PACKAGE NO/ CO. NAME : WP 11 - Fire Protection Package (JAYA SARANA ENGINEERING)
PROJECT : KM1.DS Project
WORK WEEK : 29.July.2019 to 03.August.2019
DATE SUBMIT : 27.July.2019
I
T
DAY/DATE Monday ( 29.July.2019) Tuesday (30.July.2019) Wednesday (31.July.2019) Thursday (01.August.2019) Friday (02.August.2019) Saturday (03.August.2019)
E
M LOCATION/ACTIVITY AM PM AM PM AM PM AM PM AM PM AM PM
I MATERIAL INCOMMING INSPECTION:
Pipe Inspection - Jaya Sarana Fabrication Yard 10.00
Pipe Painting Inspection (Before Installation) - Intel KM1 10.00
Fitting Inspection 10.00
II Mock-up INSPECTION:
Note:
RFI ( Request for inspection) should be submitted 2 days before inspection