Procedure Erection Tank Farm
Procedure Erection Tank Farm
Dok BKN-PJC-ETF-02
PT. BATARAKARYA NUSASAKTI No. Rev 00
Tgl 20-OCT-2019
PROCEDURE TANK ERECTION / REBUILT Hal 1-22
Catatan Revisi
Rev DESKRIPSI REVISI PEMBUAT TANGGAL
00 Naskah Awal Zainal Abidin 20-Oct-2019
ZETH MUSTAFA
0.0 Disahkan Oleh:
DIREKTUR
CATATAN:
1. Dokumen Asli dari prosedur ini dipelihara dan dikendalikan oleh Departemen PJC PT.Batarakarya Nusasakti..
2. Penggunaan Dokumen Asli ataupun Dokumen Salinan harus mengikuti aturan yang tertulis pada Dokumen
Prosedur Pengendalian Dokumen.
1
Procedur Rebuilt / Erection Tank Farm
No. Dok BKN-PJC-ETF-02
PT. BATARAKARYA NUSASAKTI No. Rev 00
Tgl 20-OCT-2019
PROCEDURE TANK ERECTION / REBUILT Hal 1-22
1.0. GENERAL
2.0. PURPOSE
Guidance for related Supervisor or Engineer to assembly and erection Storage Tank.
3.0. REFERENCES
Article I. COMMON
1.4. Temporarily installed machines and jigs for assembling work should be checked
and adjusted before start of erection work.
1.5. Electrical equipment should be checked for proper condition and insulation before
start up.
1.6. Temporarily installed equipment and services related to erection work should be
removed and location cleared to the original condition after completion of the
work.
2
Procedur Rebuilt / Erection Tank Farm
No. Dok BKN-PJC-ETF-02
PT. BATARAKARYA NUSASAKTI No. Rev 00
Tgl 20-OCT-2019
PROCEDURE TANK ERECTION / REBUILT Hal 1-22
5.1. OUTLINE
After prepare the foundation inspection report, BKN and WIKA review the report
according to items as per 5.1 and confirm the foundation drawing.
For level check at completion of foundation, the centre points shall be checked and
marked, the orientation of Tank refer to centre point have been marked.
Level and elevation check at top of foundation for check points as shown at the picture
below.
3
Procedur Rebuilt / Erection Tank Farm
No. Dok BKN-PJC-ETF-02
PT. BATARAKARYA NUSASAKTI No. Rev 00
Tgl 20-OCT-2019
PROCEDURE TANK ERECTION / REBUILT Hal 1-22
FLOW OF INSTALLATION
Completion of
Foundation
Inspection of Foundation
Arrangement of
Annular Plate
Assembly of
Bottom plate
Assembly of Shell
NDT Inspection Plate 1st stage
Perpendicular, horizontality
And roundness of shell plate
2nd and 3rd stages
NDT Inspection
Nozzle installation
Perpendicular, horizontality
And roundness of shell plate
Install ladders
Install Curb angle
And shell
Install Roof Attachment
accessories
Installation
Internal Cleaning
Water Draining
Final Documentation
4
Procedur Rebuilt / Erection Tank Farm
Check Point for Foundation
The amount of foundation check Point can be added depend on the diameter of the tank,
ever greater the area the check point shall increase . the degree axis may divide into
smallest degree as necessary , the degree axis shall be in symmetric position mirror to
centre line, for example 1/16 circle , 1/32 circle etc.
The space of check point to the centre line is depend on the necessaries, the divider can
be 1/10 diameter, 1/5 diameter etc .
Orientation on the foundation Work
procedure
- Establishing of azimuth
- Centre positioning of bottom plate arrangement
- Marking of the annular plate circle
1. Establishing of azimuth
Work Procedure:
- Preparation
- Arranging of annular plate
- Arranging of central bottom plate
- Arranging of peripheral bottom plate
- Cutting of periphery
6.1.1. Preparation
a. Marking – off the matching line (centre line) : mark off the centre line on
the annular plate (necessary for four in sixteen annular plates). Weld
the backing strip on the annular plate at both ends for one plate, at
single ends for fourteen plates, and none for rest one plate.
b. The drain nozzle should be installed by welding on the correct
orientation at the same time.
c. Mark-off the reference line, the overlap allowance etc. on the central
and peripheral bottom plates as shown below:
REFERENCE LINES
a) After setting the central bottom plate, lay the peripheral bottom plate
from centre of periphery.
b) The overlap allowance shall be in accordance to the drawing
dimensions.
c) Remove the foreign matters such as sand and dust from the area to
be overlapped.
d) Execute the tack welding on the bottom plate before regular welding.
Typical example
f) When executing the regular welding of the bottom plate, the activities
should be concerned to the welding procedure and usage of jigs to
minimize the distortion and absorb the contraction due to welding.
The tack welding and regular welding shall be accordance to the
acceptable welding procedure.
a) After welding the bottom plate, remove the attached jigs carefully to
avoiding damage the base metal, and finishing the welds by grinding
machine.
b) Where peel – off or cut away of base metal is happened while removing
the jigs, it must be repaired by welding on the damage area and
finishing by grinding machine.
The inspection of bottom plate shall be done for the following items in
accordance to specification requirement after arranging the bottom plate
and before assembly of shell plates.
a) Full Dye penetrant test or Magnetic Particle test for bottom plate
welding.
After completion of the bottom plate or the annual plate inspection, the
following items can be done for the assembly preparation.
a) Mark – off on the bottom plate the 0º, 90º, 180º and 270º lines for the
reference of shell plate erection corresponding to the foundation datum
line.
b) Mark – off the inside diameter circle of the shell plate.
c) Mark – off the circle for the datum of checking the assembly of shell
100 mm inside from the inside diameter circle of shell plate.
d) Mark – off the point for datum of assembling the shell plate.
Typical example
After marking – off the shell plate inside diameter attach the jigs for fitting
the shell plate as shown below:
HORSE SHOE
SECOND AND
SUBSEQENT SHELL
PLATES
Note : The position and size of the jig should be determined at site.
6.1.9. Attaching of shell plate jigs.
Before erection of shell plates, attach the jigs for assembly and hooks for
foot board bracket.
Note : The position and size of the jig should be determined at site
Starting from the assembling datum point, arrange the first stage shell
plates clockwise (or counter clock wise) and assemble them based on the
marking – off provided beforehand, then execute tack welding.
a) Lift the shell plate and bring into the bottom plate, match the end of
shell plate with the reference line, and fix the plate with jigs and support
it with turn buckle wire rope so as to prevent fall down of the plate and
maintain perpendicularly.
b) Arrange the second and subsequent shell plates one by one clockwise
(or counter clock wise) and execute the handling as the above item (a).
Apply the specified spacer between the abutting plates and fix them
with the fitting jigs.
d) After assembling the first stage plates, check them for perpendicularly,
level, roundness, etc. in accordance with the inspection manual. Any
error shall be corrected to make within the tolerance.
Notes: 1. Root opening should be adjusted with spacer
2. Plate to plate fitting should be adjusted with strong
back spacer etc.
As figure below shows, measure the shell plate for level, perpendicularly
and roundness in the circumferential direction. Correct the error, if any,
within the range of tolerance stipulated in the inspection and criteria.
Attaching of jigs for shell plate assembling, attach horse shoe on inside
surface of shell plate in the same manner as in the 1st stage shell plate.
a) Extend and assemble the second and subsequent shell plate with
straight strong back, curved strong back, bull pin, etc. being careful with
the root opening and offset of circumferential and longitudinal joints.
b) Execute the assembly stage up to the final shell course and install the
curb angle as per the drawing.
6.3.1.1 Make the manhole opening in close supervision with correct orientation
and elevation after adjusting the horizontally, perpendicularly and
roundness of the 1st shell plats and before assembly of 2nd shell
course. Install the nozzle after the 3rd course has been welded.
6.3.1.2 Other auxiliaries to be attached to shell plate and roof plate area after
completion of shell plate and roof plate welding respectively. Marked –
0ff it’s orientation, elevation, size, etc. to conform to the specification
and drawings and checked during every stage of work progress.
6.3.1.3 Strengthen shell plates with reinforcements to prevent the shell plates
from straining when welding manholes, nozzles, etc.
Roof Assembly
a) The roof shall be pre assembled on the temporary table on the area
that are clear for transportation and installation to the top of the tank
or at fabrication area.
a) Roof assembly shall start from the centre and spread to periphery.
c) After the plate lay down, make sure the dimension of the roof plate
is correct and the gap between the shell and edge of roof plate ring
for correct rim seal installation.
h) After completion of roof and set in to the permanent roof support the
temporary supports shall be removed.
7.1 After the assembly and welding of all tank is completed, fill water in the tank. Prior
to the water filling the following items should be checked.
7.1.1 Check all welding completed and all NDT accepted. Any repair of weld after
NDT must be completed, retested and accepted.
7.1.2 Remove all temporary supports, jigs from both inside and outside of the tank.
No. Dok BKN-PJC-ETF-02
PT. BATARAKARYA NUSASAKTI No. Rev 00
Tgl 20-OCT-2019
PROCEDURE ERECTION STORAGE TANK Hal 1-22
7.1.3 All tack weld on the shell for install jigs and temporary attachments
should grind smooth.
7.1.4 Check all attachments are installed correctly and blind flange is correct
size and properly installed.
7.1.5 Water filling speed and retaining period should as per the project
standard.
7.1.6 When water filling always watch the tank for any leakage and draw up
an inspection records of water level and each section.
After water drainage, clean inside the tank using fresh water. Remove all dirty
water left on bottom of the tank with rags and final cleaning inspection shall be
done.
22
Procedur Rebuilt / Erection Tank Farm