CE525

MID TERM

EARLY ESTIMATES

1. Early estimates are extremely important to the owner. From the perspective of
the owner, give examples of problems that may arise if an early estimate is
significantly lower than the final actual cost of a project.
2. Describe the purpose of a kick off meeting for preparing an early estimate of a
project. What are the typical items that should be addressed and confirm before
starting estimate preparation.

PROJECT BUDGETING

1. Usually each of the three principal parties (the owner, designer and contractor)
prepares a cost estimate at different times during the life of a project. Describe
the purpose of each estimate and the impact that estimating errors may have on
the other two parties.
2. Why is it important to define the range of accuracy, in percentage, that should
be applied to any estimate? Who should set this range and who should be