Professional Documents
Culture Documents
Method Statement For Installation of Earthing System: South Plage at The Pearl Qatar Infrastructure
Method Statement For Installation of Earthing System: South Plage at The Pearl Qatar Infrastructure
INSTALLATION OF
EARTHING SYSTEM
REVISION NO :1
Signature
Date April 30, 2018 April 30, 2018 April 30, 2018
* Copy Issued
Controlled Copy No: 1 MZP
to:
CONTENT
1. INTRODUCTION
4. RESOURCES
6. SEQUENCE OF WORKS
7. APPENDICES
8. CHECK LIST
1.1 Purpose
Define the specific tasks to be performed and ensure a safe system of work.
Show the procedures to ensure work complies with the specification and drawings.
Ensure work is carried out without any adverse impact on the environment.
This method statement covers the field procedure for the installation of Earthing system .
2. ROLES AND RESPONSIBILITIES
Construction Manager:
Responsibility to ensure the construction activities are being carried-out according to the plans, specifications
and client’s requirements.
Section Head:
Responsible to allocate work distribution to Site Engineers.
Safety Manager:
The HSE Manager will interface with Company, Client and Sub-Contractors for all phases of the contract with
regard to HSE matters. The HSE Manager will have direct responsibility for ensuring compliance with all HSE
requirements, procedures and work instructions for all the work force inclusive of CONTRACTOR / Sub-
Contractors. In the event of any difficulties, the HSE Manager will provide early warning and the proposed
corrective actions.
The HSE Manager has direct responsibility for ensuring that the requirements of the HSE&S Plan are met and
for advising the Project Manager of any non-compliance.
Assign HSE&S Staff shall be competent & qualified and meet CONTRACTOR HSE Job Family minimum
requirements to ensure the HSE requirements mentioned in RAMS for the task
Safety Officers:
Ensure that all necessary safety measures are in place at the location of the works with daily monitoring for the
worker on the job location; reporting any safety issues and take the necessary action on site.
Safety Supervisor:
Ensure that all necessary safety measures are in place at the location of the works, and coordinating between
the safety officers in order to have a full coverage of the working site.
QA/QC Engineers:
Continuously monitor all the work activities to ensure that it’s executed according to the procedures detailed
above and within accepted tolerances and complying with the project specifications.
3. DEFINITIONS / ABBREVIATION / REFERENCES
BS British Standard
MS Method statement
RA Risk assessment
SD Shop Drawings
4.1 Manpower
Site engineers
Supervisors
Forman
Labours
Helper
Drivers and operators
Welders
4.3 Materials
Earth Rod
Earth Conductor (Green/ Yellow) – PVC Insulated copper cable
Bare Copper Tape
Earth Bus bar
Earth Pit
All Earthing Accessories
Note:
Material inspection request shall be raised to inspect the material by QC and PMC representative
as per approved ITP and MAR.
Approved materials to be segregated and stored at warehouse at specific place and then shifted to
site as required.
The health and safety activities are to be in accordance with the relevant Health, Safety and Environmental
requirements.
Make sure all employees are Safety inducted before they can work on site.
Make sure employees take the right equipment with them on visits. Check they have been trained
and know how to use it.
Keep available, records of hazards on particular sites. Make sure all relevant people are notified.
Make sure a supply of the right equipment is available.
Helmets, steel capped high angle shoes, Safety goggles, High visibility jackets, face masks,
overalls should be appropriate and in good condition.
Assess the risks of manual handling before going to the site and look at the materials being used
or stored.
Lighting devices shall be set up at the work area and ensure the required Lux available as per
QCS 2014 during night shift
The lifting area should be barricaded and appropriate signs boards to be fixed to warn and avoid
the unauthorized entry.
Copies of drivers/operator’s license vehicle’s registration and security passes to be submitted to
Company safety department before commencing the work.
All moving crane/equipment shall have reverse horn. All major equipment and crane shall be tested
and certified by Third Party prior to mobilization to site.
Ample and unobstructed passage shall be maintained at all times in and around the truck loading
and lifting space.
All equipment movement at job site must be controlled by third party certified rigger/banks man.
Trained, Competent and Authorized Supervision present at all times to ensure workers are safely
working on site
Dissemination of HSE information shall be exercised by enforcing the application of edifying approaches at
site that culminates in the full comprehension of the job hazard/ risk assessment.
6. SEQUENCE OF WORKS
Before commencement of earthing system installation, following activities are required to be carried out:
• The site electrical engineer prepares the permit to work prior to start any activities. Permit to work
requirements shall be reviewed and discussed prior to commencement of the works via tool box
Talks/ STARRT Card Talks. PTW will be at work site at all times while the work is in progress.
• Prior to start the installation for Earthing system, mobilization of materials and equipment and the
required number of manpower deployed to start the specific activities at site.
• All the materials to be used are approved as per Material Submittal.
• Prior to installation, established and marked the exact locations of Earthing electrodes as per the
approved shop drawings.
• Provide temporary supports and platforms, scaffoldings and access ladders, wherever applicable.
• The entire work shall be done in every respect of a workman like and substantial manner.
• The Earthing System to be tested after all the installation works have been completed.
6.1 Installation of Earthing System
Toolbox talk will be conducted before starting the work. Only trained & competent electricians will
do the work.
• Pre-installation checklist shall be provided
• Ensure all relevant specification clause points are incorporated for Earthing System.
• Ground rod locations shall be checked against the approved layout drawings to ensure correct
positioning .
• Each earth electrode shall be installed vertically to the required depth in a pre-drilled hole and
compaction to be applied after backfilling.
• Depth of rods: Top of earth rod shall not exceed 300mm below grade level/ finished floor level,
unless otherwise indicated. Each electrode shall be driven to a depth such that it penetrates the
summer water table by a minimum of 2 meters.
• Earth Electrode system to provide impedance to earth of 1 ohm (max). Soil resistivity test/s shall
be conducted to determine the number of earth electrodes.
• Underground earthing conductors will be buried at least 600mm below grade.
• All Electrical Equipment will be inspected to ensure that the earth bonding facilities are installed
and located as per the approved shop drawing.
• The termination of earth cable will be inspected to ensure the crimping, exothermic welding or
bolting is secure and where applicable, protected against corrosion.
Location/Building Inspection
Type of Material /
Date:
Structure
Check all material used for installation are new/ undamaged and
have approved material submittals.
1
4 Check all plant and equipment such as, Street Lighting, Manholes
etc. are bonded rigidly to the earthing network .
6 Ensure all cables and terminal strips in junction, pull and outlet
boxes, terminal cabinets, and equipment enclosures are correctly
indentified
7 Ensure the surfaces of the materials to be jointed/ cadweld for final
connection to the earthing rods are thoroughly clean.
Inspection Comments:
Review of Method
Prior to start Material Submittal Approval
1.3 Material Submittal Statement BOQ H H S
work Forms
Submittal
2 Preparation
3 Execution
Note: The underline Nos indicate incorporated amendments made to previous revision
H = Hold Point (IR), W = Witness point (WPN), S = Surveillance, CI = Contractor's Inspection, R= Record Review
Risk Assessment For LA-PLAGE (SOUTH)
Earthing System
Risk Ratng Residual Risk
Item Actvites Hazard / Risk Who is at Risk Necessary Control Measures Acton By
S F Rating S F Rating
1 Instruction, Information, Incompetent or Workers, 2 1 2 Ensure all new employees/workers undergone Safety Induction training. 1 1 1
Training and untrained person/
Supervision inadequate Supervisor, SARRT and/or RAMS discussed to all persons involved in the task prior to
documentation works commencing.
Visitor,
Misinformation/Inadequ Trained, Competent and Authorized Supervision present at all times to
Drivers/
ate information ensure employees/workers are adhering to manual handling safe working
Operators procedure.
Poor communication
Mobile equipment operator has appropriate 3rd party certificate for type
Careless and unsafe
of equipment used and a valid Qatar driving license and is authorized to
behavior
operate the equipment and a Qualified, Competent and Authorized 3 rd
party rigger is present. Project
Trained, Competent and Authorized Banksman to be mobilized where Manager
mobile equipment is working near people, structures. i.ie. reversing or
transporting loads that restrict the driver’s vision
Site Engineer.
As a minimum the following information should be communicated to
workforce;
o Permit required for work (PTW) HSE
2 Use of hand tools Chances of scratches in hand Employs 3 2 2 Selection and physical fitness of personal for manual works Project Manager 2 1 2
carrying out to
Injury from sharp edges / task supervisors Deploy physically fit and trained workforce
skinning objects
TBT on safe use of hand tools Site Engineer.
Provision of adequate PPEs
Provision of good tools for the best performance HSE
Foreman
Risk Ratng Residual Risk
Item Actvites Hazard / Risk Who is at Risk Necessary Control Measures Acton By
S F Rating S F Rating
Foreman