Sukit River

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 50

LAND BASED

OPERATION
SUKIT RIVER
PRE-OP SITE PREPARATION
SUKIT RIVER
PRE-OP SITE PREPARATION
PHASE 1
• Manpower
• Purchasing of Materials
• Site Construction
• Studies
• Land and Marine Base Mobilization
PHASE 2
• Construction of Platform
• Dredging of Approach Channel
• Backfilling of Temporary River Mouth
• Opening of the New River Mouth
• Construction of Access Road
• Construction of Holding Area
PURCHASING OF MATERIALS
Eco-link: Oscar:
• Gabion Box • Boulders, head size
• Roll Geotextile • Base coarse
• Bamboo /Aggregates(access road,
• Timber cause way, pathway)
• Plywood (signage)
• Rolls of tire wire
SITE CONSTRUCTION
SUKIT FENCING

SAND FENCING
Materials to be use for constructing
Sukit River fence.

• 50 Bamboo (Foundation)
• Bamboo (Buho)
• 6 Roll of Nylon
• 1 kg Nail

SAND FENCING
Length: 100 m
CANTEEN FLOOR PLAN
COMFORT ROOM FLOOR PLAN
INSTALLATION OF MARKERS

225 Bamboos will be needed for the markings.


Installation will be completed within three (3) days
STUDIES
Offshore Bathymetric
Onshore Bathymetric
MOBILIZATION
LAND BASE
o 1 Dump Trucks
o 2 Backhoe
o 1 Pay Loader

MARINE
o Cutter Dredger
-Simultaneously done while
backfilling the existing river mouth
-6 m depth
-100 m wide opening
-Reinforce sides with Gabion
Boxes
3 layers
OPENING OF NEW RIVER MOUTH
Land Based Extraction
Volume to be Extracted:
Vol. = 100 x 50 x 2
Vol. = 10, 000 cubic meters
Vol. = 15, 500 Mt
No. of Days to extract
Working Hours:10 hrs
Extraction Rate of backhoe: 202. 50 MT/hr
15,500 𝑀𝑇 1 𝑑𝑎𝑦
No. of Days= 𝑀𝑇 x
202.50 10 ℎ𝑟
ℎ𝑟
No. of Days= 7.65 days
Note:
• Maintenance, repair and Downtime are not considered in
the working hours.
Marine Based Extraction
Use cutter dredger to extract the remaining 4 meters depth.
Volume to be Extracted:
Vol. = 50 x 50 x 4
Vol. = 10, 000 cubic meters
Vol. = 15, 500 Mt
No. of Days to extract
Working Hours:10 hrs
Extraction rate of cutter: 500 MT/hr
15,500 𝑀𝑇 1 𝑑𝑎𝑦
No. of Days= 𝑀𝑇 x
500 10 ℎ𝑟
ℎ𝑟
No. of Days= 3.1 days
Note:
Maintenance, repair and Downtime are not considered in the
working hours.
ENTRY TO NEW RIVER MOUTH

Backfill with sand bags so


that the trucks can pass to
deliver the boulder rocks
DREDGING OF CHANNEL

Dimensions:
100 m x 100 m x 6 m
Volume: 93,000 MT
Dredged
material will
be stockpiled
here
Northward
1 Southward
200 x 100
200 x 100
3
2
Dimensions:
100 m x 100 m x 6 m
Volume: 93,000 MT
Volume to be dredged:
Vol.= 100 x 100 x 6
Vol. =60, 000 cubic meters
Vol. =93, 000 Metric Tons

No. of Days to be dredged:


Extraction rate of Cutter: 500 MT/hr
Working Hours:10 hrs
93,000 𝑀𝑇 1 𝑑𝑎𝑦
No. of Days= 𝑀𝑇 x
500 10 ℎ𝑟
ℎ𝑟
No. of Days= 18.6 days

Note: Repair, Maintenance and Down time is not considered in


the working hours.
BACKFILLING OF TEMPORARY RIVER
MOUTH
ESTIMATED
DIMENSIONS:
Area: 9,637 m2
Depth-2 meters

Stockpile from
the cutter
dredger
Volume of River Mouth that needs to be
backfilled:
Vol1 = Area x Depth
Vol1 = 9,637 x 2
Vol1 = 19, 274 cubic meters m2
Vol1 = 29, 874.7 Metric Tons

Considering the compaction:


Compactness: 15%
Volume=29, 874.7 x (1+0.15)
Volume= 35, 425.41 MT
CONSTRUCTION OF PLATFORM

Gabion Boxes:
3 layers
30 pcs total
Isometric drawing
Excavation of the area
Laying of Geotextile
Laying of Gabion Boxes
Overall view of the laid Geotextile & Gabion Boxes
End result of the Platform Area
Volume inside the gabion box and sheet pile that need to be
backfilled:
Vol2 = 10 x 20 x 3
Vol2 = 600 cubic meters
Vol2 = 930 Metric Tons
Holding Area for RS
Note: once the river mouth is passable the pay loader will
immediately go to the new river mouth.
Steps:
• While the backhoe is opening the new river mouth, the pay
loader will scrape the designated holding area for RS to
remove the vegetation.
• Flatten the area.
HOLDING AREA FOR CS

Area to be
backfilled
HA CS
Computation:
Volume to be backfilled:
Area: 4, 503 m2
% of Compaction: 15%
Volume= 4, 503 x 2.5 x (1+0.15)
Volume= 12, 946.13m3
Volume=20, 066. 49 MT

No. of Days to backfill:


Working Hours:10 hrs
Extraction rate of cutter: 500 MT/hr
20,066.49 𝑀𝑇 1 𝑑𝑎𝑦
No. of Days= 𝑀𝑇 x
500 10 ℎ𝑟
ℎ𝑟
No. of Days= 4 days
CONSTRUCTION OF ACCESS WAY
After the holding area for RS is done and the Old River Mouth is
backfilled, the dump truck can create the access way up to the
river mouth.
Volume needed:
Vol. = 1000 m x 10 m x 0.3 m
Vol. = 3 000 m3
Vol. = 4 650 MT
OPERATIONS
Marine/Offshore Land Based
Methodologies Loading to conveyor
Offshore Dredge Plan Forms
Marine Traffic Control
EL Ops Manpower
Ops Manpower Structure
Forms
LAND BASED
LOADING TO CONVEYOR
Option 1: Dump trucks only
Given:
Daily production loading target: 12 000 MT
Capacity of DT: 18 MT
Assume Unloading & travel time:10 mins.
Computations:
12000 𝑀𝑇
No. of trips=
18 𝑀𝑇
=666.667~667 trips
To reach the daily target of 12 000 MT, a total of 667 trips is
needed to be accomplished
Computations:
Time to load the DT using a No. of trips per hr:
BH: 3 𝑡𝑟𝑢𝑐𝑘𝑠 𝑥 𝑡𝑟𝑢𝑐𝑘𝑠
18 𝑀𝑇 =
15.33 𝑚𝑖𝑛𝑠 60 𝑚𝑖𝑛𝑠/ℎ𝑟
No. of Min.= 3𝑡𝑟𝑢𝑐𝑘𝑠 𝑥 60 𝑚𝑖𝑛𝑠
3.375 𝑀𝑇/𝑚𝑖𝑛
X=
No. of Min.= 5.33 min. 15.33 𝑚𝑖𝑛𝑠
Total Cycle Time=10+5.33 X=12 trucks/hr
Total Cycle Time=15.33
No. of trucks per cycle Utilizing the 9 DT:
without delay: No of trips=3x12x18
𝑐𝑦𝑐𝑙𝑒 No. of trips=648
No. of DT=
𝑙𝑜𝑎𝑑𝑖𝑛𝑔 𝑡𝑖𝑚𝑒
15.33
=
5.33
= 3 trucks
DUMPTRUCKS & BACKHOE

Target : No. of buckets per


180 𝑀𝑇/ℎ𝑟
12 000 𝑀𝑇 hour=
𝑁𝑜. 𝑜𝑓 𝐵𝑢𝑐𝑘𝑒𝑡𝑠 = 3 𝑀𝑇/𝑏𝑢𝑐𝑘𝑒𝑡
𝑀𝑇 No. of buckets per hour=60
3
𝑏𝑢𝑐𝑘𝑒𝑡
No. of buckets=4 000
Buckets per day=60 x 18
Buckets per day=1, 080
Time to load 1 DT to
18 𝑀𝑇
hopper=
3 𝑀𝑇/𝑚𝑖𝑛 MT Loaded per day=
𝐵𝑢𝑐𝑘𝑒𝑡𝑠 𝑀𝑇
1080 =x3
= 6 mins 𝑑𝑎𝑦 𝐵𝑢𝑐𝑘𝑒𝑡
MT to be loaded to hopper per MT Loaded per day=3 240 MT
hr.
18 𝑀𝑇 𝑥
=
6 𝑚𝑖𝑛 60 𝑚𝑖𝑛/ℎ𝑟
X= 180 MT/hr
PRODUCTION TARGET
(Land Based)
Location Volume No. of Days No. of Days
(MT) (1 shift) (2 Shifts)
St. 50 Area 1 8, 990 2.22 1.11
St. 100 Area 1 8, 370 2.07 1.03
St. 150 Area 1 8, 370 2.07 1.03
St. 200 Area 1 8, 990 2.22 1.11
St. 250 Area 1 8, 990 2.22 1.11
St. 300 Area 1 12, 090 2.99 1.49
St. 350 Area 1 14, 260 3.52 1.76
St. 400 Area 1 20, 460 5.05 2.53

Production Rate of Backhoe:202.50 MT/ hr


Working hours: 10 hrs. (Excluded repair & maintenance times)
2 Backhoes are operating
TYPE OF LOADING
I. PARTIAL LOADING
II. FULL LOADING
III. SHARE LOADING
PARTIAL LOADING
Checklists
• Classification (RS/CS)
• Source
• Operator
• Signal that the stockpiled is running out
• Initial draft survey at the MV
• Go signal for the other party to load
• Operator (that will continue the loading to MV)
• Final draft survey
Procedure
• Check the stockpiled area and the daily extraction of the LB to
predict if partial loading will be activated.
• Once activated, the current party will stop loading.
• All concerns parties will accompany the surveyor to perform
the draft survey to witness that there is no foul play in
surveying the draft.
• A form will be provided for them to sign agreeing with the
result of the survey draft.
• Then the other party can start loading to the MV.
• After the MV is loaded, perform a final draft survey together
with all the concern parties agreeing with the datum.
FULL LOADING
Checklists
• Classification (RS/CS)
• Source
• Operator
Procedure:
• Check if there is enough stockpiled to load the MV.
• The operator will signed the form that he will take
responsibility in fully loading the MV.
SHARE LOADING
• The stockpiled will come from Alex.
• Oscar will provide the trucking services
LOADING OPTIONS
DATE:

FULL LOADING
PARTIAL LOADING
SHARE LOADING

OPERATOR: ________________________________________

TYPE OF SAND SOURCE


____ CS ___ HA 1
____ RS ___ HA 2
___ HA 3

FOR FULL LOADING


I, ____________________________________________________, representative of
________________________________________ having an estimated stockpile of
_______________ MT takes full responsibility to load to MV.

________________________
Signature

FOR PARTIAL LOADING


INITIAL LOADING

DRAFT SURVEY ____________ MT LOADED: ___________

________________________ ________________________
SURVEYOR ECOLINK REPRESENTATIVE

____________________________ ________________________
OSCAR'S TEAM ALEX' TEAM

FINAL LOADING

DRAFT SURVEY ____________ MT LOADED: ___________

________________________ ________________________
SURVEYOR ECOLINK REPRESENTATIVE

____________________________ ________________________
OSCAR'S TEAM ALEX' TEAM

SHARE LOADING

We, ________________________________________________________ and


___________________________________________________________ agrees to share the
loading to MV. Where the source will come from Alex' stockpile and Oscar will provide the
trucking services.

______________________________ ________________________
Signature Signature