Source:
The welding machine consists of a power source with welding
lead and an electrode holder. The function of the power source is to
provide the voltage necessary to maintain an arc between the work
piece and the end of the electrode. The amount of current provided by
the power source can be altered by a control to suit different welding
conditions. Power source may supply direct current or alternating
current to the electrode. AC transformers and DC generators supply
only one type of current, but transformer-rectifiers can be switched
between AC and DC output.
c. Welding Cables:
The welding current is conducted from the power source to the
work by multi-strand, insulated flexible copper or aluminium cables. A
return cable is required to complete the welding circuit between the
work and the power source. The size of the cable must be sufficient
16
for the maximum output of the welding power source. The earth
cable is a third cable, which acts as a safety device in the event of an
electrical fault.
d. Electrode Holder:
The holder should be relatively light, fully insulated and rated for
at least maximum power source output.
e. Return Clamp:
This is fastened to the work or bench on which the work is
placed and completes the welding circuit. The surface clamped
should be clean enough to allow good metal-to-metal contact.
Mode of Operation:
X-rays are emitted from the tube and pass through the work to
17
be inspected. Parts of the work presenting less obstruction to X-rays,
such as cavities or inclusions, allow increased exposure of the film.
The film is developed to form a radiograph with cavities or inclusions
indicated by darker images. Section thickness increases (such as
weld under-bead) appear as less dense images.
Operating Parameters:
Power consumption: 1 - 10 kW
Portability : fair
Figure 2 :Field joint coatings are carried out using Heat Shrinkable Sleeves
18
A. Materials :
The thickness of field joint coating material is such that an average thickness
of 2.0 mm is guaranteed on the complete finished field joint coating.
1) Surface Preparation :
Oil, grease, salts and other contamination are removed from steel
surface by wiping with rags soaked with suitable solvents such as naphtha or
benzene. Solvent cleaning procedure is in accordance with SSPC-SP 1.
Surface is then blast cleaned to a finish equivalent to SA 2½ of Swedish
Standard SIS-055900. The ends of existing pipe protective coating are
inspected and chamfered prior to application and cleaned as necessary. Joint
coating shall be applied immediately after completion of surface preparation.
The wrap around sleeve of size such that a minimum overlap of 100
mm is ensured (after shrinking) on both sides of the yard applied corrosion
coating of pipe is selected. Before centring the wraparound sleeve, the bare
steel surface shall be preheated over the surface to remove the moisture. The
minimum preheat temperature as recommended by the manufacturer and
shall be checked by means of pyrometer or temperature crayons. The solvent
19
free epoxy primer (if applicable) is applied prior to sleeve application.
3) Inspection:
To protect the buried line pipes from external corrosion, the line pipes
are coated. A good quality pipeline coating shall have following
characteristics:
Adherence to pipe
Non-porous
20
Should be inert to environment.
Resistance to UV degradation.
Following types of coatings are mainly used for coating of line pipes:
Coal Tar : The coal tar enamel shall consist of a uniform mixture of a specially
modified coal tar and inert non-fibrous filler.
Wrapper : The inner wrap glass fibre reinforcement material and outer wrap
material is coal tar impregnated asbestos felt or glass fibre felt.
21
3.8 FUSION BONDED EPOXY COATING
If the electric flow is detected then the test area is termed as conductive
indicating presence of discontinuities such as pinholes and voids.
This test is commonly used in the offshore industries where piping and
structures are coated with non conductor coatings.
22
section after cleaning of the pipe.
Gauge plate with < 2 mm scratch on side wall and with no dent is acceptable.
Fill 500 meters. Of water before first pig and 1000 meter water between first
and second pig.
Pressure the pipe to 125.18 to 118.55 kg/cm2 (depending upon pipe section
profile) and hold it for 24 hrs.
23
Use dwt and recording system during testing.
It is an electrochemical process.
The less noble metal become anode (positive electrode) while more noble
metal act a cathode( negative electrode).
Cathodic Protection:
• Anode: the electrode from which current leaves to the electrolyte Anode gets
corroded
1. Sacrificial Anode CP
2. Impressed Current CP
24
3.11.1 Sacrificial Anode CP :
Anodematerials:
Sea water
Soil
Anode materials:
• Lead-platinum
• Lead-silver
• Graphite
25
• Cast Iron
OPERATION:
26
Output from CP rectifier : 0-50V, 0-50A D.C.
Pipe is kept at a negative potential w.r.t the soil (Min (-)0.85 V).
Regular PSP readings are taken using copper sulphate half cell to
ascertain the protection level.
CIP Surveys are carried out using a high speed data logger with inbuilt
GPS Antenna and stick mounted Cu/CuSO4 reference electrode.
27
Figure 4: close interval potential survey
The imposed pulsed input signal minimizes interference from other current
sources.
28
defect is approached, no needle deflection when the operator is immediately
above the defect, and a decreasing needle deflection as the operator walks
away from the defect.
An empirically based rating based on the so-called %IR value has been
adopted in general terms as follows:
29
3.12 HORIZONTAL DIRECTIONAL DRILLING (HDD):
The first stage consists of directionally drilling a small diameter pilot hole
along a designed directional path.
The second stage involves progressive enlarging this pilot hole to a diameter
suitable for installation of the pipeline.
The third stage consists of pulling the pipeline back into the enlarged hole.
The initial borehole is called a pilot hole. The borehole is drilled using drilling
fluid, which is brought into the borehole by the rotating drilling head.
Bentonite in water forms thixotropic fluid which is used as drilling fluid in HDD.
Enlarging the pilot hole is accomplished using Reaming operation. It was done
by 2 different tools.
1. Fly cutter
2. Reamer
30
Figure 6: Horizontal directional drilling
For enlarging the existing hole, a fly cutter and reamer of 12” were connected
to drill pipes and pulled back.
The hole will be further enlarged using 24” reamer in 2nd stage and 36”
reamer in the next stage.
On the other side of rig, the pipe of 1600 metres is welded and tested by
Radiography.
The welded pipe is joint coated and tested by Hydrostatic test and Holiday
test.
The pull end of pipe is closed and connected to drill pipe using a swivel.
31
Entire pipe is placed on rollers for moving the pipe during pulling.
HDD Equipment
32
in barrel shall be cleared.
Arrangement of requisite spares for pigging operation
Communication system and channel to be establish and ensure for
operation.
Arrangements for collecting the condensate and transportation.
Condensate collection shall be made at all possible anticipated locations.
Tanker to be intimated advance in 12hr and stationed at all Varity
locations.
Temporary pits for collecting water/slug to be prepared in advance.
Arrangement of fire fighting equipment and PPES.
Produce of sequence operation for pigging and circulation to all the
concerned.
Selection of pigs and transportation to the site.
Tools and tackles for pigging operation.
Restriction of gas flow for smooth travel 2.5km/hr.
QOEC
FLOW DI
#1 KICKER VALVE
PIG
33
FLOW
VALVE
Ensure pig barrel isolation valve #2 and kicker line valve #1 closed.
Open the barrel vent and drain to allow the gases displaced or vent to
atmosphere.
With pig barrel vent and drain valves open position check the pressure gauge
reading and pressure gauge must be zero kg/cm2
Replace the pressure gauge with nitrogen gas hose and purge the gas upto 2-
3 kg/cm2 into the barrel and open the barrel vent and drain to avoid the gas
explosiveness while opening the barrel end closure.
Open the pig barrel and insert the pig and pushed forward until the front pig if
firmly in contact with reducer.
Close and secure the end closure and close drain and vent valves.
Gradually open the kicker line valve to pressurize the launcher allow the
pressure to equalize.
When the launcher is pressurized to line pressure then fully open the kicker
line isolation valve.
Gradually open the pig barrel isolation valve #2. i.e., full bore valve.
Double ensure that the pig barrel isolation valve is fully open.
Gradually close main valve #3 thereby increase the flow behind the pig.
Monitor pig signal for pig passage by hearing manually or through GEO
PHONE.
Once pig has entered mainline completely first open the mainline valve #3.
Close pig barrel isolation valve#2.
Close kicker line valve #1.
Gradually open the vent and drain valves and depressurize the barrel.
Repeat the launching sequence for next pigs.
34
3.13.2 Pig receiver:
QOEC
#1 EQUALISER VALVE
#3 MAINLINE VALVE
FLOW
VENT
PIG FLOW
FLOW
Ensure pig barrel isolation valve #2 and kicker line valve #1 closed.
Gradually pressurize the barrel through equalizer line across the pig barrel
isolation valve.
When the barrel is fully pressurized to the mainline pressure then open the
equalizer line valve #1 connecting the pig barrel and mainline.
Open the pig barrel isolation valve #2 i.e., fully bore valve.
Control the flow of pipeline.
Collect gas the liquid received from the pipeline in the terminal facilities such
as slug catcher, scrubber, and condensate tank open drain and soak pits etc.
Ensure the pig speed calculate are updated with current flow and pressures.
When pig is tentatively near to the receiver, close the mainline valve #3, and
allow the entire flow of gas through the pig barrel and equalizer line.
When pig is received. First open the mainline valve #3.
Gradually close the pig barrel valve #2.
35
Close the equalizer line valve #1.
Open the barrel vent and drain.
Ensure the total barrel fully empty and check the pressure gauge reading zero
kg/cm2. Close the vent and drain valves.
Purge the nitrogen gas through the pressure gauge upto 2-3kg/cm2 and open
the vent and drain valves to allow the gas to atm.
Remove the pig receiver tray, take the pig and clean the receiver with water
jet.
After cleaning insert the tray in receiver.
Close and secure the pig barrel end closures.
Repeat same operation for receiving pigs.
2) Gauge pig
3) Brush pig
4) Magnetic pig
7) Intelligent pig
VALVE LEGENDS:
36
PLUG VALVE
GLOBE VALVE
GATE VALVE
NEEDLE VALVE
PIPEBOOK:
wate hydr
otes
of
t
dryin
Date
of
g
r
37
s.n Chi He Act Wall Date Joi Wp Date RT Date Date Date Dat Date
o nag at ual thick of nt s of NO/ of ut of of e of of
e no len ness bend no. no. weld DA field peel low back
gth TE joint test erin fillin
coati g g
ng
38