All Pipes Boq

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 27

BILL-Pipe Supply & Laying (Pipe Work) For ABAHURERA Kebele

Item Descriptoin QTY Unit Rate Amount


1.00 Purchase and Supply of HDPE pipes
1.01 HDPE pipe OD 110mm PN 10,PE100 547.00
1.02 HDPE pipe OD 90mm PN 10,PE100 394.00
1.03 HDPE pipe OD 63mm PN 10,PE100 800.00
2.00 HDPE PE 100,PN10,SDR12 Supply and Installation of
fittings and Other accessories
2.01 DCI double flanged Pipe, L= 6m, DN 110 mm 3
2.02 DCI double flanged pipe with puddle flange PN 16,
L=0.6m, DN 110 mm 2
2.03 Stub flange but weld DN 110mm 3
2.04 Backing ring flanged 110mm 3
2.05 Bolt, nut and washer M-24 76
2.06 Bend 90°, DCI, DN 100 mm 2
2.07 Elbow HDPE 110mm 1
2.08 Tee reducer butt weld 110x63x110mm 1
2.09 Equal Tee butt weld 110x110mm 1
2.10 Equal Tee butt weld 63x63mm 1
2.11 Reducer butt weld 110x90mm 1
2.12 Reducer butt weld 110x63mm 1
2.13 Reducer butt weld 90x63mm 1
2.14 Welding point 110 mm Fitting 10
2.15 Welding point 90 mm Fitting 2
2.16 Welding point 63 mm Fitting 6
2.17 Welding point 110 mm Pipe 44
2.18 Welding point 90 mm Pipe 14
2.19 Welding point 63 mm Pipe 4
2.20 Laying and installation of 110mm pipe 547.00
2.21 Laying and installation of 90mm pipe 394.00
2.22 Laying and installation of 63mm pipe 800.00
3. Earth Work (Pipe trench Excavation and Backfill)
3.10 Excavation ordinary soil 814.98
3.20 Excavation in soft rock
3.30 Excavation in hard rock
3.40 Backfilling 685.72
3.50 10cm thick Bedding by selected materials for the
119.06
whole formation & backfill by selected material
3.60 Construction of concrete chamber for air valve,
3
washout, Tees etc

Test, Hand Over and Commissioning


UP TO DATE EXCUTED AMOUNT UP TO OCTOBER
BILL-Pipe Supply & Laying (Pipe Work) For hassen gurage Kebele
Item Descriptoin Unit QTY Unit Rate
1.00 Purchase and Supply of HDPE pipes
1.01 HDPE pipe OD 140mm PN 10,PE100 ml 66.00
1.02 HDPE pipe OD 125mm PN 10,PE100 ml 42.00
1.03 HDPE pipe OD 110mm PN 10,PE100 ml 148.00
2.00 HDPE PE 100,PN10,SDR12 Supply and Installation of
fittings and Other accessories
2.01 Stub flange but weld DN 110mm Pcs 1
2.02 Backing ring flanged 110mm Pcs 1
2.03 Bolt, nut and washer M-24 Pcs 8
2.04 Elbow HDPE 110mm PCS 1
2.05 Tee reducer butt weld 140x63x140mm PCS 1
2.06 Reducer butt weld 110x63mm PCS 1
2.07 Reducer butt weld 140x125mm PCS 1
2.08 Welding point 140 mm Fitting WP 3
2.09 Welding point 125 mm Fitting WP 2
2.10 Welding point 110 mm Fitting WP 4
2.11 Welding point 63 mm Fitting WP 4
2.12 Welding point 140 mm Pipe WP 6
2.13 Welding point 125 mm Pipe WP 4
2.14 Welding point 110 mm Pipe WP 5
2.15 Laying and installation of 140mm pipe ml 66.00
2.16 Laying and installation of 125mm pipe ml 42.00
2.17 Laying and installation of 110 mm pipe ml 148.00
3. Earth Work (Pipe trench Excavation and Backfill)
3.10 Excavation ordinary soil m3 132.82
3.20 Excavation in soft rock m3
3.30 Excavation in hard rock m3
3.40 Backfilling m3 111.50
3.50 10cm thick Bedding by selected materials for the whole
m3 18.44
formation & backfill by selected material
3.60 Construction of concrete chamber for air valve, washout,
No
Tees etc

Test, Hand Over and Commissioning


UP TO DATE EXCUTED AMOUNT UP TO OCTOBER
Amount
BILL-Pipe Supply & Laying (Pipe Work) For ALI-ETHIO Kebele
Item Descriptoin Unit QTY Unit Rate
1.00 Purchase and Supply of HDPE pipes
1.01 HDPE pipe OD 125mm PN 10,PE100 ml 453.00
1.02 HDPE pipe OD 110mm PN 10,PE100 ml 533.00
HDPE pipe OD 90mm PN 10,PE100 241.00
1.03 HDPE pipe OD 75mm PN 10,PE100 ml 427.00
HDPE pipe OD 63mm PN 10,PE100 445.00
2.00 HDPE PE 100,PN10,SDR12 Supply and Installation of
fittings and Other accessories
2.01 Stub flange but weld DN 110mm Pcs 1
2.02 Backing ring flanged 110mm Pcs 1
2.03 Bolt, nut and washer M-24 Pcs 8
2.04 Bend 90°, GIS, DN 3 Inch
2.05 Bend 90°, GIS, DN 2 1/2 Inch
2.06 GI SPIE weld DN 3 inch 2
2.07 GI SPIE weld DN 2 1/2 inch 2
2.08 Elbow HDPE 110mm PCS 1
2.09 Tee reducer butt weld 140x63x140mm PCS 1
2.10 Reducer butt weld 110x63mm PCS 1
2.11 Reducer butt weld 140x125mm PCS 1
2.12 Welding point 125 mm Fitting WP 3
2.13 Welding point 110 mm Fitting WP 2
2.14 Welding point 90 mm Fitting WP 4
2.15 Welding point 75 mm Fitting WP 4
2.16 Welding point 63 mm Fitting 10
2.17 Welding point 125 mm Pipe WP 16
2.18 Welding point 110 mm Pipe WP 11
2.19 Welding point 90 mm Pipe WP 5
2.20 Welding point 75 mm Pipe 9
2.21 Welding point 63 mm Pipe 4
2.22 Laying and installation of 125mm pipe ml 453.00
2.23 Laying and installation of 110mm pipe ml 533.00
2.24 Laying and installation of 90 mm pipe ml 241.00
2.25 Laying and installation of 75 mm pipe 427.00
2.26 Laying and installation of 63 mm pipe 445.00
3. Earth Work (Pipe trench Excavation and Backfill)
3.10 Excavation ordinary soil m3 1,021.78
3.20 Excavation in soft rock m3
3.30 Excavation in hard rock m3
3.40 Backfilling m3 859.09
3.50 10cm thick Bedding by selected materials for the whole
m3 147.06
formation & backfill by selected material
3.60 Construction of concrete chamber for air valve, washout,
No
Tees etc
Amount
BILL-Pipe Supply & Laying (Pipe Work) For ABDIRAHMAN Kebele
Item Descriptoin Unit QTY Unit Rate
1.00 Purchase and Supply of HDPE pipes
1.01 HDPE pipe OD 125mm PN 10,PE100 ml 112.00
1.02 HDPE pipe OD 110mm PN 10,PE100 ml 201.00
1.03 HDPE pipe OD 75mm PN 10,PE100 ml 72.00
2.00 HDPE PE 100,PN10,SDR12 Supply and Installation of
fittings and Other accessories
2.01 Stub flange but weld DN 110mm Pcs 1
2.02 Backing ring flanged 110mm Pcs 1
2.03 Bolt, nut and washer M-24 Pcs 8
2.04 Elbow HDPE 110mm PCS 1
2.05 Tee reducer butt weld OD 125x75x125mm PCS 1
Tee reducer butt weld OD 110x75x110mm 1
2.06 Reducer butt weld OD 125X110mm PCS 1
2.07 Reducer butt weld OD 110x75mm PCS 1
2.09 Welding point OD 125 mm Fitting WP 4
2.10 Welding point OD 110 mm Fitting WP 4
2.11 Welding point OS 75mm Fitting WP 3
2.12 Welding point OD 125 mm Pipe WP 3
2.13 Welding point OD 110mm Pipe WP 2
2.14 Welding point OD 75 mm Pipe WP 2
2.15 Laying and installation of OD 125mm pipe ml 112.00
2.16 Laying and installation of OD 110mm pipe ml 201.00
2.17 Laying and installation of OD 75mm pipe ml 72.00
3. Earth Work (Pipe trench Excavation and Backfill)
3.10 Excavation ordinary soil m3 193.00
3.20 Excavation in soft rock m3
3.30 Excavation in hard rock m3
3.40 Backfilling m3 162.15
3.50 10cm thick Bedding by selected materials for the
m3 27.25
whole formation & backfill by selected material
3.60 Construction of concrete chamber for air valve,
No
washout, Tees etc

Test, Hand Over and Commissioning


UP TO DATE EXCUTED AMOUNT UP TO OCTOBER
Amount
BILL-Pipe Supply & Laying (Pipe Work) For HELO-BIYO Kebele
Item Descriptoin Unit QTY Unit Rate
1.00 Purchase and Supply of HDPE pipes
1.01 HDPE pipe OD 125mm PN 10,PE100 ml 3,552.00
1.02 HDPE pipe OD 75mm PN 10,PE100 ml 75.00
HDPE pipe OD 500mm PN 10,PE100 ml 534.00
1.03 HDPE pipe OD 40mm PN 10,PE100 ml 36.00
2.00 HDPE PE 100,PN10,SDR12 Supply and Installation of
fittings and Other accessories 4197
2.01 Stub flange but weld DN 90mm Pcs 1
2.02 Backing ring flanged OD 90mm Pcs 1
2.03 Bolt, nut and washer M-24 Pcs 8
2.04 Elbow HDPE OD 90mm PCS 5
2.05 Tee reducer butt weld OD 75x40x75mm PCS 1
2.06 Equal Tee butt weld OD 50x50mm PCS 1
2.07 Reducer butt weld OD 90x75mm PCS 1
2.08 Reducer butt weld OD 75x50mm PCS 1
2.09 Welding point OD 90 mm Fitting WP 12
2.10 Welding point OD 75 mm Fitting WP 5
2.11 Welding point OD 50mm Fitting WP 4
2.12 Welding point OD 40mm Fitting WP 1
2.13 Welding point OD 90 mm Pipe WP 72
2.14 Welding point OD 75 mm Pipe WP 2
2.15 Welding point OD 50 mm Pipe WP 5
2.16 Welding point OD 40 mm Pipe WP 1
2.17 Laying and installation of OD 90mm pipe ml 3,552.00
2.18 Laying and installation of OD 75mm pipe ml 75.00
2.19 Laying and installation of OD 50 mm pipe ml 534.00
2.25 Laying and installation of OD 40 mm pipe 36.00
3. Earth Work (Pipe trench Excavation and Backfill)
3.10 Excavation ordinary soil m3 1,965.64
3.20 Excavation in soft rock m3
3.30 Excavation in hard rock m3
3.40 Backfilling m3 1,654.45
3.50 10cm thick Bedding by selected materials for the whole
m3 287.16
formation & backfill by selected material
3.60 Construction of concrete chamber for air valve,
No
washout, Tees etc
Amount
BILL-Pipe Supply & Laying (Pipe Work) For BIRKO ELEVATED Kebele
Item Descriptoin Unit QTY Unit Rate
1.00 Purchase and Supply of HDPE pipes
1.01 HDPE pipe OD 63mm PN 10,PE100 ml 117.00
1.02 HDPE pipe OD 75mm PN 10,PE100 ml 310.00
1.03 HDPE pipe OD 90mm PN 10,PE100 ml 43.00
HDPE pipe OD 110mm PN 10,PE100 ml 92.00
2.00 HDPE PE 100,PN10,SDR12 Supply and Installation of
fittings and Other accessories 562
2.01 DCI double flanged Pipe, L= 6m, DN 110 mm Pcs 3
2.02 DCI double flanged pipe with puddle flange PN 16,
Pcs
L=0.6m, DN 100 mm 2
2.03 Stub flange but weld DN 110mm Pcs 3
2.04 Backing ring flanged 110mm Pcs 3
Bend 90°, DCI, DN 100 mm Pcs 2
2.05 Bolt, nut and washer M-24 Pcs 72
2.06 45o Elbow 90x90mm Pcs 1
2.06 Tee Equal butt weld 110x63x110mm Pcs 1
2.07 Tee Reducer butt weld 110x75x110mm Pcs 1
2.08 Tee Reducer butt weld 90x63x90mm Pcs 1
2.09 Reducer butt weld 110x90mm Pcs 1
2.10 Reducer butt weld 90x63mm Pcs 1
2.11 Welding point 63 mm Fitting WP 3
2.12 Welding point 75 mm Fitting WP 1
2.13 Welding point 90 mm Fitting WP 2
2.14 Welding point 110 mm Fitting WP 4
2.15 Welding point 50 mm Pipe WP
2.16 Welding point 63 mm Pipe WP 2
2.17 Welding point 75 mm Pipe WP 11
2.18 Welding point 90 mm Pipe WP 1
2.19 Welding point 110 mm Pipe WP 3
2.20 Laying and installation of 63mm pipe ml 117.00
2.21 Laying and installation of 75mm pipe ml 310.00
2.22 Laying and installation of 90mm pipe ml 43.00
2.23 Laying and installation of 110mm pipe ml 92.00
3. Earth Work (Pipe trench Excavation and Backfill)
3.10 Excavation ordinary soil m3 369.86
3.20 Excavation in soft rock m3
3.30 Excavation in hard rock m3
3.40 Backfilling m3 336.14
3.50 10cm thick Bedding by selected materials for the whole
m3 33.72
formation & backfill by selected material
3.60 Construction of concrete chamber for air valve, washout,
No
Tees etc
Test, Hand Over and Commissioning
UP TO DATE EXCUTED AMOUNT UP TO OCTOBER
Amount
BILL-Pipe Supply & Laying (Pipe Work) For DHADHAMANE Kebele
Item Descriptoin Unit QTY Unit Rate
1.00 Purchase and Supply of HDPE pipes
1.01 HDPE pipe OD 200mm PN 10,PE100 ml 498.00
1.02 HDPE pipe OD 140mm PN 10,PE100 ml 744.00
1.03 HDPE pipe OD 110mm PN 10,PE100 ml 1,036.00
HDPE pipe OD 75mm PN 10,PE100 ml 2,054.00
2.00 HDPE PE 100,PN10,SDR12 Supply and Installation of
fittings and Other accessories
2.01 Stub flange but weld DN 200mm Pcs 1
2.02 Backing ring flanged 200mm Pcs 4
2.03 Bolt, nut and washer M-24 Pcs 14
2.04 DCI double flanged Pipe, L= 6m, DN 150 mm Pcs 4
2.05 DCI double flanged pipe with puddle flange PN 16,
Pcs
L=0.6m, DN 150 mm 4
2.06 Stub flange but weld DN 110mm Pcs 2
2.07 Backing ring flanged 160mm Pcs 64
2.08 Bend 90°, DCI, DN 150 mm Pcs 2
2.09 Bolt, nut and washer M-24 Pcs 136
2.10 90o Elbow 75x75mm Pcs 2
2.11 45o Elbow 110x110mm Pcs 54
2.12 Tee Reducer butt weld 200x75x200mm Pcs 1
2.13 Tee Equal butt weld 200x200mm Pcs 1
2.14 Tee Reducer butt weld 110x75x110mm Pcs 3
2.15 Reducer butt weld 200x140mm Pcs 1
2.16 Reducer butt weld 200x110mm Pcs 1
2.17 Reducer butt weld 110x75mm Pcs 3
2.18 Reducer butt weld 200x140mm Pcs
2.19 Welding point 200 mm Fitting WP 5
2.20 Welding point 140 mm Fitting WP 1
2.21 Welding point 110 mm Fitting WP 6
2.22 Welding point 90 mm Fitting WP 4
2.23 Welding point 75 mm Fitting 2
2.24 Welding point 200 mm Pipe WP 41
2.25 Welding point 140 mm Pipe WP 60
2.26 Welding point 110 mm Pipe WP 33
2.27 Welding point 75 mm Pipe WP 37
2.28 Laying and installation of 63mm pipe ml 498.00
2.29 Laying and installation of 200mm pipe ml 744.00
2.30 Laying and installation of 140mm pipe ml 1,036.00
2.31 Laying and installation of 110mm pipe ml 2,054.00
2.32 Laying and installation of 75mm pipe ml 0.00
3. Earth Work (Pipe trench Excavation and Backfill)
3.10 Excavation ordinary soil m3 2,184.24
3.20 Excavation in soft rock m3
3.30 Excavation in hard rock m3
3.40 Backfilling m3 1,831.12
3.50 10cm thick Bedding by selected materials for the whole
formation & backfill by selected material m3 307.10
3.60 Construction of concrete chamber for air valve, washout,
No
Tees etc

Test, Hand Over and Commissioning


UP TO DATE EXCUTED AMOUNT UP TO OCTOBER
Amount

2.4
BILL-Pipe Supply & Laying (Pipe Work) For DhagahleyKebele
Item Descriptoin Unit QTY Unit Rate
1.00 Purchase and Supply of HDPE pipes
1.01 HDPE pipe OD 40mm PN 10,PE100 ml 364.00
1.02 HDPE pipe OD 50mm PN 10,PE100 ml 278.00
2.00 HDPE PE 100,PN10,SDR12 Supply and Installation of
fittings and Other accessories
2.01 Stub flange but weld DN 50mm Pcs 1
2.02 Backing ring flanged 50mm Pcs 4
2.03 Bolt, nut and washer M-24 Pcs 4
2.04 DCI double flanged Pipe, L= 6m, DN 110 mm Pcs 4
2.05 DCI double flanged pipe with puddle flange PN 16,
Pcs
L=0.6m, DN 110 mm 2
2.06 Stub flange but weld DN 110mm Pcs 3
2.07 Backing ring flanged 110mm Pcs 3
2.08 Bolt, nut and washer M-24 Pcs 98
2.09 Bend 90°, DCI, DN 100 mm Pcs 2
2.10 45o Elbow 40x40mm Pcs 2
2.11 Tee Equal butt weld 50x50mm Pcs 1
2.12 Reducer butt weld 110x50mm Pcs 2
2.13 Reducer butt weld 50x40mm Pcs 2
2.14 Welding point 50 mm Fitting WP 3
2.15 Welding point 40 mm Fitting WP 2
2.16 Welding point 110 mm Pipe 2
2.17 Welding point 50 mm Pipe WP 6
2.18 Welding point 40 mm Pipe WP 2
2.19 Laying and installation of 63mm pipe ml
2.20 Laying and installation of 40mm pipe ml 364.00
2.21 Laying and installation of 50mm pipe ml 278.00
3. Earth Work (Pipe trench Excavation and Backfill)
3.10 Excavation ordinary soil m3 392.64
3.20 Excavation in soft rock m3
3.30 Excavation in hard rock m3
3.40 Backfilling m3 354.12
3.50 10cm thick Bedding by selected materials for the whole
m3 38.52
formation & backfill by selected material
3.60 Construction of concrete chamber for air valve, washout,
No 2
Tees etc

Test, Hand Over and Commissioning


UP TO DATE EXCUTED AMOUNT UP TO OCTOBER
Amount
BILL-Pipe Supply & Laying (Pipe Work) For DhagahleyKebele
Item Descriptoin Unit QTY Unit Rate Amount
1.00 Purchase and Supply of HDPE pipes
1.01 HDPE pipe OD 75mm PN 10,PE100 ml 156.00
1.02 HDPE pipe OD 90mm PN 10,PE100 ml 229.00
1.03 HDPE pipe OD 110mm PN 10,PE100 ml 554.00
2.00 HDPE PE 100,PN10,SDR12 Supply and Installation
of fittings and Other accessories 939
2.01 Stub flange but weld DN 110mm Pcs 1
2.02 Backing ring flanged 110mm Pcs 1
2.03 Bolt, nut and washer M-24 Pcs 8
2.04 45o Elbow 110x110mm Pcs 2
2.05 90o Elbow 110x110mm Pcs 1
2.06 90o Elbow 90x90mm Pcs 1
2.06 Tee Reducer butt weld 90z75x90mm Pcs 2
2.07 Reducer butt weld 90x75mm Pcs 2
2.07 Welding point 110 mm Fitting WP 6
Welding point 90 mm Fitting 6
2.08 Welding point 75 mm Fitting WP 4
2.09 Welding point 75 mm Pipe WP 6
Welding point 90 mm Pipe 8
2.10 Welding point 110 mm Pipe WP 19
2.11 Laying and installation of 75mm pipe ml 156.00
2.12 Laying and installation of 90mm pipe ml 229.00
2.13 Laying and installation of 110mm pipe ml 554.00
3. Earth Work (Pipe trench Excavation and Backfill)
3.10 Excavation ordinary soil m3 445.05
3.20 Excavation in soft rock m3
3.30 Excavation in hard rock m3
3.40 Backfilling m3 388.71
3.50 10cm thick Bedding by selected materials for the
m3 56.34
whole formation & backfill by selected material
3.60 Construction of concrete chamber for air valve,
No 0
washout, Tees etc

Test, Hand Over and Commissioning


UP TO DATE EXCUTED AMOUNT UP TO OCTOBER
BILL-Pipe Supply & Laying (Pipe Work) For Irresaa Kebele
Item Descriptoin Unit QTY Unit Rate
1.00 Purchase and Supply of HDPE pipes
1.01 HDPE pipe OD 180mm PN 10,PE100 ml 403.00
1.02 HDPE pipe OD 125mm PN 10,PE100 ml 377.00
1.03 HDPE pipe OD 90mm PN 10,PE100 ml 249.00
2.00 HDPE PE 100,PN10,SDR12 Supply and Installation of
fittings and Other accessories
2.01 Stub flange but weld DN 180mm Pcs 1
2.02 Backing ring flanged 150mm Pcs 1
2.03 Bolt, nut and washer M-24 Pcs 12
2.05 90o Elbow 125x125mm Pcs 1
2.06 Tee Reducer butt weld 180x125x180mm Pcs 1
2.07 Reducer butt weld 180x90mm Pcs 1
Reducer butt weld 125x90mm Pcs 1
2.07 Welding point 180 mm Fitting WP 2
Welding point 125 mm Fitting WP 3
2.08 Welding point 90 mm Fitting WP 2
2.09 Welding point 180 mm Pipe WP 34
Welding point 125 mm Pipe WP 32
2.10 Welding point 90 mm Pipe WP 9
2.11 Laying and installation of 180mm pipe ml 403.00
2.12 Laying and installation of 125mm pipe ml 377.00
2.13 Laying and installation of 90mm pipe ml 249.00
3. Earth Work (Pipe trench Excavation and Backfill)
3.10 Excavation ordinary soil m3 568.80
3.20 Excavation in soft rock m3
3.30 Excavation in hard rock m3
3.40 Backfilling m3 493.82
3.50 10cm thick Bedding by selected materials for the whole
m3 74.99
formation & backfill by selected material
3.60 Construction of concrete chamber for air valve, washout,
No
Tees etc

Test, Hand Over and Commissioning


UP TO DATE EXCUTED AMOUNT UP TO OCTOBER
Amount
BILL-Pipe Supply & Laying (Pipe Work) For Idishala Kebele
Item Descriptoin Unit QTY Unit Rate
1.00 Purchase and Supply of HDPE pipes
1.01 HDPE pipe OD 110mm PN 10,PE100 ml 288.00
1.02 HDPE pipe OD 90mm PN 10,PE100 ml 17.00
1.03 HDPE pipe OD 75mm PN 10,PE100 ml 292.00
1.04 HDPE pipe OD 63mm PN 10,PE100 ml 470.00
2.00 HDPE PE 100,PN10,SDR12 Supply and Installation of fittings
and Other accessories 1067
2.01 Stub flange but weld DN 100mm Pcs 1
2.02 Backing ring flanged 110mm Pcs 1
2.03 Bolt, nut and washer M-24 Pcs 8
2.04 DCI double flanged Pipe, L= 6m, DN 110 mm Pcs 2
2.05 DCI double flanged pipe with puddle flange PN 16,
Pcs
L=0.6m, DN 100 mm 4
2.06 Stub flange but weld DN 110mm Pcs 3
2.07 Backing ring flanged 110mm Pcs 3
2.08 Bolt, nut and washer M-24 Pcs 72
2.09 90o Elbow 125x125mm Pcs 2
2.10 Equal Tee butt weld 110x110mm Pcs 1
2.11 Tee Reducer butt weld 90x63x90mm Pcs 1
2.12 Reducer butt weld 110x63mm Pcs 2
2.13 Welding point 110 mm Fitting WP 3
2.14 Welding point 90 mm Fitting WP 3
2.15 Welding point 75 mm Fitting WP 5
2.16 Welding point 63 mm Fitting WP 4
2.17 Welding point 110 mm Pipe WP 3
2.18 Welding point 90 mm Pipe WP 0
2.19 Welding point 75 mm Pipe WP 6
2.20 Welding point 63 mm Pipe WP 4
2.21 Laying and installation of 180mm pipe ml 288.00
2.22 Laying and installation of 125mm pipe ml 17.00
2.23 Laying and installation of 90mm pipe ml 292.00
3. Earth Work (Pipe trench Excavation and Backfill)
3.10 Excavation ordinary soil m3 711.68
3.20 Excavation in soft rock m3
3.30 Excavation in hard rock m3
3.40 Backfilling m3 640.51
3.50 10cm thick Bedding by selected materials for the whole
m3 71.17
formation & backfill by selected material
3.60 Construction of concrete chamber for air valve, washout, Tees
No
etc

Test, Hand Over and Commissioning


UP TO DATE EXCUTED AMOUNT UP TO OCTOBER
Amount
BILL-Pipe Supply & Laying (Pipe Work) For OBOSHA Kebele
Item Descriptoin Unit QTY Unit Rate
1.00 Purchase and Supply of HDPE pipes
1.01 HDPE pipe OD 140mm PN 10,PE100 ml 813.00
1.02 HDPE pipe OD 90mm PN 10,PE100 ml 320.00
1.03 HDPE pipe OD 63mm PN 10,PE100 ml 983.00
2.00 HDPE PE 100,PN10,SDR12 Supply and Installation of
fittings and Other accessories 2116
2.01 DCI double flanged Pipe, L= 6m, DN 150 mm Pcs 2
2.02 DCI double flanged pipe with puddle flange PN 16,
Pcs
L=0.6m, DN 150 mm 4
2.03 Stub flange but weld DN 150mm Pcs 3
2.04 Backing ring flanged 150mm Pcs 3
2.05 Bend 90°, DCI, DN 100 mm Pcs 2
2.06 Bolt, nut and washer M-24 Pcs 72
2.07 45o Elbow 90x90mm Pcs 2
2.08 45 Elbow 63x63mm
o
Pcs 1
2.09 Tee Equal butt weld 140x140mm Pcs 1
2.10 Tee Reducer butt weld 140x90x140mm Pcs 1
2.11 Tee Reducer butt weld 140x63x140mm Pcs 1
2.12 Tee Reducer butt weld 90x63x90mm Pcs 1
2.13 Reducer butt weld 140x63mm Pcs 2
2.14 Reducer butt weld 90x63mm Pcs 1
2.15 Welding point 140 mm Fitting WP 7
2.16 Welding point 90 mm Fitting WP 7
2.17 Welding point 63 mm Fitting WP 7
2.18 Welding point 140 mm Pipe WP 64
2.19 Welding point 90 mm Pipe WP 11
2.20 Welding point 63 mm Pipe WP 16
2.21 Laying and installation of 140mm pipe ml 813.00
2.22 Laying and installation of 90mm pipe ml 320.00
2.23 Laying and installation of 63mm pipe ml 983.00
3. Earth Work (Pipe trench Excavation and Backfill)
3.10 Excavation ordinary soil m3 1,038.62
3.20 Excavation in soft rock m3
3.30 Excavation in hard rock m3
3.40 Backfilling m3 872.35
3.50 10cm thick Bedding by selected materials for the whole
m3 148.67
formation & backfill by selected material
3.60 Construction of concrete chamber for air valve, washout,
No 3
Tees etc

Test, Hand Over and Commissioning


UP TO DATE EXCUTED AMOUNT UP TO OCTOBER
Amount
40 400 0.64 1.14 291.8 0.5 291.3
50 812 0.65 1.15 607.0 1.6 605.4
63 2,815 0.663 1.163 2,170.6 8.8 2,161.8
75 3,386 0.675 1.175 2,685.5 15.0 2,670.6
90 1,493 0.69 1.19 1,225.9 9.5 1,216.4
110 3,399 0.71 1.21 2,920.1 32.3 2,887.8
125 4,536 0.725 1.225 4,028.5 55.7 3,972.9
140 1,623 0.74 1.24 1,489.3 25.0 1,464.3
180 403 0.78 1.28 402.4 10.3 392.1
200 498 0.8 1.3 517.9 15.6 502.3
19365 16,338.9 174.2 16,164.8

You might also like