PROJECT Additional Metal Works Lay bare CRTL NO.

LOCATION San jose delmonte bulacan OWNER: MRS. Ms. Dana Manzano

AREA (sqm) 1 LOT TURNOVER DATE:

B. ARCHITECTURAL WORKS QTY UNIT UNIT COST TOTAL AMOUNT


KITCHEN
1.0 MOBILIZATION/DEMOBILIZATION 1.00 lot
2.0 Fabrication of stair siding using anglebar and steel matting in painted finish 1.00 lot
45,000.00 45,000.00
3.0 Fabrication of wall garden metal using angle bar and steel matting in painted finish 1.00 lot

4.0 Fabrication of water tank enclosure using angle bar with power supply and locks 1.00 lot
TOTAL B1 ₱ 45,000.00

TOTAL CONSTRUCTION COST 45,000.00


Terms & Conditions

60% down payment of the total contract must be paid upon signing of the contract.
All Check payments must be made payable to BDO Savings Account Name: Ralph Jay M. Hular with Account Number: 6390367685
Installation of any accessories/fixtures shall have charges if not included in the contract.
Our team shall not be liable in any damage due to the negligence and natural calamity to any item after the warranty

THANK YOU FOR THE OPPORTUNITY TO WORK WITH YOU.

_________________________________________________ ______ Ralph Hular_______


CONTRACTOR
OWNER / SIGNATURE OVER PRINTED NAME

Page 1 of 1 Bid Form_standard template.v2